Labour Productivity Rate

The document provides detailed productivity rates for various construction activities, including excavation, backfilling, interlock paving, shuttering, concrete reinforcement, and masonry work. Each activity lists the required manpower, tools, and expected output per day or hour. It serves as a reference for estimating labor and material needs in construction projects.

Uploaded by

Prem Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
101 views5 pages

Labour Productivity Rate

The document provides detailed productivity rates for various construction activities, including excavation, backfilling, interlock paving, shuttering, concrete reinforcement, and masonry work. Each activity lists the required manpower, tools, and expected output per day or hour. It serves as a reference for estimating labor and material needs in construction projects.

Uploaded by

Prem Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 5

PRODUCTIVITY RATES

S.No. Man/Hr Unit

TEMPORARY FACILITES

Excavation
,. Soft Soil (Hand Tools) 1H Hand Tools M / Day 3
b. Hard Soil (Hand Tools) 1H Hand Tools M / Day 1
,. Soft Soil -- Shovel M' / He 40
d. Hard Soil -- Shovel M / Hr 25
e. Soft Soil -- lC.B M / Hr 20
f. Hard Soil -- lC.B M' / He 10
Backfillmg
,. Filling in foundation, plinth -- Shovel M / Hr 30
b. Lavel, Compaction 1H Roller Compr. ML / Day 100
,. Spreading 200 mm laye (Subkha, Roadbase) -- Shovel M / Hr 100
d. Compaction 200 mm laye (Subkha, Roadbase) 1H Roller Compr. M / Day 200

Interlock Paving
,. Compaction / Leveling 2H Roller Compr. M / Day 200
b. Spreading Sand and Burshing 2H ML / Day 200
,. Laying Tiles 1 M +2 H M / Day 60
d. Filling I Compaction 1H Plate Compr. M / Day 150
Precast Kerb Stone

Shuttering (with supports)


,. Shutt. Of Blinding lC+1H M / Day 35
b. Shutt. Of Footing (Plywood) lC+1H ML / Day 15
,. Shutt. Of Footing (Plates) lC+1H M / Day 20
d. Shutt. Of Stub Column 1C+1H M / Day 5
e. Shutt. Of Strap / Tie Beam (Plywood) 1C+1H ML / Day 12
f. Shutt. Of Strap / Tie Beam (Plates) 1C+1H M / Day 20
g. Shutt. Of Walls 1C+1H M / Day 14
h. Shutt. Of Column 20 x 20 1C+1H ML / Day 10
;, Shutt. Of Column 20 x40 1C+1H M / Day 10
j. Shutt. Of Beam with support 1C+1H M / Day 12
k. Shutt. Of Roof Slab 1C+1H ML / Day 10
I. Shutt. Of Lintel 1C+1H M / Day 6
m. Shutt. Of Copying Beam 20x20cm 1C+1H M / Day 6
,. Shutt. Of Parapet 1C+1H ML / Day 12
o. Shutt. Of Arch Lintel 1C+1H M / Day 6
p. Expansion Joint / Ground Slab 1C+1H R.M / Day 70
q. Shutt. Of beam & cloumn for 8m to 12m high 1C+1H ML / Day 8
L shutt. Of Staircase 1C+1H M / Day 12
,. De-shuttreing Works 20 % of shuttering works
CONCRETE REINFORCEMENT
Reinforcement (Tighting for Cut & Bend Steel)
,. Reinf. Of Footing 1SF+1H KG / Day 400
b. Reinf. Of Stub Column 1SF+1H KG / Day 250
,. Reinf. Of Strap Beam 1SF+1H KG / Day 300
d. Reinf. OfTie Beam 1SF+1H KG / Day 350
e. Reinf. Of Wall 1SF+1H KG / Day 400

