Technical Specifications
Technical Specifications
Development Project
           Structure
           Specifications
STRUCTURE
SECTION       DESCRIPTION
 033000                                     Cast In Place Concrete.
CAST-IN-PLACE CONCRETE
PART 1 – GENERAL
       A.     All tests listed in this document according to ASTM Standards are also accepted to
              be conducted using equivalent BS/BS EN Standards or Egyptian Code of Practice ECP
              203. Frequency of testing materials for quality assurance shall comply with ECP 203 as
              minimum requirements.
       B.     Drawings and general provisions of the Contract, including Conditions of Contract and
              Division 1 Specification Sections, apply to this Section.
1.2 SUMMARY
1.3 DEFINITIONS
1.4 SUBMITTALS
A. Product Data: For each type of manufactured material and product indicated.
       B.     Design Mixes: For each concrete mix. Include alternate mix designs when
              characteristics of materials, project conditions, weather, test results, or other
              circumstances warrant adjustments.
    G.      Qualification Data: For firms and persons specified in "Quality Assurance" Article to
            demonstrate their capabilities and experience. Include lists of completed projects with
            project names and addresses, names and addresses of architects/engineers and owners,
            and any other information required by Engineer.
    H.      Material Test Reports: From a qualified testing agency indicating and interpreting test
            results for compliance of the following with requirements indicated, based          on
            comprehensive testing of current materials:
    I.      Material Certificates: Signed by manufacturers certifying that each of the following items
            complies with requirements:
    F.        Mockups: Before casting concrete that is exposed to view on surfaces of the completed
              structure or building, cast a mockup for each exposed element, including slabs if applicable,
              to demonstrate typical joints, surface finish, texture, color, tolerances, quality of materials
              and standard of workmanship in the completed Work.
              1.    Build mockups in the location and of the size indicated or, if not indicated, as directed
                    by Engineer.
              2.    Notify Engineer seven days in advance of dates and times when mockups will be
                    constructed.
              3.    In presence of Engineer, damage parts of exposed surfaces as selected by Engineer,
                    and demonstrate materials and techniques proposed for repairs to match adjacent
                    undamaged surfaces
              4.    Obtain Engineer's approval of mockups before starting cast-in-place concrete
                    elements exposed to view.
              5.    If Engineer determines that any mockup does not meet requirements, demolish and
                    remove from the site and cast another until the mockup is approved.
              6.    Maintain mockups during construction in an undisturbed condition as a standard for
                    judging the completed Work.
              7.    Demolish and remove mockups when directed.
              8.    Before submitting design mixes, review concrete mix design and examine
                    procedures for ensuring quality of concrete materials. Require representatives of
                    each entity directly concerned with cast-in-place concrete to attend, including the
                    following:
                    a.     Contractor's superintendent.
                    b.     Independent testing agency responsible for concrete design mixes.
                    c.     Ready-mix concrete producer.
                    d.     Concrete subcontractor.
A. Deliver, store, and handle steel reinforcement to prevent bending and damage.
       B.     Waterstops: Store waterstops sunder cover to protect from moisture, sunlight, dirt, oil,
              and other contaminants.
PART 2 - PRODUCTS
       A.   Smooth-Formed Finished Concrete: Form-facing panels that will provide continuous, true,
            and smooth concrete surfaces. Furnish in largest practicable sizes to minimize number
            of joints.
       E.   Void Forms: Biodegradable paper surface, treated for moisture resistance, structurally
            sufficient to support weight of plastic concrete and other superimposed loads.
       F.   Chamfer Strips: Wood, metal, PVC, or rubber strips, 20 by 20 mm, unless otherwise
            indicated.
       G.   Form-Release Agent: Commercially formulated form-release agent that will not bond with,
            stain, or adversely affect concrete surfaces and will not impair subsequent treatments
            of concrete surfaces.
1. Formulate form-release agent with rust inhibitor for steel form-facing materials.
              1.    Furnish units that will leave no corrodible metal closer than 25 mm to the plane of
                    the exposed concrete surface.
              2.    Furnish ties that, when removed, will leave holes not larger than 25 mm in
                    diameter in concrete surface.
    A.    Reinforcing Bars: Reinforced bars shall be deformed of grade B500DWR as per Egyptian
          Standard Specifications 262-2015. Submit the following to demonstrate compliance with
          the specified Standards:
D. One test on chemical analysis per each 50 tons from consignments delivered to Site.
    E.    Reinforcement shall be accurately bent, cut or formed to the dimensions and configuration
          shown on Drawings and within the tolerances specified in Egyptian code of practice.
          Reinforcement shall be bent cold using pin sizes in accordance with Egyptian code of
          practice. Bars may be preheated only if prior approval has been requested and received.
          Reinforcement shall not be rebent or straightened without prior approval.
    F.    Only new reinforcing bars shall be furnished. On receipt and at time of installation, steel
          shall be free of loose rust, loose mill scale and any deleterious amounts of salts and coatings
          that reduce bond.
    A.    Bar Supports: Bolsters, chairs, spacers, and other devices for spacing, supporting, and
          fastening reinforcing bars and welded wire fabric in place. Manufacture bar supports
          according to CRSI's "Manual of Standard Practice" from steel wire, plastic, or precast
          concrete or fiber-reinforced concrete of greater compressive strength than concrete, and
          as follows:
              1.   For concrete surfaces exposed to view where legs of wire bar supports contact
                   forms, use CRSI Class 1 plastic-protected or CRSI Class 2 stainless-steel bar
                   supports.
              2.   Joint Dowel Bars: Plain-steel bars, Grade B240D-P as per ECP-203. Cut bars true
                   to length with ends square and free of burrs.
    A.    Portland Cement: Cement shall be low alkali with chemical composition in accordance
          with ASTM C 150/C150M type I or Type CEM I 42.5N to BS EN 197-1 standard,
          gray and white color, of same type, brand and source for the entire project unless otherwise
          approved by the Engineer. Manufacturer’s test certification shall be supplied for each
          delivery of cement and shall confirm that the cement complies with the above requirements
          and shall be submitted by the Contractor not later than the day of delivery of the cement.
          The Engineer shall have the right to call for tests, the cost of which is to be borne by the
          Contractor, on each delivery of cement to confirm that the cement meets the following
          requirements.
    B.    Silica Fume: Silica fume (SF) used as a cement replacement shall be in accordance with
          Type U, specified in ASTM C1240. There shall be a 5% to 10% percent replacement of the
          cementitious content. The silica fume shall be obtained from an approved supplier.
                         1)     Si O2        C
                         2)     Ca O         Fe2 O3
                         3)     Al2 O3       Na2 O
                         4)     K2 O         Mg O
                         5)     SO3
                   f.    Loss on ignition.
                   g.    Percentage of particles greater than 44 mm.
                   h.    Specific surface area and method of test, together with corresponding
                         particle size.
2. Delivery of silica fume to the concrete batching plant shall be in dry powder
    C.    Supplementary Cementing materials: Blending of fly ash or slag with Portland cement is
          accomplished at mixing plant. Fly ash, slag, or Pozzolanic materials may slow rate of
          concrete strengthening and affect color uniformity.
    D.    Normal-Weight Aggregates: Aggregates shall be from approved sources and shall conform
          to the requirements of Egyptian Standards 1109 or ASTM C 33/C33M or BS EN 12620,
          from the same source for entire project, uniformly graded. Petrographic analyses shall be
          made in accordance with ASTM C 295. Aggregates for exposed concrete shall not contain
          substances that cause spalling. Only aggregates not susceptible to alkali aggregate reaction
          shall be used. The Contractor shall supply samples of the materials for approval by the
          Engineer and each aggregate source shall be subject to monitoring by the Engineer.
              2.    Fine Aggregate: Fine aggregate, those passing a 5mm sieve, shall consist of crushed
                    gravel, crushed stone or natural sand with rounded or surrounded particles and shall
                    be washed as necessary to comply with the following:
                    A.     Quarry location.
                    B.     Aggregate type.
                    C.     Petrographic analysis report.
                    D.     Grading curve.
                    E.     Shape and surface texture.
                    F.     Flakiness index.
                    G.     10 percent fines value.
                    H.     Impact test.
                    I.     Shell content.
                    J.     Chloride and sulfate content.
                    K.     Relative density.
                    L.     Water absorption value and moisture content.
                    M.     Silt, clay, and dust content.
4. Testing:
                   A.    When a source of supply for each aggregate type had been established,
                         samples of materials delivered to Project site shall be taken for testing in
                         accordance with BS 812 or ASTM standard as follows:
                          1)    Tests for clay, silt and dust, and sieve analysis shall be carried out
                                for every 100 tons of fine aggregate and every 100 tons of coarse
                                aggregate.
                          2)    Chemical analyses shall be carried out on every 200 tons of
                                aggregate.
                   B.    The Engineer shall have the right to call for additional samples at any time
                         for testing of aggregates delivered to the Project site or of aggregates at the
                         source of supply in order to confirm that the aggregates meet the above
                         requirements.
                   C.    Water: Water used for mixing concrete, ice production, washing and cooling
                         aggregates, and curing concrete shall be potable water, free from impurities,
                         oil, acid, salts, alkali, organic matter, and other potentially deleterious
                         substances complying with ASTM C1602/C1602M and ECP 203
                         requirements when tested in accordance with ASTM D 512 and ASTM D
                         516. The chloride content shall not exceed 500ppm.
              1.   Once a source of satisfactory supply has been established, further tests shall be made
                   daily with a portable electrical conductivity probe calibrated against the satisfactory
                   supply. If the conductivity exceeds that of the satisfactory supply, then further
                   chemical tests shall be performed.
