Audit - JS
Audit - JS
DETAILS OF AUDIT:
This audit is commissioned by Manager - EHS with Internal Auditor team of the company
and is carried out by a competent person who is well-versed with the audit
requirements. The detailed audit report shall be circulated to all concerned persons including the
top management.
AUDIT SCORE / QUERIES / CLOSURE REPORTS / NON-CONFORMANCE REPORTS:
Audit score is given on a scale of 0 - 5 for major elements & overall. Sub-elements are scored on scale
of 0-1-2-3-4 on the following matrix:
OVERALL AUDIT SCORE: ABOVE 4.00 (EXCELLENT), 3.50 - 3.99 (V. GOOD), 3.00 - 3.49 (GOOD),
2.50 - 2.99 (FAIR), 2.00 - 2.49 (POOR), BELOW 2.00 (VERY POOR)
INDIVIDUAL SUB-ELEMENTS: 0 - NO PROCESS IN PLACE, 1 - BASIC COMPLIANCE ONLY,
2 - PARTIALLY COMPLIED, 3 - COMPLIED BUT ROOM FOR IMPROVEMENT
4 - FULLY COMPLIED
(READ DETAILED SCORE SHEET TO SEE RELATIONSHIP BETWEEN SUB ELEMENTS, MAIN ELEMENTS &
OVERALL AUDIT SCORE DERIVED FROM ELEMENT SCORES)
NCs WILL BE ISSUED FOR ELEMENT SCORE: BELOW 2.00 (MAJOR NC) & BELOW 2.50 (MEDIUM NC)
2.50 to 3.00 WILL RATE AS "OBSERVATIONS"
●All queries relating to the audit report must be addressed to the sender of the report
●The auditee (Project Head / Deputy Project Head) must acknowledge receipt of the report and
send a closure report with evidence including photographs within two weeks or earlier
●All NCRs, as attached with the audit report (in Excel) must be closed with evidence within the stipulated
time mentioned against it. This part of the report must be completed by the auditee and sent to Manager-EHS
PROJECT DETAILS:
NAME OF PROJECT:
LOCATION:
TYPE:
PROJECT HEAD: EHS COORDINATOR:
DESIGNATION: DESIGNATION:
OTHERS:
AUDIT NO.
DATE/S OF AUDIT
AUDITOR/S:
DESIGNATION/S:
MAJOR CONTRACTORS & AGENCIES WORKING AT PROJECT & THEIR WORKFORCE:
(1) Contractor 1 0 (6) Contractor 6 0
(2) Contractor 2 0 (7) Contractor 7 0
(3) Contractor 3 0 (8) Contractor 8 0
(4) Contractor 4 0 (9) All others 0
(5) Contractor 5 0 (10) Client 0
G.T. 0
SCORE /
(WEIGHTAGE)
MAJOR AUDIT ELEMENTS: ELEMENT
1 STATUTORY & LEGAL COMPLIANCE 0.00% 7.09%
2 CLIENT'S EHS ADMINISTRATION & CONTROLS 0.00% 7.87%
3 CONTRACTORS' EHS MANAGEMENT 0.00% 5.51%
4 CONTRACTORS' EHS PLANS 0.00% 3.15%
5 OCCUPATIONAL HEALTH 0.00% 7.87%
6 LIFE SAVING RULES 0.00% 7.09%
7 HEIGHT WORK SAFETY 0.00% 11.02%
8 ELECTRICAL SAFETY 0.00% 7.87%
9 SCAFFOLDS & WORKING PLATFORMS SAFETY 0.00% 5.51%
10 LIFTING OPERATIONS SAFETY 0.00% 3.15%
11 HOUSEKEEPING 0.00% 6.30%
12 EMERGENCY RESPONSE 0.00% 9.45%
13 PERSONAL PROTECTIVE EQUIPMENT 0.00% 7.09%
14 PLANT & MACHINERY MANAGEMENT 0.00% 4.72%
15 HANDLING & STORAGE OF HAZARDOUS MATERIAL 0.00% 2.36%
16 EHS PROMOTION, REWARD & RECOGNITION 0.00% 3.94%
0.00% 100.00%
1
TATA HOUSING DEVELOPMENT COMPANY LIMITED
SCORE:
Q1 Q2 Q3 Q4 TO-DATE RATING
TOTAL POINTS 508 508 508 508 508
POINTS CONSIDERED 0 0 0 0 0
POINTS SCORED 0 0 0 0 0
RATING #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0!