C = Carpenter, M = Mason, P = Painter, SF = Steel Fitter, E = Erector, H = Helper, Po = Polisher, EI = Elec, PI = Plumber
PRODUCTIVITY RATES
f. Reinf. Of Column 1 SF + 1 H KG / Day 300
g. Reinf. Of Beam 1 SF + 1 H KG / Day 300
h. Reinf. Of Solid Slab 1 SF + 1 H KG / Day 300
i. Reinf. Of Lintel 1 SF + 1 H KG / Day 150
j. Reinf. Of Copying beam 20x20cm 1 SF + 1 H KG / Day 200
k. Reinf. Of Parapet 1 SF + 1 H KG / Day 300
l. Reinf. Of Arch Lintel 1 SF + 1 H KG / Day 150
m. Reinf. Of StairCase 1 SF + 1 H KG / Day 250
Mesh Reinforcement
a. Mesh Reinforcement 1 SF + 2 H M2 / Day 300
CAST IN PLACE CONCRETE
Casting Concreting (Ready Mix)
2
a. Cast. Blinding 5cm 1M+2H M / Day 30
b. Cast. Blinding 10cm 1M+2H M2 / Day 40
2
c. Cast. Blinding 5cm, 10cm 2M+4H Pump M / Day 250
d. Cast. Of Footing 2M+4H M3 / Day 40
e. Cast. Of Footing (Pump) 3M+8H Pump M3 / Day 120
f. Cast. Of Strap / Tie Beams 1M+6H M3 / Day 20
3
g. Cast. Of Tie Beams (Pump) 2M+6H Pump M / Day 50
h. Cast. Of Ground Floor Slab 10cm 3M+5H M3 / Day 30
i. Cast. Of Ground Floor Slab 15cm 3M+5H M3 / Day 45
3
j. Cast. Of Ground Floor Slab 20cm 3M+5H M / Day 60
k. Cast. Of Wall 1M+1C+3H Pump M3 / Day 40
l. Cast. Of Column 1M+4H M3 / Day 4
m. Cast. Of Beam of Slab 1M+4H M3 / Day 12
n. Cast. Of Roof Slab 2M+2C+5H Pump M3 / Day 50
o. Cast. Of Lintel 1M+2H Nos. / Hour 4
p. Cast. Of Copying beam 20x20cm (upto 2.5m) 1C+5H RM / Day 150
q. Cast. Of Copying beam 20x20cm (above 2.5m) 1C+5H RM / Day 60
r. Cast. Of Parapet 1M+1C+4H Pump M3 / Day 10
3
s. Cast. Of Arch Lintel 1M+3H M / Day 5
t. Cast. Of Neck Column 1M+3H M3 / Day 4
u. Cast. Of Staircase 1C+1H M3 / Day 12
4 MASONRY
BLOCK WORK
Solid Block
a. 200mm Solid Block upto 2.5m Height 1M+2H Nos. / Day 140
Hollow Block
a. 100mm Hollow Block upto 2.5m height 1M+1H Nos. / Day 150
b. 100mm Hollow Block upto 2.5m to 6m height 1M+2H Nos. / Day 140
c. 150mm Hollow Block upto 2.5m height 1M+1H Nos. / Day 150
d. 200mm Hollow Block upto 2.5m height 1M+1H Nos. / Day 180
e. 200mm Hollow Block upto 2.5m to 6m height 1M+2H Nos. / Day 140
f. 200mm Block Work above 6m height 1M+2H Nos. / Day 100
g. 200mm Block Work including pointing 1M+1H Nos. / Day 120
Claustra Block
a. Claustra Block 200 x 200 1M+1H M2 / Day 10
b. Claustra Block 150 x 150 1M+1H M2 / Day 8
5 METALS
STRUCTURAL METAL FRAMING
Steel Structure
a. Painting of steel structure columns 1P+1H M2/Day/Coat 50
b. Painting of steel structure rafters 1P+1H M2/Day/Coat 40
Erection of steel structure main frame
c. 3E+3H M2/Day 250
(Eave height up to 6m span up to 25m)
Erection of steel structure main frame 2
d. 3E+3H M /Day 175
(Eave height mor than 6m span up to 36m)
2
e. Fixing of Single Skin Sheet (Roof) 3E+3H M /Day 350
f. Fixing of Single Skin Sheet (Wall) 3E+3H M2/Day 150
g. Single skin with fiber Glass insulation (Roof) 3E+3H M2/Day 250
h. Single skin with fiber Glass insulation (Wall) 3E+3H M2/Day 100
2
i. Sandwich Panels (Roof) 3E+3H M /Day 250
j. Sandwich Panels (Wall) 3E+3H M2/Day 150