              2.   The limits specified in Paragraph 2.12.I for the total salt content of the concrete shall
                   not be exceeded.
2.5 ADMIXTURES
    A.    General: Admixtures certified by manufacturer to contain no more than 0.1 percent water-
          soluble chloride ions by mass of cementitious material and to be compatible with
          other admixtures and cementitious materials. Do not use admixtures containing calcium
2.6 WATERSTOPS
    A.    Flexible Rubber Waterstops: CE CRD-C 513, for embedding in concrete to prevent passage
          of fluids through joints. Factory fabricate corners, intersections, and directional changes.
    A.    Vapor Retarder: ASTM E 1745, Class C, of one of the following materials; or polyethylene
          sheet, ASTM D 4397, not less than 0.25 mm thick:
    C.    Absorptive Cover: Burlap cloth made from jute or kenaf weighing approximately 0.29
          kg/sq. m and complying with AASHTO M182, Class 2.
              1.   Waterproof paper.
              2.   Polyethylene film.
              3.   Polyethylene-coated burlap.
    B.    Absorptive Cover: AASHTO M 182, Class 2, burlap cloth made from jute or
          kenaf, weighing approximately 305 g/sq. m when dry.
D. Water: Potable.
    B.    Bonding Agent: ASTM C 1059/C 1059M, Type II, non-redispersible, acrylic emulsion or
          styrene butadiene.
              1.   Types I and II, non-load bearing, for bonding hardened or freshly mixed concrete
                   to hardened concrete.
              2.   Types IV and V, load bearing, for bonding hardened or freshly mixed concrete to
                   hardened concrete.
    D.    Reglets: Fabricate reglets of not less than 0.55-mm- thick galvanized steel sheet.
          Temporarily fill or cover face opening of reglet to prevent intrusion of concrete or debris.
    E.    Dovetail Anchor Slots: Hot-dip galvanized steel sheet, not less than 0.85 mm thick, with
          bent tab anchors. Temporarily fill or cover face opening of slots to prevent intrusion of
          concrete or debris.
              1.   Cement Binder: ASTM C 150 or BS EN 197-1 Type CEM III/A 42.5N cement
                   or hydraulic or blended hydraulic cement as defined in ASTM C 219.
              2.   Primer: Product of underlayment manufacturer recommended for substrate,
                   conditions, and application.
              3.   Aggregate: Well-graded, washed gravel, 3 to 6 mm or coarse sand as recommended
                   by underlayment manufacturer.
              4.   Compressive Strength: Not less than 30 MPa at 28 days when tested according to
                   ASTM C109/C 109M.
    A.    Prepare design mixes for each type and strength of concrete determined by laboratory
          trial mix bases, as follows:
    B.    For reinforced structural elements in contract with soil, use cementitious additives, such as
          GGBS up to 65% or fly ash up to 35% of the cementitious weight, in combination with
          Microsilica 5% to 10% of the cementitious weight to ensure “Very Low” permeable
          concrete.
    C.    Use a qualified independent testing agency acceptable to the Engineer for preparing and
          reporting proposed mix designs for the laboratory trial mix basis.
1. Do not use the same testing agency for field quality control.
    D.    Submit written reports to the Engineer of each proposed mix for each class of concrete at
          least 15 days prior to start of Work. Do not begin concrete production until proposed mix
          designs have been reviewed and approved by the Engineer.
    G.    Water-Cement Ratio: The free water-cement ratio shall not exceed 0.45 except for blinding
          concrete where water-cement ratio can be limited to 0.6. Where cementitious additives are
          used, the water-cement ratio shall be the water content divided by the cement plus
          cementitious content. The water-cement ratio shall be continuously checked at the mixer
          with due allowance made for water contained in the aggregates. Under no circumstance
          shall water be added between the mixer and the place of concrete placement. The Engineer
          may require that the water-cement ratio be checked during tests performed on fresh concrete
          samples taken at the time of placement as specified in Paragraph 3.20.
    H.    Slump Limits: The slump of concrete mixes shall be such that the concrete can be
          transported, placed into the forms, and compacted without segregation in accordance with
          Paragraph 3.9. If no superplasticizer is required, the slump at time of placement shall be 50-
          75 mm as measured in accordance with ASTM C 143/C143M. In accordance with
          Paragraph 3.9, the concrete shall at all times exhibit a mobility that enables this placement
          to be affected with the minimum amount of difficulty.
              1.   Chlorides: The total chloride content (sum of both acid soluble and water soluble
                   chlorides) of the concrete from all sources, expressed as chloride ion, shall not
                   exceed 0.3 percent by weight of dry cement, inclusive of cementitious additives,
                   when tested in accordance with BS 1881 and ECP 203 requirements.
              2.   Sulfates: The total sulfate content of the concrete from all sources, expressed as SO3,
                   when tested in accordance with BS 1881 and ECP203 requirements, shall not exceed
                   4 percent by weight of dry cement, inclusive of cementitious additives.
              1.   The initial setting time shall be not less than one hour after the production concrete
                   is discharged into the form. With a maximum time between mixing and placing
                   concrete of one hour, the total time between mixing and initial set shall be a
                   minimum of 2 hours. There shall be a maximum setting time of 6 hours.
              2.   When trial mixes are made to determine the workability of the concrete, the initial
                   setting time of the cement paste shall be determined using the method defined in
                   ASTM C 191 but at the maximum allowable temperature and with same proportions
                   of pozzolan and retarding superplasticizer as specified in this Specification.
    K.    Test Mixes - Structural Grade Concrete: When the proposed workability, proportions of
          aggregates and superplasticizer, and strength for each grade of concrete have been
          established, test concrete shall be produced for approval by the Engineer. The following
          shall be performed for each grade of concrete:
              1.   Six separate test mixes shall be made and cured in accordance with ASTM C
                   192/C192M and tested in accordance with ASTM C 39/C39M.
              2.   The 36 cylinders for each grade of concrete shall be tested for compressive strength
                   at 28 days and the mean strength and standard deviation established for each grade.
              3.   The test mixes shall be accepted provided that:
              1.   Concrete for blinding or mudmat shall be a designed mix with the specified design
                   strength. The trial mix proportions shall be left to the discretion of the Contractor.
                   Once they have been chosen, three separate test mixes shall be made with
                   those proportions and three 150 mm test cylinders shall be made from each mix for
                   testing at 28 days. The trial mix proportions and water/cement ratio shall be
                   approved if the average strength of the nine cylinders is not less than 15 N/sq. mm.
              2.   No production test shall be made for this grade of concrete but the Engineer will
                   monitor the mix proportions and water/cement ratio.
    N.    Absorption Test: The absorption of the hardened concrete from the trial mixes for structural
          grades shall be tested as a measure of the concrete’s ability to resist the ingress of aggressive
          salts. No absorption tests shall be required for blinding or mudmat concrete. Absorption
          tests shall be in accordance with modified BS 1881: Part 122 as follows:
O. Permeability Tests:
              The concrete shall be of the “Low” to "Very Low" permeability level i.e. High
              durability satisfying the below permeability requirement
                    Use ISAT (initial Surface Absorption Test) during construction, as in-situ testing of
                    structures and will form one of the basic criteria for rejecting/accepting precast
                    concrete elements.
              2.    The chloride permeability of the concrete shall be determined using cores taken from
                    the concrete samples, in accordance with AASHTO T277 "Rapid Determination of
                    the Chloride Permeability of Concrete". The following limits shall not be exceeded:
              4.   The concrete will be deemed to comply with the permeability requirements of this
                   specification if all test results comply with the limits indicated in paragraphs 1, 2
                   and 3.
              5.   If any of the BS EN, chloride migration and the rapid chloride permeability test
                   results of unprotected surfaces of a sample failed to meet the above requirements,
                   then all the concrete work represented by such sample shall be deemed not to comply
                   with the permeability requirements.
              6.   If, in the opinion of the Engineer, the concrete that has failed to meet the
                   permeability requirements of this Specification is likely to cause durability
                   problems, three cores shall be cut from the area represented by failed samples for
                   additional BS EN, chloride migration and rapid chloride permeability testing. The
                   actual location shall be decided by the Engineer.
P. Test Construction:
              1.   Test Foundation: A test foundation footing and plinth shall be cast on grade to
                   the details provided by the Engineer in accordance with specified requirements. This
                   shall be performed before any permanent works are constructed. The concrete shall
                   be cured for the period required in Paragraph 3.13, after which an epoxy coating
                   shall be applied to that part of the plinth which would normally be above ground
                   and a bitumen coating applied to the remainder of the plinth and the footing, all in
                   accordance with Paragraph 3.17.
              2.   Test Floor Slab: A 3 m by 4 m test area of 150 mm thick floor slab constructed of
                   above ground reinforced concrete in accordance with this Specification shall be cast
                   on grade and given a Class U4 finish as specified in Paragraph 3.11.D. The concrete
                   shall be cured for the period specified in Paragraph 3.13.
              2.   Furnish the necessary equipment and establish accurate procedures for determining
                   the quantities of free moisture in the aggregates. Moisture determinations shall be
    B.    Job-Site Mixing: All concrete mixed on Project site shall be in a batch mixer of approved
          size and design complying with ACI 304 and producing a uniform distribution of the
          materials throughout the mixed concrete in accordance with ASTM C 94/C94M uniformity
          test. The contents of the drum shall be completely discharged before re-charging. After all
          the materials are in the mixer, mixing shall continue until the whole of the materials are
          uniformly distributed and the mass is of uniform color and consistency. In the case of
          concrete that contains silica fume with a density between 400-650 kg/cu. m, the mixing
          time shall be 50 percent greater than the requirement for concrete without silica fume.
