HIRA For Civil Work

The document outlines a Hazard Identification and Risk Assessment (HIRA) worksheet detailing various work activities, associated hazards, and control measures to mitigate risks. It emphasizes the importance of training, use of personal protective equipment (PPE), and adherence to safety protocols to prevent injuries and incidents at the workplace. Specific risks such as extreme weather conditions, manual material handling, and electrical work are addressed with recommended safety measures and supervision requirements.

Uploaded by

aqil7786jawed
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
32 views21 pages

HIRA For Civil Work

The document outlines a Hazard Identification and Risk Assessment (HIRA) worksheet detailing various work activities, associated hazards, and control measures to mitigate risks. It emphasizes the importance of training, use of personal protective equipment (PPE), and adherence to safety protocols to prevent injuries and incidents at the workplace. Specific risks such as extreme weather conditions, manual material handling, and electrical work are addressed with recommended safety measures and supervision requirements.

Uploaded by

aqil7786jawed
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 21

DELHI ENGINEERING SOLUTION

A - 43 Ram Dutt Enclave , Uttam Nagar New Delhi -110059

Hazard Identification & Risk Assessment and Control Measure Worksheet (HIRA) FORMAT NO:

HAZARD IDENTIFICATION RISK EVALUATION

Probability
Consequence

Risk Level
Work Activity

Severity
(Possible injury/Ill-Health/
S.N. (Job steps in Hazards Existing Control Measures
Persons-at-Risk &
sequence)
Environmental)

• Untrained/unskilled workmen • Unsafe act can lead to body • Ensure induction training of all workmen and staff employees.
Deployment of • Unsafe act injury or harm to other • Ensure skilled and trained workmen deployed at site.
1 Manpower/ Workmen • Unauthorised entry • Incident due to poor awareness 3 4 12 • Pre-job briefing /TBT to be conduct before start of work.
RISK
at site • Ergonomics Physical Injury • Unauthorised entry to be restricted in work premises. CONTROL
• Poor awareness • Wear mandatory PPE during the work like safety helmet, safety goggles,reflective jacket,
safety shoe Coverall etc.

• Adverse weather conditions • Heat Stroke • Working in cooling hours if necessary.

Probability
• Heavy Wind and dust

Risk Level
Severity
• Employee collapse required • Take regular short rest period and cool hydration drink..
Working in Extreme • Storm
2
Weather conditions • Heat & Humidity
medical attention 3 4 12 • Make sure briefing the symptoms of heat stroke to employee. Person responsible
• Death • Make sure rest shed to be provide to workmen.
• Poor Visibility • Dehydration and heat Cramps • Work must be stopped during the heavy rain and wind speed.

•Take work permit before start of work activities.


• Before start of the activity, conduct pre job briefing and have close monitoring for
supervision
• Access should be free from obstacles and obstructions..
• Physical hazard. • Bodily injury • Make proper barricading and strict
Manual Material • Property Damage • Material damage supervision to monitor the activity.
3 3 3 9 1 4 4 BISIL ENGG. SUP/HSE
Handling and shifting • Ergonomic hazard • Slips, trips and falling of men or
material. • Use proper manual handling technique.
• Use of all mandatory PPEs. to be ensured.
• Hand tools must be in good condition & ISI Standard.
• Do not move with over
load, if required handle the material with 2 or more persons.
• Loading and unloading activity to be carried out by trained and skill team & workmen.
• Tool box talk should be conducted prior start of work.
• Sharpe edge • Ensure adequately area available for unloading the material before commence of work.
• Improper Lifting • Body Injury • Work should be done under presence of supervision.
4 Loading and unloading • Fall of material • Sprain & strain 3 3 9 • Always use to mandatory PPEs before start the work . 1 4 4 BISIL ENGG. SUP/HSE
of material • Improper access • Crush & Hand Injury

• Ensure driver or operator should be valid Havey license and insurance of vehicle.
• Safe access or aggress should be provided for vehicle movement and road to be
demarcated.
• Display the traffic signage at site and traffic rules to be followed & speed limit 20 KM/h
to be adhered.
Construction vehicle • Hit or struck with vehicle • Damage Property
6 movement inside • Run over/back over • Crush Injury 3 4 12 • Working area to be barricaded along with displayed signage. 1 3 3 BISIL ENGG. SUP/HSE
• Strict supervision to be maintained during the work.
Tipper/Trailer/tractore • Unauthorised operation • Fatality/Disability • Reflective jacket must be worn in project premisson for better visibility & identification.

• Electrical work to done by trained and qualified electrician.


• Use insulated hand tools while working with power tools
• Make sure earthling to panel.
• • Make sure all cable termination should be properly tighten.
• 30mAmp ELCB/RCCB to be installed & Electrical DB shall be in good condition &
• Electrocution • ElectricShock inspected with colour code
Work site Power • Damage live cable • Fire/explosion • Inspection & checklist must be used while carried out maintenance activity and work
7 supply provision and • Short-circuit 4 5 20 permit must be taken before maintenance work. 1 3 3 BISIL ENGG. SUP/HSE
• Fatality due to high Electric Shock
Uses of power tools • Unauthorised operation and flash Over/Burn Injury • Make sure availability of fire extinguisher or sand bucket nearby work place
Hazard Identification & Risk Assessment and Control Measure Worksheet (HIRA) FORMAT NO:

HAZARD IDENTIFICATION RISK EVALUATION

Probability
Consequence

Risk Level
Work Activity

Severity
(Possible injury/Ill-Health/
S.N. (Job steps in Hazards Existing Control Measures
Persons-at-Risk &
sequence)
Environmental)

• Untrained/unskilled workmen • Unsafe act can lead to body • Ensure induction training of all workmen and staff employees.
Deployment of • Unsafe act injury or harm to other • Ensure skilled and trained workmen deployed at site.
1 Manpower/ Workmen • Unauthorised entry • Incident due to poor awareness 3 4 12 • Pre-job briefing /TBT to be conduct before start of work.
RISK
at site • Ergonomics Physical Injury • Unauthorised entry to be restricted in work premises. CONTROL
• Poor awareness • Wear mandatory PPE during the work like safety helmet, safety goggles,reflective jacket,
safety shoe Coverall etc.

• Adverse weather conditions • Heat Stroke • Working in cooling hours if necessary.

Probability
• Heavy Wind and dust

Risk Level
Severity
• Employee collapse required • Take regular short rest period and cool hydration drink..
Working in Extreme • Storm
2
Weather conditions • Heat & Humidity
medical attention 3 4 12 • Make sure briefing the symptoms of heat stroke to employee. Person responsible
• Death • Make sure rest shed to be provide to workmen.
• Poor Visibility • Dehydration and heat Cramps • Work must be stopped during the heavy rain and wind speed.

•Take work permit before start of work activities.

• Before start of the activity, conduct pre job briefing and have close monitoring for
supervision
• Access should be free from obstacles and obstructions..
• Physical hazard. • Bodily injury • Make proper barricading and strict
Manual Material • Property Damage • Material damage supervision to monitor the activity.
3 3 3 9 1 4 4 BISIL ENGG. SUP/HSE
Handling and shifting • Ergonomic hazard • Slips, trips and falling of men or
material. • Use proper manual handling technique.
• Use of all mandatory PPEs. to be ensured.

• Hand tools must be in good condition & ISI Standard.


• Do not move with over
load, if required handle the material with 2 or more persons.
• Loading and unloading activity to be carried out by trained and skill team & workmen.
• Tool box talk should be conducted prior start of work.
• Sharpe edge • Ensure adequately area available for unloading the material before commence of work.
• Improper Lifting • Body Injury • Work should be done under presence of supervision.
4 Loading and unloading • Fall of material • Sprain & strain 3 3 9 • Always use to mandatory PPEs before start the work . 1 4 4 BISIL ENGG. SUP/HSE
of material • Improper access • Crush & Hand Injury

• Ensure driver or operator should be valid Havey license and insurance of vehicle.
• Safe access or aggress should be provided for vehicle movement and road to be
demarcated.
• Display the traffic signage at site and traffic rules to be followed & speed limit 20 KM/h
to be adhered.
Construction vehicle • Hit or struck with vehicle • Damage Property
6 movement inside • Run over/back over • Crush Injury 3 4 12 • Working area to be barricaded along with displayed signage. 1 3 3 BISIL ENGG. SUP/HSE
• Strict supervision to be maintained during the work.
Tipper/Trailer/tractore • Unauthorised operation • Fatality/Disability • Reflective jacket must be worn in project premisson for better visibility & identification.

• Electrical work to done by trained and qualified electrician.


• Use insulated hand tools while working with power tools
• Make sure earthling to panel.
• • Make sure all cable termination should be properly tighten.
• 30mAmp ELCB/RCCB to be installed & Electrical DB shall be in good condition &
• Electrocution • ElectricShock inspected with colour code
Work site Power • Damage live cable • Fire/explosion • Inspection & checklist must be used while carried out maintenance activity and work
7 supply provision and • Short-circuit 4 5 20 permit must be taken before maintenance work. 1 3 3 BISIL ENGG. SUP/HSE
• Fatality due to high Electric Shock
Uses of power tools • Unauthorised operation and flash Over/Burn Injury • Make sure availability of fire extinguisher or sand bucket nearby work place
• Damage Tools • Use mandatory PPE during the electrical work. •
Ensure you, body and surface is dry during the operations

• Fall of material • All work at height will be subject to start after work permit
Hazard Identification & Risk Assessment and Control Measure Worksheet (HIRA) FORMAT NO:

HAZARD IDENTIFICATION RISK EVALUATION

Probability
Consequence

Risk Level
Work Activity

Severity
(Possible injury/Ill-Health/
S.N. (Job steps in Hazards Existing Control Measures
Persons-at-Risk &
sequence)
Environmental)

• Untrained/unskilled workmen • Unsafe act can lead to body • Ensure induction training of all workmen and staff employees.
Deployment of • Unsafe act injury or harm to other • Ensure skilled and trained workmen deployed at site.
1 Manpower/ Workmen • Unauthorised entry • Incident due to poor awareness 3 4 12 • Pre-job briefing /TBT to be conduct before start of work.
RISK
at site • Ergonomics Physical Injury • Unauthorised entry to be restricted in work premises. CONTROL
• Poor awareness • Wear mandatory PPE during the work like safety helmet, safety goggles,reflective jacket,
safety shoe Coverall etc.

