Jamal - Mixed Farm
Jamal - Mixed Farm
DEVELOPMENT
PROJECT PROPOSAL
                              Sepember, 2023
                            Dire dawa, Ethiopi
       TABLE OF CONTENTS
   1. EXECUTIVE SUMMARY
 The specific area proposed for the establishment of this project in Dire
 Dawa administration specifically in Asaliso. The required land for this
 project is 50Ha.
nationals and will generate Birr 1,029,935 average annual income for
the project with both internal and external environments and its strong
                                                                              Page 2
    viable, socially desirable financially liquid and technically feasible at large.
proposal to the dire dawa administration to acquire the required Land for
this project.
2. INTRODUCTION
    Despite the fact that, the significant role the private sector would play in
    promoting national and regional development in the past few decades in
    Ethiopia, the prevailed policy environment that has highly discouraged
    the participation of private investors both foreign and domestic was made
    the potential to be far from relaxation. This has resulted in hindering
    national and regional socio-economic progress in almost all sectors of the
                                                                                       Page 3
economy revealing the existing low productive capacity of the economy
and significant socio economic losses in various dimensions.
Recognizing the extent to which the past policy environment has highly
impeded the development of the national economy and the necessity to
promote private sector participation in various of investment ventures
that are believed to be ,more rewarding and compatible with me current
national and regional development objects and priorities the new
investment policy in the country has open the wider opportunity for
private sector participation.
Based on this, at present the private sector has started to mobilize and
invest their knowledge and financial resources in various investment
activities, which they assumed to be beneficial for them and to the
country.
                                                                              Page 4
by Proclamation No. 416/2004. The city is divided into 9 Kebeles that are
the lowest administrative units. The Administration is executing and
implementing its municipal and state functions though its formally
established institutions. Therefore, it is facilitating, supporting and
enabling the investment and development initiative of the administration
through its institutions and related legal and organizational instruments.
The general demographic situation of Dire Dawa City shows that there is a
fast population increase both from natural and migration causes. The
prospect for the speeding-up of the momentum of the population growth
of the city in the future is also higher as the size of the young age
population at present dominates its population structure. The total
population of Dire Dawa Administration, as of July 2011, was projected to
be 377.000. From this, the population of the urban was projected to be
256,774, in the same year.
The availability of well developed infrastructure and fair priced land are
among the conductive climate of investment opportunities in the city.
Telephone,   road,   power   and   waste   disposal   systems   are   major
infrastructural provision of the city. The city also has land resource which
                                                                               Page 5
can be accessed for investment activities in the inner parts and expansion
zones of the city.
Road: Dire Dawa Administration has about a total road length of 346.24
km with different hierarchy and types and extended to different parts of
the city. From this 249.9 km is gravel, 56.94 km coble stone and 39.40 km
asphalt road of different standards. Other than this, the city is connected
to surrounding regions, other parts of the country and neighboring
countries with gravel and asphalt roads. Therefore, the area is internally
and externally accessible and has proper links.
                                                                                 Page 6
Electricity: The major source of Dire Dawa city electricity supply is the
connected lines of the national grid system. According to According to
Dire Dawa Administration Statistical Abstract (2011), there are 25066
private, 259 industrial, 338 government and 3613 commercial customers
of electric from Dire Dawa substation. Based on the 200m2 transformer
coverage assumption, the total coverage of electricity in the built up area
of the city is estimated 53.3 %. The inner part of the city has more access
than the expansion areas. As this project will be established in the vicinity
of city, power access will be better, from connected line.
                                                                                Page 7
 Currently the unemployment rate of Dire Dawa City is estimated at 22.9
 %. This includes educated unemployed too. Therefore, the job seeker has
 significant number. On the other hand there are numerous public and
 private training centers engaged in offering different short and medium
 term technical trainings.
business lines. He has very good entrepreneur skills and long year of
the nation and the city, Dire Dawa. The promoter in its part believes that
to participate in Modern Mixed Farm in Dire Dawa city and hence there
environment are vital for a country to attract private investors. The very
fact that Dire Dawa Administration is well endowed with easily available
ground water and have land suitable for the feed for animal fattening,
                                                                                 Page 8
horticulture and dairy farm. Furthermore the presence of demanding
market for finished (fattened) animals and dairy farm in the Middle East
Currently, the federal democratic republic of Ethiopia paves the way for
                                                                               Page 9
The general objective of this project is to establish mixed farm in Dire
Dawa Administration to generate profit, and creating job opportunity to the
society those who are living within the Administration.
