Weekly Report

The document contains daily and weekly reports for the ZTPC project at Al Nahda, detailing manpower, activities, and comments from August 18 to September 14, 2021. It highlights various tasks such as pre-checks, cable pulling, terminations, and testing activities, along with comments on manpower and progress. The reports indicate a lack of manpower on several days and the completion of specific tasks related to the 220/66/11KV GIS project.

Uploaded by

mohmed.ramdan211
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
28 views14 pages

Weekly Report

The document contains daily and weekly reports for the ZTPC project at Al Nahda, detailing manpower, activities, and comments from August 18 to September 14, 2021. It highlights various tasks such as pre-checks, cable pulling, terminations, and testing activities, along with comments on manpower and progress. The reports indicate a lack of manpower on several days and the completion of specific tasks related to the 220/66/11KV GIS project.

Uploaded by

mohmed.ramdan211
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 14

ZTPC

DAILY REPORT DATE : 21/8/2021

IGEC MMC
Enigineer 1 0
MANPOWER
forman 2 5

Activities pre-check No open work

Strat work at 9:00 AM 8:00

END work at

COMMENTS :

ZTPC
DAILY REPORT DATE : 22/8/2021

IGEC MMC
Enigineer
MANPOWER
forman
Activities
Strat work at
END work at

COMMENTS :

ZTPC
DAILY REPORT DATE : 20/8/2021

IGEC MMC
Enigineer
MANPOWER
MANPOWER
forman
Activities
Strat work at
END work at

COMMENTS :

ZTPC
DAILY REPORT DATE : 21/8/2021

IGEC MMC
Enigineer
MANPOWER
forman
Activities
Strat work at
END work at

COMMENTS :

ZTPC
DAILY REPORT DATE : 22/8/2021

IGEC MMC
Enigineer
MANPOWER
forman
Activities
Strat work at
END work at

COMMENTS :
ZTPC
DAILY REPORT DATE : 23/8/2021

IGEC MMC
Enigineer
MANPOWER
forman
Activities
Strat work at
END work at

COMMENTS :

ZTPC
DAILY REPORT DATE : 24/8/2021

IGEC MMC
Enigineer
MANPOWER
forman
Activities
Strat work at
END work at

COMMENTS :

ZTPC
DAILY REPORT DATE : 25/8/2021

IGEC MMC
Enigineer
MANPOWER
forman
Activities
Strat work at
END work at

COMMENTS :

ZTPC
DAILY REPORT DATE : 26/8/2021

IGEC MMC
Enigineer
MANPOWER
forman
Activities
Strat work at
END work at

COMMENTS :

ZTPC
DAILY REPORT DATE : 27/8/2021

IGEC MMC
Enigineer
MANPOWER
forman
Activities
Strat work at
END work at

COMMENTS :

ZTPC
DAILY REPORT DATE : 28/8/2021

IGEC MMC
Enigineer
MANPOWER
forman
Activities
Strat work at
END work at

COMMENTS :

ZTPC
DAILY REPORT DATE : 29/8/2021

IGEC MMC
Enigineer
MANPOWER
forman
Activities
Strat work at
END work at

COMMENTS :

ZTPC
DAILY REPORT DATE : 30/8/2021

IGEC MMC
Enigineer
MANPOWER
forman
Activities
Strat work at
END work at
COMMENTS :

ZTPC
DAILY REPORT DATE : 31/8/2021

IGEC MMC
Enigineer
MANPOWER
forman
Activities
Strat work at
END work at

COMMENTS :
ZTPC

Cable TEAM CIVIL


0 0
0 0

No manpower

ZTPC

Cable TEAM CIVIL

ZTPC

Cable TEAM CIVIL


ZTPC

Cable TEAM CIVIL

ZTPC

Cable TEAM CIVIL


ZTPC

Cable TEAM CIVIL

ZTPC

Cable TEAM CIVIL

ZTPC

Cable TEAM CIVIL


ZTPC

Cable TEAM CIVIL

ZTPC

Cable TEAM CIVIL

ZTPC
Cable TEAM CIVIL

ZTPC

Cable TEAM CIVIL

ZTPC

Cable TEAM CIVIL


ZTPC

Cable TEAM CIVIL


ZTPC
AL NAHDA
220/66/11KV GIS

Employee IGEC

August 3rd Week


Week ending: 24/8/2021

Day Date ACTIVITES Comments

Wednesday 18/8/2021 ES&DS Timing Test for D01(100%) Test Finishe at 2:00 PM

Test Finishe at 2:00 PM and testing


team worked untill 5:00 PM on
Thursday 19/8/2021 ES&DS Timing Test for D04(100%) wrong termination at D02 & D03

Friday 20/8/2021 Pre-check

Saturday 21/8/2021 Pre-check Fixing wrong termination

Finished all pre-check on


Sunday 22/8/2021 Pre-check
DS,ES,CT&VT

Test Finished at 1:00 PM because


Monday 23/8/2021 ES&DS Timing for D11(100%) Eng/Hassan have something to do
outside

Test started with Eng/Hassan on


ES&DS Timing for
10:30 finished 1:15 because he
Tuseday 24/8/2021 D10,D9,D07(100%) & D8(85%
was tired & IGEC continue without
Finished)
owner

ZTPC
AL NAHDA
220/66/11KV GIS

Employee IGEC

August 4th Week


Week ending: 31/8/2021

Day Date ACTIVITES Comments

ES&DS Timing for D07,D06and D05 Testing start on 10:00 am & finished at
Wednesday 25/8/2021
(100%) 2:00pm

Testing start on 10:00 am & finished at


Thursday 26/8/2021 ES&DS Timing for D03 only
12:00 am

Friday 27/8/2021 pre-check on CB

ES&DS Timing for D02 only & IGEC


Saturday 28/8/2021 Team make a pre-check for CB and Testing start on 11:00 am
66KV Pre-check