• Adverse weather conditions • Heat Stroke • Working in cooling hours if necessary.

Probability
• Heavy Wind and dust

Risk Level
Severity
• Employee collapse required • Take regular short rest period and cool hydration drink..
Working in Extreme • Storm
2
Weather conditions • Heat & Humidity
medical attention 3 4 12 • Make sure briefing the symptoms of heat stroke to employee. Person responsible
• Death • Make sure rest shed to be provide to workmen.
• Poor Visibility • Dehydration and heat Cramps • Work must be stopped during the heavy rain and wind speed.

•Take work permit before start of work activities.

• Before start of the activity, conduct pre job briefing and have close monitoring for
supervision
• Access should be free from obstacles and obstructions..
• Physical hazard. • Bodily injury • Make proper barricading and strict
Manual Material • Property Damage • Material damage supervision to monitor the activity.
3 3 3 9 1 4 4 BISIL ENGG. SUP/HSE
Handling and shifting • Ergonomic hazard • Slips, trips and falling of men or
material. • Use proper manual handling technique.
• Use of all mandatory PPEs. to be ensured.

• Hand tools must be in good condition & ISI Standard.


• Do not move with over
load, if required handle the material with 2 or more persons.
• Loading and unloading activity to be carried out by trained and skill team & workmen.
• Tool box talk should be conducted prior start of work.
• Sharpe edge • Ensure adequately area available for unloading the material before commence of work.
• Improper Lifting • Body Injury • Work should be done under presence of supervision.
4 Loading and unloading • Fall of material • Sprain & strain 3 3 9 • Always use to mandatory PPEs before start the work . 1 4 4 BISIL ENGG. SUP/HSE
of material • Improper access • Crush & Hand Injury

• Ensure driver or operator should be valid Havey license and insurance of vehicle.
• Safe access or aggress should be provided for vehicle movement and road to be
demarcated.
• Display the traffic signage at site and traffic rules to be followed & speed limit 20 KM/h
to be adhered.
Construction vehicle • Hit or struck with vehicle • Damage Property
6 movement inside • Run over/back over • Crush Injury 3 4 12 • Working area to be barricaded along with displayed signage. 1 3 3 BISIL ENGG. SUP/HSE
• Strict supervision to be maintained during the work.
Tipper/Trailer/tractore • Unauthorised operation • Fatality/Disability • Reflective jacket must be worn in project premisson for better visibility & identification.

• Electrical work to done by trained and qualified electrician.


• Use insulated hand tools while working with power tools
• Make sure earthling to panel.
• • Make sure all cable termination should be properly tighten.
• 30mAmp ELCB/RCCB to be installed & Electrical DB shall be in good condition &
• Electrocution • ElectricShock inspected with colour code
Work site Power • Damage live cable • Fire/explosion • Inspection & checklist must be used while carried out maintenance activity and work
7 supply provision and • Short-circuit 4 5 20 permit must be taken before maintenance work. 1 3 3 BISIL ENGG. SUP/HSE
• Fatality due to high Electric Shock
Uses of power tools • Unauthorised operation and flash Over/Burn Injury • Make sure availability of fire extinguisher or sand bucket nearby work place
• Damage Tools • Use mandatory PPE during the electrical work. •
Ensure you, body and surface is dry during the operations

• Make sure access route obstructed free.


Hazard Identification & Risk Assessment and Control Measure Worksheet (HIRA) FORMAT NO:

HAZARD IDENTIFICATION RISK EVALUATION

Probability
Consequence

Risk Level
Work Activity

Severity
(Possible injury/Ill-Health/
S.N. (Job steps in Hazards Existing Control Measures
Persons-at-Risk &
sequence)
Environmental)

• Untrained/unskilled workmen • Unsafe act can lead to body • Ensure induction training of all workmen and staff employees.
Deployment of • Unsafe act injury or harm to other • Ensure skilled and trained workmen deployed at site.
1 Manpower/ Workmen • Unauthorised entry • Incident due to poor awareness 3 4 12 • Pre-job briefing /TBT to be conduct before start of work.
RISK
at site • Ergonomics Physical Injury • Unauthorised entry to be restricted in work premises. CONTROL
• Poor awareness • Wear mandatory PPE during the work like safety helmet, safety goggles,reflective jacket,
safety shoe Coverall etc.

• Adverse weather conditions • Heat Stroke • Working in cooling hours if necessary.

Probability
• Heavy Wind and dust

Risk Level
Severity
• Employee collapse required • Take regular short rest period and cool hydration drink..
Working in Extreme • Storm
2
Weather conditions • Heat & Humidity
medical attention 3 4 12 • Make sure briefing the symptoms of heat stroke to employee. Person responsible
• Death • Make sure rest shed to be provide to workmen.
• Poor Visibility • Dehydration and heat Cramps • Work must be stopped during the heavy rain and wind speed.

•Take work permit before start of work activities.

• Before start of the activity, conduct pre job briefing and have close monitoring for
supervision
• Access should be free from obstacles and obstructions..
• Physical hazard. • Bodily injury • Make proper barricading and strict
Manual Material • Property Damage • Material damage supervision to monitor the activity.
3 3 3 9 1 4 4 BISIL ENGG. SUP/HSE
Handling and shifting • Ergonomic hazard • Slips, trips and falling of men or
material. • Use proper manual handling technique.
• Use of all mandatory PPEs. to be ensured.

• Hand tools must be in good condition & ISI Standard.


• Do not move with over
load, if required handle the material with 2 or more persons.
• Loading and unloading activity to be carried out by trained and skill team & workmen.
• Tool box talk should be conducted prior start of work.
• Sharpe edge • Ensure adequately area available for unloading the material before commence of work.
• Improper Lifting • Body Injury • Work should be done under presence of supervision.
4 Loading and unloading • Fall of material • Sprain & strain 3 3 9 • Always use to mandatory PPEs before start the work . 1 4 4 BISIL ENGG. SUP/HSE
of material • Improper access • Crush & Hand Injury

• Ensure driver or operator should be valid Havey license and insurance of vehicle.
• Safe access or aggress should be provided for vehicle movement and road to be
demarcated.
• Display the traffic signage at site and traffic rules to be followed & speed limit 20 KM/h
to be adhered.
Construction vehicle • Hit or struck with vehicle • Damage Property
6 movement inside • Run over/back over • Crush Injury 3 4 12 • Working area to be barricaded along with displayed signage. 1 3 3 BISIL ENGG. SUP/HSE
• Strict supervision to be maintained during the work.
Tipper/Trailer/tractore • Unauthorised operation • Fatality/Disability • Reflective jacket must be worn in project premisson for better visibility & identification.

• Electrical work to done by trained and qualified electrician.


• Use insulated hand tools while working with power tools
• Make sure earthling to panel.
• • Make sure all cable termination should be properly tighten.
• 30mAmp ELCB/RCCB to be installed & Electrical DB shall be in good condition &
• Electrocution • ElectricShock inspected with colour code
Work site Power • Damage live cable • Fire/explosion • Inspection & checklist must be used while carried out maintenance activity and work
7 supply provision and • Short-circuit 4 5 20 permit must be taken before maintenance work. 1 3 3 BISIL ENGG. SUP/HSE
• Fatality due to high Electric Shock
Uses of power tools • Unauthorised operation and flash Over/Burn Injury • Make sure availability of fire extinguisher or sand bucket nearby work place
• Damage Tools • Use mandatory PPE during the electrical work. •
Ensure you, body and surface is dry during the operations

• Compactor machine to be operate by competent person.


Hazard Identification & Risk Assessment and Control Measure Worksheet (HIRA) FORMAT NO:

HAZARD IDENTIFICATION RISK EVALUATION

Probability
Consequence

Risk Level
Work Activity

Severity
(Possible injury/Ill-Health/
S.N. (Job steps in Hazards Existing Control Measures
Persons-at-Risk &
sequence)
Environmental)

• Untrained/unskilled workmen • Unsafe act can lead to body • Ensure induction training of all workmen and staff employees.
Deployment of • Unsafe act injury or harm to other • Ensure skilled and trained workmen deployed at site.
1 Manpower/ Workmen • Unauthorised entry • Incident due to poor awareness 3 4 12 • Pre-job briefing /TBT to be conduct before start of work.
RISK
at site • Ergonomics Physical Injury • Unauthorised entry to be restricted in work premises. CONTROL
• Poor awareness • Wear mandatory PPE during the work like safety helmet, safety goggles,reflective jacket,
safety shoe Coverall etc.

• Adverse weather conditions • Heat Stroke • Working in cooling hours if necessary.

Probability
• Heavy Wind and dust

Risk Level
Severity
• Employee collapse required • Take regular short rest period and cool hydration drink..
Working in Extreme • Storm
2
Weather conditions • Heat & Humidity
medical attention 3 4 12 • Make sure briefing the symptoms of heat stroke to employee. Person responsible
• Death • Make sure rest shed to be provide to workmen.
• Poor Visibility • Dehydration and heat Cramps • Work must be stopped during the heavy rain and wind speed.

•Take work permit before start of work activities.

• Before start of the activity, conduct pre job briefing and have close monitoring for
supervision
• Access should be free from obstacles and obstructions..
• Physical hazard. • Bodily injury • Make proper barricading and strict
Manual Material • Property Damage • Material damage supervision to monitor the activity.
3 3 3 9 1 4 4 BISIL ENGG. SUP/HSE
Handling and shifting • Ergonomic hazard • Slips, trips and falling of men or
material. • Use proper manual handling technique.
• Use of all mandatory PPEs. to be ensured.

• Hand tools must be in good condition & ISI Standard.


• Do not move with over
load, if required handle the material with 2 or more persons.
• Loading and unloading activity to be carried out by trained and skill team & workmen.
• Tool box talk should be conducted prior start of work.
• Sharpe edge • Ensure adequately area available for unloading the material before commence of work.
• Improper Lifting • Body Injury • Work should be done under presence of supervision.
4 Loading and unloading • Fall of material • Sprain & strain 3 3 9 • Always use to mandatory PPEs before start the work . 1 4 4 BISIL ENGG. SUP/HSE
of material • Improper access • Crush & Hand Injury

• Ensure driver or operator should be valid Havey license and insurance of vehicle.
• Safe access or aggress should be provided for vehicle movement and road to be
demarcated.
• Display the traffic signage at site and traffic rules to be followed & speed limit 20 KM/h
to be adhered.
Construction vehicle • Hit or struck with vehicle • Damage Property
6 movement inside • Run over/back over • Crush Injury 3 4 12 • Working area to be barricaded along with displayed signage. 1 3 3 BISIL ENGG. SUP/HSE
• Strict supervision to be maintained during the work.
Tipper/Trailer/tractore • Unauthorised operation • Fatality/Disability • Reflective jacket must be worn in project premisson for better visibility & identification.