                                                                              Page 10
and fattening farms project is purely a private one intended to give service
to those consuming these products in Households, hotels, restaurants,
tearooms, bars, and other private and public organization.
There is a clear indication the consumption of milk by urban population is
growing from time to time. Based on understanding the establishment of
dairy farm is planned. There is also an increasing demand for milk and
fattening animals in the urban center, restaurants, for meat. The total land
area required for the implementation of this project estimated around 20
hectare.   This   land   will   be   gained   through   leased   policy   of   the
administration.
6.2 Horticulture farm
6.2.1 Production management
 Crop rotation: - Better results could be achieved by rotating a given
     crop between two or three farm plots. It is recommended that the
     same or closely related crops should not be planted on the same
     ground. This will not only deplete the soil, but also favor the build-up
     of diseases and insects on that particular crop. Crop rotation is
     equally important for fruit crops. As a general recommendation the
     land should be cropped with a vegetable rotation following a fruit
     crop for minimum period of 3 years before any fruit crop is replanted.
 Irrigation water application method selected: - Without irrigation
     application vegetable production would be impossible for the area
     like Dire Dawa Administration especially during the months of
     October to March where the dry spell reach the temperature. Even
     during the rainy seasons of April to September, dry periods of two to
     three weeks are common where the soil moisture drops below field
     capacity which calls for supplementary irrigation while it is vice versa
     for the deep rooted crops. Heavy irrigation will be applied once a
     week for deep rooted crops while two to four times light irrigation per
     weeks is recommended for shallow rooted crops. Furrow and basin
                                                                                     Page 11
    irrigation are the two common methods of irrigation water application
    to the fields. Basin irrigation is more practical and applied to fruit
    trees such as papaya, Banana, and Orange. Smaller size basin will be
    applied which facilitate efficient utilization of the available water as
    per sandy loam nature of the project area soil. This will help to
    minimize deep percolation losses in reducing operational cost and
    increases irrigation efficiency.
Weeding: - The principal purpose of cultivation is control of emergence
    and overwhelming weeds. These weeds are harmful which complete
    with the crops for water, and nutrients. The result of this competition
    is fully reflected on the productivity of the crop, its quality and
    appearance to win market demand. In addition, weeds often carry or
    harbor diseases and insects. So early and timely shallow cultivation
    to control weeds is considered to be one of the important cultural
    practices, Applying cultural practices at most is preferred to minimize
    environmental counter effect of chemical application protection
    methods.
Disease and insect control: - There are many diseases and insects that
    attack fruits. Some of these diseases and insects are specific only to
    one crop type while others may attack several crops. Therefore
    control measures would be practiced to keep on the effects of
    disease and insects. Some of the control practices include crop
    rotation, destruction of infested plants and residues, use of resistant
    varieties and spraying and dusting with fungicides and insecticides.
Planting System: - Direct sowing and transplanting from nursery will be
    the two major planting systems that would be applied based on the
    requirements of each horticultural crop.
a. Direct Seedling: from the already selected vegetable crops carrot and
  tomato will be grown to maturity from the seeds planted in the field.
  The depth of seedling varies according to soil type, size of the seed and
                                                                               Page 12
  moisture status of the soil. Thinning of seedlings is an important
  operation in the direct seedling method of establishing stands.
b. Trans-Planting: transplants are raised in the nursery with the two
  common methods, i.e. bare root on seedbed and in plastic tubes of
  different size as per the soil nutrient condition and the plant
  physiological characteristics. Where bare root seedlings produce the
  first two leaves vigorous once are identified at a spacing of 15-20 cm
  with application of thinning practice. Plastic tube seedlings will be
  applied for crops that are difficult to transplant bare root such as seeds
  of high value ex. “Solo” papaya.
c. Harvest and post harvest practices: these are fully considered in
  this project study to minimize the problem poor quality product and
  short life storage of the crop. To ensure the product meets market
  requirements in general and export in particular this practice should be
  part and parcel of the farm management irrigation production with
  handling within the farm and during transportation. Mechanical
  damage, physical and physiological changes frequently pre-dispose the
  products to attack. Hence, poor quality product will imply failure to
  meet the requirements and loss reliability from the customers and
  finally will be put out of the market. The following are factors
  considered to improve product handling of the farm.