              1.   Whenever mixing is to be suspended for half an hour or longer, the drum of the
                   mixer shall be thoroughly washed out with clean water. Provide a competent operator
                   who shall be in continuous control of the mixer. No retempering of concrete,
                   which has partially hardened, by the addition of cement, aggregate, or water shall be
                   allowed.
              2.   Provide batch ticket for each batch discharged and used in the Work, indicating
                   Project identification name and number, date, mix type, mix time, quantity, and
                   amount of water introduced.
C. Ready-Mixed Concrete:
              2.   When air temperature is between 30 deg.C (82 deg.F) and 32 deg.C (90 deg.
                   F), delivery time from the time water is added to the mix until it is placed in its
                   final position in the form shall not exceed 60 minutes. When air temperature is 35
                   deg.C, delivery time shall not exceed 2.5 hours (by using additives).
              3.   Before discharging concrete at the point of delivery, provide the Engineer with
                   a delivery ticket for each batch of concrete containing the following information
                   as a minimum:
PART 3 – EXECUTION
3.1 FORMWORK
       A.   Design, erect, shore, brace, and maintain formwork, according to ACI 301, to support
            vertical, lateral, static, and dynamic loads, and construction loads that might be applied,
            until concrete structure can support such loads.
       B.   Construct formwork so concrete members and structures are of size, shape, alignment,
            elevation, and position indicated, within tolerance limits of ECP 203 Chapter 9.
              1.    Class A, 4 mm.
              2.    Class B, 6 mm.
              3.    Class C, 10 mm.
              4.    Class D, 25 mm.
       E.     Fabricate forms for easy removal without hammering or prying against concrete surfaces.
              Provide crush or wrecking plates where stripping may damage cast concrete surfaces.
              Provide top forms for inclined surfaces steeper than 1.5 horizontal to 1 vertical. Kerf wood
              inserts for forming keyways, reglets, recesses, and the like, for easy removal.
       F.     Set edge forms, bulkheads, and intermediate screed strips for slabs to achieve required
              elevations and slopes in finished concrete surfaces. Provide and secure units to support
              screed strips; use strike-off templates or compacting-type screeds.
       G.     Provide temporary openings for cleanouts and inspection ports where interior area of
              formwork is inaccessible. Close openings with panels tightly fitted to forms and securely
              braced to prevent loss of concrete mortar. Locate temporary openings in forms at
              inconspicuous locations.
       J.     Form openings, chases, offsets, sinkages, keyways, reglets, blocking, screeds, and
              bulkheads required in the Work. Determine sizes and locations from trades providing such
              items.
       K.     Clean forms and adjacent surfaces to receive concrete. Remove chips, wood, sawdust, dirt,
              and other debris just before placing concrete.
       L.     Retighten forms and bracing before placing concrete, as required, to prevent mortar leaks
              and maintain proper alignment.
       M.     Coat contact surfaces of forms with form-release agent, according to manufacturer's written
              instructions, before placing reinforcement.
    A.      Place and secure anchorage devices and other embedded items required for adjoining work
            that is attached to or supported by cast-in-place concrete. Use Setting Drawings, templates,
            diagrams, instructions, and directions furnished with items to be embedded.
    A.    General: Formwork, for sides of beams, walls, columns, and similar parts of the Work, that
          does not support weight of concrete may be removed after cumulatively curing at not
          less than 10 deg C for 24 hours after placing concrete provided concrete is hard enough to
          not be damaged by form-removal operations and provided curing and protection
          operations are maintained.
    B.    Leave formwork, for beam soffits, joists, slabs, and other structural elements, that supports
          weight of concrete in place until concrete has achieved the following:
    C.    Clean and repair surfaces of forms to be reused in the Work. Split, frayed, delaminated, or
          otherwise damaged form-facing material will not be acceptable for exposed surfaces. Apply
          new form-release agent.
    D.    When forms are reused, clean surfaces, remove fins and laitance, and tighten to close joints.
          Align and secure joints to avoid offsets. Do not use patched forms for exposed concrete
          surfaces unless approved by Engineer.
    A.    Comply with ACI 318M, ACI 301, and recommendations in ACI 347R for design,
          installation, and removal of shoring and reshoring.
    C.    Plan sequence of removal of shores and reshore to avoid damage to concrete. Locate and
          provide adequate reshoring to support construction without excessive stress or deflection.
    A.    Vapor Retarder: Place, protect, and repair vapor-retarder sheets according to ASTM E 1643
          and manufacturer's written instructions.
    B.    Fine-Graded Granular Material: Cover vapor retarder with fine-graded granular material,
          moisten, and compact with mechanical equipment to elevation tolerances of plus 0 mm or
          minus 20 mm.
    C.    Granular Fill: Cover vapor retarder with granular fill, moisten, and compact with
          mechanical equipment to elevation tolerances of plus 0 mm or minus 20 mm.
              1.   Place and compact a 15-mm- thick layer of fine-graded granular material over
                   granular fill.
C. Set wire ties with ends directed into concrete, not toward exposed concrete surfaces.
    D.    Install welded wire fabric in longest practicable lengths on bar supports spaced to
          minimize sagging. Lap edges and ends of adjoining sheets at least one mesh spacing.
          Offset laps of adjoining sheet widths to prevent continuous laps in either direction. Lace
          overlaps with wire.
                   a.    Bars for separate buildings or large structures shall not be bundled together.
                         Bars for small structures may be bundled together but each bar or group of
                         bars that have the same piece mark shall be tagged and coded.
                   b.    Metal tags or approved equal shall be provided and labeled with legible
                         markings.
                   c.    All bundles shall be tagged at each end. Tags shall show piece marks
                         corresponding to the mark numbers on the placement drawings and on the
                         bar list.
                   d.    Bars shall be bundled in the largest size practical for handling and
                         shipping.
    F.    Clean reinforcement of loose rust and mill scale, earth, ice, and other materials that
          reduce or destroy bond with concrete.
I. Concrete Cover:
              1.   Concrete cover has to satisfy the ECP 203 and also comply with Table 2-14 in
                   ECP 203 to satisfy three hours fire rating for all vertical elements and two hours fire
                   rating for all horizontal elements.
              2.   Cover to reinforcement shall be checked before any concrete is cast. The bending of
                   reinforcement at a cold joint is not permitted. Concrete cover shall be checked with
                   a cover meter as soon as formwork is removed.
    J.    All lap splices shall be in accordance with the ECP-203 splice requirements unless
          otherwise shown on Drawings. All reinforcement bars shall be developed in accordance
          with the Egyptian Code of Practice unless otherwise shown on Drawings. Welded wire
          fabric shall be lapped 1.5 mesh plus the extension on the wires unless otherwise shown
          on Drawings.
3.7 JOINTS
A. General: Construct joints true to line with faces perpendicular to surface plane of concrete.
    B.    Construction Joints: Install so strength and appearance of concrete are not impaired, at
          locations indicated or as approved by Engineer.
              1.   Grooved Joints: Form contraction joints after initial floating by grooving and
                   finishing each edge of joint to a radius of 3 mm repeat grooving of contraction joints
                   after applying surface finishes. Eliminate groove tool marks on concrete surfaces.
              2.   Sawed Joints: Form contraction joints with power saws equipped with shatterproof
                   abrasive or diamond-rimmed blades. Cut 3-mm wide joints into concrete when
                   cutting action will not tear, abrade, or otherwise damage surface and before concrete
                   develops random contraction cracks.
              1.   Extend joint-filler strips full width and depth of joint, terminating flush with finished
                   concrete surface, unless otherwise indicated.
              2.   Terminate full-width joint-filler strips not less than 12 mm or more than 25 mm
                   below finished concrete surface where joint sealants, specified in Section 079200
                   "Joint Sealants," are indicated.
              3.   Install joint-filler strips in lengths as long as practicable. Where more than one length
                   is required, lace or clip sections together.
    E.    Dowel Joints: Install dowel sleeves and dowels or dowel bar and support assemblies at
          joints where indicated.
3.8 WATERSTOPS
    C.    Transportation: Concrete, after being discharged from the mixer, shall be transported as
          rapidly as possible to its final position in the Work by agitator trucks, which shall prevent
          adulteration, segregation, loss of workability or contamination of the ingredients. The
          containers that convey the concrete shall be kept clean and free from hardened or partially
          hardened concrete.
              1.   The addition of water at the point of discharge is prohibited and trucks shall have
                   the water tank completely disconnected from the drum.
              2.   The use of chutes, spouts, skips and pumps shall be permitted if approval is obtained.
                   Under no circumstances shall any aluminum pipe or other conveying equipment
                   containing aluminum be allowed to contact fresh concrete when it is conveyed to its
                   point of placement.
              3.   Method of pouring and pouring sequence shall be submitted by the Contractor to the
                   Engineer’s approval.
              1.   Concrete shall not be dropped into place from a height exceeding 1.5 m nor through
                   dense reinforcing steel, which could cause segregation of the coarse aggregate.
                   Structural concreting against open excavation will not be permitted as the concrete
                   cannot be coated afterwards.