• Electrical work to done by trained and qualified electrician.


• Use insulated hand tools while working with power tools
• Make sure earthling to panel.
• • Make sure all cable termination should be properly tighten.
• 30mAmp ELCB/RCCB to be installed & Electrical DB shall be in good condition &
• Electrocution • ElectricShock inspected with colour code
Work site Power • Damage live cable • Fire/explosion • Inspection & checklist must be used while carried out maintenance activity and work
7 supply provision and • Short-circuit 4 5 20 permit must be taken before maintenance work. 1 3 3 BISIL ENGG. SUP/HSE
• Fatality due to high Electric Shock
Uses of power tools • Unauthorised operation and flash Over/Burn Injury • Make sure availability of fire extinguisher or sand bucket nearby work place
• Damage Tools • Use mandatory PPE during the electrical work. •
Ensure you, body and surface is dry during the operations

• Fall of material • Injury Fatality • Ensure proper supporting system used


Hazard Identification & Risk Assessment and Control Measure Worksheet (HIRA) FORMAT NO:

HAZARD IDENTIFICATION RISK EVALUATION

Probability
Consequence

Risk Level
Work Activity

Severity
(Possible injury/Ill-Health/
S.N. (Job steps in Hazards Existing Control Measures
Persons-at-Risk &
sequence)
Environmental)

• Untrained/unskilled workmen • Unsafe act can lead to body • Ensure induction training of all workmen and staff employees.
Deployment of • Unsafe act injury or harm to other • Ensure skilled and trained workmen deployed at site.
1 Manpower/ Workmen • Unauthorised entry • Incident due to poor awareness 3 4 12 • Pre-job briefing /TBT to be conduct before start of work.
RISK
at site • Ergonomics Physical Injury • Unauthorised entry to be restricted in work premises. CONTROL
• Poor awareness • Wear mandatory PPE during the work like safety helmet, safety goggles,reflective jacket,
safety shoe Coverall etc.

• Adverse weather conditions • Heat Stroke • Working in cooling hours if necessary.

Probability
• Heavy Wind and dust

Risk Level
Severity
• Employee collapse required • Take regular short rest period and cool hydration drink..
Working in Extreme • Storm
2
Weather conditions • Heat & Humidity
medical attention 3 4 12 • Make sure briefing the symptoms of heat stroke to employee. Person responsible
• Death • Make sure rest shed to be provide to workmen.
• Poor Visibility • Dehydration and heat Cramps • Work must be stopped during the heavy rain and wind speed.

•Take work permit before start of work activities.

• Before start of the activity, conduct pre job briefing and have close monitoring for
supervision
• Access should be free from obstacles and obstructions..
• Physical hazard. • Bodily injury • Make proper barricading and strict
Manual Material • Property Damage • Material damage supervision to monitor the activity.
3 3 3 9 1 4 4 BISIL ENGG. SUP/HSE
Handling and shifting • Ergonomic hazard • Slips, trips and falling of men or
material. • Use proper manual handling technique.
• Use of all mandatory PPEs. to be ensured.

• Hand tools must be in good condition & ISI Standard.


• Do not move with over
load, if required handle the material with 2 or more persons.
• Loading and unloading activity to be carried out by trained and skill team & workmen.
• Tool box talk should be conducted prior start of work.
• Sharpe edge • Ensure adequately area available for unloading the material before commence of work.
• Improper Lifting • Body Injury • Work should be done under presence of supervision.
4 Loading and unloading • Fall of material • Sprain & strain 3 3 9 • Always use to mandatory PPEs before start the work . 1 4 4 BISIL ENGG. SUP/HSE
of material • Improper access • Crush & Hand Injury

• Ensure driver or operator should be valid Havey license and insurance of vehicle.
• Safe access or aggress should be provided for vehicle movement and road to be
demarcated.
• Display the traffic signage at site and traffic rules to be followed & speed limit 20 KM/h
to be adhered.
Construction vehicle • Hit or struck with vehicle • Damage Property
6 movement inside • Run over/back over • Crush Injury 3 4 12 • Working area to be barricaded along with displayed signage. 1 3 3 BISIL ENGG. SUP/HSE
• Strict supervision to be maintained during the work.
Tipper/Trailer/tractore • Unauthorised operation • Fatality/Disability • Reflective jacket must be worn in project premisson for better visibility & identification.

• Electrical work to done by trained and qualified electrician.


• Use insulated hand tools while working with power tools
• Make sure earthling to panel.
• • Make sure all cable termination should be properly tighten.
• 30mAmp ELCB/RCCB to be installed & Electrical DB shall be in good condition &
• Electrocution • ElectricShock inspected with colour code
Work site Power • Damage live cable • Fire/explosion • Inspection & checklist must be used while carried out maintenance activity and work
7 supply provision and • Short-circuit 4 5 20 permit must be taken before maintenance work. 1 3 3 BISIL ENGG. SUP/HSE
• Fatality due to high Electric Shock
Uses of power tools • Unauthorised operation and flash Over/Burn Injury • Make sure availability of fire extinguisher or sand bucket nearby work place
• Damage Tools • Use mandatory PPE during the electrical work. •
Ensure you, body and surface is dry during the operations

• Bar cutting machine to be inspected prior to use.


Hazard Identification & Risk Assessment and Control Measure Worksheet (HIRA) FORMAT NO:

HAZARD IDENTIFICATION RISK EVALUATION

Probability
Consequence

Risk Level
Work Activity

Severity
(Possible injury/Ill-Health/
S.N. (Job steps in Hazards Existing Control Measures
Persons-at-Risk &
sequence)
Environmental)

• Untrained/unskilled workmen • Unsafe act can lead to body • Ensure induction training of all workmen and staff employees.
Deployment of • Unsafe act injury or harm to other • Ensure skilled and trained workmen deployed at site.
1 Manpower/ Workmen • Unauthorised entry • Incident due to poor awareness 3 4 12 • Pre-job briefing /TBT to be conduct before start of work.
RISK
at site • Ergonomics Physical Injury • Unauthorised entry to be restricted in work premises. CONTROL
• Poor awareness • Wear mandatory PPE during the work like safety helmet, safety goggles,reflective jacket,
safety shoe Coverall etc.

• Adverse weather conditions • Heat Stroke • Working in cooling hours if necessary.

Probability
• Heavy Wind and dust

Risk Level
Severity
• Employee collapse required • Take regular short rest period and cool hydration drink..
Working in Extreme • Storm
2
Weather conditions • Heat & Humidity
medical attention 3 4 12 • Make sure briefing the symptoms of heat stroke to employee. Person responsible
• Death • Make sure rest shed to be provide to workmen.
• Poor Visibility • Dehydration and heat Cramps • Work must be stopped during the heavy rain and wind speed.

•Take work permit before start of work activities.

• Before start of the activity, conduct pre job briefing and have close monitoring for
supervision
• Access should be free from obstacles and obstructions..
• Physical hazard. • Bodily injury • Make proper barricading and strict
Manual Material • Property Damage • Material damage supervision to monitor the activity.
3 3 3 9 1 4 4 BISIL ENGG. SUP/HSE
Handling and shifting • Ergonomic hazard • Slips, trips and falling of men or
material. • Use proper manual handling technique.
• Use of all mandatory PPEs. to be ensured.

• Hand tools must be in good condition & ISI Standard.


• Do not move with over
load, if required handle the material with 2 or more persons.
• Loading and unloading activity to be carried out by trained and skill team & workmen.
• Tool box talk should be conducted prior start of work.
• Sharpe edge • Ensure adequately area available for unloading the material before commence of work.
• Improper Lifting • Body Injury • Work should be done under presence of supervision.
4 Loading and unloading • Fall of material • Sprain & strain 3 3 9 • Always use to mandatory PPEs before start the work . 1 4 4 BISIL ENGG. SUP/HSE
of material • Improper access • Crush & Hand Injury

• Ensure driver or operator should be valid Havey license and insurance of vehicle.
• Safe access or aggress should be provided for vehicle movement and road to be
demarcated.
• Display the traffic signage at site and traffic rules to be followed & speed limit 20 KM/h
to be adhered.
Construction vehicle • Hit or struck with vehicle • Damage Property
6 movement inside • Run over/back over • Crush Injury 3 4 12 • Working area to be barricaded along with displayed signage. 1 3 3 BISIL ENGG. SUP/HSE
• Strict supervision to be maintained during the work.
Tipper/Trailer/tractore • Unauthorised operation • Fatality/Disability • Reflective jacket must be worn in project premisson for better visibility & identification.

• Electrical work to done by trained and qualified electrician.


• Use insulated hand tools while working with power tools
• Make sure earthling to panel.
• • Make sure all cable termination should be properly tighten.
• 30mAmp ELCB/RCCB to be installed & Electrical DB shall be in good condition &
• Electrocution • ElectricShock inspected with colour code
Work site Power • Damage live cable • Fire/explosion • Inspection & checklist must be used while carried out maintenance activity and work
7 supply provision and • Short-circuit 4 5 20 permit must be taken before maintenance work. 1 3 3 BISIL ENGG. SUP/HSE
• Fatality due to high Electric Shock
Uses of power tools • Unauthorised operation and flash Over/Burn Injury • Make sure availability of fire extinguisher or sand bucket nearby work place
• Damage Tools • Use mandatory PPE during the electrical work. •
Ensure you, body and surface is dry during the operations

• Make sure use guarded power tools and unguarded machine should be replaced and
Hazard Identification & Risk Assessment and Control Measure Worksheet (HIRA) FORMAT NO:

HAZARD IDENTIFICATION RISK EVALUATION

Probability
Consequence

Risk Level
Work Activity

Severity
(Possible injury/Ill-Health/
S.N. (Job steps in Hazards Existing Control Measures
Persons-at-Risk &
sequence)
Environmental)

• Untrained/unskilled workmen • Unsafe act can lead to body • Ensure induction training of all workmen and staff employees.
Deployment of • Unsafe act injury or harm to other • Ensure skilled and trained workmen deployed at site.
1 Manpower/ Workmen • Unauthorised entry • Incident due to poor awareness 3 4 12 • Pre-job briefing /TBT to be conduct before start of work.
RISK
at site • Ergonomics Physical Injury • Unauthorised entry to be restricted in work premises. CONTROL
• Poor awareness • Wear mandatory PPE during the work like safety helmet, safety goggles,reflective jacket,
safety shoe Coverall etc.

