             BUSINESS PLAN FOR MIXED USE BUILDING
Table of Contents
                                                    2
                     BUSINESS PLAN FOR MIXED USE BUILDING
List of tables
Table 1: Office Space Demand Forecast..........................................................12
Table 4: Utilities................................................................................................20
                                                                                                                       3
                                       BUSINESS PLAN FOR MIXED USE BUILDING
            1 Executive Summary
1    Project Name               Mixed use Building
2    Project type               Multipurpose service business building
3    Project Owner              Tewodros Gezahegn
4    Nationality                Ethiopian
5    Project location           Sheger city Lega tefo Lega Dedi SUB-CITY
6    Project Composition        multipurpose Building (G+2) used for diverse business centers
                                like banking & insurance, super market, shops, restaurant,
                                café, beauty salon, Pharmacy, bed rooms and offices.
7    Premises Required          The                                             2
                                      promoter already acquired a total of 1300m
8    Project Capital            The total investment capital of the project is estimated at birr 138,000,000.00 of
                                which birr (94.3%) 130.13million is for fixed investment items while the remaining
                                balances of birr (5.7%) 7.9 million will be initial working capital.
9    Source of Finance          138,000,000.00 ETB is required from this amount 30% or 41,000,000 ETB
                                from owner equity and the rest 70% 96, 600,000 from bank loan.
10   Employment                 The total manpower required for the envisioned project will be 375 people’s
     Opportunity                employees at f ull capacity.
                                       Permanent’ “workers 155
                                         o   Skilled 65 and Unskilled 90
                                       Temporary workers 220
                                         o   Skilled 115 and Unskilled 40
14   Benefits of the project    Provide service and source of revenue, employment opportunity, save/generate
     for the city and country   the country foreign exchange, benefit for the local community stimulate the
                                local economy and technology transfer,
                                                                                                                     4
                        BUSINESS PLAN FOR MIXED USE BUILDING
2. Introduction
During the past decade robust public and private expenditure on infrastructure and other
construction works has served as a catalyst for Ethiopia’s rapid economic development. The
country has consistently invested more than 30% of GDP into Gross Fixed Capital Formation
(GFCF) expenditure since 2010 and as a result, Ethiopia has emerged as one of the fastest-
growing economies in the world. The market value of the construction sector is currently
estimated at more than US$7bn. According to the 2017 edition of African Economic
Outlook, construction activities in Ethiopia accounted for 15.9% of GDP at current prices
during the 2015/16 fiscal year.
                                                                                                5
                        BUSINESS PLAN FOR MIXED USE BUILDING
The current fast and dynamic economic growth of Ethiopia especially in Sheger necessitates
equivalent growth of building and construction sector. The sector should expand rapidly to support
the overall economic development sustainable.
In the building sector of the economy, the multi- purpose in the one becoming rapidly expanding in
Sheger since dynamic economic development of urban economy requires the construction of these
buildings in the city to support the growing of business service sectors like supermarkets, Beauty
salon, shops, offices cinemas, Computer Center, Cafeterias, Restaurant, Assembly hall, apartments
and other activities. In this regard, mixed used building expands in the all parts of the city.
Investment and property development play an important role in any emerging markets or
economies. Property generally comprises residential houses and commercial real estate property
(mainly mixed- use building) developed for rental business, company office and sale. The property
investment market in Ethiopia remained under developed for several years. As a consequence, the
supply of residential houses and non-residential real estate that can be used for residence, office
space, shopping malls and catering services in the urban centers of the country is
disproportionately low to cope with the growing demand in the country spinning from the average
growth in GDP of 5.5% over the last ten years and population increase. The relatively good
performance of the macro- economy (real growth in GDP, low inflation rate and growth in
investment and export sector) has stimulated unprecedented investment growth in the property
sector over the last five years. The growth of investment in the property market over the last five
years in consistent with the global experience suggesting that investment in the residential and
commercial property is greatly influenced by the performance of the macroeconomic conditions. In
general, a stable macroeconomic condition leads to economic and business growth and develops
investors’ confidence. This certainly spurs large demand in the property market for office space,
shopping malls, catering services, apartment and residential houses. Following growing demand
trends, and with the expectation of high return on their investment capital, large number of land
developers pooled their financial resources and invested in the property market.