*COMMENTS
*ENTER AS SHOWN ABOVE
EXECUTIVE SUMMARY:
Overview of audit
2
TATA HOUSING DEVELOPMENT COMPANY LIMITED
Register of Regulations (ROR) with all legal and other
requirements applicable to the project is maintained
and reviewed by PH and updated every quarter and
annually by corporate EHS. PH is maintaining / has
3 access to the BOCWA, 1996, Rules 1998 and other acts 4 NO SCORE
and rules as applicable to the project
TOTAL 36 0
SCORE 0.00 VERY POOR
ELEMENT 2 - CLIENT'S EHS ADMINISTRATION & CONTROLS
SL. NO. SUB ELEMENT AUDITED SCORE ACTUAL COMMENTS
Display of EHS policy done prominently in English &
Hindi. Contents of policy understood by all employees
1 including contractors' employees 4 NO SCORE
3
TATA HOUSING DEVELOPMENT COMPANY LIMITED
Preparation of and adherence to annual training
calendar. Special drives carried out during National
6 Safety Week or other important occasions. 4 NO SCORE
Maintaining training records
TOTAL 40 0
SCORE 0.00 VERY POOR
ELEMENT 3 - CONTRACTORS' EHS MANAGEMENT
SL. NO. SUB ELEMENT AUDITED SCORE ACTUAL COMMENTS
All contractors are fully conversant with client's health
and safety standard for contractors and their site team
is found to be participating fully in EHS management
1 as per the requirements therein 4 NO SCORE
TOTAL 28 0
SCORE 0.00 VERY POOR
ELEMENT 4 - CONTRACTORS' EHS PLANS
SL. NO. SUB ELEMENT AUDITED SCORE ACTUAL COMMENTS
Contractors have submitted a detailed site-specific EHS
plan which is duly signed off with each major
1 contractor or agency engaged by the client 4 NO SCORE
4
TATA HOUSING DEVELOPMENT COMPANY LIMITED
All major contractors and their sub-contractors are
represented in the Project Safety Committee as
2 specified under the BOCA, 1996 and are abiding by 4 NO SCORE
decisions taken by the committee
TOTAL 16 0
SCORE 0.00 VERY POOR
ELEMENT 5 - OCCUPATIONAL HEALTH
SL. NO. SUB ELEMENT AUDITED SCORE ACTUAL COMMENTS
Equipped occupational health centre is maintained by
principal contractor / jointly by contractors / jointly by
1 client and contractors with doctor's chamber, 4 NO SCORE
examination at an easily accessible place
TOTAL 40 0
SCORE 0.00 VERY POOR
ELEMENT 6 - LIFE SAVING RULES
SL. NO. SUB ELEMENT AUDITED SCORE ACTUAL COMMENTS
All persons present at the site including visitors have
been provided with necessary Personal Protective
1 Equipment (PPE) are using the same properly and as 4 NO SCORE
required
5
TATA HOUSING DEVELOPMENT COMPANY LIMITED
All safety signage displayed at site (preferably in
multiple languages) are understood and obeyed at all
2 times 4 NO SCORE
TOTAL 36 0
SCORE 0.00 VERY POOR
ELEMENT 7 - HEIGHT WORK SAFETY
SL. NO. SUB ELEMENT AUDITED SCORE ACTUAL COMMENTS
All workers and supervisors required to work at
heights of more than 1.8 mtrs., including work to be
1 done externally, on the periphery or on top of 4 NO SCORE
structures or equipment or scaffolds / platforms.
6
TATA HOUSING DEVELOPMENT COMPANY LIMITED
All excavations of more than 1.8 mtrs. depth are made
as required by the barricaded by rigid materials as per
standard, excavated soil kept at a minimum distance
of 1.5 mtrs. from the edges and shoring arrangements
made where required. Excavation less than 1.8 mtrs.
are duly enclosed by warning tapes. (Electrical cables
7 & other underground utilities, de-watering 4 NO SCORE
arrangements and other measures should be factored
in for excavation additionally for added safety)
TOTAL 56 0
SCORE 0.00 VERY POOR
ELEMENT 8 - ELECTRICAL SAFETY
SL. NO. SUB ELEMENT AUDITED SCORE ACTUAL COMMENTS
The project as a whole and individual principal
contractors have a Single-Line-Diagram/s (SLD), as per
standard, prepared by a qualified electrician clearly
showing the sources of power and it's distribution.
1 Such SLDs are duly updated from time to time 4 NO SCORE
7
TATA HOUSING DEVELOPMENT COMPANY LIMITED
All temporary Distribution Boards (DBs) are installed as
per standard at a safe and clean location mounted on
insulated legs and regularly inspected by a competent
electrical supervisor or engineer. All cables are routed
6 through proper clamps well above the floor height 4 NO SCORE
TOTAL 40 0
SCORE 0.00 VERY POOR
ELEMENT 9 - SCAFFOLDS & WORKING PLATFORMS SAFETY
SL. NO. SUB ELEMENT AUDITED SCORE ACTUAL COMMENTS
Scaffolds and working platforms of various types are
erected, maintained and dismantled only by suitably
qualified scaffold erectors and skilled workers.
