0% found this document useful (0 votes)
39 views13 pages

Installation Check List.

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
39 views13 pages

Installation Check List.

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 13

No. 86 / E - 1, 2nd Cross, 3rd Main Road, Industrial Suburb, 2nd Stage, Yeshwanthpur, Bangalore 560 022.

INSTALLATION CHECK LIST FOR LT CABLES

PROJECT: M/S.ROACH CURIO HILTON HOTEL, BANGALORE Date :

Drawing Title : Check List No.

Drawing No. Rev. No.

Floor : Location :

Sl. No. Description

1 Received LT Cables as per the PO


2 Laying of LT Cables Activities
Remarks
3 Cable dressing Yes No.
Both End
From To Meggar valve
Condition
4
5
6
7
8
9
10
REMARKS/COMMENTS:

NAME: NAME:

SIGNATURE: SIGNATURE:

CLIENT: PMC:
No. 86 / E - 1, 2nd Cross, 3rd Main Road, Industrial Suburb, 2nd Stage, Yeshwanthpur, Bangalore 560 022.

INSTALLATION CHECK LIST FOR DISTRIBUTION BOARD

PROJECT: M/S.ROACH CURIO HILTON HOTEL, BANGALORE Date :

Drawing Title : Check List No.

Drawing No. Rev. No.

Floor : Location :

Activities
Sl. No. Description
Yes No. N/A

1 Received DB as per the PO & BOQ


2 Marking of DB
3 DB adequately supported
4 Supports alignment checked
5 Metallic DB solidly grounded
6 DB grounding bushing installed
7 Bonding wire grounding connections completed
Surface finish of DB cabinet is good , no scratches, damages, dents
8
etc., noticed.

9 Painting on shuttering plates is done beneath all DB boxes

Make and model of DB is as per the approved sample/ as per


10
approved makes list.
DB location is as per the approved shop drawings or as per the
11
consultants approval.

12 Plumb, square etc., of DB installed are proper (verified with spirit level)

If any dead cement mortar inside DB, it is removed and appearance is


13
clean and tidy.

14 DB is covered with Polythene sheet prior to installation or erection

15 DIN rails are fixed up rigidly and firmly.

16 All the MCBs are fixed up tightly to the DIN rails.

17 The rating of MCBs is correct and it is as per the specification

Dressing of wires is done properly phase wise and appearance is


18
neat and tidy.
Neutral link and terminal blocks are in place and these are fixed up to
19
the DB rigidly and firmly.
Earthing is done for the DB, routing is done properly, General
20
appearance is neat and tidy.

21 All the conduits are terminated into DB properly neatly, no excessive

22 Conduiting is done than the envisaged.

The adaptor box is fixed up neatly, properly and the end caps are in
23
tact.
REMARKS/COMMENTS:

NAME: NAME: NAME:

SIGNATURE: SIGNATURE: SIGNATURE:

CLIENT: PMC: CONTRACTOR:


No. 86 / E - 1, 2nd Cross, 3rd Main Road, Industrial Suburb, 2nd Stage, Yeshwanthpur, Bangalore 560 022.

INSTALLATION CHECK LIST FOR CABLE TRAY

PROJECT: M/S.ROACH CURIO HILTON HOTEL, BANGALORE Date :

Drawing Title : Check List No.

Drawing No. Rev. No.

Floor : Location :

Activities
Sl. No. Description
Yes No. N/A

1 Received Cable trays as per the PO & BOQ


2 Marking of Cable trays
Supports
3 Cable trays adequately supported
4 Supports alignment checked
Grounding
4 Cable trays and fittings correct size and type
5 Identification of Cable trays installed
6 Installed Cabletrays in accordance with shop drawing
7 Proper identification on every Cable trays
8 Metallic Cable trays solidly grounded
9 Cabletrays grounding bushing installed
10 Bonding wire grounding connections completed

Quality of Cable trays are good, no damages, no rusting and general


11
appearance is neat

12 Size of cable trays is as per the approved shop drawings


13 Routing of the cable try is as per the approved drawings
14 Cable tray installed will not foul with other services installations

15 The thickness and frame height of cable tray is as per the specification

16 Joining plates are fixed up properly.

Supporting rods size and span is as per the specifications/ as per the
17
approved drawings.