To this effect, the owner of the envisioned Mixed-Use Building Ethiopia-based company,
Tewodros Gezahegn, who has been living for long time in this city, planned to buy and rent in
Lega Tafo Lega Dadi Sub-city and undertaken this project study to check the market, technical and
financial feasibility of this project. The promoter is very ambitious and committed to realize the
                                                                                                  6
                 BUSINESS PLAN FOR MIXED USE BUILDING
project to buy
                                                        7
                        BUSINESS PLAN FOR MIXED USE BUILDING
and rent B+ G+2 mixed use building. Hence, they expect to get the necessary support from United
Bank to make the project to be operational.
Besides, the government policies and incentives for the private sector investment are very
promising that motivates the promoter to engaged in mixed use building business.
2. Project Objectives
The major goal of this project is to contribute towards the growth of the trade sector in Sheger.
                                                                                                    8
                          BUSINESS PLAN FOR MIXED USE BUILDING
           To construct and develop modern shops, offices, and restaurant & cafeteria facilities that
            enable to provide standard services to customers.
           To undertake trading and other refuted business activities that enable to generate a
            reasonable to the invested capital.
           To develop modern business center that would provide full services on city standard.
           To create employment opportunities.
           Contribute towards the beautification of the city through the construction of modern
            building infrastructure and facilities.
           To establish economically viable, socially acceptable and environmentally friend mixed
            use Apartment.
The long-term goal of the project is become the best choice trade center in the city. The proposed
project will have a total area of 1300m2 in which the construction area is 1000m2, designed to
reader a multipurpose giving business, which will in turn plays significant role towards solving
shortage of business center in Sheger .
The historical nature of the city as business unique location in one of the most attractive centers in
Ethiopian (100% urban center). The owners plan the project to render banking and insurance,
shopping facility, offices and cafeteria services to create high quality class to satisfy the interest of
customers in the city. Based on environmental and other considerations, the entrepreneur has
determined the type and size of the building which is already determined by the site; conceptual
planning and preliminary analysis have been carried out by analysts.
In order to attract its clients to the service, the project will develop high standard shop & banking
rooms and office of best choices and will also save best quality apartments, restaurant and café.
                                                                                                      9
                         BUSINESS PLAN FOR MIXED USE BUILDING
Mixed-use projects are developments which combine two or more types of revenue producing real
estate developments. Mixed-use projects may be either low rise suburban projects or high rise, high
density urban projects. Mixed-use projects were created to satisfy a convenience and marketing
demand using valuable property for its highest and best use. For instance, to have a hotel function
provides advantage for office visitors while creating a demand for the hotel itself. The synergy
created between the components creates vitality for the mixed-use development and generally
combining different functions in one single project is superior to each single development. Mixed-
use developments are characterized by:
       three or more significant revenue-producing uses (such as retail/entertainment, office,
        residential, hotel, and /or civic/cultural/recreation) that in well planned projects are mutually
        supporting;
       significant physical and functional integration of project components (and thus a relatively
        close-knit and intensive use of land), including uninterrupted pedestrian connections,
       development in conformance with a coherent plan (that frequently stipulates the type and
        scale of uses, permitted densities and related items).
Integrated shared parking is a key component, improving land-use efficiencies and reducing cost.
Pedestrian circulation and orientation are critical elements in the planning process, because without
them, the project will not work as a whole and will not achieve the desired synergies and sense of
place that are the hallmarks of mixed-use developments. This second criteria distinguishes mixed-
use developments from other real estate projects that may include three or more significant revenue
producing uses but do not fully integrate them such as business parks or master planned
communities. Physical configuration of mixed-use developments can be categorized into three
groups as below:
       Mixed-use Towers: These are single, high rise, high density towers. Functions are layered
        vertically. Mostly located in downtown. They have striking physical profile and create land
        marks so helpful in marketing the development but have a disadvantage of creating less
        public outdoor space.
       Integrated Multi-tower Structures: These structures architecturally connect individual
        buildings and towers in one multi-component development. Common building may be an
                                                                                                      10
                           BUSINESS PLAN FOR MIXED USE BUILDING
       atrium, a shopping center or underground parking area. Mostly found in downtown central
           business district (CBD) or high-density suburban downtowns.