              2.   When vertical lifts of concrete are interrupted or delayed for more than one hour, the
                   surface of the unfinished concrete shall be thoroughly cleaned and washed with
                   cement grout immediately before fresh concrete is added and the first layer of new
                   concrete placed shall not exceed 150mm depth and particular care shall be taken with
                   compaction of this new layer to ensure good bond.
              3.   Method of pouring and pouring sequence shall be submitted by the Contractor to the
                   Engineer’s approval.
              4.   Consolidate placed concrete with mechanical vibrating equipment. Use equipment
                   and procedures for consolidating concrete recommended by ACI 309R.
              5.   Do not use vibrators to transport concrete inside forms. Insert and withdraw vibrators
                   vertically at uniformly spaced locations no farther than the visible effectiveness of
                   the vibrator. Place vibrators to rapidly penetrate placed layer and at least 150 mm
                   into preceding layer. Do not insert vibrators into lower layers of concrete that have
                   begun to lose plasticity. At each insertion, limit duration of vibration to time
                   necessary to consolidate concrete and complete embedment of reinforcement and
                   other embedded items without causing mix constituents to segregate.
E. Do not add water or admixture to concrete during delivery, at Project site, or during
    F.    Deposit and consolidate concrete for floors and slabs in a continuous operation, within
          limits of construction joints, until placement of a panel or section is complete.
    G.    Compaction and Vibration: Full compaction of the concrete shall be achieved throughout
          the entire depth of the layer. It shall be thoroughly worked against the formwork and
          around the reinforcement and successive layers shall be thoroughly bonded together. Air
          bubbles formed during the mixing and casting shall be expelled particular care shall be
          taken where sloping formwork is used.
    H.    Hot-Weather Placement: When hot weather conditions exist that would impair quality and
          strength of concrete, place concrete complying with ACI 305 and as specified.
    A.    Rough-Formed Finish: As-cast concrete texture imparted by form-facing material with tie
          holes and defective areas repaired and patched. Remove fins and other projections
          exceeding ACI 347R limits for class of surface specified.
              1.   Smooth-Rubbed Finish: Not later than one day after form removal, moisten concrete
                   surfaces and rub with carborundum brick or another abrasive until producing a
                   uniform color and texture. Do not apply cement grout other than that created by
                   the rubbing process.
              3.   Cork-Floated Finish: Wet concrete surfaces and apply a stiff grout. Mix one part
                   CEM III/A cement and one part fine sand with a 1:1 mixture of bonding agent and
                   water. Add white CEM III/A cement in amounts determined by trial patches so color
                   of dry grout will match adjacent surfaces. Compress grout into voids by grinding
                   surface. In a swirling motion, finish surface with a cork float.
    D.    Related Unformed Surfaces: At tops of walls, horizontal offsets, and similar unformed
          surfaces adjacent to formed surfaces, strike off smooth and finish with a texture matching
          adjacent formed surfaces. Continue final surface treatment of formed surfaces uniformly
          across adjacent unformed surfaces, unless otherwise indicated.
    A.    General: Comply with recommendations in ACI 302.1R for screeding, restraightening, and
          finishing operations for concrete surfaces. Do not wet concrete surfaces.
    B.    Scratch Finish: While still plastic, texture concrete surface that has been screeded and bull-
          floated or darbied. Use stiff brushes, brooms, or rakes.
    C.    Float Finish: Consolidate surface with power-driven floats or by hand floating if area is
          small or inaccessible to power driven floats. Restraighten, cut down high spots, and fill low
          spots. Repeat float passes and restraightening until surface is left with a uniform, smooth,
          granular texture.
              1.   Apply float finish to surfaces indicated, to surfaces to receive trowel finish, and
                   to floor and slab surfaces to be covered with fluid-applied or sheet waterproofing,
                   built- up or membrane roofing, or sand-bed terrazzo.
    D.    Trowel Finish: After applying float finish, apply first trowel finish and consolidate concrete
          by hand or power-driven trowel. Continue troweling passes and restraighten until surface
          is free of trowel marks and uniform in texture and appearance. Grind smooth any surface
          defects that would telegraph through applied coatings or floor coverings.
              1.   Apply a trowel finish to surfaces indicated and to floor and slab surfaces exposed
                   to view or to be covered with resilient flooring, carpet, ceramic or quarry tile set over
                   a cleavage membrane, paint, or another thin film-finish coating system
                   a.    Specified overall values of flatness, F(F) 35; and levelness, F(L) 25; with
                         minimum local values of flatness, F(F) 24; and levelness, F(L) 17; for slabs-
                         on-grade.
                   b.    Specified overall values of flatness, F(F) 30; and levelness, F(L) 20; with
                         minimum local values of flatness, F(F) 24; and levelness, F(L) 15; for
                         suspended slabs.
              3.   Finish and measure surface so gap at any point between concrete surface and an
                   unleveled freestanding 3-m long straightedge, resting on two high spots and placed
                   anywhere on the surface, does not exceed the following:
a. 5 mm.
    E.    Trowel and Fine-Broom Finish: Apply a partial trowel finish, stopping after second
          troweling, to surfaces indicated and to surfaces where ceramic or quarry tile is to be installed
          by either thickset or thin-set method. Immediately after second troweling, and when
          concrete is still plastic, slightly scarify surface with a fine broom.
    F.    Broom Finish: Apply a broom finish to exterior concrete platforms, steps, and ramps, and
          elsewhere as indicated.
              3.   After curing, lightly work surface with a steel wire brush or an abrasive stone, and
                   water to expose slip-resistive aggregate.
    H.    Mineral Dry-Shake Floor Hardener Finish: After initial floating, apply mineral dry-shake
          materials to surfaces according to manufacturer's written instructions and as follows:
              3.   After final floating, apply a trowel finish. Cure concrete with curing compound
                   recommended by dry-shake material manufacturer and apply immediately after final
                   finishing.
    A.    Filling In: Fill in holes and openings left in concrete structures, unless otherwise indicated,
          after work of other trades is in place. Mix, place, and cure concrete, as specified, to blend
          with in-place construction. Provide other miscellaneous concrete filling indicated or
          required to complete Work.
    B.    Curbs: Provide monolithic finish to interior curbs by stripping forms while concrete is still
          green and by steel-troweling surfaces to a hard, dense finish with corners, intersections, and
          terminations slightly rounded.
    C.    Equipment Bases and Foundations: Provide machine and equipment bases and foundations
          as shown on Drawings. Set anchor bolts for machines and equipment at correct elevations,
          complying with diagrams or templates of manufacturer furnishing machines and equipment.
    D.    Steel Pan Stairs: Provide concrete fill for steel pan stair treads, landings, and associated
          items. Cast-in inserts and accessories as shown on Drawings. Screed, tamp, and trowel-
          finish concrete surfaces.
    E.    Tolerance and concrete dimensions for in-situ concrete members shall, under no
          circumstances, exceed the permissible ones as indicated in the ACI.
    A.    General: Protect freshly placed concrete from premature drying and excessive cold or
          hot temperatures. Comply with Egyptian code requirements
    B.    Evaporation Retarder: Apply evaporation retarder to unformed concrete surfaces if hot, dry,
          or windy conditions cause moisture loss approaching 1 kg/sq. m x h before and during
          finishing operations. Apply according to manufacturer's written instructions after placing,
          screeding, and bull floating or darbying concrete, but before float finishing.
    C.    Formed Surfaces: Cure formed concrete surfaces, including underside of beams, supported
          slabs, and other similar surfaces. If forms remain during curing period, moist cure after
          loosening forms. If removing forms before end of curing period, continue curing by one
          or a combination of the following methods:
    D.    Unformed Surfaces: Begin curing immediately after finishing concrete. Cure unformed
          surfaces, including floors and slabs, concrete floor toppings, and other surfaces, by one or
          a combination of the following methods:
              1.   Moisture Curing: Keep surfaces continuously moist for not less than seven days
                   with the following materials:
                   a.     Water.
                   b.     Continuous water-fog spray.
                   c.     Absorptive cover, water saturated, and kept continuously wet. Cover
                          concrete surfaces and edges with 300 mm lap over adjacent absorptive
                          covers.
              2.   Moisture-Retaining-Cover Curing: Cover concrete surfaces with moisture-retaining
                   cover for curing concrete, placed in widest practicable width, with sides and ends
                   lapped at least 300 mm, and sealed by waterproof tape or adhesive. Cure for not
                   less than seven days. Immediately repair any holes or tears during curing period
                   using cover material and waterproof tape.
              1.   Horizontal Surfaces: Horizontal surfaces shall be saturated with water and then
                   treated with curing compound. Apply curing compound as soon as final finishing
                   operations are complete (within 2 hours and after surface water sheen has
                   disappeared). Apply uniformly in continuous operation by power spray or roller
                   according to manufacturer's directions. Recoat areas subjected to heavy rainfall
                   within 3 hours after initial application. The surfaces shall then be bonded and
                   flooded with water or draped with wet burlap together with a perforated soaker
                   hosepipe, covered with white impervious sheeting held firmly in place along all
                   edges and kept continuously wet for the duration of the curing period.
              2.   Vertical Surfaces: Vertical timber formwork shall be draped with wet burlap as soon
                   as concrete is placed. Vertical surfaces shall be treated with curing compound as
                   soon as formwork is removed, draped with wet burlap, covered with white
                   impervious sheeting held firmly in place along all edges and kept continuously wet
                   for the duration of the curing period. Care shall be taken to avoid drying winds.
    A.    Penetrating Liquid Floor Treatment: Prepare, apply, and finish penetrating liquid floor
          treatment according to manufacturer's written instructions.