• Adverse weather conditions • Heat Stroke • Working in cooling hours if necessary.

Probability
• Heavy Wind and dust

Risk Level
Severity
• Employee collapse required • Take regular short rest period and cool hydration drink..
Working in Extreme • Storm
2
Weather conditions • Heat & Humidity
medical attention 3 4 12 • Make sure briefing the symptoms of heat stroke to employee. Person responsible
• Death • Make sure rest shed to be provide to workmen.
• Poor Visibility • Dehydration and heat Cramps • Work must be stopped during the heavy rain and wind speed.

•Take work permit before start of work activities.

• Before start of the activity, conduct pre job briefing and have close monitoring for
supervision
• Access should be free from obstacles and obstructions..
• Physical hazard. • Bodily injury • Make proper barricading and strict
Manual Material • Property Damage • Material damage supervision to monitor the activity.
3 3 3 9 1 4 4 BISIL ENGG. SUP/HSE
Handling and shifting • Ergonomic hazard • Slips, trips and falling of men or
material. • Use proper manual handling technique.
• Use of all mandatory PPEs. to be ensured.

• Hand tools must be in good condition & ISI Standard.


• Do not move with over
load, if required handle the material with 2 or more persons.
• Loading and unloading activity to be carried out by trained and skill team & workmen.
• Tool box talk should be conducted prior start of work.
• Sharpe edge • Ensure adequately area available for unloading the material before commence of work.
• Improper Lifting • Body Injury • Work should be done under presence of supervision.
4 Loading and unloading • Fall of material • Sprain & strain 3 3 9 • Always use to mandatory PPEs before start the work . 1 4 4 BISIL ENGG. SUP/HSE
of material • Improper access • Crush & Hand Injury

• Ensure driver or operator should be valid Havey license and insurance of vehicle.
• Safe access or aggress should be provided for vehicle movement and road to be
demarcated.
• Display the traffic signage at site and traffic rules to be followed & speed limit 20 KM/h
to be adhered.
Construction vehicle • Hit or struck with vehicle • Damage Property
6 movement inside • Run over/back over • Crush Injury 3 4 12 • Working area to be barricaded along with displayed signage. 1 3 3 BISIL ENGG. SUP/HSE
• Strict supervision to be maintained during the work.
Tipper/Trailer/tractore • Unauthorised operation • Fatality/Disability • Reflective jacket must be worn in project premisson for better visibility & identification.

• Electrical work to done by trained and qualified electrician.


• Use insulated hand tools while working with power tools
• Make sure earthling to panel.
• • Make sure all cable termination should be properly tighten.
• 30mAmp ELCB/RCCB to be installed & Electrical DB shall be in good condition &
• Electrocution • ElectricShock inspected with colour code
Work site Power • Damage live cable • Fire/explosion • Inspection & checklist must be used while carried out maintenance activity and work
7 supply provision and • Short-circuit 4 5 20 permit must be taken before maintenance work. 1 3 3 BISIL ENGG. SUP/HSE
• Fatality due to high Electric Shock
Uses of power tools • Unauthorised operation and flash Over/Burn Injury • Make sure availability of fire extinguisher or sand bucket nearby work place
• Damage Tools • Use mandatory PPE during the electrical work. •
Ensure you, body and surface is dry during the operations

• Reinforcement to be carried out by trained and competent person.


Hazard Identification & Risk Assessment and Control Measure Worksheet (HIRA) FORMAT NO:

HAZARD IDENTIFICATION RISK EVALUATION

Probability
Consequence

Risk Level
Work Activity

Severity
(Possible injury/Ill-Health/
S.N. (Job steps in Hazards Existing Control Measures
Persons-at-Risk &
sequence)
Environmental)

• Untrained/unskilled workmen • Unsafe act can lead to body • Ensure induction training of all workmen and staff employees.
Deployment of • Unsafe act injury or harm to other • Ensure skilled and trained workmen deployed at site.
1 Manpower/ Workmen • Unauthorised entry • Incident due to poor awareness 3 4 12 • Pre-job briefing /TBT to be conduct before start of work.
RISK
at site • Ergonomics Physical Injury • Unauthorised entry to be restricted in work premises. CONTROL
• Poor awareness • Wear mandatory PPE during the work like safety helmet, safety goggles,reflective jacket,
safety shoe Coverall etc.

• Adverse weather conditions • Heat Stroke • Working in cooling hours if necessary.

Probability
• Heavy Wind and dust

Risk Level
Severity
• Employee collapse required • Take regular short rest period and cool hydration drink..
Working in Extreme • Storm
2
Weather conditions • Heat & Humidity
medical attention 3 4 12 • Make sure briefing the symptoms of heat stroke to employee. Person responsible
• Death • Make sure rest shed to be provide to workmen.
• Poor Visibility • Dehydration and heat Cramps • Work must be stopped during the heavy rain and wind speed.

•Take work permit before start of work activities.

• Before start of the activity, conduct pre job briefing and have close monitoring for
supervision
• Access should be free from obstacles and obstructions..
• Physical hazard. • Bodily injury • Make proper barricading and strict
Manual Material • Property Damage • Material damage supervision to monitor the activity.
3 3 3 9 1 4 4 BISIL ENGG. SUP/HSE
Handling and shifting • Ergonomic hazard • Slips, trips and falling of men or
material. • Use proper manual handling technique.
• Use of all mandatory PPEs. to be ensured.

• Hand tools must be in good condition & ISI Standard.


• Do not move with over
load, if required handle the material with 2 or more persons.
• Loading and unloading activity to be carried out by trained and skill team & workmen.
• Tool box talk should be conducted prior start of work.
• Sharpe edge • Ensure adequately area available for unloading the material before commence of work.
• Improper Lifting • Body Injury • Work should be done under presence of supervision.
4 Loading and unloading • Fall of material • Sprain & strain 3 3 9 • Always use to mandatory PPEs before start the work . 1 4 4 BISIL ENGG. SUP/HSE
of material • Improper access • Crush & Hand Injury

• Ensure driver or operator should be valid Havey license and insurance of vehicle.
• Safe access or aggress should be provided for vehicle movement and road to be
demarcated.
• Display the traffic signage at site and traffic rules to be followed & speed limit 20 KM/h
to be adhered.
Construction vehicle • Hit or struck with vehicle • Damage Property
6 movement inside • Run over/back over • Crush Injury 3 4 12 • Working area to be barricaded along with displayed signage. 1 3 3 BISIL ENGG. SUP/HSE
• Strict supervision to be maintained during the work.
Tipper/Trailer/tractore • Unauthorised operation • Fatality/Disability • Reflective jacket must be worn in project premisson for better visibility & identification.

• Electrical work to done by trained and qualified electrician.


• Use insulated hand tools while working with power tools
• Make sure earthling to panel.
• • Make sure all cable termination should be properly tighten.
• 30mAmp ELCB/RCCB to be installed & Electrical DB shall be in good condition &
• Electrocution • ElectricShock inspected with colour code
Work site Power • Damage live cable • Fire/explosion • Inspection & checklist must be used while carried out maintenance activity and work
7 supply provision and • Short-circuit 4 5 20 permit must be taken before maintenance work. 1 3 3 BISIL ENGG. SUP/HSE
• Fatality due to high Electric Shock
Uses of power tools • Unauthorised operation and flash Over/Burn Injury • Make sure availability of fire extinguisher or sand bucket nearby work place
• Damage Tools • Use mandatory PPE during the electrical work. •
Ensure you, body and surface is dry during the operations

• Barricading the working area.


Hazard Identification & Risk Assessment and Control Measure Worksheet (HIRA) FORMAT NO:

HAZARD IDENTIFICATION RISK EVALUATION

Probability
Consequence

Risk Level
Work Activity

Severity
(Possible injury/Ill-Health/
S.N. (Job steps in Hazards Existing Control Measures
Persons-at-Risk &
sequence)
Environmental)

• Untrained/unskilled workmen • Unsafe act can lead to body • Ensure induction training of all workmen and staff employees.
Deployment of • Unsafe act injury or harm to other • Ensure skilled and trained workmen deployed at site.
1 Manpower/ Workmen • Unauthorised entry • Incident due to poor awareness 3 4 12 • Pre-job briefing /TBT to be conduct before start of work.
RISK
at site • Ergonomics Physical Injury • Unauthorised entry to be restricted in work premises. CONTROL
• Poor awareness • Wear mandatory PPE during the work like safety helmet, safety goggles,reflective jacket,
safety shoe Coverall etc.

• Adverse weather conditions • Heat Stroke • Working in cooling hours if necessary.

Probability
• Heavy Wind and dust

Risk Level
Severity
• Employee collapse required • Take regular short rest period and cool hydration drink..
Working in Extreme • Storm
2
Weather conditions • Heat & Humidity
medical attention 3 4 12 • Make sure briefing the symptoms of heat stroke to employee. Person responsible
• Death • Make sure rest shed to be provide to workmen.
• Poor Visibility • Dehydration and heat Cramps • Work must be stopped during the heavy rain and wind speed.

•Take work permit before start of work activities.

• Before start of the activity, conduct pre job briefing and have close monitoring for
supervision
• Access should be free from obstacles and obstructions..
• Physical hazard. • Bodily injury • Make proper barricading and strict
Manual Material • Property Damage • Material damage supervision to monitor the activity.
3 3 3 9 1 4 4 BISIL ENGG. SUP/HSE
Handling and shifting • Ergonomic hazard • Slips, trips and falling of men or
material. • Use proper manual handling technique.
• Use of all mandatory PPEs. to be ensured.

• Hand tools must be in good condition & ISI Standard.