                                                                                Page 13
       Temperature management of the particular crops as per their
        physiological requirements in addition to market.
       Based on the above necessary requirements the farm had the
        facilities of refrigerated room, skilled man power to follow the pre
        and post harvest standards and refrigerated transportation to the
        destination market of the perishable crops.
Horticulture cost
                          Project Years
N   Description           1     2     3     4     5     6     7     8     9       10
o
    Purchase         of
1   vegetable seeds 260         290   320   320   370   370   370   370   370     370
    Purchase         of
2   fruit seeds           300   300   340   370   370   370   370   370   370     370
    Purchase         of
3   chemicals/fungi       240   240   240   280   280   320   320   320   320     320
    cide              ,
    insecticide
4   Miscellaneous         950   950   950   950   950   140   140   140   140     140
                                                        0     0     0     0       0
                          175   178   185   192   197   246   246   246   246     246
    Total                 0     0     0     0     0     0     0     0     0       0
                                                                                Page 14
The specific area proposed for the establishment of this project is in Dire
Dawa where there is suitable land for this project. The promoter of this
investment project to be forwarded to the dire dawa Investment office to
acquire required License for this project.
The specific area proposed for the establishment of this project in Dire
Dawa administration specifically in Asaliso. The required land for this
project is 50Ha.
                                                                               Page 15
resources and satisfy the needs and requirements of customers would
definitely lead to failure planned business objectives. The argument which
states that there is no bad business but bad management clearly defines
the roles and significances of organization and management. Under
normal condition every manager needs his or her company to be
profitable, competitive and maintain leadership position. To successfully
achieve the above ambitions of managers, attainment of management
efficiency and effectiveness is a must. To this effect existence of sound
organization and management capacity has found out to be an important
tool.
Analysis if fundamental aspects of optimal organization and organizational
capacity assessment tools and procedures reveal that; existence of clearly
identified and defined company vision, Missions, Values, Short nad long
term objectives including the following are among major indicators of
sound organization and management.
     Existence of shared understanding among company stakeholders
     Existence of compatibility of company missions with company
        organizational structure
     Existence of fully staffed and operational organizational structure
     Existence of clearly identified and defined lines of authority,
        responsibility, lines of communications and guide lines.
     Existence of clearly identified and defined administrative and
        working systems procedures and guide lines
     Existence     of   leadership,   management   and   supervisory   skills,
        experience and capabilities.
     Existence of adequate and desirable professional, technical and
        other support staff etc.
Business processes are central to the functioning of an organization. Yet,
they have been neglected for a long time in managerial studies mainly due
to the fact that departments in companies are structured in a functional or
                                                                                  Page 16
product   oriented    way.      Many    companies,   under     business     process
improvement are breaking away from this type of organizations and intend
to establish process based organizations in order to cope with the
increasing complexity and dynamics of the economic environment.
To   distinguish   process      based   organizations   from     other     types   of
organizations it is essential to start with the definition of business process.
Davenport (1993, p.5) defines a business process as <<... a structured,
measured set of activities designed to produce a specific output for a
particular customer of market>>. Hammer and champy (1993, p.35)
defines. <<... a business process as a collection of activities that takes
one or more kinds of input and creates an output that is of value to the
customer>>.
                                                                                        Page 17
structured the same shortcomings o functionally organized companies are
applicable on the business level of product-based companies.
Based on the above basic principles and procedures the A.S.K International
P.L.C Business Centre real estate development project workflow process
has planned to be organized and managed.
A Operations Core Process
The parking and garage, the shopping, offices and hall rental day to day
operations shall be carried out by operations/ customer core process. The
operations core process shall have retail customer group, corporate
customer group, engineering and technology group and treasury group.
B. Development Core Process
The development core process shall be entrusted in creating fertile
ground, designing and developing systems and strategies which would
help the company to expand business development horizons, markets,
customers etc. Accordingly, this core process shall have the following
business groups
     Research and development group
     Business development group
     Market new and development group
     Systems and strategies design and development
C Support and Control Core Process
The support and control core process shall be responsible to provide
necessary inputs, facilities enabler and related support to the operations
and development core process and ensures the validity of their
performance against pre-planned budget and use of resources, etc at
large. Accordingly, the support core process shall have the following major
business groups.