              1.   Remove curing compounds, sealers, oil, dirt, laitance, and other contaminants
                   and complete surface repairs.
              2.   Do not apply to concrete that is less than seven days old.
              3.   Apply liquid until surface is saturated, scrubbing into surface until a gel forms; rewet;
                   and repeat brooming or scrubbing. Rinse with water; remove excess material until
                   surface is dry. Apply a second coat in a similar manner if surface is rough or porous.
    B.    Sealing Coat: Uniformly apply a continuous sealing coat of curing and sealing compound
          to hardened concrete by power spray or roller according to manufacturer's written
          instructions.
A. Prepare, clean, and install joint filler according to manufacturer's written instructions.
              1.   Defer joint filling until concrete has aged at least six months. Do not fill joints until
                   construction traffic has permanently ceased.
    B.    Remove dirt, debris, saw cuttings, curing compounds, and sealers from joints; leave
          contact faces of joint clean and dry.
    C.    Install semirigid epoxy joint filler full depth in saw-cut joints and at least 50 mm deep in
          formed joints. Overfill joint and trim joint filler flush with top of joint after hardening.
    A.    Concrete exposed by the removal of formwork shall be inspected by the Engineer before
          any remedial work, subsequent coating or other treatment that would hinder the proper
          inspection of the concrete is carried out. Any concrete not complying with this requirement
          shall be liable for rejection.
    B.    Concrete not meeting the specified requirements shall be removed and rebuilt without delay
          unless the Engineer approves that a repair may be satisfactorily effected. This agreement
          shall not preclude the subsequent rejection of the repaired work by the Engineer. The
          proposed method for removal and replacement of defective work shall be submitted to the
          Engineer for approval for each concrete placement before the removal commences.
    D.    Defective Concrete: Repair and patch defective areas when approved by Engineer. Remove
          and replace concrete that cannot be repaired and patched to Engineer's approval.
    E.    Patching Mortar: Mix dry-pack patching mortar, consisting of one part CEM III/A cement
          to two and one-half parts fine aggregate passing a 1.2-mm sieve, using only enough water
          for handling and placing.
    F.    Repairing Formed Surfaces: Surface defects include color and texture irregularities, cracks,
          spalls, air bubbles, honeycombs, rock pockets, fins and other projections on the surface,
          and stains and other discolorations that cannot be removed by cleaning.
              1.   Immediately after form removal, cut out honeycombs, rock pockets, and voids more
                   than 13 mm in any dimension in solid concrete but not less than 25 mm in depth.
                   Make edges of cuts perpendicular to concrete surface. Clean, dampen with water,
                   and brush-coat holes and voids with bonding agent. Fill and compact with patching
                   mortar before bonding agent has dried. Fill form-tie voids with patching mortar
                   or cone plugs secured in place with bonding agent.
              2.   Repair defects on surfaces exposed to view by blending white CEM III/A cement
                   and standard CEM III/A cement so that, when dry, patching mortar will match
              3.   Repair defects on concealed formed surfaces that affect concrete's durability and
                   structural performance as determined by Engineer.
    G.    Repairing Unformed Surfaces: Test unformed surfaces, such as floors and slabs, for finish
          and verify surface tolerances specified for each surface. Correct low and high areas. Test
          surfaces sloped to drain for trueness of slope and smoothness; use a sloped template.
              1.   Repair finished surfaces containing defects. Surface defects include spalls, popouts,
                   honeycombs, rock pockets, crazing and cracks in excess of 0.25 mm wide or
                   that penetrate to reinforcement or completely through unreinforced sections
                   regardless of width, and other objectionable conditions.
2. After concrete has cured at least 14 days, correct high areas by grinding.
              3.   Correct localized low areas during or immediately after completing surface finishing
                   operations by cutting out low areas and replacing with patching mortar. Finish
                   repaired areas to blend into adjacent concrete.
              4.   Correct other low areas scheduled to receive floor coverings with a repair
                   underlayment. Prepare, mix, and apply repair underlayment and primer according to
                   manufacturer's written instructions to produce a smooth, uniform, plane, and level
                   surface. Feather edges to match adjacent floor elevations.
              5.   Correct other low areas scheduled to remain exposed with a repair topping. Cut out
                   low areas to ensure a minimum repair topping depth of 6 mm to match adjacent floor
                   elevations. Prepare, mix, and apply repair topping and primer according to
                   manufacturer's written instructions to produce a smooth, uniform, plane, and level
                   surface.
              6.   Repair defective areas, except random cracks and single holes 25 mm or less
                   in diameter, by cutting out and replacing with fresh concrete. Remove defective
                   areas with clean, square cuts and expose steel reinforcement with at least 20 mm
                   clearance all around. Dampen concrete surfaces in contact with patching concrete
                   and apply bonding agent. Mix patching concrete of same materials and mix as
                   original concrete except without coarse aggregate. Place, compact, and finish to
                   blend with adjacent finished concrete. Cure in same manner as adjacent concrete.
              7.   Repair random cracks and single holes 25 mm or less in diameter with patching
                   mortar. Groove top of cracks and cut out holes to sound concrete and clean off dust,
                   dirt, and loose particles. Dampen cleaned concrete surfaces and apply bonding agent.
                   Place patching mortar before bonding agent has dried. Compact patching mortar and
                   finish to match adjacent concrete. Keep patched area continuously moist for at least
                   72 hours.
    I.    Repair materials and installation not specified above may be used, subject to Engineer's
          approval.
    A.    The following are typical concrete protection and waterproofing requirements except
          at basements, tunnels, and other buried structures. General: All concrete shall have
          surface holes investigated and filled with a filler compatible with the coating to be applied
          (if that coating alone cannot fill the hole) provided that they are small and formed by air
          bubbles caught against the formwork. For surface holes having any dimension greater than
          10 mm, refer to paragraph 3.16.
    B.    Blinding or Mudmat Concrete: Unless otherwise shown on Drawings, all foundations shall
          be placed on 75 mm thick blinding or mudmat concrete and all slab on grade shall be placed
          on 50 mm thick blinding or mudmat. Prior to placing this concrete, the subsoil shall be well
          consolidated and free from loose material.
    C.    Impervious Membrane: Concrete shall be cast onto impervious sheeting complying with
          ASTM E 154 laid over the concrete blinding or mudmat. Overlap shall be 150 mm and the
          sheeting shall extend 150 mm beyond the edge of all foundations.
    D.    Surfaces Below Ground Level: Surfaces below ground level shall be coated with 3 coats of
          modified bitumen giving a total coating thickness of 1 mm. A square scrape master sample
          shall be taken to determine the weight of specified thickness of coating from a 300 mm by
          300 mm patch. The weight can then be compared with test samples. With surfaces at grade
          coated as specified, the bitumen shall overlap the epoxy coating by 75 mm. Before soil is
          backfilled around the foundations, the coated surfaces shall be permanently covered with
          impervious sheeting as specified in Paragraph 3.17.C and overlain with protection board,
          suitably banded to retain it in position. Overlap of the sheeting shall be 150 mm.
              1.   Exposed external concrete surfaces for a depth of 150 mm below and 300 mm above
                   ground level, or to the underside of base plates (whichever is lowest), shall be primed
                   with a low viscosity primer and coated with 2 coats of a light gray colored epoxy
                   paint with a minimum thickness of 125 microns per coat.
              2.   Application trials shall be carried out on the chosen coating. Concrete surface
                   preparation and application shall be in accordance with the manufacturer’s
                   instructions.
    F.    Exposed External Surfaces Above Ground Level: General exposed exterior surfaces above
          grade shall be coated as specified in Paragraph 3.17.E. The coating shall extend to the
          underside of the baseplates; i.e., cover the grout.
    G.    External Surfaces Exposed to Saline Waters: Exterior surfaces in the sea splash zone or in
          the tidal zone, or the interior faces of structures containing saline water, shall be coated as
          specified in Paragraph 3.17.E.
 3.18     GROUTING
B. Materials:
              1.   Type G1: For interior bases protected from weather and saline bearing waters and
                   not subject to heavy or vibratory loads, grout shall consist of one part CEM III/A
                   cement to two parts well graded sand by volume. Sand shall comply with Paragraph
                   2.5.C.2. A retarding superplasticizer may be used if necessary to obtain the correct
                   fluidity in high ambient temperatures.
              2.   Type G3: For all other exterior work exposed to potential saline ingress, a proprietary
                   general purpose non-shrink grout, especially formulated for high temperature work.
C. Placement:
              2.   Grout strength shall not be less than 30 N/sq. mm at 28 days. Document to Engineer
                   that this strength is being achieved. Grouting shall not proceed until the steel work
                   or equipment has been leveled and plumbed with the bases being supported in the
                   meantime by steel packers and shims.
              3.   Completely fill anchor bolt sleeves with grout before placing grout under base plates.
                   The gravity grouting method shall be used wherein the flowable self-leveling grout
                   is poured on one side of a base until it flows out at the opposite side. Packers and
                   shims used to level bases shall be removed after the grout has set and the resulting
                   pocket repaired with similar grout.
    B.    Joints: Joints shall be designed and constructed in accordance with ACI 504R. Details and
          positioning of joints, together with the materials to be used, shall be shown on the
          Drawings.
          1.     Waterstops shall be in accordance with Paragraph 2.6. Jointing of waterstops shall
                 be made by welding in an approved fashion. Lapping of waterstops at joints and the
                 use of adhesives for jointing purposes shall not be permitted unless specifically
                 authorized. Waterstops shall not be perforated or damaged. Concrete shall be
    C.    Coating: Coat inside faces of structures containing saline waters as specified in Paragraph
          3.17.F.