          Mixed-use Town Centers, Urban Villages and Districts: This type of mixed-use projects is
           made up of variety of individual buildings around streets, parks or squares and seems like
           an urban district more than a single project. Mostly developed outside downtowns. Mixed-
           use town centers, urban villages and districts are clearly the direction that most mixed-use
           designs are moving today. They also offer greater flexibility for timing and phasing
           projects, important factors in improving feasibility and reducing risk. The existing
           promising investment opportunities, the demands of service need along with relatively
           sound investment support made by the government in such kinds of feasible projects,
           compelled the project promoter to initiate the multipurpose oriented business project to be
           established. Despite the promising business opportunities of the city, the trend on such
           kinds of investment found to not enough. The mismatch between the demand for and
           supply of such kind of services in easily observed in the city.
Therefore, the existing shortage or absence in the supply of these services, along with its commercial
   and administrative access, better location and infrastructure access, escalating trend of urbanization
   and business activities, thus it is with such reason that this project is identified and proposed and
   assumed to be more profitable.
In general, the country’s privatized and free market economy; good governance creates a favorable
   environment for the development of investment for private investors.
The envisaged project deemed to add to the economic development of the city in general in specific
   with following ways:
A. Source of Revenue
As public policy of any nation, the government collects different forms of taxes from different
   business organizations and individuals. Among the different forms of taxes, business income taxes,
   payroll income tax, lease payment and VAT are collected from undertaking business activities.
   Therefore, the building will serve as sources of revenue for the city.
                                                                                                      11
                          BUSINESS PLAN FOR MIXED USE BUILDING
B. Employment opportunity
   One of the problems that our country faced is unemployment. Therefore, the current objective of
   the government is working on tackling the problem of unemployment and fostering the
   development process either through creating self-employment or employment in other
   organization. Hence, this project will hire 26 individuals after completion of the project and more
   than 400 individuals during construction.
   The license area is located in Sheger City Lega Tafo Lega Dadi Sub city, the total area of the
   project is 1300 m2.
                                                                                                   12
                       BUSINESS PLAN FOR MIXED USE BUILDING
There are a number of factors which affects the demand of standardized mixed-use building. Of
these factors, the most important to have influence is population growth and the level of income.
The currently expanding service industry in Sheger and from every corner of the country the city
has been inviting skilled and unskilled labor forces to the center; in addition, the number of both
national and international offices has been increasing. Above all the increase in the number of
population increases for the provision of different services. Nowadays, most of the private business
                                                                                                 13
                        BUSINESS PLAN FOR MIXED USE BUILDING
organizations need their own small-medium offices in order to give their services and provide their
products, and they prefer the place that found in the center or close to the road.
As clearly indicated in the introductory part of this proposal, Sheger is the dynamically growing
urban center of Ethiopia. Though the market demand gap for mixed use building is not clearly
understand there is wider gap for such demand as many merchants, organizations are flouring to
the city every day. From prior business experiences, the demand of mixed-use building is very
high and hence the demand and the supply gap is very wide.
There has been a significant growth in the number of local and international trades across the
country. This increase is mainly associated with the stimulation of economic activist and partly due
to an increase in the flow of international and local traders in to the Sheger. Since Sheger is an
important commercial center in addition there is a significant increase in business activates and
hence increasing the number of traders. Even though there is a lack of quantitative estimates that
depict the actual demand and also the annual growth rate commercial facilities are scarce in the
city.As a result, there is a large gap between the developed and that of the supply for modern Bank
and cafeteria accommodation hence this project would not face any problem of demand scarcity
for its business Centre and it would provide good service to customers.
Commercial building/office sector has shown a dynamic change in the past few years. The reason
for this could be rapid economic growth and a supporting public infrastructural development.
Other factors relevant in the specific case of commercial buildings are the large increases in
national and international businesses, particularly firms in the services sector.
The business of multipurpose buildings in Sheger in booming highly due to the recent rapid growth
experienced in Ethiopia. As a result, a good number of local and international organizational are
coming in place. Government offices which used to operate in limited spaces all over the city are
also concentrating on leasing new and modern buildings. Increasing numbers of international
organization which in the past had typically converted residences into office space are now moving
towards renting whole floors or even multiple floors in modern city-center commercial buildings.