• Do not move with over
load, if required handle the material with 2 or more persons.
• Loading and unloading activity to be carried out by trained and skill team & workmen.
• Tool box talk should be conducted prior start of work.
• Sharpe edge • Ensure adequately area available for unloading the material before commence of work.
• Improper Lifting • Body Injury • Work should be done under presence of supervision.
4 Loading and unloading • Fall of material • Sprain & strain 3 3 9 • Always use to mandatory PPEs before start the work . 1 4 4 BISIL ENGG. SUP/HSE
of material • Improper access • Crush & Hand Injury

• Ensure driver or operator should be valid Havey license and insurance of vehicle.
• Safe access or aggress should be provided for vehicle movement and road to be
demarcated.
• Display the traffic signage at site and traffic rules to be followed & speed limit 20 KM/h
to be adhered.
Construction vehicle • Hit or struck with vehicle • Damage Property
6 movement inside • Run over/back over • Crush Injury 3 4 12 • Working area to be barricaded along with displayed signage. 1 3 3 BISIL ENGG. SUP/HSE
• Strict supervision to be maintained during the work.
Tipper/Trailer/tractore • Unauthorised operation • Fatality/Disability • Reflective jacket must be worn in project premisson for better visibility & identification.

• Electrical work to done by trained and qualified electrician.


• Use insulated hand tools while working with power tools
• Make sure earthling to panel.
• • Make sure all cable termination should be properly tighten.
• 30mAmp ELCB/RCCB to be installed & Electrical DB shall be in good condition &
• Electrocution • ElectricShock inspected with colour code
Work site Power • Damage live cable • Fire/explosion • Inspection & checklist must be used while carried out maintenance activity and work
7 supply provision and • Short-circuit 4 5 20 permit must be taken before maintenance work. 1 3 3 BISIL ENGG. SUP/HSE
• Fatality due to high Electric Shock
Uses of power tools • Unauthorised operation and flash Over/Burn Injury • Make sure availability of fire extinguisher or sand bucket nearby work place
• Damage Tools • Use mandatory PPE during the electrical work. •
Ensure you, body and surface is dry during the operations

• Competent supervision and adequate Inspection of concrete mixer machines


Hazard Identification & Risk Assessment and Control Measure Worksheet (HIRA) FORMAT NO:

HAZARD IDENTIFICATION RISK EVALUATION

Probability
Consequence

Risk Level
Work Activity

Severity
(Possible injury/Ill-Health/
S.N. (Job steps in Hazards Existing Control Measures
Persons-at-Risk &
sequence)
Environmental)

• Untrained/unskilled workmen • Unsafe act can lead to body • Ensure induction training of all workmen and staff employees.
Deployment of • Unsafe act injury or harm to other • Ensure skilled and trained workmen deployed at site.
1 Manpower/ Workmen • Unauthorised entry • Incident due to poor awareness 3 4 12 • Pre-job briefing /TBT to be conduct before start of work.
RISK
at site • Ergonomics Physical Injury • Unauthorised entry to be restricted in work premises. CONTROL
• Poor awareness • Wear mandatory PPE during the work like safety helmet, safety goggles,reflective jacket,
safety shoe Coverall etc.

• Adverse weather conditions • Heat Stroke • Working in cooling hours if necessary.

Probability
• Heavy Wind and dust

Risk Level
Severity
• Employee collapse required • Take regular short rest period and cool hydration drink..
Working in Extreme • Storm
2
Weather conditions • Heat & Humidity
medical attention 3 4 12 • Make sure briefing the symptoms of heat stroke to employee. Person responsible
• Death • Make sure rest shed to be provide to workmen.
• Poor Visibility • Dehydration and heat Cramps • Work must be stopped during the heavy rain and wind speed.

•Take work permit before start of work activities.

• Before start of the activity, conduct pre job briefing and have close monitoring for
supervision
• Access should be free from obstacles and obstructions..
• Physical hazard. • Bodily injury • Make proper barricading and strict
Manual Material • Property Damage • Material damage supervision to monitor the activity.
3 3 3 9 1 4 4 BISIL ENGG. SUP/HSE
Handling and shifting • Ergonomic hazard • Slips, trips and falling of men or
material. • Use proper manual handling technique.
• Use of all mandatory PPEs. to be ensured.

• Hand tools must be in good condition & ISI Standard.


• Do not move with over
load, if required handle the material with 2 or more persons.
• Loading and unloading activity to be carried out by trained and skill team & workmen.
• Tool box talk should be conducted prior start of work.
• Sharpe edge • Ensure adequately area available for unloading the material before commence of work.
• Improper Lifting • Body Injury • Work should be done under presence of supervision.
4 Loading and unloading • Fall of material • Sprain & strain 3 3 9 • Always use to mandatory PPEs before start the work . 1 4 4 BISIL ENGG. SUP/HSE
of material • Improper access • Crush & Hand Injury

• Ensure driver or operator should be valid Havey license and insurance of vehicle.
• Safe access or aggress should be provided for vehicle movement and road to be
demarcated.
• Display the traffic signage at site and traffic rules to be followed & speed limit 20 KM/h
to be adhered.
Construction vehicle • Hit or struck with vehicle • Damage Property
6 movement inside • Run over/back over • Crush Injury 3 4 12 • Working area to be barricaded along with displayed signage. 1 3 3 BISIL ENGG. SUP/HSE
• Strict supervision to be maintained during the work.
Tipper/Trailer/tractore • Unauthorised operation • Fatality/Disability • Reflective jacket must be worn in project premisson for better visibility & identification.

• Electrical work to done by trained and qualified electrician.


• Use insulated hand tools while working with power tools
• Make sure earthling to panel.
• • Make sure all cable termination should be properly tighten.
• 30mAmp ELCB/RCCB to be installed & Electrical DB shall be in good condition &
• Electrocution • ElectricShock inspected with colour code
Work site Power • Damage live cable • Fire/explosion • Inspection & checklist must be used while carried out maintenance activity and work
7 supply provision and • Short-circuit 4 5 20 permit must be taken before maintenance work. 1 3 3 BISIL ENGG. SUP/HSE
• Fatality due to high Electric Shock
Uses of power tools • Unauthorised operation and flash Over/Burn Injury • Make sure availability of fire extinguisher or sand bucket nearby work place
• Damage Tools • Use mandatory PPE during the electrical work. •
Ensure you, body and surface is dry during the operations

• Competent supervision and adequate Inspection of mixer machines


Hazard Identification & Risk Assessment and Control Measure Worksheet (HIRA) FORMAT NO:

HAZARD IDENTIFICATION RISK EVALUATION

Probability
Consequence

Risk Level
Work Activity

Severity
(Possible injury/Ill-Health/
S.N. (Job steps in Hazards Existing Control Measures
Persons-at-Risk &
sequence)
Environmental)

• Untrained/unskilled workmen • Unsafe act can lead to body • Ensure induction training of all workmen and staff employees.
Deployment of • Unsafe act injury or harm to other • Ensure skilled and trained workmen deployed at site.
1 Manpower/ Workmen • Unauthorised entry • Incident due to poor awareness 3 4 12 • Pre-job briefing /TBT to be conduct before start of work.
RISK
at site • Ergonomics Physical Injury • Unauthorised entry to be restricted in work premises. CONTROL
• Poor awareness • Wear mandatory PPE during the work like safety helmet, safety goggles,reflective jacket,
safety shoe Coverall etc.

• Adverse weather conditions • Heat Stroke • Working in cooling hours if necessary.

Probability
• Heavy Wind and dust

Risk Level
Severity
• Employee collapse required • Take regular short rest period and cool hydration drink..
Working in Extreme • Storm
2
Weather conditions • Heat & Humidity
medical attention 3 4 12 • Make sure briefing the symptoms of heat stroke to employee. Person responsible
• Death • Make sure rest shed to be provide to workmen.
• Poor Visibility • Dehydration and heat Cramps • Work must be stopped during the heavy rain and wind speed.

•Take work permit before start of work activities.

• Before start of the activity, conduct pre job briefing and have close monitoring for
supervision
• Access should be free from obstacles and obstructions..
• Physical hazard. • Bodily injury • Make proper barricading and strict
Manual Material • Property Damage • Material damage supervision to monitor the activity.
3 3 3 9 1 4 4 BISIL ENGG. SUP/HSE
Handling and shifting • Ergonomic hazard • Slips, trips and falling of men or
material. • Use proper manual handling technique.
• Use of all mandatory PPEs. to be ensured.

• Hand tools must be in good condition & ISI Standard.


• Do not move with over
load, if required handle the material with 2 or more persons.
• Loading and unloading activity to be carried out by trained and skill team & workmen.
• Tool box talk should be conducted prior start of work.
• Sharpe edge • Ensure adequately area available for unloading the material before commence of work.
• Improper Lifting • Body Injury • Work should be done under presence of supervision.
4 Loading and unloading • Fall of material • Sprain & strain 3 3 9 • Always use to mandatory PPEs before start the work . 1 4 4 BISIL ENGG. SUP/HSE
of material • Improper access • Crush & Hand Injury

• Ensure driver or operator should be valid Havey license and insurance of vehicle.
• Safe access or aggress should be provided for vehicle movement and road to be
demarcated.
• Display the traffic signage at site and traffic rules to be followed & speed limit 20 KM/h
to be adhered.
Construction vehicle • Hit or struck with vehicle • Damage Property
6 movement inside • Run over/back over • Crush Injury 3 4 12 • Working area to be barricaded along with displayed signage. 1 3 3 BISIL ENGG. SUP/HSE
• Strict supervision to be maintained during the work.
Tipper/Trailer/tractore • Unauthorised operation • Fatality/Disability • Reflective jacket must be worn in project premisson for better visibility & identification.

• Electrical work to done by trained and qualified electrician.


• Use insulated hand tools while working with power tools
• Make sure earthling to panel.
• • Make sure all cable termination should be properly tighten.
• 30mAmp ELCB/RCCB to be installed & Electrical DB shall be in good condition &
• Electrocution • ElectricShock inspected with colour code
Work site Power • Damage live cable • Fire/explosion • Inspection & checklist must be used while carried out maintenance activity and work
7 supply provision and • Short-circuit 4 5 20 permit must be taken before maintenance work. 1 3 3 BISIL ENGG. SUP/HSE
• Fatality due to high Electric Shock
Uses of power tools • Unauthorised operation and flash Over/Burn Injury • Make sure availability of fire extinguisher or sand bucket nearby work place
• Damage Tools • Use mandatory PPE during the electrical work. •
Ensure you, body and surface is dry during the operations

• Machine should be inspected prior start of work.


