Turbine Presentation

The forthcoming meeting will cover safety initiatives, equipment downtime analysis, running contracts for mechanical maintenance, and repair plans for FY 2025-26 and FY 2026-27. Notable machine breakdowns include TG 2's steam line leakage, STG 4's turbine overhaul, and Turbo-Blower 11's emergency repair due to lubrication failure. Upcoming capital repairs include revamping Turbo-generator 1 and overhauling STB machines, with a new micro TG proposed at BPTG PRDS.

Uploaded by

pbs.9407982196
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
39 views1 page

Turbine Presentation

The forthcoming meeting will cover safety initiatives, equipment downtime analysis, running contracts for mechanical maintenance, and repair plans for FY 2025-26 and FY 2026-27. Notable machine breakdowns include TG 2's steam line leakage, STG 4's turbine overhaul, and Turbo-Blower 11's emergency repair due to lubrication failure. Upcoming capital repairs include revamping Turbo-generator 1 and overhauling STB machines, with a new micro TG proposed at BPTG PRDS.

Uploaded by

pbs.9407982196
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Following are the main Topics for forthcoming meeting :

1. Safety Initiatives/Good Practices


2. Break down analysis of last 30-days for the equipment down for more than 2 Hrs.
3. List of Running Contracts for Mech. Maint. in Shop with details of Job description, Validity &
Value
4. Total plan of Repair & Maintenance on short term & long term, Capital Repairs and details of
proposed/undergoing IPU/AMR schemes for FY 2025-26 & FY 2026-27.
5. Status of Drawing Development & De-Proprietarization
6. List of Emergency Procurement for last 1-year i.e. 2024-25 with item description, Qty. &
Value with reasons of emergency procurement.

Machine Breakdown for More than 2 hrs:

1. TG 2 got down on for 3 days to attend leakage in steam line. For which machine needed
to cool down which takes approx. 48 hrs . Later, Flood test done to identify the leakage point
which found in turbine HP casing drain. Attending the leakage was essential as it may cause fire
incident if carried over to oil line.
2. STG 4 was down from 23 April 2025 to 23 May 2025 for overhauling of turbine and generator. Its
overhauling was pending as machine was running since 2019. There were major issues like
vacuum which was causing reduced generation (18 MW) at full steam load.
3. Turbo-Blower 11 got under emergency repair due to failure of lubrication oil in turbine bearing
which cause heavy damage in turbine rotor and its thrust bearing. Both turbine and blower
overhauling was done in Feb – march 2025.

Upcoming Capital repairs/Shutdown for 2025-26:

1. Turbo-generator 1 revamping to be completed in August 2025 so that it could run with full
capacity of 12 MW with lower steam consumption.
2. Short term shutdown of STG – 4 for improving vacuum of turbine so that full generation of
turbo-generator can be achieved.
3. STB – 1, 2 & 3 Capital Repair to be carried out in co-ordination with BF 8 shutdown. Machines
overhauling was not carried out since its commissioning.
4. BPTG overhauling to be carried out in December 2025 as soon as we receive the recommended
spares for overhauling.
5. Overhauling of TB 9 so that it could run at higher rpm and air pr. To cater furnace 4 & 6 with
higher volume of cold blast and pressure.

New IPU cases:

1. Micro TG proposed at BPTG PRDS