                                                                                                 14
                            BUSINESS PLAN FOR MIXED USE BUILDING
    The demand for office space is a derived demand because firms rent space as an input to the
    production of services or goods they provide to businesses and households in the local or national
    economy.
    Following our survey of office space users in several areas are mainly firms providing banking,
    offices, cafeteria and restaurants, supermarkets, computer center service. Future demand for office
    space is actually driven from growth in number of offices in the city which in turn is influenced by
    the macro-economic growth in the country. Assuming that demand for office space is directly
    related to the growth in the economy, the forecast for office space demand is shown in the
    following table;
                      Office space demand under base case Office space demand under high
                      economic                              case economic
         Years E.C         Growth                                 Growth
         2010/2011                              9,916,543                      11,304,859
         2011/2012                             11,007,363                      12,057,416
         2012/2013                             12,218,173                      12,953,878
         2013/2014                             13,562,173                      13,963,577
         2014/2015                             15,054,011                      14,554,534
         2015/2016                             16,709,952                      14,987,431
    Source: estimation based on GTP’s forecasted Ethiopian Economic Growth
                   Business Community
                   Business organization
                   The government bureau
                   Non-governmental organizations
In order to penetrate and gain considerable market share, one of the major marketing strategies for the
project is consistently rendering quality service to its tenants. Due emphasis must be placed on improving
                                                                                                      15
                            BUSINESS PLAN FOR MIXED USE BUILDING
quality of service and facilities. The major marketing strategies to promote the project and gain
considerable market share include:
           Advertising through different means focusing on the existing service and facilities
           Promote in association to the key location and nearby business
           Working on sustained promotional work.
           Working on public relations to reach and influence key personas and organization with a
            capacity of making decision.
           Keeping the quality of its service/ facilities and consistently improving with changing
            situations.
           Seasonal discount pricing different others customer centric marketing strategies will be
            used by the company.
3.7 Competition
    There are different forms of competition that may face the envisaged mixed-use building. These
    are price and non-price-based competition. Moreover, there are different competitors that will
    compete with the project either directly or indirectly. But the mixed-use building under discussion
    has diversified marketing strategies that could enable it come up with the different competitors in
    the market. Moreover, it will frequently conduct competitors research which focuses on, the
    strength and the weaknesses, the different competitors’ strategies, the techniques they use in
    rendering the service, their customer handling methods, and others. Generally, the project has
    many other projects all over Sheger villages which compete with it.
    In order to provide mixed use business center building services of a high standard, it has been
    planned to construct and develop the infrastructure and facilities that would viable to meet the
    requirements of an international standard business center. Accordingly, various buildings and
    facilities will be constructed phase by phase starting with the most needed ones that are essential to
    commence the operation of its business activities. With the completion of construction, the
    building will provide a combined service such as shops, offices, restaurant and café service as well
    as modern business center that primarily serve its guests and major clients.
                                                                                                       16
                               BUSINESS PLAN FOR MIXED USE BUILDING
Table 2: The plan is that the ground will be partitioned in to different rooms:
Since the project will be engaged in mixed building the main sources of its annual revenue would be
from the rental of building spaces such as different types of shops, offices, and banking, café and
restaurant. Therefore, the sources of revenue have been classified in to one category namely the rental of
banking and supermarket, offices, shops, restaurant and café, meeting halls based on these
classifications. Based on the market price of similar mixed-use building in the area, the envisioned
buildings set the following fair price (Before VAT) for its service, hence when the building construction
fully get operational it is assumed to generate a yearly income of ETB 142,504,850.00.
                                                                                                       17
                           BUSINESS PLAN FOR MIXED USE BUILDING
4 Technical Studies
The envisioned mixed purpose building will provide different rental services to the different
customer groups for different purpose. The building will have basement, ground and 20 (twenty)
floors. The purpose of the building explained as follows;
            The ground floor, first floor second floor and third floor designed for different
             business centers like banks, supermarket, beauty salon (man and women), Computer
             center, pharmacy, internet café, boutiques, bakery, different shops and other business
             activities,
            2rd floor designed for Offices.
The total land required for the envisioned project is estimated to be 1300m 2. The total area for the
construction of the building will be 1000m2, as revealed below.