18 Alignment of cable tray is completed.


19 Earthing of cable tray is completed.

20 The vertical distance between two cable trays is 300mm is maintained.

REMARKS/COMMENTS:

NAME: NAME: NAME:

SIGNATURE: SIGNATURE: SIGNATURE:

CLIENT: PMC: CONTRACTOR:


No. 86 / E - 1, 2nd Cross, 3rd Main Road, Industrial Suburb, 2nd Stage, Yeshwanthpur, Bangalore 560 022.

INSTALLATION CHECK LIST FOR CONDUITS

PROJECT: M/S.ROACH CURIO HILTON HOTEL, BANGALORE Date :

Drawing Title : Check List No.

Drawing No. Rev. No.

Floor : Location :

Activities
Sl. No. Description
Yes No. N/A

1 Received Conduit as per the PO & BOQ


2 Marking of Conduiting
3 Fixing of saddles
4 Laying of conduit
Supports
5 Conduit adequately supported
6 Supports alignment checked
Conduit
7 Conduit and fittings correct size and type
8 Identification of conduits installed
9 Bend free of damage
10 Installed conduits in accordance with shop drawing
11 Boxes installed are the correct size and type
12 Boxes are properly supported and installed at correct location
13 Proper identification on every junction box and drop points
14 Pull/splicing box installed at accessible location
Grounding
15 Metallic conduits solidly grounded
16 Conduit grounding bushing installed
General
17 Pipe to pipe gap should be minimum 25mm
18 Threading to be done by machine

Quality of conduits are good, no damages, no rusting and general


19
appearance is neat

20 Painting on shuttering plates is done beneath all junction boxes


21 Conduits dropped near DB is neat and tidy
22 For long distance at every 15mts dummy JB to be used
REMARKS/COMMENTS:

NAME: NAME: NAME:

SIGNATURE: SIGNATURE: SIGNATURE:

CLIENT: PMC: CONTRACTOR:


No. 86 / E - 1, 2nd Cross, 3rd Main Road, Industrial Suburb, 2nd Stage, Yeshwanthpur, Bangalore 560 022.

INSTALLATION CHECK LIST FOR WIRES

PROJECT: M/S.ROACH CURIO HILTON HOTEL, BANGALORE Date :

Drawing Title : Check List No.

Drawing No. Rev. No.

Floor : Location :

Activities
Sl. No. Description
Yes No. N/A

1 No Evident Mechanical Damage to Insulation

2 Wire colour and size as specified in wire schedule

Number of Wires drawn in conduit do not exceed the limit specified in


3
the wiring schedule

Wires are provided with yellow PVC identification ferrules giving circuit
4
reference as per wire schedule

When routed on wall / structure surface, Wires are neatly bunched and
5
clamped to supports

Termination of Wires using insulated lugs. Wire stripping to be just


6 sufficient for termination and no bare conductor to be seen after
termination of wire
REMARKS/COMMENTS:

NAME: NAME: NAME:

SIGNATURE: SIGNATURE: SIGNATURE:

CLIENT: PMC: CONTRACTOR:


No. 86 / E - 1, 2nd Cross, 3rd Main Road, Industrial Suburb, 2nd Stage, Yeshwanthpur, Bangalore 560 022.

INSTALLATION CHECK LIST FOR EARTHING

PROJECT: M/S.ROACH CURIO HILTON HOTEL, BANGALORE Date :

Drawing Title : Check List No.

Drawing No. Rev. No.

Floor : Location :

Activities
Sl. No. Description
Yes No. N/A

1 Received Copper plate/GI pipe as per the PO & BOQ


2 Marking of earth pit

Proper identification on every junction box and drop points pull/splicing


3
box installed at accesible location

Quality of GI flat , Cu flat conductor is good , no damage,no bents etc.,


4
and general appearance is neat and tidy.

5 The bolt jointing of all the conductor is proper


6 The routing of earth strips is acceptable

The square, plumb, verticality of earth strip is proper no rectification


7
needed

DMC insulators are used for earth strips running along with metal
8
bodies/cable trays.

