Bom
Bom
1 LOT 3-7
LOCATION: MALAGASANG 2 - IMUS, CAVITE
WORK ITEM COST ESTIMATE SHEET
A. MATERIALS
DESCRIPTION/PARTICULARS UNIT QTY UNIT COST AMOUNT TOTAL AMOUNT
A. MATERIALS
DESCRIPTION/PARTICULARS UNIT QTY UNIT COST AMOUNT TOTAL AMOUNT
A. MATERIALS
DESCRIPTION/PARTICULARS UNIT QTY UNIT COST AMOUNT TOTAL AMOUNT
A. MATERIALS
DESCRIPTION/PARTICULARS UNIT QTY UNIT COST AMOUNT TOTAL AMOUNT
A. MATERIALS
DESCRIPTION/PARTICULARS UNIT QTY UNIT COST AMOUNT TOTAL AMOUNT
Reinforced Concrete Wall ( 1st Floor & 2nd Floor) 64.19 cu.m
A. MATERIALS
DESCRIPTION/PARTICULARS UNIT QTY UNIT COST AMOUNT TOTAL AMOUNT
2.03 cu.m
Gate Post 0.43 cu.m
Concrete Precast Mould 1.599
A. MATERIALS
DESCRIPTION/PARTICULARS UNIT QTY UNIT COST AMOUNT TOTAL AMOUNT
A. MATERIALS
DESCRIPTION/PARTICULARS UNIT QTY UNIT COST AMOUNT TOTAL AMOUNT
A. MATERIALS
DESCRIPTION/PARTICULARS UNIT QTY UNIT COST AMOUNT TOTAL AMOUNT
A. MATERIALS
DESCRIPTION/PARTICULARS UNIT QTY UNIT COST AMOUNT TOTAL AMOUNT
SUB-TOTAL
D. DIRECT COST 146,883.05
ITEM QUANTITY 102.69 cu.mOCM 14,688.31
CONTRACTORS PROFIT 22,032.46
VALUE ADDED TAX 17,625.97
TOTAL COST 201,229.78
UNIT COST 1,959.58
ADJUSTED UNIT COST 1,959.60
CORRECTED TOTAL COST 201,231.47
PROJECT TITLE: HAMILTON EXECUTIVE RESIDENCES BLK. 1 LOT 3-7
LOCATION: MALAGASANG 2 - IMUS, CAVITE
WORK ITEM COST ESTIMATE SHEET
A. MATERIALS
DESCRIPTION/PARTICULARS UNIT QTY UNIT COST AMOUNT TOTAL AMOUNT
ROOF FRAMING
50MM x 150MM x 1.2mm thk.C-PURLINS pcs 59 375.00 22,125.00
50MM x 100MM x 0.8mm thk.C-PURLINS pcs 5 300.00 1,500.00
2"x3" C Purlins x 6m pcs 12 564.00 6,768.00
10 MMØ Sag Rod (typical) x 6m pcs 8 98.00 784.00
SUB-TOTAL 31,177.00 31,177.00
B. LABOR
NO. OF NO. OF
PERSONNEL/CREW UNIT RATE AMOUNT TOTAL AMOUNT
CREW DAYS
SUB-TOTAL
D. DIRECT COST 71,977.00
ITEM QUANTITY 442.90 sq.m
OCM 7,197.70
CONTRACTORS PROFIT 10,796.55
VALUE ADDED TAX 8,637.24
TOTAL COST 98,608.49
UNIT COST 222.64
ADJUSTED UNIT COST 222.70
CORRECTED TOTAL COST 98,633.83
PROJECT TITLE: HAMILTON EXECUTIVE RESIDENCES BLK. 1 LOT 3-7
LOCATION: MALAGASANG 2 - IMUS, CAVITE
WORK ITEM COST ESTIMATE SHEET
A. MATERIALS
DESCRIPTION/PARTICULARS UNIT QTY UNIT COST AMOUNT TOTAL AMOUNT
SUB-TOTAL
D. DIRECT COST 19,996.00
ITEM QUANTITY 8.16 sq.m
OCM 1,999.60
CONTRACTORS PROFIT 2,999.40
VALUE ADDED TAX 2,399.52
TOTAL COST 27,394.52
UNIT COST 3,357.17
ADJUSTED UNIT COST 3,357.20
CORRECTED TOTAL COST 27,394.75
PROJECT TITLE: HAMILTON EXECUTIVE RESIDENCES BLK. 1 LOT 3-7
LOCATION: MALAGASANG 2 - IMUS, CAVITE
WORK ITEM COST ESTIMATE SHEET
A. MATERIALS
DESCRIPTION/PARTICULARS UNIT QTY UNIT COST AMOUNT TOTAL AMOUNT
SUB-TOTAL
D. DIRECT COST 186,452.87