Hazard Identification & Risk Assessment and Control Measure Worksheet (HIRA) FORMAT NO:

HAZARD IDENTIFICATION RISK EVALUATION

Probability
Consequence

Risk Level
Work Activity

Severity
(Possible injury/Ill-Health/
S.N. (Job steps in Hazards Existing Control Measures
Persons-at-Risk &
sequence)
Environmental)

• Untrained/unskilled workmen • Unsafe act can lead to body • Ensure induction training of all workmen and staff employees.
Deployment of • Unsafe act injury or harm to other • Ensure skilled and trained workmen deployed at site.
1 Manpower/ Workmen • Unauthorised entry • Incident due to poor awareness 3 4 12 • Pre-job briefing /TBT to be conduct before start of work.
RISK
at site • Ergonomics Physical Injury • Unauthorised entry to be restricted in work premises. CONTROL
• Poor awareness • Wear mandatory PPE during the work like safety helmet, safety goggles,reflective jacket,
safety shoe Coverall etc.

• Adverse weather conditions • Heat Stroke • Working in cooling hours if necessary.

Probability
• Heavy Wind and dust

Risk Level
Severity
• Employee collapse required • Take regular short rest period and cool hydration drink..
Working in Extreme • Storm
2
Weather conditions • Heat & Humidity
medical attention 3 4 12 • Make sure briefing the symptoms of heat stroke to employee. Person responsible
• Death • Make sure rest shed to be provide to workmen.
• Poor Visibility • Dehydration and heat Cramps • Work must be stopped during the heavy rain and wind speed.

•Take work permit before start of work activities.

• Before start of the activity, conduct pre job briefing and have close monitoring for
supervision
• Access should be free from obstacles and obstructions..
• Physical hazard. • Bodily injury • Make proper barricading and strict
Manual Material • Property Damage • Material damage supervision to monitor the activity.
3 3 3 9 1 4 4 BISIL ENGG. SUP/HSE
Handling and shifting • Ergonomic hazard • Slips, trips and falling of men or
material. • Use proper manual handling technique.
• Use of all mandatory PPEs. to be ensured.

• Hand tools must be in good condition & ISI Standard.


• Do not move with over
load, if required handle the material with 2 or more persons.
• Loading and unloading activity to be carried out by trained and skill team & workmen.
• Tool box talk should be conducted prior start of work.
• Sharpe edge • Ensure adequately area available for unloading the material before commence of work.
• Improper Lifting • Body Injury • Work should be done under presence of supervision.
4 Loading and unloading • Fall of material • Sprain & strain 3 3 9 • Always use to mandatory PPEs before start the work . 1 4 4 BISIL ENGG. SUP/HSE
of material • Improper access • Crush & Hand Injury

• Ensure driver or operator should be valid Havey license and insurance of vehicle.
• Safe access or aggress should be provided for vehicle movement and road to be
demarcated.
• Display the traffic signage at site and traffic rules to be followed & speed limit 20 KM/h
to be adhered.
Construction vehicle • Hit or struck with vehicle • Damage Property
6 movement inside • Run over/back over • Crush Injury 3 4 12 • Working area to be barricaded along with displayed signage. 1 3 3 BISIL ENGG. SUP/HSE
• Strict supervision to be maintained during the work.
Tipper/Trailer/tractore • Unauthorised operation • Fatality/Disability • Reflective jacket must be worn in project premisson for better visibility & identification.

• Electrical work to done by trained and qualified electrician.


• Use insulated hand tools while working with power tools
• Make sure earthling to panel.
• • Make sure all cable termination should be properly tighten.
• 30mAmp ELCB/RCCB to be installed & Electrical DB shall be in good condition &
• Electrocution • ElectricShock inspected with colour code
Work site Power • Damage live cable • Fire/explosion • Inspection & checklist must be used while carried out maintenance activity and work
7 supply provision and • Short-circuit 4 5 20 permit must be taken before maintenance work. 1 3 3 BISIL ENGG. SUP/HSE
• Fatality due to high Electric Shock
Uses of power tools • Unauthorised operation and flash Over/Burn Injury • Make sure availability of fire extinguisher or sand bucket nearby work place
• Damage Tools • Use mandatory PPE during the electrical work. •
Ensure you, body and surface is dry during the operations

• Make sure electrical does not pass through concrete curing area.
Hazard Identification & Risk Assessment and Control Measure Worksheet (HIRA) FORMAT NO:

HAZARD IDENTIFICATION RISK EVALUATION

Probability
Consequence

Risk Level
Work Activity

Severity
(Possible injury/Ill-Health/
S.N. (Job steps in Hazards Existing Control Measures
Persons-at-Risk &
sequence)
Environmental)

• Untrained/unskilled workmen • Unsafe act can lead to body • Ensure induction training of all workmen and staff employees.
Deployment of • Unsafe act injury or harm to other • Ensure skilled and trained workmen deployed at site.
1 Manpower/ Workmen • Unauthorised entry • Incident due to poor awareness 3 4 12 • Pre-job briefing /TBT to be conduct before start of work.
RISK
at site • Ergonomics Physical Injury • Unauthorised entry to be restricted in work premises. CONTROL
• Poor awareness • Wear mandatory PPE during the work like safety helmet, safety goggles,reflective jacket,
safety shoe Coverall etc.

• Adverse weather conditions • Heat Stroke • Working in cooling hours if necessary.

Probability
• Heavy Wind and dust

Risk Level
Severity
• Employee collapse required • Take regular short rest period and cool hydration drink..
Working in Extreme • Storm
2
Weather conditions • Heat & Humidity
medical attention 3 4 12 • Make sure briefing the symptoms of heat stroke to employee. Person responsible
• Death • Make sure rest shed to be provide to workmen.
• Poor Visibility • Dehydration and heat Cramps • Work must be stopped during the heavy rain and wind speed.

•Take work permit before start of work activities.

• Before start of the activity, conduct pre job briefing and have close monitoring for
supervision
• Access should be free from obstacles and obstructions..
• Physical hazard. • Bodily injury • Make proper barricading and strict
Manual Material • Property Damage • Material damage supervision to monitor the activity.
3 3 3 9 1 4 4 BISIL ENGG. SUP/HSE
Handling and shifting • Ergonomic hazard • Slips, trips and falling of men or
material. • Use proper manual handling technique.
• Use of all mandatory PPEs. to be ensured.

• Hand tools must be in good condition & ISI Standard.


• Do not move with over
load, if required handle the material with 2 or more persons.
• Loading and unloading activity to be carried out by trained and skill team & workmen.
• Tool box talk should be conducted prior start of work.
• Sharpe edge • Ensure adequately area available for unloading the material before commence of work.
• Improper Lifting • Body Injury • Work should be done under presence of supervision.
4 Loading and unloading • Fall of material • Sprain & strain 3 3 9 • Always use to mandatory PPEs before start the work . 1 4 4 BISIL ENGG. SUP/HSE
of material • Improper access • Crush & Hand Injury

• Ensure driver or operator should be valid Havey license and insurance of vehicle.
• Safe access or aggress should be provided for vehicle movement and road to be
demarcated.
• Display the traffic signage at site and traffic rules to be followed & speed limit 20 KM/h
to be adhered.
Construction vehicle • Hit or struck with vehicle • Damage Property
6 movement inside • Run over/back over • Crush Injury 3 4 12 • Working area to be barricaded along with displayed signage. 1 3 3 BISIL ENGG. SUP/HSE
• Strict supervision to be maintained during the work.
Tipper/Trailer/tractore • Unauthorised operation • Fatality/Disability • Reflective jacket must be worn in project premisson for better visibility & identification.

• Electrical work to done by trained and qualified electrician.


• Use insulated hand tools while working with power tools
• Make sure earthling to panel.
• • Make sure all cable termination should be properly tighten.
• 30mAmp ELCB/RCCB to be installed & Electrical DB shall be in good condition &
• Electrocution • ElectricShock inspected with colour code
Work site Power • Damage live cable • Fire/explosion • Inspection & checklist must be used while carried out maintenance activity and work
7 supply provision and • Short-circuit 4 5 20 permit must be taken before maintenance work. 1 3 3 BISIL ENGG. SUP/HSE
• Fatality due to high Electric Shock
Uses of power tools • Unauthorised operation and flash Over/Burn Injury • Make sure availability of fire extinguisher or sand bucket nearby work place
• Damage Tools • Use mandatory PPE during the electrical work. •
Ensure you, body and surface is dry during the operations

• Worker are pay attention at all time when loading and off-loading of scaffolding
Hazard Identification & Risk Assessment and Control Measure Worksheet (HIRA) FORMAT NO:

HAZARD IDENTIFICATION RISK EVALUATION

Probability
Consequence

Risk Level
Work Activity

Severity
(Possible injury/Ill-Health/
S.N. (Job steps in Hazards Existing Control Measures
Persons-at-Risk &
sequence)
Environmental)

• Untrained/unskilled workmen • Unsafe act can lead to body • Ensure induction training of all workmen and staff employees.
Deployment of • Unsafe act injury or harm to other • Ensure skilled and trained workmen deployed at site.
1 Manpower/ Workmen • Unauthorised entry • Incident due to poor awareness 3 4 12 • Pre-job briefing /TBT to be conduct before start of work.
RISK
at site • Ergonomics Physical Injury • Unauthorised entry to be restricted in work premises. CONTROL
• Poor awareness • Wear mandatory PPE during the work like safety helmet, safety goggles,reflective jacket,
safety shoe Coverall etc.

• Adverse weather conditions • Heat Stroke • Working in cooling hours if necessary.

Probability
• Heavy Wind and dust

Risk Level
Severity
• Employee collapse required • Take regular short rest period and cool hydration drink..
Working in Extreme • Storm
2
Weather conditions • Heat & Humidity
medical attention 3 4 12 • Make sure briefing the symptoms of heat stroke to employee. Person responsible
• Death • Make sure rest shed to be provide to workmen.
• Poor Visibility • Dehydration and heat Cramps • Work must be stopped during the heavy rain and wind speed.

•Take work permit before start of work activities.

• Before start of the activity, conduct pre job briefing and have close monitoring for
supervision
• Access should be free from obstacles and obstructions..
• Physical hazard. • Bodily injury • Make proper barricading and strict
Manual Material • Property Damage • Material damage supervision to monitor the activity.
3 3 3 9 1 4 4 BISIL ENGG. SUP/HSE
Handling and shifting • Ergonomic hazard • Slips, trips and falling of men or
material. • Use proper manual handling technique.
• Use of all mandatory PPEs. to be ensured.

• Hand tools must be in good condition & ISI Standard.