       No           Description                Land M2
                                               Basement           Ground First floor- floor
                                                                         Twenty
       1     Building (G+2)
       1.1   Basement                                1000
       1.2   Ground                                                  1000
       1.3   First floor- Floor Twenty                                                    1000
                    Total                            1000
                                                                                                  18
                       BUSINESS PLAN FOR MIXED USE BUILDING
4.2.1 Building
The building has been completed and is fully operational. The rest of the work will be completed
the next time and you will be able to earn extra income by renting out unoccupied rooms..
Mechanical and Electrical install coincided with each other due to the need for coordination
between the two divisions. There were several periods of construction during the schedule in
which there were multiple construction activities occurring at the same time.
The construction site must be organized accordingly as these processes take place. As with any
construction project, the goal of the schedule will to complete all the maintenance and finishing
activities. This date of completion of maintenance & finishing works are practical based on the
time of year.
Although functional spaces for the project were laid out in significant detail, the rest of the
building had designated spaces but set layouts. It was at the discretion of the project promoter to
devise typical layouts for the non-detailed commercial and office spaces. To make sure that the
building’s layouts were practical, the project owner researched typical architectural layouts for
laboratory and executive office spaces. The walls and partitions throughout the floor were
congruent with the structural frame and column locations.
                                                                                                19
                         BUSINESS PLAN FOR MIXED USE BUILDING
One of principle deliverables of the project is the structural design of the building. The structural
bays were coordinated with the layout of the building adjustments would be made to the bays if
specific layouts were necessary. The frame would be made up of a grid with repeating standard
structural bays. Included in the structural system were bay sizes, shape and size of structural
members, floor compositions and curtain walls. These elements were established to resist gravity at
lateral loads as appropriate.
The gravity load design was completed for two frames; one of structural steel and one of
reinforced concrete. The structural steel frame was choose for further design based on cost per
square foot, local availability of material and constructability considerations, such as erection and
fabrication. The steel system was then be designed for lateral loading with necessary adjustment
being made to framing.
The project group prepared hand structural design calculations for a typical bay of a reinforced
concrete frame. In all reinforced concrete bay designs, a superimposed dead load of 8 pounds per
square foot was assumed for mechanical equipment, floor coverings and ceilings.
Similarly, the design of the typical bay accounted for the use of different commercial space, in
which a live load of 1000 pounds per square was assumed. Loads was calculated based on the
requirements of the minimum Design loads for Buildings and other Structures.
                                                                                                  20
                        BUSINESS PLAN FOR MIXED USE BUILDING
The design of a superstructure may be accurate, have considered all possibilities and still fail
because the substructure is incapable of distributing the applied loads to the supporting soil.
Foundation design takes more into consideration than merely the loading from the columns. While
the main part of the project focused on the structural frame and its alternate designs, a preliminary
foundation plan was designed based upon maximum load carried from the superstructure through
the columns. The foundation design conducted by the project team consisted of the selection of
foundation type, determination of the bearing capacity and the design for typical interior and
exterior spread footings.
The construction process for this project is normally a disjointed three mages development by
which the conceptualized need of the promoter of this project is translated into a functional facility
that was meet their needs in terms of time, cost and quality.
Based on a general program of the project owners the consultant who was going to be hired makes
site studies, develops structural designs, prepares drawings and specifications, determines
quantities involved and estimated the resultants costs. All these activities was done in the first
phase of the project which is the design stage after the document are produced by the designers
have been received, and the works secured the project is supposed to construct by its own
company. And then, the project constructor was expected to prepare and submits a detailed
construction program which includes material schedule, manpower requirement and cash flow
forecast.
                                                                                                   21
                           BUSINESS PLAN FOR MIXED USE BUILDING
4.3 Utilities
A number of utilities world be put in place in order to ensure smooth functioning of the project.
These utilities include:
Table 4: Utilities
                                                                                          Cost
No       Description                              Qty.              Unit cost             (Birr)
1  Electricity supply, kWh                        100,000           1.30*10,000           130,000
2  Water Supply m3                                50,000            10*500,000            500,000
                                                                                          20,000
3     Telephone and Internet Broadband
                                                  2000              19*2000               38,000
4     Fuel, Oil and lubricant
Total 1,188,000
                                                                                                    22
                           BUSINESS PLAN FORMIXED USE BUILDING
       The Mixed-use building has a total site area of 1300 m2. The building floor area has
       covered 1000 m2 and the remaining 300 m2 is left for construction. The type of buildings
       and its corresponding civil construction cost is given on Table 5.