                                                                              Page 18
      Human resources and personnel mgt group
      Finance and accounts mgt group
      Materials, property and logistics mgt group
      Supervision and control business group
                                                                            Page 19
      responsible to monitor, control support and facilitate the individual and
      team efforts of all core process staff
      C Supervisory MGT level
      There shall be three supervisory management level operations, marketing
      and business development, support and control core process heads/team
      leaders. The supervisory level managers shall be reporting to the general
      manager
      Each supervisory level manager shall be responsible to plan, coordinate
      and control the activities, resources; process and output of his/her
      respective core process in an efficient, effective and economical manner.
Promoters
G.M
SEC
                                                                                  Page 20
Page 21
     8. PROJECT COST ESTIMATES
                                                                               Page 22
Machinery and Equipment
The total cost of machinery and equipment is estimated at Birr 4,000,000. Detailed
list of machinery and equipment is given below.
List of Machinery and Equipment requirement
    No        Description                     Unit   Qty   Unit        Total cost
                                                           cost
      1.      Truck       (130    quintal No               250,000
              capacity)                                                   500,000
      2.      Medical equipment’s             No            1,861,0
                                                                  00      722,000
      3.      Electric             power No                 1,756,0
              generator                                           00    1,048,000
      4.      Submersible motor               No           785,000        570,000
      5.      Feed mixer                      No            1,780,0
                                                                  00    1,560,000
      6.      Milling machine                 No           950,000      1,040,000
               Total cost                                               4,000,000
                                                                                    Page 23
Installation cost
           N    Description                                             Total cost
           o
           1    Electric installation                                    133,200
           2    Telephone line installation                               25,000
           3    Fax line installation                                       8000
           4    Internet line installation                                  9,250
                Water line installation                                   35,500
                Total cost                                              210,950
                                                                                     Page 24
  12     Guard                        2                        900           10,800
  13     Daily labourer               20                     10400          124,800
         Total                        45                 34,800         417,600
         Employees’        Benefit                           3,480           41,760
         (10% of Salary)
         Grand Total                                     38,280         459,360
Training Requirement
                                                                                        Page 25
                                                     expenses
 Installation 232,286
                                                                   Page 26
            Employee salary &wages                                 131,400
1. Asset
2. Liability
     Current Liability-------------------------------------------------
                                                                                Page 27
     Long term liability --------------------------------------------3,700,000
3. Capital
                                                                                  Page 28
                                                           10,880,0     15,232,      21,324,8
                                                                   00         000             00
                                                           1             2               3
       Total Revenue                           25,280,0         35,392,00     53,580,80
                                                          00             0               0
       Sales tax                                 505600            707840       1071616
       Net Revenue                            24,774,40
                                                           0   34,684,160     52,509,184
       Less: Operational Expenses
              land lease                         74,400           74,400            74,400
              Employee salary and               459,360
               wages                                              505,296            81,840
              Training payment                  300,000          330,000           555,826
              Utilities expenses                235,000          258,500           363,000
              Cost of Raw material           2,001,880         2,202,068           284,350
              Others                            137,314          151,045      2,422,275
              Depreciation                   3,002,125         3,002,125      3,002,125
       Total Expenses                         6,210,079         6,523,434      6,783,816
       Gross profit                           18,564,32
                                                           1   28,160,726     45,725,368
       Income tax 35%                         6497512.3                        16003878.
                                                           5    9856254.1                8
       Net Profit                             12,066,80
                                                           9   18,304,472     29,721,489
                                                                                              Page 29
 12.         Depreciation
No   Description          Original        Method         Expect      Annual
                          value                          ed life    depreciati
                                                                        on
     Building &            9,850,00 Straight line        30
     construction                  0                     years
                                                                        328333
                           38,860,0 Straight line        15
                                  00                     years         2590666
     Office furniture’s     665,000 Straight line        8 years         83125
     Total
     depreciation                                                    3,002,125
The proposed project has no environmental impact rather this type of investment
project could help to mitigate the environment in general and climate of the
project area in particular. Thus, this is an environmental friendly project that will
contribute much for the improvement of the environmental through using modern
technology. The project location is also ideal for the disposal and treatment of
wastes and the promoter is prepared to be a minimum polluter and environmental
friend through providing incentive to local people to grow seedling and manage
accordingly. On the other hand the positive social impact of the project on the
society is significant. The project creates employment opportunities for 45
peoples.
