JSA Number:
JOB SAFETY ANALYSIS DATED ISSUED: 14 October 2024
JOB DESCRIPTION :
AREA/UNIT :
TAG NO. / EQUIPMENT DESCRIPTION :
REFERENCES :
PPE Required to do this Job :
Potensi Bahaya Pernyataan Kontrol
Langkah Kerja (Fisika, Kimia, Biologi, Potensi Kejadian (Diperlukan untuk mengurangi konsekuensi/dampak dan Peluang
dll.) kemungkinan terjadi)
Job Preparation
Preparation :
1. Tools
2. PJSM
3. PTW
Physical: Hand scratch, Finger Use proper hand glove
Prepare Tools
Hand Injury Injuries Prepare proper tools
Job Description
Electrical Job
Perform Drawer LOTO on MCB OFF Position
MOTOR HYD. STARTER - 23PDE005B5
MLO PUMP MOTOR 1 - 23PDE005B1
MLO PUMP MOTOR 2 - 23PDE005B2
Psychosocial : Wrong Ensure to LOTO on correct breaker (EGC - B), refer
Electric shock
SLO PUMP MOTOR 1 - 23PDE005B3 breaker to drawing
SLO PUMP MOTOR 2 - 23PDE005B4
ENCL. FAN MOTOR 1 - 23VDE005B1
ENCL. FAN MOTOR 2 - 23VDE005B2
MLO HEATER - 23BAP005B1
GG LO HEATER - 23BAP005B4
HYDRAULIC HEATER 23BAP005B5
- Check Drawers, clean up & check
Physical: Hand Injury Scratch (sharp object) Use medium hand glove & proper tools
tightness
- Check grounding arrangement, clean up
Physical: Hand Injury Scratch (sharp object) Use medium hand glove & proper tools
& check tightness
- Check all Junction Box motors accessories,
Physical: Hand Injury Scratch (sharp object) Use medium hand glove & proper tools
clean up & check tightness
- Perform Winding Insulation Test & Electrocution by
Physical: Electrocution Perform by competent personnel
Continuity Insulation tester
Connect motor connection with necessary
Physical: Hand Injury Slipped torque Use medium hand glove & proper torque wrench
torque
Job Completion
Physical: Slippery area Ensure unit and around area has tidy and clean.
1. Tidy up area.
-STF Pinched injury Segregate waste to trash bin
2. Clean up unit and area.
-Pinched point
3. Test runs the equipment.