Before laying external earth strips ensure that road roller , proclaimer,
9
compactors etc., works are fully completed

Before laying of earth strips on walls ensure that plastering works are
10
completed

11 The earth pit locations are as per the approved drawing


12 Earth pit to earth pit minimum distance of 3mtrs is maintained
13 Earth pit is located 1.5mtr away from the building structure.

Earth pits, earth strips installed will not foul with other services
14
installations

The earth strips entry points in to the building are sealed properly with
15
water proofing course/sealant.

16 Ensure earth resistance value of earth pit is within the acceptable limit

REMARKS/COMMENTS:

NAME: NAME: NAME:

SIGNATURE: SIGNATURE: SIGNATURE:

CLIENT: PMC: CONTRACTOR:


No. 86 / E - 1, 2nd Cross, 3rd Main Road, Industrial Suburb, 2nd Stage, Yeshwanthpur, Bangalore 560 022.

INSTALLATION CHECK LIST FOR SWITCH AND SOCKET

PROJECT: M/S.ROACH CURIO HILTON HOTEL, BANGALORE Date :

Drawing Title : Check List No.

Drawing No. Rev. No.

Floor : Location :

Activities
Sl. No. Description
Yes No. N/A

1 Tightness of conduit in partition


2 Mounting level of Back-Box as per drawing
3 Levelling of Backbox using spirit level
4 Depth of back box should be 20mm from Final finised Partition surface
5 Ensure that check-nut is provided for conduit inside the metal box
6 Check the configuration of Switch and Socket on the front plate
7 Check the colour of the front plate as per the requirement.
REMARKS/COMMENTS:

NAME: NAME: NAME:

SIGNATURE: SIGNATURE: SIGNATURE:

CLIENT: PMC: CONTRACTOR:


No. 86 / E - 1, 2nd Cross, 3rd Main Road, Industrial Suburb, 2nd Stage, Yeshwanthpur, Bangalore 560 022.

INSTALLATION CHECK LIST FOR LIGHT FIXTURE

PROJECT: M/S.ROACH CURIO HILTON HOTEL, BANGALORE Date :

Drawing Title : Check List No.

Drawing No. Rev. No.

Floor : Location :

Activities
Sl. No. Description
Yes No. N/A

1 Received Light Fixture as per the BOQ


2 Marking of location for Light Fixtures
Supports
3 Light fixtures adequately supported
4 Supports allignment checked
Grounding
4 Light grounding bushing installed
5 Bonding wire grounding connections completed
6 Pull boxes and junction Light grounded

Make and model of light fixtures is as per the approved makes list/
7
approved mock up sample.

Quality of light fixture is good, no damages and surface finish is neat


8
and new.

9 Electronic ballast is same as that approved sample


10 Louvers provided are as per the mock up model
11 The suspension system is rigid and proper.

Proper covering of light fixture is done to protect from dust, painting


12
etc.,

The painting marks if any removed without making scratches on the


13
light fixture.

Cable wire color code is correct and identification tags installed at


14
panel board

15 All wire entries are sealed with a non-setting sealant


16 Lighting photo cell control is correctly installed
17 Lighting fixture fitted with fuse holder and enclosure cover
18 Earthinbg terminal screws are fixed
REMARKS/COMMENTS:

NAME: NAME: NAME:

SIGNATURE: SIGNATURE: SIGNATURE:

CLIENT: PMC: CONTRACTOR:


No. 86 / E - 1, 2nd Cross, 3rd Main Road, Industrial Suburb, 2nd Stage, Yeshwanthpur, Bangalore 560 022.

INSTALLATION CHECK LIST FOR HT Cables

PROJECT: M/S.ROACH CURIO HILTON HOTEL, BANGALORE Date :

Drawing Title : Check List No.

Drawing No. Rev. No.

Floor : Location :

Sl. No. Description

1 Received HT Cables as per the PO


2 Laying of HT Cables Activities
Remarks
3 Cable dressing Yes No.

From To Meggar valve Both End Condition

4
5
6
7
8
9
10
REMARKS/COMMENTS:

NAME: NAME: NAME:

SIGNATURE: SIGNATURE: SIGNATURE:

CLIENT: PMC: CONTRACTOR


No. 86 / E - 1, 2nd Cross, 3rd Main Road, Industrial Suburb, 2nd Stage, Yeshwanthpur, Bangalore 560 022.