    D.    Testing: In addition to the testing required in Paragraph 3.20.C, further tests to determine
          the water tightness of the structure shall be performed based on the requirements of ACI
          350.1-01. Testing shall be performed after completion of the structure, installation of
          fittings and accessories, but before the application of internal waterproofing, and before
          any backfilling behind the structure's walls has taken place. The following measures
          should be considered:
              1.   All tank penetrations and outlets shall be securely sealed to prevent loss of water
                   from the tank during the test. Tank penetrations and outlets shall be monitored before
                   and during the test and shall be repaired from leakage (if any) prior to taking
                   test measurements.
              2.   Rate of initial filling of a new tank should not exceed 1.2m/hr (of the tank height).
                   Tank filling shall be continued until the water surface is at the design maximum
                   water level or 100 mm below any fixed overflow level, whichever is lower.
              4.   The change in water volume in the structure shall be calculated and corrected, if
                   necessary for evaporation, precipitation and temperature. If loss exceeds the required
                   criterion, the structure shall be considered to have failed the test. The structure shall
                   also be considered to have failed the test if observed flowing or seeping from the
                   structure or if moisture can be transferred from exterior surface to a dry hand. The
                   structure shall not be considered to have failed the acceptance criterion if dampness
                   or wetness on top of a footing, in the absence of flowing water, is observed.
A. General:
1. Testing Laboratory:
                   a.     Sampling, curing and testing shall be performed using the relevant procedures
                          in ASTM C 31/C31M, ASTM C 39/C39M, and ASTM C 172.
b. Permeability Tests:
               c.    Records: Records shall be kept of the mix details and position in the works of
                     all batches of concrete and of all samples taken for cylinders and other
                     specimens and of their test results. A copy shall be supplied to the Engineer
                     within 24 hours after recording/testing. Records shall contain, but not be
                     limited to, the following information:
               d.    For the 28-day tests, the concrete will be deemed to comply with the specified
                     design strength if the average strength determined from all sets of 3
                     consecutive tests is at least equal to the specified design strength and no
                     individual strength test falls below the specified design strength by more than
                     3.5 N/sq. mm. Any concrete not complying with the specified design strength
                     shall be at risk for removal and replacement at the Contractor’s expense.
              4.   Cement Content and Water/Cement Ratio: Samples of freshly mixed concrete shall
                   be chosen by the Engineer at least once per month from each structural grade and
                   determination made of cement content and water/cement ratio in accordance with
                   BS 1881. If the cement content is less than 90 percent of the requirement in
                   Paragraph 2.12.E. or the water/cement ratio greater than 110 percent of the
                   requirement in Paragraph 2.12.G. then there shall be an investigation to establish
                   the cause and the Engineer may reject the casted concrete for the pour from which
                   the samples were taken. The Engineer may request an analysis of fresh concrete
                   from any pour. No analysis of freshly mixed concrete is required for blinding or
                   mudmat concrete.
              5.   Salt Content: The total concentrations of sulfates and chlorides in the fine and
                   coarse aggregates shall be measured at least once a week for all structural grades
                   of concrete. Tests shall be in accordance with BS EN 1744-1. Concentrations of
                   each ion shall not exceed the limits specified in Paragraph 2.4.E.1 for coarse
                   aggregates, 2.4.E.2 for fine aggregates and 2.12.I for the total salt content of
                   concrete. If these limits are exceeded, the concrete pour from which the samples
                   were taken shall be rejected and further tests performed on the cast concrete in
                   accordance with Paragraph 3.20.C to determine the total extent of the problem.
                   Slump: Slump tests shall be performed in accordance with ASTM C 143/C143M.
                   There shall be a minimum of one test at the point of discharge for each day's pour
                   for each type of concrete. Additional tests shall be performed when concrete
                   consistency appears to have changed
              1.   General: The Engineer may request samples to be taken and tests carried out on
                   any hardened structural grade concrete as specified below if he suspects that the
                   concrete does not meet the specified requirements. If the tests confirm that the
                   concrete does not meet the requirements of this Specification, then the Engineer
                   may require the concrete to be removed at the Contractor’s expense. If the tests
                   confirm that the concrete meets the requirements of this Specification, then the
                   cost of taking the samples shall not be at the Contractor’s expense.
              2.   Compressive Strength Tests: The Engineer may request cores to be drilled from a
                   particular pour. 100 mm diameter cores shall be drilled as requested, in accordance
                   with ASTM C 42/C42M, and sent for crushing. If the cores from that pour have an
                   average compressive strength less than 85 percent of the characteristic strength or
                   any individual core has a compressive strength less than 75 percent of the
                   characteristic strength, it shall be evidence that the concrete from which it was taken
                   is not in accordance with the specified requirements.
              3.   Concrete Cover: The Engineer may check the concrete cover over the reinforcement
                   with a cover meter. Any indication that the cover is generally less than the
                   requirements specified in Paragraph 3.6.I shall be checked by limited surface
                   concrete removal. If it is confirmed that the actual cover is generally less than
                   specified, then the concrete shall be removed at the Contractor’s expense. In the case
                   of localized lack of cover and where appearance is not important, a repair shall be
                   effected by removal of the inadequate cover and the cutting back of concrete for 50
                   mm behind the reinforcement. Resurfacing of the concrete with the specified cover
                   shall be carried out as a repair by a specialist subcontractor as specified in Paragraph
                   3.16.
              6.   Salt Content: Engineer may request samples to be taken from two 20 mm diameter
                   drillings into the concrete surface, spaced 75 mm apart. Each drilling shall proceed
                   in 25 mm increments for a total depth of 100 mm and the dust from the 4 samples in
                   each hole shall be sent for sulfate and chloride content analysis in accordance with
                   BS 1881 Part 124. Should the tests show that the limits specified in Paragraph 2.12.I
                   are exceeded, the concrete shall be removed.
    A.    Protect liquid floor treatment from damage and wear during the remainder of
          construction period. Use protective methods and materials, including temporary covering,
          recommended in writing by liquid floor treatments installer.
PART 1 – GENERAL
1.2 SUMMARY
       A. Section includes polymer-modified cement waterproofing for wet areas and where
          indicated in drawings.
B. Related Requirements:
B. Product Certificates: For each type of waterproofing, patching, and plugging material.
        1) Build mockup of typical vertical and horizontal surfaces in locations and sizes as
           directed by the Engineer.
        2) Approval of mockups does not constitute approval of deviations from the Contract
           Documents contained in mockups unless Engineer specifically approves such
           deviations in writing.
        3) Subject to compliance with requirements, approved mockups may become part
           of the completed Work if undisturbed at time of Substantial Completion.
       A. Weather Limitations: Proceed with application only when existing and forecasted
          weather conditions permit polymer-modified cement waterproofing to be performed
          according to manufacturer's written instructions.
       B. Proceed with waterproofing work only after pipe sleeves, vents, curbs, inserts, drains, and
          other projections through the substrate to be waterproofed have been completed. Proceed
          only after substrate defects, including honeycombs, voids, and cracks, have been repaired
          to provide a sound substrate free of forming materials, including reveal inserts.
1.8 WARRANTY
       A. General Warranty: Any special warranty specified in this Article shall not deprive the
          Employer of other rights Employer may have under other provisions of the Contract
          Documents and shall be in addition to, and run concurrent with, other warranties made by
          the Contractor under the requirements of the Contract Documents.
PART 2- PRODUCTS
  Resistance to artificial weathering (2000 hours of UV radiation and        No blistering, cracking or flaking, no change
  condensation), EN 1062/11                                                  in color
Resistance to negative hydraulic pressure UNI8298/B 2.5 bar (equivalent to 25 m water column)
  Impact resistance, EN ISO 6272 Class I:4 N·m Class II: 10 N·m Class III:   Class Ill (equivalent to the fall of a 1 kg steel ball from a
  20N·m                                                                      height of 2 m)
  Abrasion resistance, EN ISO 5470/1 (Load 1000 g abrading wheel             Weight loss < 3000 mg
  H22/1000 cycles)
Class I : 3 days contact, reduction shore 50 % class II : 28 days contact, reduction shore 50 % Class Reduction Shore
 Testing liquid 11 (20% sodium hydroxide) :Inorganic bases and their salts undergoing acid hy-drolysis
 in aqueous solution (pH< 8) excepting ammonium solutions and oxidizing salt solutions (e.g               II          0%
 hypochlorite)
 Testing liquid 12 (20% sodium chloride) : Non-oxidising inorganic salt solutions with pH= 6 - 8          II          0%
I. Water: Potable.
2.3 MIXES
PART 3 -EXECUTION
3.1 EXAMINATION
       A. Examine substrates, areas, and conditions, with Applicator present, for suitable conditions
          where waterproofing is to be applied.
B. Proceed with application only after unsatisfactory conditions have been corrected.
       C. Notify Engineer in writing of active leaks or defects that would affect system
          performance.
3.2 PREPARATION
       B. Protect other work from damage caused by cleaning, preparation, and application of
          waterproofing. Provide temporary enclosure to confine spraying operation and to ensure
          adequate ambient temperatures and ventilation conditions for application.
       C. Do not allow waterproofing, patching, and plugging materials to enter reveals or annular
          spaces intended for resilient sealants or gaskets, such as joint spaces between pipes and
          pipe sleeves.