1 Qualification and experience certificates are available 4 NO SCORE
with client and the concerned contractor
TOTAL 28 0
SCORE 0.00 VERY POOR
ELEMENT 10 - LIFTING SAFETY
SL. NO. SUB ELEMENT AUDITED SCORE ACTUAL COMMENTS
All lifting equipment including cranes, mini-cranes,
mobile cranes, man hoists, material hoists and other
devices such as hooks, hook assy., slings, shackles and
other components used for lifting of materials or
personnel are installed by competent persons,
1 periodically maintained in sound order and tested and 4 NO SCORE
certified by a 3rd Party as required under the standard
and by law
8
TATA HOUSING DEVELOPMENT COMPANY LIMITED
All operators, riggers, slingers, signalers and other
personnel connected with any lifting operation are
duly qualified, competent and experienced to
2 undertake the job and follow safe operating 4 NO SCORE
procedures
TOTAL 16 0
SCORE 0.00 VERY POOR
ELEMENT 11 - HOUSEKEEPING
SL. NO. SUB ELEMENT AUDITED SCORE ACTUAL COMMENTS
The site has formal housekeeping groups working
1 under the overall Project Safety Committee 4 NO SCORE
TOTAL 32 0
SCORE 0.00 VERY POOR
ELEMENT 12 - EMERGENCY RESPONSE
SL. NO. SUB ELEMENT AUDITED SCORE ACTUAL COMMENTS
Is there is drawn up a written emergency
preparedness and response plan specific to the project
1 based on local conditions 4 NO SCORE
9
TATA HOUSING DEVELOPMENT COMPANY LIMITED
All important contact numbers including those of
government agencies / disaster management cells are
6 prominently displayed 4 NO SCORE
TOTAL 48 0
SCORE 0.00 VERY POOR
ELEMENT 13 - PERSONAL PROTECTIVE EQUIPMENT
SL. NO. SUB ELEMENT AUDITED SCORE ACTUAL COMMENTS
Requirement of various PPE, depending on specific
work being performed, has been clearly identified and
suitable arrangements have been made for
1 maintaining sufficient stocks of all items 4 NO SCORE
TOTAL
36 0
SCORE 0.00 VERY POOR
ELEMENT 14 - PLANT & MACHINERY MANAGEMENT
SL. NO. SUB ELEMENT AUDITED SCORE ACTUAL COMMENTS
10
TATA HOUSING DEVELOPMENT COMPANY LIMITED
Client has a detailed list of all plant & machinery
brought into the site by contractors or any agency
1 deployed therein and their specific locations 4 NO SCORE
All such plant & machinery items are duly tested and
certified by the manufacturers as well as by 3rd Party
2 4 NO SCORE
certifying agency as required under the law
TOTAL 24 0
SCORE 0.00 VERY POOR
ELEMENT 15 - HANDLING & STORAGE OF HAZARDOUS MATERIAL
SL. NO. SUB ELEMENT AUDITED SCORE ACTUAL COMMENTS
All hazardous material has been identified, properly
labeled and MSDS duly prepared as per
1 manufacturers' specifications 4 NO SCORE
TOTAL 12 0
SCORE 0.00 VERY POOR
ELEMENT 16 - EHS PROMOTION, REWARD & RECOGNITION
SL. NO. SUB ELEMENT AUDITED SCORE ACTUAL COMMENTS
There is a formal reward & recognition system in place
jointly managed by client and contractors for
1 rewarding exceptional work done by line 4 NO SCORE
management, supervisors and workers
TOTAL 20 0
SCORE 0.00 VERY POOR
G. T. 508 0
SCORE CONSIDERED FOR AUDIT 508 0
FINAL SCORE 0.00 VERY POOR
PHOTOGRAPHS / OTHER EVIDENCE
11
TATA HOUSING DEVELOPMENT COMPANY LIMITED
12
TATA HOUSING DEVELOPMENT COMPANY LIMITED
13
TATA HOUSING DEVELOPMENT COMPANY LIMITED
C2 - Confidential
14
Ratings Comments
0 NO PROCESS IN PLACE
1 BASIC COMPLIANCE ONLY
2 PARTIALLY COMPLIED
COMPLIED BUT ROOM FOR
3 IMPROVEMENT
4 FULLY COMPLIED