• Do not move with over
load, if required handle the material with 2 or more persons.
• Loading and unloading activity to be carried out by trained and skill team & workmen.
• Tool box talk should be conducted prior start of work.
• Sharpe edge • Ensure adequately area available for unloading the material before commence of work.
• Improper Lifting • Body Injury • Work should be done under presence of supervision.
4 Loading and unloading • Fall of material • Sprain & strain 3 3 9 • Always use to mandatory PPEs before start the work . 1 4 4 BISIL ENGG. SUP/HSE
of material • Improper access • Crush & Hand Injury

• Ensure driver or operator should be valid Havey license and insurance of vehicle.
• Safe access or aggress should be provided for vehicle movement and road to be
demarcated.
• Display the traffic signage at site and traffic rules to be followed & speed limit 20 KM/h
to be adhered.
Construction vehicle • Hit or struck with vehicle • Damage Property
6 movement inside • Run over/back over • Crush Injury 3 4 12 • Working area to be barricaded along with displayed signage. 1 3 3 BISIL ENGG. SUP/HSE
• Strict supervision to be maintained during the work.
Tipper/Trailer/tractore • Unauthorised operation • Fatality/Disability • Reflective jacket must be worn in project premisson for better visibility & identification.

• Electrical work to done by trained and qualified electrician.


• Use insulated hand tools while working with power tools
• Make sure earthling to panel.
• • Make sure all cable termination should be properly tighten.
• 30mAmp ELCB/RCCB to be installed & Electrical DB shall be in good condition &
• Electrocution • ElectricShock inspected with colour code
Work site Power • Damage live cable • Fire/explosion • Inspection & checklist must be used while carried out maintenance activity and work
7 supply provision and • Short-circuit 4 5 20 permit must be taken before maintenance work. 1 3 3 BISIL ENGG. SUP/HSE
• Fatality due to high Electric Shock
Uses of power tools • Unauthorised operation and flash Over/Burn Injury • Make sure availability of fire extinguisher or sand bucket nearby work place
• Damage Tools • Use mandatory PPE during the electrical work. •
Ensure you, body and surface is dry during the operations

• Only trained and authorised scaffolds to erect scaffolding.


Hazard Identification & Risk Assessment and Control Measure Worksheet (HIRA) FORMAT NO:

HAZARD IDENTIFICATION RISK EVALUATION

Probability
Consequence

Risk Level
Work Activity

Severity
(Possible injury/Ill-Health/
S.N. (Job steps in Hazards Existing Control Measures
Persons-at-Risk &
sequence)
Environmental)

• Untrained/unskilled workmen • Unsafe act can lead to body • Ensure induction training of all workmen and staff employees.
Deployment of • Unsafe act injury or harm to other • Ensure skilled and trained workmen deployed at site.
1 Manpower/ Workmen • Unauthorised entry • Incident due to poor awareness 3 4 12 • Pre-job briefing /TBT to be conduct before start of work.
RISK
at site • Ergonomics Physical Injury • Unauthorised entry to be restricted in work premises. CONTROL
• Poor awareness • Wear mandatory PPE during the work like safety helmet, safety goggles,reflective jacket,
safety shoe Coverall etc.

• Adverse weather conditions • Heat Stroke • Working in cooling hours if necessary.

Probability
• Heavy Wind and dust

Risk Level
Severity
• Employee collapse required • Take regular short rest period and cool hydration drink..
Working in Extreme • Storm
2
Weather conditions • Heat & Humidity
medical attention 3 4 12 • Make sure briefing the symptoms of heat stroke to employee. Person responsible
• Death • Make sure rest shed to be provide to workmen.
• Poor Visibility • Dehydration and heat Cramps • Work must be stopped during the heavy rain and wind speed.

•Take work permit before start of work activities.

• Before start of the activity, conduct pre job briefing and have close monitoring for
supervision
• Access should be free from obstacles and obstructions..
• Physical hazard. • Bodily injury • Make proper barricading and strict
Manual Material • Property Damage • Material damage supervision to monitor the activity.
3 3 3 9 1 4 4 BISIL ENGG. SUP/HSE
Handling and shifting • Ergonomic hazard • Slips, trips and falling of men or
material. • Use proper manual handling technique.
• Use of all mandatory PPEs. to be ensured.

• Hand tools must be in good condition & ISI Standard.


• Do not move with over
load, if required handle the material with 2 or more persons.
• Loading and unloading activity to be carried out by trained and skill team & workmen.
• Tool box talk should be conducted prior start of work.
• Sharpe edge • Ensure adequately area available for unloading the material before commence of work.
• Improper Lifting • Body Injury • Work should be done under presence of supervision.
4 Loading and unloading • Fall of material • Sprain & strain 3 3 9 • Always use to mandatory PPEs before start the work . 1 4 4 BISIL ENGG. SUP/HSE
of material • Improper access • Crush & Hand Injury

• Ensure driver or operator should be valid Havey license and insurance of vehicle.
• Safe access or aggress should be provided for vehicle movement and road to be
demarcated.
• Display the traffic signage at site and traffic rules to be followed & speed limit 20 KM/h
to be adhered.
Construction vehicle • Hit or struck with vehicle • Damage Property
6 movement inside • Run over/back over • Crush Injury 3 4 12 • Working area to be barricaded along with displayed signage. 1 3 3 BISIL ENGG. SUP/HSE
• Strict supervision to be maintained during the work.
Tipper/Trailer/tractore • Unauthorised operation • Fatality/Disability • Reflective jacket must be worn in project premisson for better visibility & identification.

• Electrical work to done by trained and qualified electrician.


• Use insulated hand tools while working with power tools
• Make sure earthling to panel.
• • Make sure all cable termination should be properly tighten.
• 30mAmp ELCB/RCCB to be installed & Electrical DB shall be in good condition &
• Electrocution • ElectricShock inspected with colour code
Work site Power • Damage live cable • Fire/explosion • Inspection & checklist must be used while carried out maintenance activity and work
7 supply provision and • Short-circuit 4 5 20 permit must be taken before maintenance work. 1 3 3 BISIL ENGG. SUP/HSE
• Fatality due to high Electric Shock
Uses of power tools • Unauthorised operation and flash Over/Burn Injury • Make sure availability of fire extinguisher or sand bucket nearby work place
• Damage Tools • Use mandatory PPE during the electrical work. •
Ensure you, body and surface is dry during the operations

• UNSAFE signage must be put on scaffold during the erection of scaffold.


Hazard Identification & Risk Assessment and Control Measure Worksheet (HIRA) FORMAT NO:

HAZARD IDENTIFICATION RISK EVALUATION

Probability
Consequence

Risk Level
Work Activity

Severity
(Possible injury/Ill-Health/
S.N. (Job steps in Hazards Existing Control Measures
Persons-at-Risk &
sequence)
Environmental)

• Untrained/unskilled workmen • Unsafe act can lead to body • Ensure induction training of all workmen and staff employees.
Deployment of • Unsafe act injury or harm to other • Ensure skilled and trained workmen deployed at site.
1 Manpower/ Workmen • Unauthorised entry • Incident due to poor awareness 3 4 12 • Pre-job briefing /TBT to be conduct before start of work.
RISK
at site • Ergonomics Physical Injury • Unauthorised entry to be restricted in work premises. CONTROL
• Poor awareness • Wear mandatory PPE during the work like safety helmet, safety goggles,reflective jacket,
safety shoe Coverall etc.

• Adverse weather conditions • Heat Stroke • Working in cooling hours if necessary.

Probability
• Heavy Wind and dust

Risk Level
Severity
• Employee collapse required • Take regular short rest period and cool hydration drink..
Working in Extreme • Storm
2
Weather conditions • Heat & Humidity
medical attention 3 4 12 • Make sure briefing the symptoms of heat stroke to employee. Person responsible
• Death • Make sure rest shed to be provide to workmen.
• Poor Visibility • Dehydration and heat Cramps • Work must be stopped during the heavy rain and wind speed.

•Take work permit before start of work activities.

• Before start of the activity, conduct pre job briefing and have close monitoring for
supervision
• Access should be free from obstacles and obstructions..
• Physical hazard. • Bodily injury • Make proper barricading and strict
Manual Material • Property Damage • Material damage supervision to monitor the activity.
3 3 3 9 1 4 4 BISIL ENGG. SUP/HSE
Handling and shifting • Ergonomic hazard • Slips, trips and falling of men or
material. • Use proper manual handling technique.
• Use of all mandatory PPEs. to be ensured.

• Hand tools must be in good condition & ISI Standard.


• Do not move with over
load, if required handle the material with 2 or more persons.
• Loading and unloading activity to be carried out by trained and skill team & workmen.
• Tool box talk should be conducted prior start of work.
• Sharpe edge • Ensure adequately area available for unloading the material before commence of work.
• Improper Lifting • Body Injury • Work should be done under presence of supervision.
4 Loading and unloading • Fall of material • Sprain & strain 3 3 9 • Always use to mandatory PPEs before start the work . 1 4 4 BISIL ENGG. SUP/HSE
of material • Improper access • Crush & Hand Injury

• Ensure driver or operator should be valid Havey license and insurance of vehicle.
• Safe access or aggress should be provided for vehicle movement and road to be
demarcated.
• Display the traffic signage at site and traffic rules to be followed & speed limit 20 KM/h
to be adhered.
Construction vehicle • Hit or struck with vehicle • Damage Property
6 movement inside • Run over/back over • Crush Injury 3 4 12 • Working area to be barricaded along with displayed signage. 1 3 3 BISIL ENGG. SUP/HSE
• Strict supervision to be maintained during the work.
Tipper/Trailer/tractore • Unauthorised operation • Fatality/Disability • Reflective jacket must be worn in project premisson for better visibility & identification.

• Electrical work to done by trained and qualified electrician.