                                                 23
                          BUSINESS PLAN FORMIXED USE BUILDING
The list of manpower and the annual cost of labor is indicated in Table 6.
                                                24
                    BUSINESS PLAN FORMIXED USE BUILDING
Workers for this type of plant were available throughout the year. No foreseeable problems
are expected as most of the work requires no previous skills.
The building is in full swing, with some work to be completed. The major activities include
Bank loan processing to buy and rent the building. The time schedule for major activities is
presented below:
  SN         Activities                                Date
  1          Preparation Project Proposal              Semp 2024
  2          Bank loan processing                      Mar- April 2024
  6          Service execution                         May, 2024
Organizational Structure
The organizational structure of the project is designed by including all the necessary
personnel under the right division. At the top of the organizational structure, there will be
manager with the responsibility of supervising the overall activity of the building.
Depending up on the nature of the center and the amount of work to be performs; there
exist auxiliary units under the general manager.
Employees under each unit will be supervised by the department head that is accountable
for the general manager. General Manager is appointed by the owners
As clearly shown in the organizational structure, the center organization has one general
manager and three main sections. Under the general manager there are the, Marketing
Department, Maintenance and Building administration department. Under building admin
                                            25
                        BUSINESS PLAN FORMIXED USE BUILDING
   dept there exist two sections i.e., HRM & finance and general service. Further sub sections
   are also organized under technical and maintenance manager. The following section deals
   with the duties and responsibilities of each department.
 He/she will plan, organize, direct and control the overall activities of the building.
 He/she will devise policies and strategies that will enable the center to be profitable.
 He/she will incorporate modern technological innovation that will facilitate the service
   delivery of the building to increase customer’s satisfaction.
 He/she will plan, organize, direct and control the human and non-human resources of the
   building so as to achieve the short and long run objectives of the organization.
   The building Administration Department of the multipurpose building has two main
   sections (HRM and Finance and General Service section). It has responsible for
   undertaking the following activities;
                                              26
                      BUSINESS PLAN FORMIXED USE BUILDING
         Will prepare the annual financial statements and prepare condensed reports for both
          the General Manager and other concerned government body.
         Follow the overall status of the business and provide maintenance and repair services
         Will handle the overall marketing activities of the organization which include
          planning, organizing, directing, and controlling.
         Will develop the marketing strategies for future multipurpose building development
         Will develop effective customer handling strategies.
         Execute the promotion methods.
                                             27
                           BUSIN          Owners
                                   ESS PLAN FORMIXED USE BUIL
                                                          DING
General Manager
Personnel                                                    Promotion
&Property            Financ
                     e
                     Officer
                     s
Supervisors
                                                 28
                            BUSINESS PLAN FORMIXED USE BUILDING
Therefore the said amount of finance is needed for undertaking the following.
                                                29
                                    BUSINESS PLAN FORMIXED USE BUILDING
                 C.   Vehicle
    SN           Description         UOM     Qty    Unit Cost in Fr.       Total cost in       Remark
                                                                               Birr
    1     Mini-Bus                  Unit    5      600,000.00             3,000,000.00       Duty Free
          Total                                                           3,000,000.00
                 D. Office Equipment’s
SN                    Description           Measurement     Qty        Unit cost in   Total cost in
                                                                           birr            Birr
1        Managerial tables                 Unit            5.00           2,600.00         13,000.00
2        Managerial chairs                 Unit            5.00           1,950.00         9,750.00
3        Office table with chair           Unit            7.00           1,350.00         9,450.00
4        Secretarial table with chairs     Unit            2.00           1,450.00         2,900.00
5        Computer with chairs              Unit            5.00          15,000.00         75,000.00
6        Shelf                             Unit                           3,500.00         3,500.00
7        Filing cabinets                   Unit            1.00           1,500.00         1,500.00
8        Guest chairs                      Unit            1.00             900.00         4,500.00
9        Fax & Telephone machine           Unit            5.00           1,300.00         1,300.00
10       Carpet and Curtain                LS              1.00                            23,000.00
         Total                                                                         143,900.00
                                                     30
                            BUSINESS PLAN FORMIXED USE BUILDING
                                              31
                                       BUSINESS PLAN FORMIXED USE BUILDING
                                                          32
                         BUSINESS PLAN FORMIXED USE BUILDING
      B. Depreciation
Building                                    10%
                                              33
                          BUSINESS PLAN FORMIXED USE BUILDING
                                            34
                              BUSINESS PLAN FORMIXED USE BUILDING
         B. Pay-Back Periods
      The investment cost and income statement projection are used to project the pay-back
      period. The building’s total investment will be fully recovered at the 5.2 year of operation.