                1) At holes and cracks 1.6 mm wide or larger in substrate, remove loosened chips
                   and cut reveal with side’s perpendicular to surface, not tapered, and minimum 25
                   mm deep. Fill reveal with patching compound flush with surface.
                  a) Lightweight Concrete Unit Masonry: Etch withI0 percent muriatic acid solution
                     or abrade surface by wire brushing. Remove acid residue until pH readings of
                     water after rinse are not more than 1.0 pH lower or 2.0 pH higher than pH of
                     water before rinse.
                  b) Medium- and Normal-Weight Concrete Unit Masonry: Sandblast or bush
                     hammer to a depth of 1.6 mm.
3.3 APPLICATION
                1) Saturate surface with water for several hours and maintain damp condition until
                   applying waterproofing. Remove standing water.
                2) Apply waterproofing to surfaces, and extend waterproofing onto adjacent
                   surfaces as follows:
                  a) Coating Thickness: Maximum application thickness of 1.2 mm per coat for total
                     thickness as required for specified water permeability.
                  b) Apply first coat as a slurry with brush or roller, and apply subsequent coats with
                     brush, roller, spray, or trowel.
       C. Curing: Cure waterproofing for not less than five days immediately after application and
          prior to being placed in service.
       D. Curing: Moist-cure waterproofing for not less than three days immediately after
          application has set, followed by air drying prior to being placed in service unless
          otherwise recommended in writing by manufacturer.
       E. Protective Topping: Apply 25-mm thick, protective topping over floor surfaces. Moist-
          cure topping for not less than three days.
3.4 PROTECTION
       A. Protect applied polymer modified cement waterproofing from rapid drying, severe
          weather exposure, and water accumulation. Maintain completed Work in moist condition
          for not less than 7 days by covering with impervious sheeting or as recommended by
          waterproofing manufacturer.
       B. Flood Testing: Flood test each deck area for leaks, according to ASTM D 5957, after
          completing waterproofing but before overlying construction is placed. Install temporary
          containment assemblies, plug or dam drains, and flood with potable water.
EARTH MOVING
PART 1 – GENERAL
    A. All tests listed in this document according to ASTM Standards are also accepted to be
       conducted using equivalent BS/BS EN Standards or Egyptian Code of Practice ECP-203
       (2017).
    B. Drawings and general provisions of the Contract, including Conditions of Contract and
       Division 1 Specification Sections, apply to this Section.
1.2 SUMMARY
    A. Egyptian Construction Specifications forms the basis of the Specification for the WORK. The
       following clauses are to be added and or supplemented to those of Construction
       Specifications (ECP).
    B. Excavate, backfill, compact and grade the site to the elevations shown on the drawings, as
       specified herein and as needed to meet the requirements of the construction shown in the
       Contract Documents, including, but not limited to, the following:
              a.   Construction of foundations
              b.   Reinforced concrete pits and trenches
              c.   Ground bearing slabs
C. Related Sections
In addition to the general conditions of contract, the Contractor shall also refer to the following
specifications:
              a.   Cast-in-place Concrete
              b.   Bored Piles
              c.   Sub-Structure Water Proofing
Employer – the person named as the employer in the Contract Agreement and the legal successors in
title to this person.
Contractor -The person(s) named as the contractor in the Contract Agreement and the l e g a l
successors in title to t h i s person(s). [Includes sub-contractors and consultants (Contractor’s
Representative) appointed by the Contractor to undertake the works]
1.3 REFERENCES
      1) Except where otherwise specified, work shall be in accordance with the Egyptian Standards
         relevant to this specification. The latest editions shall be used, including all current
         amendments and additions.
      2) Any differences between the Contractor requirements and this specification shall be
         submitted to the Employer for his ruling.
1.4 SUBMITTALS
         2) Prior to starting work on the contract the Contractor shall submit for Employer
            approval details of the proposed sources of all materials, and place of manufacture,
            together with full documentary evidence that the materials and manufacture will
            comply with the specification.
         3) Further submissions shall be made for any change of material quality or source and the
            Employer approval obtained before the new materials or place of manufacture are used.
         1) Material shall be obtained from suppliers operating quality systems accordance with an
            in-house system approved by the Employer.
PART 2 – PRODUCTS
2.1 GENERAL
              All materials, suppliers and sources must be approved in writing by the Employer
              prior to their use in the works. Prior to approval being given all or any of the
              following must be complied with, as required by the Employer:
            a) Provision of a material to site and subsequent testing of the sample for compliance with
               the Specification and standards. Refer “testing requirements” section contained in this
               specification.
            b) Site inspection at up to three locations where the material has been used over the previous
               5 years.
            c) Provision of test data for material produced at the supplier’s source over the previous 6
Material which is unsuitable for use in fill or retention in excavation as part of the formation and for
re-use after excavation and is as described below:
a. Top soil including materials from swamps, marshes, bogs & perishables.
e. . Soil of liquid limit > 40% and plasticity index > 11%
f. Material which is not well graded and with uniformity coefficient <3
g. Material having hazardous and /or unacceptable chemical and/or physical properties.
i. Sabkha soil
         j.     Material containing more than 5% of water soluble salts by weight of dry soil
                (individually, water soluble chloride exceeding 1% or water soluble sulphate exceeding
                1.5%) as determined by BS 1377 part 3
k. Any other material which the Engineer may deem to be unsuitable for earthworks
        1. Material shall comply with the requirements of structural fill where it supports the works
           above, and non-structural fill elsewhere.
        2. Any fill material used within 1.0 meters of concrete structures or cement- bound
           materials shall not have a water-soluble sulphate content exceeding
        A. Material shall be granular crushed rock with maximum size 50 mm unless otherwise
           specified by the Employer.
B. Aggregate crushing value shall not exceed 30% in accordance with ECP
        D. Material on wet sieving, in accordance with ECP, shall comply with the requirements
           shown in Table 1 below or as approved by Employer
                                                % Passing
        Sieve                   Class A                   Class B                          Class C
               63                 100                          0                        0
               50              90 – 10 0                    100                         0
               37.5             60 – 9 0                 70 – 100                       0
               25               42 – 77                   55 – 85                    100
               20               35 – 70                   50 – 80                       90 – 100
               10               25 – 60                   40 – 70                          50 – 85
                 5              15 – 40                   30 – 60                          35 – 65
               2.36             10 – 26                   20 – 50                          25 – 50
              0.425              5 – 15                   10 – 30                          15 – 30
              0.075              2–9                      5 – 15                    5 – 15
              Rock fill shall consist of hard durable inert natural material of suitable size for
              deposition and compaction. The maximum size of such materials shall not exceed two-
              thirds of the thickness of the compacted layer and shall be graded so that when the layer
              compacted is uniformly dense and the surface is closed.
2.7 FILL MATERIAL FOR DEPOSITION BELOW STANDING WATER (IF NEEDED)
        1. In circumstances where backfill has to be deposited below standing water, only rock, as
           specified in Section 6, Road works, is to be used unless otherwise instructed by
           Employer.
        2. Also if agreed by the Employer, fill material for deposition below standing water shall be
           granular material with a 10% fines value of not less than 50 KN as tested in accordance
           with BS 812: part 103 (method 8), except that samples shall be soaked in water at room
           temperature for 48 hours prior to testing without having been previously oven-dried. The
           material shall have a maximum particle size not greater than 400 mm and shall have a
           particle distribution size in the smaller fractions as shown in Table 2 below.
              6.3 mm                                                    0-100
              3.35 mm                                                   0-35
              2.36 mm                                                   0-10
              600 micron                                                 0-2
Table 2: Particle Size Distribution for material for Deposition below Standing Water
        1. Fill material for deposition on soft ground shall be granular material with a 10% fines
           value of not less than 50 KN as tested in accordance with ECP, except that samples shall
           be soaked in water at room temperature for 48 hours prior to testing without having been
           previously oven- dried.
        2. The material shall consist of granular material graded from 400 mm to 150 mm, except
           that not more than 10% shall be less than 150 mm size. For treatment of small areas of
           soft ground, the Employer may require the size range to be reduced to such sizes as the
           Employer may direct.
        3. Soft spots are to be removed and backfilled with suitable excavation surplus material or
           any other suitable soil as permitted by the Employer.
        1. Solid rock shall mean rock found in ledges or masses, greater than 0.3 m3 in volume in
           its original position, which has to be loosened either by blasting, by hydraulic breaker, by
           pneumatic tools or, if excavated by hand, by wedges and sledge hammers.
        2. Descriptions of soils and rocks shall comply with the requirements of ECP when included
           or otherwise agreed with the Employer. The criteria which are to be used to
           distinguish between the various types of soil, soft rock and hard rock will be agreed
           between the Contractor and the Employer on Site.
1. Material for Improved Subgrade layer shall meet the following requirements:
              Subgrade: the compacted existing ground or fill for 500 mm beneath formation Which if
              falls under clause 2.3 in this specs, shall be improved as following:
         a. Replace with suitable surplus excavation soil or any other suitable soil as permitted by
                 the Employer.
         b.      The existing natural ground shall then be scarified in place to a minimum depth of
                 150 mm for the full width of the embankment except where the material is classified
         c.       Soaked CBR value at 95% maximum dry density (soaked) not less than 30% when
                  tested .
        2. A chemical analysis of the proposed material shall be carried out to satisfy the following
           requirements:
        3. When approved by the Employer a sulphate content greater than that specified in
           section 2 may be acceptable when the carbonate content is in the region of 40- 50% .