• Use insulated hand tools while working with power tools
• Make sure earthling to panel.
• • Make sure all cable termination should be properly tighten.
• 30mAmp ELCB/RCCB to be installed & Electrical DB shall be in good condition &
• Electrocution • ElectricShock inspected with colour code
Work site Power • Damage live cable • Fire/explosion • Inspection & checklist must be used while carried out maintenance activity and work
7 supply provision and • Short-circuit 4 5 20 permit must be taken before maintenance work. 1 3 3 BISIL ENGG. SUP/HSE
• Fatality due to high Electric Shock
Uses of power tools • Unauthorised operation and flash Over/Burn Injury • Make sure availability of fire extinguisher or sand bucket nearby work place
• Damage Tools • Use mandatory PPE during the electrical work. •
Ensure you, body and surface is dry during the operations
Hazard Identification & Risk Assessment and Control Measure Worksheet (HIRA) FORMAT NO:

HAZARD IDENTIFICATION RISK EVALUATION

Probability
Consequence

Risk Level
Work Activity

Severity
(Possible injury/Ill-Health/
S.N. (Job steps in Hazards Existing Control Measures
Persons-at-Risk &
sequence)
Environmental)

• Untrained/unskilled workmen • Unsafe act can lead to body • Ensure induction training of all workmen and staff employees.
Deployment of • Unsafe act injury or harm to other • Ensure skilled and trained workmen deployed at site.
1 Manpower/ Workmen • Unauthorised entry • Incident due to poor awareness 3 4 12 • Pre-job briefing /TBT to be conduct before start of work.
RISK
at site • Ergonomics Physical Injury • Unauthorised entry to be restricted in work premises. CONTROL
• Poor awareness • Wear mandatory PPE during the work like safety helmet, safety goggles,reflective jacket,
safety shoe Coverall etc.

• Adverse weather conditions • Heat Stroke • Working in cooling hours if necessary.

Probability
• Heavy Wind and dust

Risk Level
Severity
• Employee collapse required • Take regular short rest period and cool hydration drink..
Working in Extreme • Storm
2
Weather conditions • Heat & Humidity
medical attention 3 4 12 • Make sure briefing the symptoms of heat stroke to employee. Person responsible
• Death • Make sure rest shed to be provide to workmen.
• Poor Visibility • Dehydration and heat Cramps • Work must be stopped during the heavy rain and wind speed.

•Take work permit before start of work activities.

• Before start of the activity, conduct pre job briefing and have close monitoring for
supervision
• Access should be free from obstacles and obstructions..
• Physical hazard. • Bodily injury • Make proper barricading and strict
Manual Material • Property Damage • Material damage supervision to monitor the activity.
3 3 3 9 1 4 4 BISIL ENGG. SUP/HSE
Handling and shifting • Ergonomic hazard • Slips, trips and falling of men or
material. • Use proper manual handling technique.
• Use of all mandatory PPEs. to be ensured.

• Hand tools must be in good condition & ISI Standard.


• Do not move with over
load, if required handle the material with 2 or more persons.
• Loading and unloading activity to be carried out by trained and skill team & workmen.
• Tool box talk should be conducted prior start of work.
• Sharpe edge • Ensure adequately area available for unloading the material before commence of work.
• Improper Lifting • Body Injury • Work should be done under presence of supervision.
4 Loading and unloading • Fall of material • Sprain & strain 3 3 9 • Always use to mandatory PPEs before start the work . 1 4 4 BISIL ENGG. SUP/HSE
of material • Improper access • Crush & Hand Injury

• Ensure driver or operator should be valid Havey license and insurance of vehicle.
• Safe access or aggress should be provided for vehicle movement and road to be
demarcated.
• Display the traffic signage at site and traffic rules to be followed & speed limit 20 KM/h
to be adhered.
Construction vehicle • Hit or struck with vehicle • Damage Property
6 movement inside • Run over/back over • Crush Injury 3 4 12 • Working area to be barricaded along with displayed signage. 1 3 3 BISIL ENGG. SUP/HSE
• Strict supervision to be maintained during the work.
Tipper/Trailer/tractore • Unauthorised operation • Fatality/Disability • Reflective jacket must be worn in project premisson for better visibility & identification.

• Electrical work to done by trained and qualified electrician.


• Use insulated hand tools while working with power tools
• Make sure earthling to panel.
• • Make sure all cable termination should be properly tighten.
• 30mAmp ELCB/RCCB to be installed & Electrical DB shall be in good condition &
• Electrocution • ElectricShock inspected with colour code
Work site Power • Damage live cable • Fire/explosion • Inspection & checklist must be used while carried out maintenance activity and work
7 supply provision and • Short-circuit 4 5 20 permit must be taken before maintenance work. 1 3 3 BISIL ENGG. SUP/HSE
• Fatality due to high Electric Shock
Uses of power tools • Unauthorised operation and flash Over/Burn Injury • Make sure availability of fire extinguisher or sand bucket nearby work place
• Damage Tools • Use mandatory PPE during the electrical work. •
Ensure you, body and surface is dry during the operations
Hazard Identification & Risk Assessment and Control Measure Worksheet (HIRA) FORMAT NO:

HAZARD IDENTIFICATION RISK EVALUATION

Probability
Consequence

Risk Level
Work Activity

Severity
(Possible injury/Ill-Health/
S.N. (Job steps in Hazards Existing Control Measures
Persons-at-Risk &
sequence)
Environmental)

• Untrained/unskilled workmen • Unsafe act can lead to body • Ensure induction training of all workmen and staff employees.
Deployment of • Unsafe act injury or harm to other • Ensure skilled and trained workmen deployed at site.
1 Manpower/ Workmen • Unauthorised entry • Incident due to poor awareness 3 4 12 • Pre-job briefing /TBT to be conduct before start of work.
RISK
at site • Ergonomics Physical Injury • Unauthorised entry to be restricted in work premises. CONTROL
• Poor awareness • Wear mandatory PPE during the work like safety helmet, safety goggles,reflective jacket,
safety shoe Coverall etc.

• Adverse weather conditions • Heat Stroke • Working in cooling hours if necessary.

Probability
• Heavy Wind and dust

Risk Level
Severity
• Employee collapse required • Take regular short rest period and cool hydration drink..
Working in Extreme • Storm
2
Weather conditions • Heat & Humidity
medical attention 3 4 12 • Make sure briefing the symptoms of heat stroke to employee. Person responsible
• Death • Make sure rest shed to be provide to workmen.
• Poor Visibility • Dehydration and heat Cramps • Work must be stopped during the heavy rain and wind speed.

•Take work permit before start of work activities.

• Before start of the activity, conduct pre job briefing and have close monitoring for
supervision
• Access should be free from obstacles and obstructions..
• Physical hazard. • Bodily injury • Make proper barricading and strict
Manual Material • Property Damage • Material damage supervision to monitor the activity.
3 3 3 9 1 4 4 BISIL ENGG. SUP/HSE
Handling and shifting • Ergonomic hazard • Slips, trips and falling of men or
material. • Use proper manual handling technique.
• Use of all mandatory PPEs. to be ensured.

• Hand tools must be in good condition & ISI Standard.


• Do not move with over
load, if required handle the material with 2 or more persons.
• Loading and unloading activity to be carried out by trained and skill team & workmen.
• Tool box talk should be conducted prior start of work.
• Sharpe edge • Ensure adequately area available for unloading the material before commence of work.
• Improper Lifting • Body Injury • Work should be done under presence of supervision.
4 Loading and unloading • Fall of material • Sprain & strain 3 3 9 • Always use to mandatory PPEs before start the work . 1 4 4 BISIL ENGG. SUP/HSE
of material • Improper access • Crush & Hand Injury

• Ensure driver or operator should be valid Havey license and insurance of vehicle.
• Safe access or aggress should be provided for vehicle movement and road to be
demarcated.
• Display the traffic signage at site and traffic rules to be followed & speed limit 20 KM/h
to be adhered.
Construction vehicle • Hit or struck with vehicle • Damage Property
6 movement inside • Run over/back over • Crush Injury 3 4 12 • Working area to be barricaded along with displayed signage. 1 3 3 BISIL ENGG. SUP/HSE
• Strict supervision to be maintained during the work.
Tipper/Trailer/tractore • Unauthorised operation • Fatality/Disability • Reflective jacket must be worn in project premisson for better visibility & identification.

• Electrical work to done by trained and qualified electrician.


• Use insulated hand tools while working with power tools
• Make sure earthling to panel.
• • Make sure all cable termination should be properly tighten.
• 30mAmp ELCB/RCCB to be installed & Electrical DB shall be in good condition &
• Electrocution • ElectricShock inspected with colour code
Work site Power • Damage live cable • Fire/explosion • Inspection & checklist must be used while carried out maintenance activity and work
7 supply provision and • Short-circuit 4 5 20 permit must be taken before maintenance work. 1 3 3 BISIL ENGG. SUP/HSE
• Fatality due to high Electric Shock
Uses of power tools • Unauthorised operation and flash Over/Burn Injury • Make sure availability of fire extinguisher or sand bucket nearby work place
• Damage Tools • Use mandatory PPE during the electrical work. •
Ensure you, body and surface is dry during the operations
DELHI ENGINEERING SOLUTION
A-43 Ram Dutt Enclave Uttam Nagar New Delhi - 110059
Table 3: Risk Index Matrix
Risk Category
Probability/ Likelihood of Accident
1 2 3 4 5
Rare Remote Occasional Frequent Almost Certain
5 Catastrophic M M H H H
Severity of
Accident/

4 Major M M M H H
injury

3 Moderate L M M M H

2 L M M M M

1 Negligible L L L M M

No additional risk control measures may be needed. However, frequent review may be needed to
Low Risk Acceptable
ensure that the risk level assigned is accurate and does not increase over time.

A careful evaluation of the hazards should be carried out to ensure that the risk level is reduced to as
Medium Risk Moderately acceptable low as reasonably practicable within a defined time period. Interim risk control measures, such as
administrative controls, may be implemented. Management attention is required.

High Risk Not acceptable

Table 1: Probability/Likelihood of Accident Table 2: Severity of Accident/injury


Probability/ Likelihood Rating Description Consequence Rating Description
Not expected to occur
Rare 1 but still possible Catastrophic 5 Fatality, fatal diseases or multiple major injuries

Serious injuries or life-threatening occupational


Remote 2 Not likely to occur under Major 4 disease (includes amputations, major fractures,
normal circumstances multiple injuries, occupational cancer, acute
poisoning)

Injury requiring medical treatment or ill-health


Possible or known to leading to disability (includes lacerations, burns,
Occasional 3 occur Moderate 3 sprains, minor fractures, dermatitis, deafness
and work-related upper limb disorders.

Injury or ill-health requiring first-aid only


Frequent 4 Common occurrence Minor 2 (includes minor cuts and bruises, irritation, ill-
health with temporary discomfort)
Almost Certain 5 Continual or repeating Negligible 1 Not likely to cause injury or ill-health
experience