                                                    35
                        BUSINESS PLAN FORMIXED USE BUILDING
environmental aspects. The environmental impact assessment has included all phases
of the project namely construction phase and operational phase.
                                           36
                         BUSINESS PLAN FORMIXED USE BUILDING
2.2. Evaluation
       The project promoter evaluates the on-going process of the project at each phase
       of implementation. Even if joint evaluation conducted at the end of the project,
       the engineering estimation of bill of quantity is the basic tool of project success
       evaluation. This evaluation will be based on the agreed upon project document
                                            37
                    BUSINESS PLAN FORMIXED USE BUILDING
Conclusion
The objective of this proposed feasibility study is primarily to facilitate the entrepreneur
with the investment information and provide an overview about project. The proposed
feasibility may form the basis of an important investment decision and in order to serve this
objective, the document covers various aspects of Concept Development, Start-up,
Production, Marketing, Finance and Business Management.
The feasibility is based on the information obtained from various sources as well as
discussions with businessmen. For financial model, since the forecast/projections relate to
the future periods, actual results are likely to differ because of the events and circumstances
that don’t occur frequently as expected.
Whilst due care and attention has been taken in performing the exercise, no liability can be
inferred for any in-accuracy or omissions reported from the results thereof. It is essential
that our report be read in its entirety with financial model in order to fully comprehend the
impact of key assumptions on the range of values determined.
The project is accessible and has the necessary infrastructure such as road, telephone, water
and electric power. The proposed project clearly identifies all the necessary equipment,
inputs, management of the company and the required man power. The highest authority in
the project will be vested in the hand of the owner. He will control the overall activities of
the proposed project. Demand projection divulges that there is high demand for building
rental in the country. Accordingly, the planned project is set to provide quality services in
the area.
The proposed project possesses wide range of economic and social benefits such as
increasing the level of investment, tax revenue and employment creation for both women
and youths. It will have also environmental concerns to protect it by planting trees around
its working area and by utilizing environmentally friendly raw materials. Generally, the
                                           38
          BUSINESS PLAN FORMIXED USE BUILDING
project
                          39
                    BUSINESS PLAN FORMIXED USE BUILDING
                                          40
                                             BUSINESS PLAN FORMIXED USE BUILDING
                                                                  41
                                                                    BUSINESS PLAN FORMIXED USE BUILDING
Raw Material Cost               513,027            538,678        565,612       593,893         623,588       654,767       687,505       721,881   757,975        795,873
Sub-total
Total Direct cost
B. Indirect cost
 Wages and Salary 1,238,400 1,300,320 1,365,336 1,433,603 1,505,283 1,580,547 1,659,574 1,742,553 1,829,681 1,921,165
 Repair and Maintenance        667,449.00     667,450.00     667,451.00    667,452.00      667,453.00    667,454.00    667,455.00    667,456.00    667,457.0   667,458.00
                                                                                                                                                    0
 Property Insurance                4,275.00       4,275.00   4,275.00      4,275.00        4,275.00      4,275.00      4,275.00      4,275.00      4,275.00    4,275.00
 Utility                       1,188,000      1,247,400      1,309,770     1,375,259       1,444,021     1,516,222     1,592,034     1,671,635     1,755,217   1,842,978
 Land lease                    422,640        422,641        422,642       422,643         422,644       422,645       422,646       422,647       422,648     422,649
     Advertising      and      50,000.00       50,001.00     50,002.00     50,003.00       50,004.00     50,005.00     50,006.00     50,007.00     50,008.00   50,009.00
Promotion
 Miscellaneous Expense         40,000.00       40,001.00     40,002.00         40,003.00   44,003.30     48,403.63     53,243.99     58,568.39     64,425.23   70,867.75