INSTALLATION CHECK LIST FOR LT PANEL

PROJECT:M/S.ROACH CURIO HILTON HOTEL, BANGALORE Date :

Drawing Title : Check List No.

Drawing No. Rev. No.

Floor : Location :

Activities
Sl. No. Description
Yes No. N/A

1 Received LT Panel as per the PO & BOQ


2 Marking of LT Panel Board
3 Ensure panel made out of the 16 CRCA sheet steel
Supports
4 LT Panel adequately supported
5 Supports alignment checked
LT Panel
5 LT Panel and fittings correct size and type
6 Identification of LT Panel installed
7 Installed LT Panel in accordance with shop drawing
8 Ensure base channel made out of 100x50x6mm
9 Ensure the cable entry (Top / Bottom)
Grounding
10 LT Panel solidly grounded
11 LT Panel grounding bushing installed
12 Bonding wire grounding connections completed
General
13 Ensure the over current, earth fault release is as per panel
14 schematic diagram approved

15 Ensure for the colour of painting (Siemens Grey)


16 Ensure for the rating and make of incomer MCCB / ACB as per
17 panel schematic diagram approved
18 Ensure for the instrument panel accessories is as per panel
19 schematic diagram approved
20 Ensure the make of CT, indicating lamps, selector switch,
21 control wiring, MCB and accessories is as per requirement
22 Ensure the rating of capacitors and contactors
23 Ensure for the sizes of bus bars and earthing strips
24 Ensure for the surface finish of panel is good, no scratches,
25 damages, dents, weather proof gaskets damages, etc. are noticed
26 Ensure whether the panel is supplied in sections / in whole
27 Ensure for cable entry accessability - Front / Rear
REMARKS/COMMENTS:

NAME: NAME: NAME:

SIGNATURE: SIGNATURE: SIGNATURE:

CLIENT: PMC: CONTRACTOR:


No. 86 / E - 1, 2nd Cross, 3rd Main Road, Industrial Suburb, 2nd Stage, Yeshwanthpur, Bangalore 560 022.

INSTALLATION CHECK LIST FOR RMU

PROJECT :M/S.ROACH CURIO HILTON HOTEL, BANGALORE Date :

Drawing Title : Check List No.

Drawing No. Rev. No.

Floor : Location :

Activities
Sl. No. Description
Yes No. N/A
1 Received RMU as per the PO & BOQ
2 Marking of RMU Board
3 Ensure panel made out of the 16 CRCA sheet steel
Supports
4 RMU adequately supported
5 Supports alignment checked
RMU
5 RMU and fittings correct size and type
6 Identification of RMU installed
7 Installed RMU in accordance with shop drawing
8 Ensure base channel made out of 100x50x6mm
9 Ensure the cable entry (Top / Bottom)
Grounding
10 RMU solidly grounded
11 RMU grounding bushing installed
12 Bonding wire grounding connections completed
General
13 Ensure the over current, earth fault release is as per panel
14 schematic diagram approved
15 Ensure for the colour of painting (Siemens Grey)
16 Ensure for the rating and make of incomer MCCB / ACB as per
17 panel schematic diagram approved
18 Ensure for the instrument panel accessories is as per panel
19 schematic diagram approved
20 Ensure the make of CT, indicating lamps, selector switch,
21 control wiring, MCB and accessories is as per requirement
22 Ensure the rating of capacitors and contactors
23 Ensure for the sizes of bus bars and earthing strips
24 Ensure for the surface finish of panel is good, no scratches,
25 damages, dents, weather proof gaskets damages, etc. are noticed
26 Ensure whether the panel is supplied in sections / in whole
27 Ensure for cable entry accessability - Front / Rear
REMARKS/COMMENTS:
NAME: NAME: NAME:
SIGNATURE: SIGNATURE: SIGNATURE:
CLIENT: PMC: CONTRACTOR: