ROOF STRUCTURE, COVERINGS AND RAIN WATER
DISPOSAL
Structural framed steel work
Supply, fabricate, hoist, erect and fix the following 5No. mild steel
trusses T38,49,43,54,52,55,58 grinding all welds smooth and
priming with two coats of approved metal primer all to Structural
Engineer's details
40 x 40 x 2mm Rafters                                                   64.8    Lm   14,000.0    907,200.0
40 x 40 x 2mm Tie beams                                                  54     Lm   14,000.0    756,000.0
40 x 40 x 2mm Struts and ties                                           108     Lm   14,000.0   1,512,000.0
180 x 180 x 6mm Thick mild steel base plate welded to steel
beams (measured separately) four times holed 10mm diameter
bolts                                                                    36     No   12,000.0    432,000.0
10mm Diameter grade 8.8 250mm long bolts complete with
heads, nuts and washers and bedded in concrete beams                    144     No    2,500.0    360,000.0
Supply, fabricate, hoist, erect and fix the following 1No. mild steel
truss T37,40,55 grinding all welds smooth and priming with two
coats of approved metal primer all to Structural Engineer's details
40 x 40 x 2mm Rafters                                                    54     Lm   14,000.0    756,000.0
40 x 40 x 2mm Tie beams                                                 43.2    Lm   14,000.0    604,800.0
40 x 40 x 2mm Struts and ties                                            84     Lm   14,000.0   1,176,000.0
180 x 180 x 8mm Thick mild steel base plate welded to steel
beams (measured separately) four times holed 10mm diameter
bolts
                                                                         12     No   12,000.0    144,000.0
10mm Diameter grade 8.8 250mm long bolts complete with
heads, nuts and washers and bedded in concrete beams
                                                                         48     No    2,500.0    120,000.0
Supply, fabricate, hoist, erect and fix the following 1No. mild steel
truss T36,41,45,53,31,56 grinding all welds smooth and priming
with two coats of approved metal primer all to Structural
Engineer's details
40 x 40 x 2mm Rafters                                                   119.7   Lm   14,000.0   1,675,800.0
40 x 40 x 2mm Tie beams                                                 112.5   Lm   14,000.0   1,575,000.0
40 x 40 x 2mm Struts and ties                                           100.8   Lm   14,000.0   1,411,200.0
180 x 180 x 8mm Thick mild steel base plate welded to steel
beams (measured separately) four times holed 10mm diameter
bolts                                                                    18      No   12,000.0    216,000.0
10mm Diameter grade 8.8 250mm long bolts complete with
heads, nuts and washers and bedded in concrete beams
                                                                         72      No    2,500.0    180,000.0
Supply, fabricate, hoist, erect and fix the following 1No. mild steel
truss T35,42,56,57,60,59 grinding all welds smooth and priming
with two coats of approved metal primer all to Structural
Engineer's details
40 x 40 x 2mm Rafters                                                    330     Lm   14,000.0   4,620,000.0
40 x 40 x 2mm Tie beams                                                 275.22   Lm   14,000.0   3,853,080.0
40 x 40 x 2mm Struts and ties                                            104     Lm   14,000.0   1,456,000.0
180 x 180 x 8mm Thick mild steel base plate welded to steel
beams (measured separately) four times holed 10mm diameter
bolts
                                                                         33      No   12,000.0    396,000.0
10mm Diameter grade 8.8 250mm long bolts complete with
heads, nuts and washers and bedded in concrete beams
                                                                         132     No    2,500.0    330,000.0
Supply, fabricate, hoist, erect and fix the following 1No. mild steel
truss T1,2,11,34,35,23,25,13grinding all welds smooth and
priming with two coats of approved metal primer all to Structural
Engineer's details
40 x 40 x 2mm Rafters                                                    144     Lm   14,000.0   2,016,000.0
40 x 40 x 2mm Tie Beam                                                  125.4    Lm   14,000.0   1,755,600.0
40 x 40 x 2mm Struts and ties                                           118.2    Lm
                                                                                      14,000.0   1,654,800.0
180 x 180 x 8mm Thick mild steel base plate welded to steel
beams (measured separately) four times holed 10mm diameter
bolts
                                                                         12      No   12,000.0    144,000.0
10mm Diameter grade 8.8 250mm long bolts complete with
heads, nuts and washers and bedded in concrete beams
                                                                         48      No    2,500.0    120,000.0
Supply, fabricate, hoist, erect and fix the following 10No. mild
steel trusses T6,15,17,14,10,18,30,28,26,24 and grinding all
welds smooth and priming with two coats of approved metal
primer all to Structural Engineer's details
40 x 40 x 2mm Rafters                                                    231     Lm   14,000.0   3,234,000.0
40 x 40 x 2mm Tie beams                                                 204.05   Lm   14,000.0   2,856,700.0
40 x 40 x 2mm Struts and ties                                           233.2    Lm   14,000.0   3,264,800.0
180 x 180 x 8mm Thick mild steel base plate welded to steel
beams (measured separately) four times holed 10mm diameter
bolts                                                                     22       No     12,000.0     264,000.0
10mm Diameter grade 8.8 250mm long bolts complete with
heads, nuts and washers and bedded in concrete beams
                                                                          88       No      2,500.0     220,000.0
Supply, fabricate, hoist, erect and fix the following 2No. mild steel
trusses T22,27,33,21,20,19,17,16,03 grinding all welds smooth
and priming with two coats of approved metal primer all to
Structural Engineer's details
40 x 40 x 2mm Rafters                                                     264      Lm     14,000.0    3,696,000.0
40 x 40 x 2mm Tie beams                                                   242      Lm     14,000.0    3,388,000.0
40 x 40 x 2mm Struts and ties                                             220      LM     14,000.0    3,080,000.0
180 x 180 x 6mm Thick mild steel base plate welded to steel
beams (measured separately) four times holed 10mm diameter
bolts                                                                     22       No     12,000.0     264,000.0
10mm Diameter grade 8.8 250mm long bolts complete with
heads, nuts and washers and bedded in concrete beams
                                                                          88       No      2,500.0     220,000.0
Structural unframedsteel work
Generally
100 x 50 x 20 x 2mm Thick Z-purlins                                     1713.004   LM     30,000.0   51,390,120.0
12mm Diameter x 1200mm long mild steel sag rods complete
with nuts and washers                                                     238      No      6,000.0    1,428,000.0
Sundries
Allow for gusset plates, cleats, bolts, drilling holes etc.                1330    Item               1,000,000.0
Roof sheeting and eaves soffits
28 Gauge pre-painted galvanised steel as described:-
IT4 Sheet roof coverings fixed to Z-purlins (measured separately)
at 1200mm centres general spacing with and including galvanised
steel hook bolts complete with nuts and felt washers                     1,786     SM     40,000.0   71,440,000.0
Ridge/hip cappings                                                        190      LM     30,000.0    5,700,000.0
Mild steel
600mm Girth x 2mm thick valley flashings                                  110      LM     48,750.0    5,362,500.0
Allow for connecting Iron sheets Self tapping screws               2579   No     750.0      1,934,250.0
Pvc
Fascia
250 x 3mm Thick                                                    200    LM   35,000.0     7,000,000.0
Rain water disposal
Gutters
160mm Diameter half round UPVC rain water gutter secured to
timber fascia board with and including screwed metal brackets at
900mm centres                                                      200    LM   25,000.0     5,000,000.0
Extra over 160mm UPVC gutter for angle connector                    16    No   30,000.0       480,000.0
100mm uPVC balloon grating
                                                                    16    No   30,000.0       480,000.0
Down pipes
100mm Diameter UPVC down pipe secured to block wall with
holderbats and jointed with approved compound.
                                                                   160    LM   25,000.0     4,000,000.0
Extra over for swannecks                                            32    No   30,000.0       960,000.0
Extra over for bends                                                32    No   30,000.0       960,000.0
Extra over for shoes
                                                                    32    No   30,000.0       960,000.0
Eaves soffits
Finishings
2No. 100 x 50mm softwood joists in one direction and 75 x 50mm
softwood bearers at 600mm centres in other direction; Cement :
sand 1:4 to ceiling mesh with provision of breathing holes.
                                                                   108    SM   30,000.0     3,240,000.0
Total cost                                                                                209,993,850.0