ITEM QUANTITY 356.31 sq.m
OCM 18,645.29
CONTRACTORS PROFIT 27,967.93
VALUE ADDED TAX 22,374.34
TOTAL COST 255,440.43
UNIT COST 716.91
ADJUSTED UNIT COST 717.00
CORRECTED TOTAL COST 255,474.27
PROJECT TITLE: HAMILTON EXECUTIVE RESIDENCES BLK. 1 LOT 3-7
LOCATION: MALAGASANG 2 - IMUS, CAVITE
WORK ITEM COST ESTIMATE SHEET
A. MATERIALS
DESCRIPTION/PARTICULARS UNIT QTY UNIT COST AMOUNT TOTAL AMOUNT
SUB-TOTAL
D. DIRECT COST 228,930.00
ITEM QUANTITY 1.00 lot OCM 22,893.00
CONTRACTORS PROFIT 34,339.50
VALUE ADDED TAX 27,471.60
TOTAL COST 313,634.10
UNIT COST 313,634.10
ADJUSTED UNIT COST 313,634.10
CORRECTED TOTAL COST 313,634.10
PROJECT TITLE: HAMILTON EXECUTIVE RESIDENCES BLK. 1 LOT 3-7
LOCATION: MALAGASANG 2 - IMUS, CAVITE
WORK ITEM COST ESTIMATE SHEET
A. MATERIALS
DESCRIPTION/PARTICULARS UNIT QTY UNIT COST AMOUNT TOTAL AMOUNT
Powder Coated Sliding &Fixed Window (1.2 m x 1.4 m) pcs 5 6,442.00 32,210.00
Powder Coated Sliding &Fixed Window (1.0 m x 1.2 m) pcs 5 2,588.00 12,940.00
Powder Coated Sliding &Fixed Window (1.2 m x 1.0 m) pcs 10 2,588.00 25,880.00
Powder Coated Swing &Fixed Window (1.5 m x 2.0 m) pcs 5 1,211.72 6,058.60
Powder Coated Awning Window (0.4 m x 0.6 m) pcs 7 3,377.00 23,639.00
Powder Coated Sliding &Fixed Window (0.4 m x 1.2 m) pcs 5 2,385.00 11,925.00
Powder Coated Sliding &Fixed Window (1.2 m x 1.2 m) pcs 8 2,598.00 20,784.00
Powder Coated Awning &Fixed Window (1.2 m x 0.6 m) pcs 2 3,377.00 6,754.00
SUB-TOTAL
D. DIRECT COST 142,290.60
ITEM QUANTITY 1.00 cu.m OCM 14,229.06
CONTRACTORS PROFIT 21,343.59
VALUE ADDED TAX 17,074.87
TOTAL COST 194,938.12
UNIT COST 194,938.12
ADJUSTED UNIT COST 194,938.20
CORRECTED TOTAL COST 194,938.20
SUB-TOTAL
D. DIRECT COST 29,510.00
ITEM QUANTITY 1.00 cu.m
OCM 2,951.00
CONTRACTORS PROFIT 4,426.50
VALUE ADDED TAX 3,541.20
TOTAL COST 40,428.70
UNIT COST 40,428.70
ADJUSTED UNIT COST 40,428.70
CORRECTED TOTAL COST 40,428.70
PROJECT TITLE: HAMILTON EXECUTIVE RESIDENCES BLK. 1 LOT 3-7
LOCATION: MALAGASANG 2 - IMUS, CAVITE
WORK ITEM COST ESTIMATE SHEET
A. MATERIALS
DESCRIPTION/PARTICULARS UNIT QTY UNIT COST AMOUNT TOTAL AMOUNT
SUB-TOTAL
D. DIRECT COST 226,862.20
ITEM QUANTITY 221.17 cu.m
OCM 22,686.22
CONTRACTORS PROFIT 34,029.33
VALUE ADDED TAX 27,223.46
TOTAL COST 310,801.21
UNIT COST 1,405.26
ADJUSTED UNIT COST 1,405.30
CORRECTED TOTAL COST 310,810.20
PROJECT TITLE: HAMILTON EXECUTIVE RESIDENCES BLK. 1 LOT 3-7
LOCATION: MALAGASANG 2 - IMUS, CAVITE
WORK ITEM COST ESTIMATE SHEET
A. MATERIALS
DESCRIPTION/PARTICULARS UNIT QTY UNIT COST AMOUNT TOTAL AMOUNT
A. MATERIALS
DESCRIPTION/PARTICULARS UNIT QTY UNIT COST AMOUNT TOTAL AMOUNT
30mm² THHN WIRE lm 70.00 263.00 18,410.00
2mm² THHN WIRE lm 6.00 24.00 144.00
1mm² BARE CU. WIRE (Meralco Grounding) lm 9.00 60.00 540.00
8mm² BARE CU. WIRE (Meralco Grounding) lm 9.00 120.00 1,080.00
Utility Box pcs 66.00 30.00 1,980.00
Entrance Cap pcs 10.00 30 300.00
Electrical Tape pcs 20.00 30 600.00
PVC Electrical Conduit #1-1 /4" pcs 5.00 100 500.00
PVC Electrical Conduit #1 /2" pcs 105.60 40 4,224.00
PVC Electrical Elbow #1-1 /4" pcs 5.00 20 100.00
PVC Electrical Elbow #1 /2" pcs 111.00 10 1,110.00
Flexible Hose #1 /2 mtr 95.00 10 950.00
Square Box pcs 5.00 25 125.00
SUB-TOTAL 30,063.00 30,063.00
B. LABOR
NO. OF NO. OF
PERSONNEL/CREW UNIT RATE AMOUNT TOTAL AMOUNT
CREW DAYS
SUB-TOTAL
C EQUIPMENT
NO. OF UNIT NO. OF
EQUIPMENT RATE AMOUNT TOTAL AMOUN
EQPT. DAY/HR DAY/HR
SUB-TOTAL
D. DIRECT COST 30,063.00
ITEM QUANTITY 1.00 lot
OCM 300.63
CONTRACTORS PROFIT 4,509.45
VALUE ADDED TAX 3,607.56
TOTAL COST 38,480.64
UNIT COST 38,480.64
ADJUSTED UNIT COST 38,480.70
CORRECTED TOTAL CO 90,378.40
PROJECT TITLE: PROPOSED TWO STOREY RESIDENTIAL BUILDING
LOCATION: MALAGASANG 2 - IMUS, CAVITE
WORK ITEM COST ESTIMATE SHEET
SUB-TOTAL
C. DIRECT COST 151,670.00
ITEM QUANTITY 1.00 OCM lot 1,516.70
CONTRACTORS PROFIT 22,750.50
VALUE ADDED TAX 18,200.40
TOTAL COST 194,137.60
UNIT COST 194,137.60
ADJUSTED UNIT COST 194,137.60
CORRECTED TOTAL CO 294,448,497.92
PROJECT TITLE: HAMILTON EXECUTIVE RESIDENCES BLK. 1 LOT 3-7
LOCATION: MALAGASANG 2 - IMUS, CAVITE
WORK ITEM COST ESTIMATE SHEET
A. MATERIALS
DESCRIPTION/PARTICULARS UNIT QTY UNIT COST AMOUNT TOTAL AMOUNT
Twin Hi-Rib Longspan Roof 0.60mm 88 pcs. 683 60104 60104
Tekscrew 2 box 430 860 860
Vulcaseal 4 pcs. 110 440 440
SUB-TOTAL 61,404.00 61,404.00
B.
NO. OF NO. OF
UNIT RATE AMOUNT TOTAL AMOUNT
CREW DAYS
1 Tinsmith 2 700.000 1400 1400
2 Laborer 2 600.00 1,200.00 1,200.00
SUB-TOTAL
2,600.00 2,600.00
C. DIRECT COST 64,004.00
ITEM QUANTITY 236.58 lot OCM 640.04
CONTRACTORS PROFIT 9,600.60
VALUE ADDED TAX 7,680.48
TOTAL COST 81,925.12
UNIT COST 346.29
ADJUSTED UNIT COST 346.30
CORRECTED TOTAL CO 221,645.85
PROJECT TITLE: HAMILTON EXECUTIVE RESIDENCES BLK. 1 LOT 3-7
LOCATION: MALAGASANG 2 - IMUS, CAVITE
WORK ITEM COST ESTIMATE SHEET
A. MATERIALS
DESCRIPTION/PARTICULARS UNIT QTY UNIT COST AMOUNT TOTAL AMOUNT
Neutralizer 46 gal 422 19412 19412
Penetrating Sealer 46 gal 385 17710 17710
Flat Latex/Primer 110 gal 689 75790 75790
Wall Putty 92 gal 189.5 17434 17434
Semi-Gloss/Gloss Latex 110 gal 219.5 24145 24145
Sand Paper 20 pcs 18 360 360
Paint Brush 2" 4 pcs 15 60 60
Paint Roller 9" 6 pcs 50 300 300
Paint Tray 9" 6 pcs 153 918 918
Masking Tape 6 pcs 99 594 594
SUB-TOTAL 156,723.00 156,723.00
B.
NO. OF NO. OF
UNIT RATE AMOUNT TOTAL AMOUNT
CREW DAYS
15 Painter 22 537.000 11814 11814
SUB-TOTAL11,814.00 11,814.00
C. DIRECT COST 168,537.00
ITEM QUANTITY 1,374.98 lot OCM 1,685.37
CONTRACTORS PROFIT 25,280.55
VALUE ADDED TAX 20,224.44
TOTAL COST 215,727.36
UNIT COST 156.89
ADJUSTED UNIT COST 156.90
CORRECTED TOTAL CO 264,434.55
PROJECT TITLE: HAMILTON EXECUTIVE RESIDENCES BLK. 1 LOT 3-7
LOCATION: MALAGASANG 2 - IMUS, CAVITE
WORK ITEM COST ESTIMATE SHEET
A. MATERIALS
DESCRIPTION/PARTICULARS QTY UNIT UNIT COST AMOUNT TOTAL AMOUNT
Cement 121 bags 250.67 30331.07 30331.07
Screeened Sand 9.9 cu. m. 385 3811.5 3811.5
SUB-TOTAL 34,142.57 34,142.57
B.
NO. OF NO. OF
UNIT RATE AMOUNT TOTAL AMOUNT
CREW DAYS
2 Mason 25 947.000 47350 47350
3 Labor 25 645 48,375.00 48,375.00
SUB-TOTAL 47,350.00 47,350.00
C. DIRECT COST 81,492.57
ITEM QUANTITY 1,226.61 lot OCM 814.93
CONTRACTORS PROFIT 12,223.89
VALUE ADDED TAX 9,779.11
TOTAL COST 104,310.49
UNIT COST 85.04
ADJUSTED UNIT COST 85.10
CORRECTED TOTAL CO 69,350.18
PROJECT TITLE: HAMILTON EXECUTIVE RESIDENCES BLK. 1 LOT 3-7
LOCATION: MALAGASANG 2 - IMUS, CAVITE
WORK ITEM COST ESTIMATE SHEET
A. MATERIALS
DESCRIPTION/PARTICULARS QTY UNIT UNIT COST AMOUNT TOTAL AMOUNT
FIXTURES
Water Closet 15 set 5492 82380 82380
Shower Set 10 set 3,500.00 35000 35000
Lavatory Set 15 set 2,304.00 34560 34560
Kitchen Sink Set 5 set 4210 21050 21050
Floor Drain 20 pcs 304 6080 6080
SEWER & DRAINAGE
2 1/2" Ø PVCSP x 3m 22 pcs 250 5500 5500
3" Ø PVCSP x 3m 43 pcs 280 12040 12040
4" Ø PVCSP x 3m 25 pcs 350 8750 8750
4" Ø PVCDP x 3m 25 pcs 370 9250 9250
2 1/2"x3" Ø PVC Tee Reducers 5 30\ 120 600 600
4"x3" Ø PVC Tee Reducers 5 pcs 150 750 750
2"x3" Ø PVC Wye Reducers 15 pcs 200 3000 3000
4"x3" Ø PVC Wye Reducers 5 pcs 250 1250 1250
4" Ø PVC Pipe Tee 5 pcs 300 1500 1500
3" Ø PVC Pipe Tee 25 pcs 250 6250 6250
3" Ø PVC P-trap 10 pcs 180 1800 1800
2 1/2” Ø PVC P-trap 10 pcs 170 1700 1700
2 1/2" Ø PVC Pipe Coupling 2 pcs 50 100 100
3" Ø PVC Pipe Coupling 18 pcs 70 1260 1260
4" Ø PVC Pipe Coupling 20 pcs 100 2000 2000
3” Ø PVC Pipe 90º Elbow 30 pcs 80 2400 2400
4” Ø PVC Pipe 45º Elbow 25 pcs 120 3000 3000
3” Ø PVC Pipe 45º Elbow 5 pcs 100 500 500
4” Ø PVC Wye 25 pcs 250 6250 6250
3” Ø PVC Wye 5 pcs 200 1000 1000
4” Ø PVC Clean Out 20 pcs 300 6000 6000
3” Ø PVC Clean Out 25 pcs 250 6250 6250
PVC Solvent / Neltex 5 can 250 1250 1250
Epoxy A&B 2 can 450 900 900
Tapelon Tape 5 pcs 25 125 125
Vulcaseal 10 liter 200 2000 2000
Pipe Straps/Hangers 100 pcs 15 1500 1500
Rubber Gaskets/O-Rings 50 liter 150 7500 7500
WATERLINE
1/2” Ø PVC Pipe x 3m 33 pcs 86.9 2867.7 2867.7
3/4” Ø PVC Pipe Pipe x 3m 5 pcs 131.55 657.75 657.75
1/2” Ø PVC Pipe 90º Elbow 105 pcs 11.25 1181.25 1181.25
1/2” Ø PVC Pipe Tee 45 pcs 14 630 630
1/2” X3/4" Ø PVC Pipe Tee Reducer 10 pcs 8 80 80
1/2" Ø PVC Pipe Coupling 15 pcs 3.95 59.25 59.25
T
T