HOTWORKS PERMI
Declaration of Daily Hot Works
 _________________________________________________________________________________________________________________
                     ATMC-SZR
Site Location: _________________________                           ATMC_SZR Extension area
                                         Specific Hot Work Area:____________________________
       15 04 25
Date: _____________                        10 PM
                              Start Time:________________                  7 AM
                                                              End Time:______________
______________________________________________________________________________________
   •   This Declaration is applicable to all HOT WORKS involving flame, hot air, arc welding and cutting
       equipment, brazing and soldering (excluding the use of electric soldering irons), blowlamps,
       bitumen boilers, angle-grinders and any other heat producing equipment as specified in the
       Method Statement.
   •   Dates will be specified on “HOT WORK PERMIT” for weekly basis.
   •   Hot Works Areas will be inspected and verified by contractor HSE Supervisor and Facility
       Management representative / supervisor.
We undersigned, confirm that we have understood the site safety rules and the restrictions on Hot Work
Permit. All hot works will be carried out in accordance with best current trade practice and that all
appropriate health and safety controls.
We confirm that:
  ✓ This declaration is completed today before commencing HOT WORKS and submitted to site security.
  ✓ I (Contractor HSE Supervisor) will be physically present onsite of HOT WORKS to supervise the team
     as required throughout the time duration mentioned above.
  ✓ The team shall access and work only in the designated and permitted Hot work areas.
  ✓ The location of work has been examined and there are no flammable and combustible liquids,
     vapours, gases, dusts or other materials / hazards. Area is protected against heat / ignition for up to
     8 to 10 meters (around, above and below the Hot works area).
  ✓ For HOT Works, a fire warden will be stand by with an extinguisher appropriate to the fire risk. His
     role will be that of a fireman and he will not be directly involved in the execution of any part of the
     works.
  ✓ The operatives, including the “fire warden”, are fully aware and have been instructed of the building
     fire procedures and the whereabouts of the nearest fire alarm points and telephones.
  ✓ Any change in the scope of work, details of circumstances and assumptions not declared
     automatically revokes this declaration and permit. Work can be stopped immediately.
  ✓ Such changes if any will be notified to ATM/ PM FM, Security and HSE representative immediately
     by email.
  ✓ POST WORK COMPLETION: The work area will be cleaned, inspected and restored to original
     conditions.
______________________________________________________________________________________
CONTRACTOR HSE SUPERVISOR: __________________ SIGNATURE: _____________DATE & TIME: ______________________
FACILITY MANAGEMENT: ________________________SIGNATURE: ___________ DATE & TIME: _______________________
_______________________________________________________________________________________________________
RECEIVD BY SECURITY: __________________________ SIGNATURE: _________________ DATE & TIME: __________________