ZTPC
DAILY REPORT DATE : 21/8/2021
IGEC MMC
Enigineer 1 0
MANPOWER
forman 2 5
Activities pre-check No open work
Strat work at 9:00 AM 8:00
END work at
COMMENTS :
ZTPC
DAILY REPORT DATE : 22/8/2021
IGEC MMC
Enigineer
MANPOWER
forman
Activities
Strat work at
END work at
COMMENTS :
ZTPC
DAILY REPORT DATE : 20/8/2021
IGEC MMC
Enigineer
MANPOWER
MANPOWER
forman
Activities
Strat work at
END work at
COMMENTS :
ZTPC
DAILY REPORT DATE : 21/8/2021
IGEC MMC
Enigineer
MANPOWER
forman
Activities
Strat work at
END work at
COMMENTS :
ZTPC
DAILY REPORT DATE : 22/8/2021
IGEC MMC
Enigineer
MANPOWER
forman
Activities
Strat work at
END work at
COMMENTS :
ZTPC
DAILY REPORT DATE : 23/8/2021
IGEC MMC
Enigineer
MANPOWER
forman
Activities
Strat work at
END work at
COMMENTS :
ZTPC
DAILY REPORT DATE : 24/8/2021
IGEC MMC
Enigineer
MANPOWER
forman
Activities
Strat work at
END work at
COMMENTS :
ZTPC
DAILY REPORT DATE : 25/8/2021
IGEC MMC
Enigineer
MANPOWER
forman
Activities
Strat work at
END work at
COMMENTS :
ZTPC
DAILY REPORT DATE : 26/8/2021
IGEC MMC
Enigineer
MANPOWER
forman
Activities
Strat work at
END work at
COMMENTS :
ZTPC
DAILY REPORT DATE : 27/8/2021
IGEC MMC
Enigineer
MANPOWER
forman
Activities
Strat work at
END work at
COMMENTS :
ZTPC
DAILY REPORT DATE : 28/8/2021
IGEC MMC
Enigineer
MANPOWER
forman
Activities
Strat work at
END work at
COMMENTS :
ZTPC
DAILY REPORT DATE : 29/8/2021
IGEC MMC
Enigineer
MANPOWER
forman
Activities
Strat work at
END work at
COMMENTS :
ZTPC
DAILY REPORT DATE : 30/8/2021
IGEC MMC
Enigineer
MANPOWER
forman
Activities
Strat work at
END work at
COMMENTS :
ZTPC
DAILY REPORT DATE : 31/8/2021
IGEC MMC
Enigineer
MANPOWER
forman
Activities
Strat work at
END work at
COMMENTS :
ZTPC
Cable TEAM CIVIL
0 0
0 0
No manpower
ZTPC
Cable TEAM CIVIL
ZTPC
Cable TEAM CIVIL
ZTPC
Cable TEAM CIVIL
ZTPC
Cable TEAM CIVIL
ZTPC
Cable TEAM CIVIL
ZTPC
Cable TEAM CIVIL
ZTPC
Cable TEAM CIVIL
ZTPC
Cable TEAM CIVIL
ZTPC
Cable TEAM CIVIL
ZTPC
Cable TEAM CIVIL
ZTPC
Cable TEAM CIVIL
ZTPC
Cable TEAM CIVIL
ZTPC
Cable TEAM CIVIL
ZTPC
AL NAHDA
220/66/11KV GIS
Employee IGEC
August 3rd Week
Week ending: 24/8/2021
Day Date ACTIVITES Comments
Wednesday 18/8/2021 ES&DS Timing Test for D01(100%) Test Finishe at 2:00 PM
Test Finishe at 2:00 PM and testing
team worked untill 5:00 PM on
Thursday 19/8/2021 ES&DS Timing Test for D04(100%) wrong termination at D02 & D03
Friday 20/8/2021 Pre-check
Saturday 21/8/2021 Pre-check Fixing wrong termination
Finished all pre-check on
Sunday 22/8/2021 Pre-check
DS,ES,CT&VT
Test Finished at 1:00 PM because
Monday 23/8/2021 ES&DS Timing for D11(100%) Eng/Hassan have something to do
outside
Test started with Eng/Hassan on
ES&DS Timing for
10:30 finished 1:15 because he
Tuseday 24/8/2021 D10,D9,D07(100%) & D8(85%
was tired & IGEC continue without
Finished)
owner
ZTPC
AL NAHDA
220/66/11KV GIS
Employee IGEC
August 4th Week
Week ending: 31/8/2021
Day Date ACTIVITES Comments
ES&DS Timing for D07,D06and D05 Testing start on 10:00 am & finished at
Wednesday 25/8/2021
(100%) 2:00pm
Testing start on 10:00 am & finished at
Thursday 26/8/2021 ES&DS Timing for D03 only
12:00 am
Friday 27/8/2021 pre-check on CB
ES&DS Timing for D02 only & IGEC
Saturday 28/8/2021 Team make a pre-check for CB and Testing start on 11:00 am
66KV Pre-check
CB Timing for all 220KV LCC panels Test start on 11:50 am & finish on
Sunday 29/8/2021
(100%) & 66KV Pre-check 2:15 pm
Monday 30/8/2021 Pre-check
CONTACT RESISTANCE FOR F19+S
Tuseday 31/8/2021
(100%)
ZTPC
AL NAHDA
220/66/11KV GIS
Employee IGEC
SEPTEMBER 1ST Week
Week ending: 7/9/2021
Day Date ACTIVITES Comments
Wednesday 1/9/2021 Pre-check
Thursday 12/9/2021 Pre-check
Friday 3/9/2021
CONTACT RESISTANCE FOR
Saturday 4/9/2021
F19,F18,F17,F16,F15,F14 (100%)
CONTACT RESISTANCE FOR
Sunday 5/9/2021
F13,F,F12,F11,F10,F09 (100%)
CONTACT RESISTANCE FOR
Monday 6/9/2021
F08,F07,F06,F05,F04,F03 (100%)
Tuseday 7/9/2021 Pre-check FOR DS &ES Timing
ZTPC
AL NAHDA
220/66/11KV GIS
Employee IGEC
SEPTEMBER 2nd Week
Week ending: 14/9/2021
Day Date ACTIVITES Comments
Timing for DS&ES
Wednesday 8/9/2021
F03,F04,F05,F06,F07,F08 (100%)
Timing for DS&ES
Thursday 9/9/2021
F09,F10,F11,F12,F13, F14 (100%)
Friday 10/9/2021
Timing for DS&ES
Saturday 11/9/2021 F15,F16,F17,F18,F19 (100%) AND
Pre-check for 66KV GIS LCC CT
Sunday 12/9/2021 Pre-check for 66KV GIS LCC CT
Monday 13/9/2021
Tuseday 14/9/2021
ZTPC
WEEKLY REPORT
AL NAHDA
220/66/11KV GIS
Employee MMC
August 3rd Week
Week ending: 24/8/2021
Day Date ACTIVITES Comments
Wednesday 18/8/2021 No Open Work
Thursday 19/8/2021 No Open Work
Friday 20/8/2021
Saturday 21/8/2021 Install 220kv control panels relay
Install 220kv control panels relay & pulling
Sunday 22/8/2021
236m of cables
Install 220kv control panels relay ,Modify 66kv
Monday 23/8/2021 ACDC /11kv AUX TR raceway & pulling 272m of Finished 66kv ACDC pathway
cables
Finished AUX TR raceway & Need manpower
Install the AUX TR raceway & pulling 138m of
Tuseday 24/8/2021 for cable pulling (Actual cable team) &
cables
increase manpower for termination
ZTPC
WEEKLY REPORT
AL NAHDA
220/66/11KV GIS
Employee MMC
August 4th Week
Week ending: 31/8/2021
Day Date ACTIVITES Comments
Terminate DC cables for 66KV
Wednesday 25/8/2021
protection&control panels & PULLING 304m
Modify ACDC-66kv tray , entre DC cables from
Thursday 26/8/2021
F01+RW to F06 +RW and pulling 731m
Friday 27/8/2021
Termination in ACDC ROOM & 66KV LCC , Pulling team start work from 4:00pm to
Saturday 28/8/2021
Pulling 1632m 7:00pm
EL SWEEDY came to site to check the oil
Terminate CT cables from control room to 66KV
Sunday 29/8/2021 tanks and didn't work coz he is waiting the
LCC GIS & Pulling 1136m
permation from his manager
Install cable ladder between control and 220kv
Monday 30/8/2021 building , termination in 66kv LCC & pulling
2417m
Termination team work BB cables & cable team
Tuseday 31/8/2021 EL SWEEDY start work on 175MVA Tr
pulling 1527m
ZTPC
WEEKLY REPORT
AL NAHDA
220/66/11KV GIS
Employee
MMC
SEPTEMBER 1ST Week
Week ending: 7/9/2021
Day Date ACTIVITES Comments
Termination team work on 66kv
Wednesday 1/9/2021 protection&control panels & cable team pulling
3387m
Thursday 2/9/2021 Cable team pulling 2187m
Friday 3/9/2021 Cable team pulling 3614m
Preparing for Oil Works on 175MVA Transformer
, termination team preparing to terminate
Saturday 4/9/2021 cables in control room and terminate cables for
38 Drum arrives to the site
66KV LCC AND Cable team pulling 3726m
start Oil works , termination and cable pulling
Sunday 5/9/2021 3348m
start Oil works , termination and cable pulling
Monday 6/9/2021 832m
start Oil works , termination and cable pulling
Tuseday 7/9/2021 2764m
ZTPC
WEEKLY REPORT
AL NAHDA
220/66/11KV GIS
Employee MMC
SEPTEMBER 2nd Week
Week ending: 21/9/2021
Day Date ACTIVITES Comments
Oil works on 175MVA Transformer and
Wednesday 8/9/2021 termination works
2 mistaks in cable pulling 230m size 4×4
Oil works on 175MVA Transformer and
Thursday 9/9/2021 termination works
Friday 10/9/2021 Oil works on 175MVA Transformer
Oil works on 175MVA Transformer and 3 persons for termination and no one for
Saturday 11/9/2021 termination works cable pulling
cable team is 2 persons arrive on 10:30, and
Oil works on 175MVA Transformer , termination arrive to site 3 technicans all now in site is 6
Sunday 12/9/2021 works and check all pulled cables persons for termination (That's not enough
compare with open work)
Monday 13/9/2021
Tuseday 14/9/2021