14. PROJECT IMPLEMENTATION STRATEGY
 14.1 Project Formulation and Establishment
A. exchange of views and creating shared understanding
                                                                             Page 30
The project proposal and strategic planning management document shall be
distributed to all potential stakeholders such as concerned members of the family,
government institutions and to selected financer with a view of creating satisfactory
exchange of views and promote shared understanding in advance.
B. Determination of establishment phase target activities
During the project formulation and establishment phase, the following major tasks
are required to be successfully accomplished.
Registration, licensing and acquisitions of operations commencement authorization
Acquisitions of construction permits
Preparation of every legally required document
Appointment of strong and capable implementation team
C. Promotion and Fund Raising
To prepare promotional strategic planning mgt guidelines
To prepare promotional ideas, materials, logistics and facilities
To conduct promotional tasks and build strong constituency of support
To evaluate the process of promotion and progress
To prepare fund raising strategic planning guideline
To assess and identify major project donors
To assess and identify the interests, rules, regulations and conditions of targeted and
prioritized financers
To prepare all necessary requirements of financers and apply for fund
To undertake follow ups and secure fund
D. Organizational Builds up
Establishing and organizing project office
Preparing project working and administrative systems and procedural guidelines
Commissioning construction
Purchase of all on and off site durable and consumer goods
Staff recruitment, orientation and employment
To conduct pre operational trial runs, checking the validity of all activities
                                                                                 Page 31
  14.2 Budgeting Implementation strategy
  A. Budgeting concept Definition
  The   realization     of    any   strategic   decision   needs   proper   identification   and
  understanding       of     project   objectives,   and   necessary    activities.   Moreover,
  determination of time phase out process and resources to the completion of each
  task which calls for budget making process and existence of effective strategic
  budgeting is a key implementation strategy for the success of project objectives. In
  consideration to the significance of sound budgeting system and procedures, it has
  been selected and proposed as one of the best implementation strategy.
  There is no doubt that the internal and external activities, resources, process and
  output of any organization should be managed effectively and efficiently. To attain
  short and long term objectives of the project the management must chart the entire
  tasks in advance in a comprehensive and coordinated manner. A budget is a
  comprehensive and coordinated plan expressed in financial term for the operation
  and resources of a project for some specific period in the futures. A budget is the
  plan of project’s expectation in clear & formal terms to avoid confusion and to
  facilitate their attainability. Thus the roles and significances of budgeting are;
 To state the project’s expectation in clear and formal terms, to avoid confusion and to
  facilitate their attainability
 To communicate expectation to all concerned
 To provide a detailed plan of action for reducing uncertain and proper direction of
  institutional group and individual efforts
 To provide a means of measuring and controlling performance
 To coordinate all institutional, group and individual efforts towards the success of
  project objectives.
                                                                                      Page 32
Sales budget
Operations budget
Financial budget
Capital budget
Statement of Smart objectives and goals is probably the starting point and pace
maker for all other types of budgets. The sources of sound project objectives/goals
are again the internal and external environments. Analysis of the patterns of project
internal and external environments, pinpointing project opportunities and challenges
with a focus on the demand for the project services, existence of external
opportunities and internal capabilities, it is pertinent to define project objectives and
goals in clear and formal terms at the outset.
The objectives and goals of any project emanate the operations, financial and capital
budget needs. The project corporate level objectives and goals, operations and
capital budgets are required to be further apportioned for all core process which
together form corporate budget.
The process of setting sound budget is a complex and complicated process, because
of the involvement of various factors in it. However, budget setting process starts
with the determination of limiting factors at the outset. The most important project
limiting factors are,
The demand for the project services
The economic life of the project
Existence of factor and non factor inputs
External opportunities supporting the project ideas and internal capabilities to
establish, operate, manage and control etc are some among others. Based on the
above limiting factors, the first step of budget setting process starts with definitions
and establishment of project basic objectives and goals
Second step: at this stage, it is necessary to identify and describe all on and off site
activities necessary to successful achievement of stated objectives and goals,
determination of logical sequence of activity execution process, time phase out to
complete each task in clear and unambiguous terms. Third step: at this stage, it is
                                                                              Page 33
   very important to assess identify and define the resource needs of all activities,
   measure, quantify and state in clear and formal terms.