C = Carpenter, M = Mason, P = Painter, SF = Steel Fitter, E = Erector, H = Helper, Po = Polisher, El = Elec, Pl = Plumber
PRODUCTIVITY RATES
k. Corner Flashing & Trims, etc 1E+3H Rm/Day 80
l. 4m x 4m double Sliding Door 1E+3H No. 1
m. Wall or Roof opening + Frames (1.0m x 1.0m) 1E+3H No. 8
n. Ridge Ventilator 1E+3H No./Day 6
o. Gutter / Down Spout 1E+3H Rm/Day 70
6 MOISTURE THERMAL CONTROL
WATER PROOFING & DAMP PROOFING
Polythene Sheet
a. Polytheen under footings 1C+1H M2/Day 200
b. Polytheen under slab 1C+1H M2/Day 1000
c. Polytheen under tie beams 1H Rm/Day 200
Bitumin Paint
2
a. Cold Bituminous Painting 1H M /Day/Coat 100
b. Hot Bituminous Painting 2H M2/Day/Coat 60
Bituminous Membrance
2
a. Bituminous Membrance + Protection Board 1C+1H M /Day 30
SEALERS
Construction Joint
a. Flexel Board 1C+1H RM /Hr 18
b. Sealant 1H RM /Hr 7
8 FINISHES
PLASTER
Internal Plaster
a. Ceiling Plaster 1M+1H M2/Day 10
b. Wall plaster up to 3m Height 1M+1H M2/Day 20
c. Wall plaster 3m to 6m Height 1M+2H M2/Day 17
d. Wall plaster above 6m Height 1M+2H M2/Day 15
e. Fixing of Plaster Mesh 1C+1H Rm/Day 90
f. Fixing of Corner beed 1M+1H Rm/Day 30
External Plaster
a. Wall plaster up to 3m Height 1M+1H M2/Day 20
b. Wall plaster 3m to 6m Height 1M+2H M2/Day 18
c. Wall plaster above 6m Height 1M+2H M2/Day 15
TILES
Mosaic
a. Floor Mosaic Tiles 1M+1H M2/Day 15
b. Mosaic Skirting 1M+1H Rm/Day 40
c. Mosaic Steps (Riser & Tread) 1M+1H Rm/Day 14
d. Mosaic Polishing 1 Po + 1 H M2/Day 100
Ceramic
2
a. Fixing of Ceramic Wall Tiles (Glue Type) 1M+1H M /Day 10
b. Grouting of Ceramic Wall Tiles 1M+1H M2/Day 30
c. Fixing of Ceramic Wall Tiles (Cement Mortar Type) 1M+1H M2/Day 8
d. Fixing of Ceramic Floor Tiles 20 x 20cm 1M+1H M2/Day 12
e. Fixing of Ceramic Floor Tiles 30 x 30cm 1M+1H M2/Day 15
f. Fixing of Ceramic Floor Tiles 50 x 50cm 1M+1H M2/Day 20
g. Grouting of Ceramic Floor Tiles 1M+1H M2/Day 40
h. Ceramic Skirting 1M+1H Rm/Day 30
PVC Tiles
a. PVC Tiles 1M+1H M2/Day 35
b. PVC Skirting 1M+1H Rm/Day 40

Marble
a. Marble Wall 1M+1H M2/Day 6
b. Marble Floor 1M+1H M2/Day 15
c. Marble Skirting 1M+1H Rm/Day 30
d. Marble Steps (Riser & Treads) 1M+1H Rm/Day 10

Floor Screed (50mm)


a. Floor Screed (50mm) 1M+1H M2/Day 50
b. Cement Skirting 1M+1H Rm/Day 25

Wooden Skirting

C = Carpenter, M = Mason, P = Painter, SF = Steel Fitter, E = Erector, H = Helper, Po = Polisher, El = Elec, Pl = Plumber
PRODUCTIVITY RATES
a. Timber 1C+1H Rm/Day 100

Thershold
a. Thershold 1M Rm/Day 10

False Ceiling
a. False Ceiling ‐ Suspended Type 1 C + 1H M2/Day 30

Dry Wall Partition


a. Dry wall Partition 1 C + 1H M2/Day 20

PAINTING & WALL COVERINGS


Tyrolene (Cullamix)
a. Tyrolene over plastered surface 1M+1H M2/Day/Coat 100
2
b. Tyrolene over block wall 1M+1H M /Day/Coat 100
Normal Paint
a. Primer 1P M2/Day/Coat 200
b. Stucco (Putty) 1P M2/Day/Coat 80
2
c. Emulsion Paint 1P M /Day/Coat 100
d. Oil Paint 1P M2/Day/Coat 60
Epoxy Painting
2
a. Epoxy Painting 1P+1H M /Day/Coat 50