CB Timing for all 220KV LCC panels Test start on 11:50 am & finish on
Sunday 29/8/2021
(100%) & 66KV Pre-check 2:15 pm

Monday 30/8/2021 Pre-check

CONTACT RESISTANCE FOR F19+S


Tuseday 31/8/2021
(100%)

ZTPC
AL NAHDA
220/66/11KV GIS

Employee IGEC

SEPTEMBER 1ST Week


Week ending: 7/9/2021

Day Date ACTIVITES Comments

Wednesday 1/9/2021 Pre-check

Thursday 12/9/2021 Pre-check

Friday 3/9/2021

CONTACT RESISTANCE FOR


Saturday 4/9/2021
F19,F18,F17,F16,F15,F14 (100%)

CONTACT RESISTANCE FOR


Sunday 5/9/2021
F13,F,F12,F11,F10,F09 (100%)

CONTACT RESISTANCE FOR


Monday 6/9/2021
F08,F07,F06,F05,F04,F03 (100%)

Tuseday 7/9/2021 Pre-check FOR DS &ES Timing

ZTPC
AL NAHDA
220/66/11KV GIS

Employee IGEC

SEPTEMBER 2nd Week


Week ending: 14/9/2021

Day Date ACTIVITES Comments

Timing for DS&ES


Wednesday 8/9/2021
F03,F04,F05,F06,F07,F08 (100%)
Timing for DS&ES
Thursday 9/9/2021
F09,F10,F11,F12,F13, F14 (100%)

Friday 10/9/2021

Timing for DS&ES


Saturday 11/9/2021 F15,F16,F17,F18,F19 (100%) AND
Pre-check for 66KV GIS LCC CT

Sunday 12/9/2021 Pre-check for 66KV GIS LCC CT

Monday 13/9/2021

Tuseday 14/9/2021
ZTPC
WEEKLY REPORT

AL NAHDA
220/66/11KV GIS

Employee MMC

August 3rd Week


Week ending: 24/8/2021

Day Date ACTIVITES Comments

Wednesday 18/8/2021 No Open Work

Thursday 19/8/2021 No Open Work

Friday 20/8/2021

Saturday 21/8/2021 Install 220kv control panels relay

Install 220kv control panels relay & pulling


Sunday 22/8/2021
236m of cables

Install 220kv control panels relay ,Modify 66kv


Monday 23/8/2021 ACDC /11kv AUX TR raceway & pulling 272m of Finished 66kv ACDC pathway
cables

Finished AUX TR raceway & Need manpower


Install the AUX TR raceway & pulling 138m of
Tuseday 24/8/2021 for cable pulling (Actual cable team) &
cables
increase manpower for termination

ZTPC
WEEKLY REPORT
AL NAHDA
220/66/11KV GIS

Employee MMC

August 4th Week

Week ending: 31/8/2021

Day Date ACTIVITES Comments

Terminate DC cables for 66KV


Wednesday 25/8/2021
protection&control panels & PULLING 304m

Modify ACDC-66kv tray , entre DC cables from


Thursday 26/8/2021
F01+RW to F06 +RW and pulling 731m

Friday 27/8/2021

Termination in ACDC ROOM & 66KV LCC , Pulling team start work from 4:00pm to
Saturday 28/8/2021
Pulling 1632m 7:00pm

EL SWEEDY came to site to check the oil


Terminate CT cables from control room to 66KV
Sunday 29/8/2021 tanks and didn't work coz he is waiting the
LCC GIS & Pulling 1136m
permation from his manager

Install cable ladder between control and 220kv


Monday 30/8/2021 building , termination in 66kv LCC & pulling
2417m

Termination team work BB cables & cable team


Tuseday 31/8/2021 EL SWEEDY start work on 175MVA Tr
pulling 1527m

ZTPC
WEEKLY REPORT

AL NAHDA
220/66/11KV GIS

Employee
MMC

SEPTEMBER 1ST Week

Week ending: 7/9/2021

Day Date ACTIVITES Comments

Termination team work on 66kv


Wednesday 1/9/2021 protection&control panels & cable team pulling
3387m

Thursday 2/9/2021 Cable team pulling 2187m

Friday 3/9/2021 Cable team pulling 3614m

Preparing for Oil Works on 175MVA Transformer


, termination team preparing to terminate
Saturday 4/9/2021 cables in control room and terminate cables for
38 Drum arrives to the site
66KV LCC AND Cable team pulling 3726m

start Oil works , termination and cable pulling


Sunday 5/9/2021 3348m

start Oil works , termination and cable pulling


Monday 6/9/2021 832m

start Oil works , termination and cable pulling


Tuseday 7/9/2021 2764m

ZTPC
WEEKLY REPORT

AL NAHDA
220/66/11KV GIS

Employee MMC

SEPTEMBER 2nd Week


Week ending: 21/9/2021

Day Date ACTIVITES Comments

Oil works on 175MVA Transformer and


Wednesday 8/9/2021 termination works
2 mistaks in cable pulling 230m size 4×4

Oil works on 175MVA Transformer and


Thursday 9/9/2021 termination works

Friday 10/9/2021 Oil works on 175MVA Transformer

Oil works on 175MVA Transformer and 3 persons for termination and no one for
Saturday 11/9/2021 termination works cable pulling

cable team is 2 persons arrive on 10:30, and


Oil works on 175MVA Transformer , termination arrive to site 3 technicans all now in site is 6
Sunday 12/9/2021 works and check all pulled cables persons for termination (That's not enough
compare with open work)

Monday 13/9/2021

Tuseday 14/9/2021