   Fourth step
   Group all activities according to their similarities
   Establish major budget centers
   Allocate the resources required to major and sub budget centers
   Prepare objectives/goals, operations, financial and capital budgets at corporate, core
   process and sub process and assign centre of responsibilities
   B. ESSENTIALS OF BUDGET MGT
   To make the objectives and purposes of budgets productive and positive impact
   generating we propose the following budget administration. It should be well
   recognized that corporate and functional levels budgets are prepared by line
   executives while the organization and implementation of budgeting is a staff
   function. Joint efforts of all line execution and a staff function in the preparation,
   administration organization and implementation of budgeting should be done in a
   coordinated manner. To this effect there should exist the following systems of budget
   administration.
   The budget committee consists of all members of the management committee which
   bring together all activities of different project functional unites.
   The primary function, of the budget committee is to decide on the general policies of
   the project and directs all project functional unites to prepare their respective
   budgets.
   Budget director/officer
                                                                              Page 34
 To undertake satisfactory exchanges among all project concerned stakeholders on
   budgets and budgeting
 To educate all concerned on budget and budgeting
 To undertake monitoring evaluation and control activities
 To prepare periodic or extra ordinary budgeting reports
 To disseminate the feedbacks of budgetary monitoring and evaluation to all concerned
   stakeholders
 To suggest sound and workable recommendations for immediate corrective measures
   Budget manual
   The budget manual is a written set of instruction which serves as a rule book and
   reference for the implementation of a budget.
                                                                                Page 35
  Existence of, sound, and appropriate, indicators, which show, the success/ failure, of
  the planned objective outcome, output and inputs used.
  Appropriate source and means of verifying that the planned, objective outcome,
  output and inputs were in accordance with/ deviated from the planned
  Clearly stated important assumption with/without which the planned objective
  would/would not be successful.
  The role and significance of monitoring evaluation and control are briefly described
  as follows.
 Monitoring
                                                                             Page 36
  internal and external resources for better future. Thus, an integrated monitoring and
  evaluation system in a single whole enables organizations optimally benefit from
  available resources through satisfaction of existing and potential customers in their
  best interests.
  The monitoring evaluation and control system should be designed to serve both the
  strategic and operational phases. The monitoring evaluation and control system
  designed for both strategic and operational phases are described as follows.
  This is a continuous and systematic monitoring evaluation and control of the validity
  of basic assumption under which it operates. Thus, a regular and continuous
  proactive check against the validity of planned strategy aimed at changing or
  improving the condition of vital assumption.
  Performance management and control is a managerial process of designing          and
  developing sound indicators parameters means and sources of verifications
  necessary to measure activities resources, process and output of individuals, groups
  and institutions against   the targeted standards and come up with logical results
  which would help to make sound decisions. Although there are numerous areas
  whose performance are needed to be well managed and control, the most important
  areas and performance management indicators used in laundry and dry cleaning
  business are briefly identified and described as under.
  Operational control strategy is designed to guide monitor and evaluate the progress
  of all planned activities against their respective planned objectives as in meeting
  targets representing the planning horizon. Accordingly, all planned activities shall
  have the following basic system to be used as a monitoring evaluation and control
  mechanisms.
      Components of narrative description
 Objectives
 Outcome
 Output
 Input
  Indicators that show
                                                                             Page 37
     Objectives have been achieved
     Planned outcome has been attained
     Desired output has been obtained
     Input are properly allocated and employed in all terms
   Relevant means and source of verification shall be clearly identified and employed
   accordingly;
 Strategic planning documents
 Audit report
 Field visit and on site survey
 Past data etc shall be used
                                                                                   Page 38
  satisfaction. To do this it is pertinent to understand the dynamics of project realities
  in the changing world. To change the workflow process to desirable small scale the
  following implementation strategy are proposed.
 To undertake a detailed task analysis and determine the condition, process and time
  phase out for each task.
 To determine the resource requirements availability quality magnitude and cost
 Determination of technology and system requirements
 Determination of skill, profession and experience requirement
 To design and develop strategic fit and incorporating human resources into system
  integration
 Acquisition of top management support.
  Organizational culture change implementation strategy
                                                                               Page 39
 Promotion of employee career and skill development operational plan
 Avoiding under/over employment
 Promotion of transparent, accountable and non discriminatory data based decision
  making practices
 Provision of clearly defined job description, evaluation, lines of authority and
  responsibilities as well as lines of communication and information flows.
 Provision of management and leadership support and guidelines.
Page 40