9 MECHANICAL
COPPER & PVC PIPES
Copper & PVC Pipes
a. 1/2" to 1" Copper Pipe (Hot water) 1 Pl + 1 H Rm/Day 12
b. 1/2" 1 1/2" PVC Pipe 1 Pl + 1 H Rm/Day 20
c. 2" to 3" PVC Pipe 1 Pl + 1 H Rm/Day 75
d. 3" to 6" PVC Pipe 1 Pl + 1 H Rm/Day 60

PLUMBING FIXTURES
Plumbibg Fixtures
a. Shower Tray 1 Pl + 1 H Nos. / Day 2
b. Kitchen Sink 1 Pl + 1 H Nos. / Day 2
c. Urinals + Partition 1 Pl + 1 H Nos. / Day 3
d. Wash Basin 1 Pl + 1 H Nos. / Day 2
e. W/C Asian 1 Pl + 1 H Nos. / Day 2
f. W/C Western 1 Pl + 1 H Nos. / Day 2
g. Bidet 1 Pl + 1 H Nos. / Day 2
h. Booster Pump 1 Pl Nos. / Day 1
i. Manhole 60cm to 90 cm 1M+1H Nos. / Day 2
PLUMBING APPLIANCES
Plumbing Appliances
a. Water Heater 1 Pl + 1 H Nos. / Day 2

10 ELECTRICAL
ELECTRICAL
Race Ways
a. Conduits 1 El + 1 H Rm/Day 50
b. Trunking 1 El + 1 H Rm/Day 50

Conductors & Crounding


a. Laying Cables 1 El + 2 H Rm/Day 150

Wiring
a. Wiring 1 El + 1 H Rm/Day 300

Boards
a. D.B's 1 El + 1 H Nos. / Day 2
b. M.D.B's 1 El + 1 H Nos. / Day 1

C = Carpenter, M = Mason, P = Painter, SF = Steel Fitter, E = Erector, H = Helper, Po = Polisher, El = Elec, Pl = Plumber
Block Check
Court and ministry
Budget unit for Block works 6892.5
400mm thick wall M2 2,998 5 M2 599.6
300mm thick wall M2 5,577 6 M2 929.5
Quantities

200mm thick wall M2 31,539 7 M2 4505.571429


150mm thick wall M2 45 8 M2 5.625
100mm thick wall M2 7,811 9 M2 867.8888889 Variance
47,970 total 6908.185317 -15.6853
Block analysis
Number of
M2 M3
size (.4*.2*.2) block daily
1 0.4 25 5 m2/day 125
1 0.3 18.75 6 m2/day 112.5
1 0.2 25 7 m2/day 175
1 0.15 18.75 8 m2/day 150
1 0.1 12.5 9 m2/day 112.5

Activity ID Activity Name Start Finish Remaining Labor Units


Block 371 14-Aug-16 6-Nov-17 4190.37
Block 287 15-Nov-16 28-Oct-17 2702.13

6892.5

DIVISION 09 - FINISHES
Section 09 24 00 - Cement Plastering

Budget Manday
Cor&Ministry Plaster 852.74
Court Plaster 4555.23
Ministry Plaster 3406.56
facad Plaster 0
8814.53
Aver.
Rate/day
To Walls 67124 M2 14 4794.571429
To Ceiling 8,571 M2 11 779.1363636
AAD#05 A11-5 BASEMENT CEILING PLASTER
To walls and ceiling
for the dry areas 42021.38824 M2 13 3232.41448
8806.122272 8.407728154

Division 31, Section 31 23 23 Fill

Budget Manday
Cor&Ministry Backfill 250
Court Backfill 3412
Ministry Backfill 1274
4936
Aver.
Rate/day
68124.5 M3 25 2724.98 Roller
Back Filling
M3 30 283.8520833 Shovel
M3 36 1892.347222 6 wheel.

4901.179306 34.82069444

Section 09 90 00 - Painting and Coating Activity ID Activity Name Budget Units


One coat of Antiseptic, 1 Cor&Ministry paint 320.04
One coat of Antiseptic, 1 Court paint 1953.87
Section 09 91 00 - Painting 6,383 Ministry paint 1388.85
Section 09 91 00 - Painting (Cont'n) 66,753 facad paint 0
3662.76
Aver. /day

Paint 73,136 M2 80 2742.6 3 layer

Cielling paint 68,453 M2 75 912.7066667


3655.306667 7.453333333