Total operating cost            4,123,791      4,270,766      4,425,090     4,587,130       4,761,271     4,944,319     5,136,739     5,339,022     5,551,686   5,775,275
                                                                                                 42
                                                                 BUSINESS PLAN FORMIXED USE BUILDING
Income       before    13,035,05       14,643,569         16,380,679 18,055,279           20,145,379 22,184,667           24,705,145      27,191,888 30,232,314 33,262,446
Depreciation    and
interest               9
Less: interest 448,658.00 448,658.00 448,658.00 448,658.00 448,659.00 448,660.00 448,661.00 448,662.00 448,663.00 448663
Income       before    12,586,401      14,194,911         15,932,021      17,606,621      19,696,720      21,736,007      24,256,484      26,743,226      29,783,651      32,813,783
Depreciation
Less: Depreciation     0.00            0.00               667,449         667,450         667,451         667,452         667,453         667,454         667,455         667,455
Profit /Loss Before    12,586,401      14,194,911         15,264,572.00   16,939,171.00   19,029,269.00   21,068,555.00   23,589,031.00   26,075,772.00   29,116,196.00   32,146,328.00
Tax
Less: Tax (30%)        3,775,920.30    4,258,473.30       4,579,371.60    5,081,751.30    5,708,780.70    6,320,566.50    7,076,709.30    7,822,731.60    8,734,858.80    9,643,898.40
Net Profit or Loss     8,810,480.70    9,936,437.70       10,685,200.40   11,857,419.70   13,320,488.30   14,747,988.50   16,512,321.70   18,253,040.40   20,381,337.20   22,502,429.60
After Tax
                                                                                              43
                                   BUSINESS PLAN FORMIXED USE BUILDING
                                                      44
                                                                  BUSINESS PLAN FORMIXED USE BUILDING
1 2 3 4 5 6 7 8 9
                                                                    -                                          -                 -
183           -                    -                                          -                                                               -                      -
                                                                                              45
                                                     BUSINESS PLAN FORMIXED USE BUILDING
Long-term        24,158,528
                                 0            0
Loan
Inflow                           17,158,850   18,914,335    20,805,769   22,642,409   24,906,650      27,128,986   29,841,884   32,530,910   35,784,000   39,037,721
Operations
Sales revenue 0 17,158,850 18,914,335 20,805,769 22,642,409 24,906,650 27,128,986 29,841,884 32,530,910 35,784,000 39,037,721
TOTAL            34,512,183      17,158,850   18,914,335    20,805,769   22,642,409   24,906,650      27,128,986   29,841,884   32,530,910   35,784,000   39,037,721
INFLOWS
OUTFLOWS
 Investment      34,512,183
cost                             0            0            0             0            0               0            0            0            0            0
Operating cost       0           4,123,791    4,270,766    4,425,090     4,587,130    4,761,271       4,944,319    5,136,739    5,339,022    551,686      5,775,275
Financing
Cost
  · Principal        0           0            0            0             3,451,218    3,451,218      3,451,218     3,451,218    3,451,218    3,451,218    3,451,218
  ·Interest          0           448,658      448,658      448,658       448,658      448,658        448,658       448,658      448,658      448,658      448,658
Income Tax           0           3,775,920    4,258,473    4,579,371     5,081,751    5,708,780       6,320,566    7,076,709    7,822,731    8,734,858    9,643,898
TOTAL            34,512,183
                                 8,348,369    8,977,897     9,453,119    13,568,757   14,369,927     15,164,761    16,113,324   17,061,629   13,186,420   19,319,049
OUTFLOWS
                                                                               46
                                      BUSINESS PLAN FORMIXED USE BUILDING
NET CASH        0
                    8,810,481   9,936,438    11,352,650   9,073,652    10,536,723   11,964,225   13,728,560   15,469,281   22,597,580    19,718,672
FLOW
BEGINNING
CASH        0       0           8,810,481    18,746,919   30,099,569   39,173,221   49,709,944   61,674,169   75,402,729   90,872,010    113,469,590
BALANCE
ENDING
CASH        0       8,810,481   18,746,919   30,099,569   39,173,221   49,709,944   61,674,169   75,402,729   90,872,010   113,469,590   133,188,262
BALANCE