The Heavy Equipment & Dump Truck Report details the operational status, fuel usage, and working hours of two excavator units over a period from January 18 to February 16, 2025. The report highlights instances of breakdowns, standby periods, and working conditions, with varying percentages of operational efficiency. Overall, the report provides a comprehensive overview of equipment performance and fuel consumption during the specified dates.

Uploaded by

andi hasnani
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
28 views3 pages

Laporan HM

The Heavy Equipment & Dump Truck Report details the operational status, fuel usage, and working hours of two excavator units over a period from January 18 to February 16, 2025. The report highlights instances of breakdowns, standby periods, and working conditions, with varying percentages of operational efficiency. Overall, the report provides a comprehensive overview of equipment performance and fuel consumption during the specified dates.

Uploaded by

andi hasnani
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

HEAVY EQUIPMENT & DUMP TRUCK REPORT

FUEL First Last Total HM DWH Standby Breakdown Before Lunch After Lunch First Last Total KM
Date Unit Type Operator First condition Addition Rest of fuel Average Usage Equipment Stat. Working (HM) Working Hours Shift Kilometer Ritase PA MA UA
19/01/2025 EXCA UNIT 01 HE ONGKI Breakdown 0 0 - 8.0 - 8.0 8:00 12:00 13:00 17:00 8:00 Day 0% 0% 0%
20/01/2025 EXCA UNIT 01 HE ONGKI Working 8909.7 8914.2 4.5 4.5 - - 8:00 12:00 13:00 17:00 8:00 Day 100% 100% 100%
20/01/2025 EXCA UNIT 01 HE ONGKI Breakdown 8914.2 8914.2 - 3.5 - 3.5 8:00 12:00 13:00 17:00 8:00 Day 0% 0% 0%
20/01/2025 EXCA UNIT 01 HE ONGKI Working 8909.7 8914.2 4.5 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 56% 100% 100%
21/01/2025 EXCA UNIT 01 HE ONGKI Working 8914.2 8917.2 3.0 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 38% 100% 100%
22/01/2025 EXCA UNIT 01 HE ONGKI Working 8917.2 8917.2 3.9 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 49% 100% 100%
23/01/2025 EXCA UNIT 01 HE ONGKI Standby 8917.2 8917.2 - 8.0 8.0 - 8:00 12:00 13:00 17:00 8:00 Day 100% 0% 0%
24/01/2025 EXCA UNIT 01 HE ONGKI Breakdown 8922.4 8922.4 - 1.2 - 1.2 8:00 12:00 13:00 17:00 8:00 Day 0% 0% 0%
24/01/2025 EXCA UNIT 01 HE ONGKI Working 8917.2 8922.4 5.2 6.8 - - 8:00 12:00 13:00 17:00 8:00 Day 76% 100% 100%
25/01/2025 EXCA UNIT 01 HE ONGKI Working 8922.4 8931.2 8.8 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 110% 100% 100%
26/01/2025 EXCA UNIT 01 HE ONGKI Working 8931.2 8935.4 4.2 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 52% 100% 100%
27/01/2025 EXCA UNIT 01 HE ONGKI Working 8935.4 8942.6 7.2 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 90% 100% 100%
28/01/2025 EXCA UNIT 01 HE ONGKI Working 8942.6 8950.5 7.9 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 99% 100% 100%
29/01/2025 EXCA UNIT 01 HE ONGKI Working 8950.5 8958.7 8.2 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 103% 100% 100%
30/01/2025 EXCA UNIT 01 HE ONGKI Working 8958.7 8966.8 8.1 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 101% 100% 100%
31/01/2025 EXCA UNIT 01 HE ONGKI Working 8966.8 8976 9.2 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 115% 100% 100%
1/02/2025 EXCA UNIT 01 HE ONGKI Breakdown 8976 8976 - 8.0 - 8.0 8:00 12:00 13:00 17:00 8:00 Day 0% 0% 0%
2/02/2025 EXCA UNIT 01 HE ONGKI Working 8976 8985.3 9.3 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 116% 100% 100%
3/02/2025 EXCA UNIT 01 HE ONGKI Working 8985.3 8995.1 9.8 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 123% 100% 100%
4/02/2025 EXCA UNIT 01 HE ONGKI Working 8995.1 9003.2 8.1 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 101% 100% 100%
5/02/2025 EXCA UNIT 01 HE ONGKI Standby 9003.2 9003.2 - 8.0 8.0 - 8:00 12:00 13:00 17:00 8:00 Day 100% 0% 0%
6/02/2025 EXCA UNIT 01 HE ONGKI Standby 8995.1 8995.1 - 8.0 8.0 - 8:00 12:00 13:00 17:00 8:00 Day 100% 0% 0%
7/02/2025 EXCA UNIT 01 HE ONGKI Working 9005.2 9007.6 2.4 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 30% 100% 100%
8/02/2025 EXCA UNIT 01 HE ONGKI Working 9007.6 9015.3 7.7 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 96% 100% 100%
9/02/2025 EXCA UNIT 01 HE ONGKI Working 9015.3 9023 7.7 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 96% 100% 100%
10/02/2025 EXCA UNIT 01 HE ONGKI Working 9023 9025.5 2.5 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 31% 100% 100%
11/02/2025 EXCA UNIT 01 HE ONGKI Working 9025.5 9031.1 5.6 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 70% 100% 100%
12/02/2025 EXCA UNIT 01 HE ONGKI Working 9031.1 9038.8 7.7 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 96% 100% 100%
13/02/2025 EXCA UNIT 01 HE ONGKI Working 9038.8 9045.9 7.1 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 89% 100% 100%
14/02/2025 EXCA UNIT 01 HE ONGKI Working 9045.9 9052.8 6.9 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 86% 100% 100%
15/02/2025 EXCA UNIT 01 HE ONGKI Working 9052.8 9058 5.2 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 65% 100% 100%
16/02/2025 EXCA UNIT 01 HE ONGKI Working 9058 9065 7.0 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 88% 100% 100%
HEAVY EQUIPMENT & DUMP TRUCK REPORT

