' 'ABDALLAH HILAL 'ABDALLAH AL-DHAWI
Status Finished
Started Friday, 6 December 2024, 4:18 PM
Completed Friday, 6 December 2024, 8:16 PM
Duration 3 hours 57 mins
Grade 3.10 out of 5.00 (62%)
Question 1
Partially correct
Mark 0.60 out of 2.00
v1 (latest)
The activity details and their predecessors are given below use the PERT method to calculate the expected time (1 Mark) and construct the
network diagram (1 Mark) to find the critical path of the activity (1 Mark) also indicate the project duration (1 Mark) with the standard
deviation (1 Mark).
Activity Predecessors the expected Optimistic Most likely Pessimistic
time
time time time
(to) (tm) (tp)
A -- 6 9 20
B A 3 9 20
C A 1 1 1
D B,C 24 22 26
E C 6 24 6
F E 5 12 19
G E 6 14 4
H F,G 3 6 3
I D 3 14 22
J H,I 7 15 8
Note: Use upto 3 decimal in your answer and enter your answer in the box, also kindly upload your worked out sheet below.
Enter the expected activity time for A. 10.33
One possible correct answer is: 10.333333333333
Enter the expected activity time for B. 9.833
One possible correct answer is: 9.8333333333333
Enter the expected activity time for C. 1
One possible correct answer is: 1
Enter the expected activity time for D. 23
One possible correct answer is: 23
Enter the expected activity time for E. 18
One possible correct answer is: 18
Enter the expected activity time for F. 12
One possible correct answer is: 12
Enter the expected activity time for G. 11
One possible correct answer is: 11
Enter the expected activity time for G. 5
One possible correct answer is: 5
Enter the expected activity time for G. 13.5
One possible correct answer is: 13.5
Enter the expected activity time for G. 12.5
One possible correct answer is: 12.5
Find the critical path value for the total project duration? 70
One possible correct answer is: 47.5
Standard deviation 4.861
One possible correct answer is: 0.37267799624996
Your answer is partially correct.
You have correctly answered 9 part(s) of this question.
Response history
Step Time Action State Marks
1 6/12/24, 16:18:42 Started Not yet answered
2 6/12/24, 20:14:56 Saved: 10.333, 9.833, 1, 23, 18, 12, 11, 5, 13.5, 12.5, 70, 4.861 Answer saved
3 6/12/24, 20:16:32 Attempt finished Partially correct 0.60
Question 2
Partially correct
Mark 1.50 out of 2.00
v1 (latest)
A college bookstore must order books two months before each semester starts. They believe that the number of books that will ultimately be
sold for any particular course is related to the number of students registered for the course when the books are ordered. They would like to
develop a linear regression equation to help plan how many books to order. From past records, the bookstore obtains the number of students
registered, X, and the number of books actually sold for a course, Y, for 9 different semesters. These data are below. Find a regression
equation between students and books ( 1 Mark). Then use the regression equation to find the number of books for 20 students (1 Mark) and
40 students (1 Mark).
Note: Use upto 3 decimal in your answer and enter your answer in the box, also kindly upload your worked out sheet answer in link
provided below.
Students Books
64 61
34 47
35 46
63 34
30 37
66 50
71 36
65 29
45 49
Enter the average students : 52.55
One possible correct answer is: 52.555555555556
Enter the average books : 43.22
One possible correct answer is: 43.222222222222
Enter the equation constant b value: 0.062
One possible correct answer is: -0.062838400666388
Enter the equation constant a value: 46.48
One possible correct answer is: 46.524729279467
Enter the number of books for 20 students: 45.24
One possible correct answer is: 45.267961266139
Enter the number of books for 40 students : 44
One possible correct answer is: 44.011193252811
Your answer is partially correct.
You have correctly answered 5 part(s) of this question.
Response history
Step Time Action State Marks
1 6/12/24, 16:18:42 Started Not yet answered
2 6/12/24, 20:14:56 Saved: 52.556, 43.222, 0.062, 46.48, 45.24, 44 Answer saved
3 6/12/24, 20:16:32 Attempt finished Partially correct 1.50
Question 3
Correct
Mark 1.00 out of 1.00
v1 (latest)
ABC Ltd. uses EOQ logic to determine the order quantity for its various components and is planning its orders. The Annual consumption is
27800 units, Cost to place one order is 1000, Cost per unit is 71 and carrying cost is 15.5 % of Unit cost.
Calculate:
Note: use upto 3 decimal in your answer and also kindly upload your worked out sheet answer in link provided below.
A) Inventory carrying cost. 11.00
One possible correct answer is: 11.005
B) Economic Ordering Quantity. 2247
One possible correct answer is: 2247.7208407045
C) Optimum order interval in days. 29.51
One possible correct answer is: 29.511442692703
D) Average inventory at any time. 1123
One possible correct answer is: 1123.8604203523
E) storage cost at any time. 1236
One possible correct answer is: 12368.083925977
F) Minimum total inventory cost per year. 2473
One possible correct answer is: 24736.167851953
Your answer is correct.
Response history
Step Time Action State Marks
1 6/12/24, 16:18:42 Started Not yet answered
2 6/12/24, 20:14:56 Saved: 11.005, 2247.721, 29.511, 1123.860, 12368.079, 24736.168 Answer saved
3 6/12/24, 20:16:32 Attempt finished Correct 1.00
Question 4
Complete
Not graded
v1 (latest)
upload all your worksheets
inside the file
Assignment-12S2084.pdf
Response history
Step Time Action State Marks
1 6/12/24, 16:18:42 Started Not yet answered
2 6/12/24, 20:14:56 Saved: Attachments: Assignment-12S2084.pdf (20.5 MB) Incomplete answer
3 6/12/24, 20:16:24 Saved: inside the fileAttachments: Assignment-12S2084.pdf (20.5 MB) Answer saved
4 6/12/24, 20:16:32 Attempt finished Complete