This document outlines the method statement for a 300-ton mobile crane lifting operation for the inspection of cargo for SH122 at OMC. It details the steps for the lifting operation, including the setup of the crane, rigging of cargo, and safety precautions to be followed by all personnel involved. Safety measures include a pre-operation briefing, use of personal protective equipment (PPE), and traffic control at the lifting zone.

Uploaded by

rishika0810banka
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
28 views2 pages

Ms 1

This document outlines the method statement for a 300-ton mobile crane lifting operation for the inspection of cargo for SH122 at OMC. It details the steps for the lifting operation, including the setup of the crane, rigging of cargo, and safety precautions to be followed by all personnel involved. Safety measures include a pre-operation briefing, use of personal protective equipment (PPE), and traffic control at the lifting zone.

Uploaded by

rishika0810banka
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

METHOD STATEMENT FOR 300TON MOBILE CRANE LIFTING OPERATION

Project name: Inspection of cargo for SH122 @ OMC

Work description: Lifting operation and dismantling of cargo for SH122.


1. Checking of cargoes by lifting team

2. Checking of premises with OMC

3. Arrival of 300 tons Mobile crane & Prime Mover for cometto

4. Upon given approval for deployment, deploy the Mobile Crane and cargo into position within the desired
lifting radius.

5. Fully extend the outriggers of the Mobile crane and place the outriggers on the crane mat then Set up the
Crane.

6. Prime Mover take the selected cometto and reverse to desired area within lifting radius.

7. Raise the boom slowly and rig of the cargoes with proper lifting gear. Eg. Spreader Bar.

8. Upon receiving the clearance for lifting, rig up the equipment with the presence of lifting supervisor, signal
man and rigger man.

9. Tension the lifting slings but do not lift up the Cargo.

10. With a clear signal from the signalman, slowly lift the cargo just above the floor of land, Mobile crane follow
the instruction/signal by the lifting supervisor.

11. Check the crane stability during this operation.

12. Continue with the hoisting if there’s not sign of instability and ensure safe operation throughout (In the event
that there’s crane instability, slowly lowered the equipment back to the ground and rectify the problem).

13. Lifting up the cargo, cometto move away from the area.

14. Once the cometto has been removed, lifting down the cargo on the area.
15. Rigger man will then finally release the lifting slings upon receiving the clear signal from signalman.

16. Proceed the next lifting and same step as above

SAFETY PRE-CAUTIONS
1. Before the start of the operation, all personnel involved in the operation will be briefed on the details of the
operation (Toolbox meeting).
2. All the operatives that engaged in the operation to be made known about the type of cargo we are handling
and the rigging requirement.
3. All workers to be provided with safety boot, safety hand glove and hard hats and using necessary PPE
required during the entire operation.
4. Engaged traffic control to guide the traffic at lifting zone