FUEL First Last Total HM DWH Standby Breakdown Before Lunch After Lunch First Last Total KM
Date Unit Type Operator First condition Addition Rest of fuel Average Usage Equipment Stat. Working (HM) Working Hours Shift Kilometer Ritase PA MA UA
18/01/2025 EXCA UNIT 02 HE WAHYU Working 8155.4 8162.8 7.4 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 93% 100% 100%
19/01/2025 EXCA UNIT 02 HE WAHYU Working 8162.8 8168.9 6.1 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 76% 100% 100%
20/01/2025 EXCA UNIT 02 HE WAHYU Working 8168.9 8176.8 7.9 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 99% 100% 100%
21/01/2025 EXCA UNIT 02 HE WAHYU Working 8176.8 8183 6.2 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 77% 100% 100%
22/01/2025 EXCA UNIT 02 HE WAHYU Working 8183 8186.9 3.9 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 49% 100% 100%
23/01/2025 EXCA UNIT 02 HE WAHYU Standby 8186.9 8186.9 - 8.0 8.0 - 8:00 12:00 13:00 17:00 8:00 Day 100% 0% 0%
24/01/2025 EXCA UNIT 02 HE WAHYU Working 8186.9 8193.3 6.4 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 80% 100% 100%
25/01/2025 EXCA UNIT 02 HE WAHYU Working 8193.3 8199 5.7 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 71% 100% 100%
26/01/2025 EXCA UNIT 02 HE WAHYU Working 8199 8206.3 7.3 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 91% 100% 100%
27/01/2025 EXCA UNIT 02 HE WAHYU Working 8206.3 8213.4 7.1 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 89% 100% 100%
28/01/2025 EXCA UNIT 02 HE WAHYU Working 8213.4 8221.5 8.1 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 101% 100% 100%
29/01/2025 EXCA UNIT 02 HE WAHYU Working 8221.5 8230 8.5 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 106% 100% 100%
30/01/2025 EXCA UNIT 02 HE WAHYU Working 8230 8238.1 8.1 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 101% 100% 100%
31/01/2025 EXCA UNIT 02 HE WAHYU Working 8238.1 8247.4 9.3 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 116% 100% 100%
1/02/2025 EXCA UNIT 02 HE WAHYU Breakdown 8247.4 8247.4 - 8.0 - 8.0 8:00 12:00 13:00 17:00 8:00 Day 0% 0% 0%
2/02/2025 EXCA UNIT 02 HE WAHYU Working 8247.4 8256.7 9.3 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 116% 100% 100%
3/02/2025 EXCA UNIT 02 HE WAHYU Working 8256.7 8264.2 7.5 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 94% 100% 100%
4/02/2025 EXCA UNIT 02 HE WAHYU Breakdown 8264.2 8264.2 - 8.0 - 8.0 8:00 12:00 13:00 17:00 8:00 Day 0% 0% 0%
5/02/2025 EXCA UNIT 02 HE WAHYU Standby 8264.2 8264.2 - 8.0 8.0 - 8:00 12:00 13:00 17:00 8:00 Day 100% 0% 0%
6/02/2025 EXCA UNIT 02 HE WAHYU Standby 8264.2 8264.2 - 8.0 8.0 - 8:00 12:00 13:00 17:00 8:00 Day 100% 0% 0%
7/02/2025 EXCA UNIT 02 HE WAHYU Working 8268.3 8271.8 3.5 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 44% 100% 100%
8/02/2025 EXCA UNIT 02 HE WAHYU Working 8271.8 8278.8 7.0 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 88% 100% 100%
9/02/2025 EXCA UNIT 02 HE WAHYU Working 8278.8 8286.6 7.8 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 98% 100% 100%
10/02/2025 EXCA UNIT 02 HE WAHYU Working 8286.6 8290.3 3.7 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 46% 100% 100%
11/02/2025 EXCA UNIT 02 HE WAHYU Working 8290.3 8296.0 5.7 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 71% 100% 100%
12/02/2025 EXCA UNIT 02 HE WAHYU Working 8296.0 8303.3 7.3 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 91% 100% 100%
13/02/2025 EXCA UNIT 02 HE WAHYU Working 8303.3 8311.4 8.1 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 101% 100% 100%
14/02/2025 EXCA UNIT 02 HE WAHYU Working 8311.4 8319 7.6 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 95% 100% 100%
15/02/2025 EXCA UNIT 02 HE WAHYU Working 8319 8324.3 5.3 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 66% 100% 100%
16/02/2025 EXCA UNIT 02 HE WAHYU Working 8324.3 8331.5 7.2 8.0 - - 8:00 12:00 13:00 17:00 8:00 Day 90% 100% 100%
WEEKLY PRODUCTIVITY HE & DT
250 PRODUCTIVITY HE & DT
200

150

100

50

0
EXCA UNIT 01 EXCA UNIT 02
Work 161.7 172
Standby 24 24
Breakdown 20.7 16
AWH 232 232

18/01/2025 - 16/02/2025
PRODUCTIVITY
Equipment List Type PIC VENDOR Work Standby Breakdown AWH
PA MA UA EU
EXCA UNIT 01 Exca PC 200 Bucket ONGKI AR 161.7 24 20.7 232 80% 89% 87% 70%
EXCA UNIT 02 Exca PC 200 Bucket WAHYU AR 172 24 16 232 84% 91% 88% 74%
333.7 48.0 36.7 464.0 82% 90% 87% 72%