        4. The moisture content of the compacted material shall not vary by more than ±3% of the
           optimum moisture content when tested .
Geotextile fabrics where required below fill on soft ground, on fill below standing water and
where required by the Employer shall meet the following minimum requirements:
PART 3 – EXECUTION
3.1 GENERAL
         A.       The works are to be set out from primary datum level(s) and setting-out point(s)
                  indicated on the drawings or from information provided by the Employer.
         C.      Should the Contractor dispute the original ground levels shown on the Drawings he
                 shall agree these with the Employer before disturbing the original ground.
         A.      Prior to the commencement of work, the Contractor shall submit to the Employer the
                 detailed proposals for methods of construction (including temporary works and
                 construction plant) for all earthworks. The detailed proposals shall include but not be
                 limited to the numbers and types of plant, routings and expected outputs, locations of
                 spoil heaps, installation and removal of Temporary Works, attendance and
                 supervision, protection of existing services and controls to ensure quality assurance
                 and safety.
         A.      The Contractor is to ascertain the position of all existing services within the area of the
                 construction Works.
         B.      All existing services must be maintained and protected during the progress of the
                 Works. The Contractor shall be responsible for any damage caused to the underground
                 services and/or any delays arising from such damage.
3.2 TESTING
1) Testing Laboratory
               A. An on-site testing laboratory shall not be required. The Contractor shall be required
                  to provide the services of an independent testing laboratory approved by the
                  Employer for the purposes of carrying out the testing, all as prescribed in the
                  Specification.
B. Test equipment shall include for carrying out the following tests:
               D. The Contractor shall follow and comply with regular Circulars regarding testing and
                  laboratories, Quality forms, Safety forms etc. Which are issued from the Employer
                  or relevant authorities.
               E. The Contractor shall only engage independent laboratories from the latest approved
                  laboratory list issued by the Employer or relevant authorities for Quality Control
                  purposes.
               F. The Contractor shall provide all necessary containers, plant, transport and labor for
                  obtaining and handling of samples.
               G. The Contractor shall provide all necessary staff for testing including a suitably
                  qualified laboratory supervisor who will be subject to the Employer written
                  approval.
3.3 WORKMANSHIP
         1.    In the setting-out and construction of excavations and filled areas the Contractor
               shall allow for settlement, heave and lateral spreading of embankments whether caused
               by consolidation of fill, settlement of foundation, heave in excavations or change in
               volume of materials after excavation or any other cause.
2. The tolerance limits for the permanent finished earthworks shall be as follows:
         3.    The moisture content and acceptability of material arising within the Site shall be
               determined in its unexcavated state.
         4.    The Contractor shall employ plant and methods of working which maintain acceptable
               material in a suitable condition for use and or reuse in the Works.
         5.    Should for any reason whatsoever the ground becomes unstable the Contractor
               shall inform the Employer immediately and shall submit for the Employer approval proposals for
               dealing with the unstable ground. If necessary the Contractor shall proceed with the work
6. Adverse Conditions
              A. The Contractor shall not carry out any excavation or placing of fill materials
                 when conditions are such that the Works or other Works would be adversely affected.
                 Once any operation has been stopped, owing to adverse weather or other
                 conditions, it shall not be re-started without the approval of the Employer.
              B. The Contractor shall plan his operations so as to take account of the season and to
                 take full advantage of favorable climatic conditions. Additionally, the Contractor's
                 temporary drainage of the Works shall take these factors into account.
              C. The Contractor shall seek the Employer approval to any changes in his method of
                 working that are necessary to ensure full compliance with this requirement before the
                 changes are implemented
              A. The Contractor shall make his own arrangements for stockpiles and for provision of
                 storage areas for soil but shall submit proposals for these, and other temporary
                 earthworks, for the approval of the Employer.
              B. Such Works shall be stable under all conditions and shall not impede the natural
                 drainage of the area in which they may be situated. The Contractor shall satisfy the
                 Employer by testing and calculation as appropriate as to their stability.
              C. Fill materials shall not be stockpiled in the vicinity of excavations nor shall they be
                 stockpiled on embankments.
              A. The Contractor shall arrange for the rapid disposal of water, from whatever
                 source, from all earthworks, excavations, stockpiles or completed formations of all
                 types during construction and, where practicable, the water shall be discharged into
                 the permanent drainage system. Adequate means for trapping silt, oil or other
                 deleterious matter shall be provided on temporary systems discharging into permanent
                 drainage systems. In depressions, pumping shall be used as necessary to keep them
                 free of water.
              C. All temporary water courses, ditches, drains etc. shall be filled in or removed and the
                 ground reinstated prior to completion of the Works. Buried pipes may, subject to the
                 approval of the Employer, be left in position but in that case shall be completely filled
                 with grout.
              B. The Contractor shall supply the Employer with a copy of all such survey records
                 (including photographs). All such records shall be adequately referenced as to
                 location, direction of view, date, etc.
              C. Before commencing work alongside adjoining property the Contractor shall submit to
                 the Employer his detailed proposals for carrying out the work including diagrams of
                 his proposed methods of support together with his calculations and estimates of
                 vertical and lateral movements, and his means for keeping the Works free of water.
              B. The Contractor shall submit his proposals to the Employer for his approval
                 before starting such operations. The proposals shall include the Contractor's
                 assessment of likely settlement together with calculations and conditions assumed.
              C. The Contractor shall take all necessary precautions to prevent any adjacent ground
                 from being adversely affected by loss of fines through any de-watering process.
         11. Protection of all earthworks covered by this Specification shall be provided by the
             Contractor, by methods approved by the Employer, until the Works are certified
             complete by the Employer.
         12. The Contractor shall notify the Employer immediately of any landslips, and shall then
             deal with these without delay and as the Employer may direct. If any slip or fall
             disturbs or weakens any foundation, support or potential support the Contractor shall
              A. Contaminated and waste materials shall be removed from site in accordance with the
                 requirements of the Local Authorities. The Contractor shall satisfy the Employer
                 that all waste materials are taken only to a disposal site/treatment plant which is
                 licensed to accept waste of that nature.
              C. All unacceptable material shall, unless the Employer permits or instructs otherwise,
                 be removed from the Site and run to either tips provided by the Contractor or
                 otherwise disposed of by the Contractor. Public roads may only be used for haulage if
                 arrangements acceptable to the Employer and the Approving Authority are agreed
                 beforehand.
         15. Open ditches, culverts and outfalls for drainage purposes shall be maintained by the
             Contractor. New ditches, culverts and outfalls shall be constructed before cuttings are
             opened or embankments or filling begun. The sides shall be dressed fair throughout and
             the bottoms accurately graded so as to carry off water to the outlet.
              A. Where the Contractors proposals include running over the location of the permanent
                 Works he shall provide, above the formation levels shown on the Drawings, a suitable
                 running layer of 300 mm minimum depth above formation levels for the movement
                 and operation of plant, materials and labor associated with his Works so that
                 material at formation and below is not adversely affected.
              B. Prior to commencement of work, the Contractor shall submit his proposals to the
                 Employer for his approval for haul roads.
              C. During the execution of the Works, the Contractor shall maintain the running layer to
                 the satisfaction of the Employer.
              D. The running layer shall be removed in a manner which does not adversely
                 disturb the previous construction or interfere with subsequent operations for the
                 Permanent Works.
3.4 EXCAVATION
3.4.1 General
              A. The Contractor shall record the strata through which he excavates together with their
                 locations and depths. He shall provide a copy of the records to the Employer as
                 the work proceeds. Where excavation produces a combination of acceptable and
                 unacceptable materials, the Contractor shall carry out the excavation in such a
                 manner that acceptable materials are excavated separately for use in the
                 Works without contamination by unacceptable materials which shall be removed
                 off site. Where excavation produces a combination of acceptable materials with
                 different characteristics, these materials shall be excavated and stored separately.
              B. Any old foundations, tree roots, buried refuse or obstructions encountered during
                 the course of excavation shall be taken out and removed from the Site excluding
                 combustible materials which shall either, with the Employer and local authority
                 approval, be burnt under controlled conditions or removed from the Site. Care shall be
                 taken to ensure that roots to existing trees to be retained are not disturbed. Should
                 unforeseen services be encountered the Employer shall be notified immediately
                 and no action taken pending his instructions.
              C. When rock is encountered, the Employer shall be notified immediately and it shall
                 then be removed only to the net extent to permit the Works to be properly executed.
                 The Contractor shall free the faces and bottoms of the excavations of loose material
                 which can be moved with a crowbar. For excavations in which concrete is to be
                 placed, the resulting cavities and any large fissures shall be filled with concrete. For
                 trenches filling shall be as shown on the Drawings and as directed by the Employer.
                 The quantities of material shall be measured and agreed with the Employer as work
                 proceeds and prior to removal. Rock projections, boulders or other hard spots in
                 excavations shall be removed to a depth not less than 100 mm below formation
                 level and as directed by the Employer and a new formation prepared, and the
                 excavation filled as specified. The quantities of these materials shall be measured
                 and agreed with the Employer as work proceeds and prior to removal.
              D. The Contractor shall carry out his operations in such a manner as to ensure that
                 damage to or deterioration of the formation or final surface of the excavation and
                 the ground below is not caused. The natural moisture content of the ground below the
              G. Excavations shall be kept free from noxious or explosive gases, whether generated in
                 strata by blasting or otherwise. The Contractor shall satisfy himself that each
                 excavation is safe before allowing entry of personnel. The Contractor shall carry out
                 tests for the presence of noxious or explosive gases, or to detect a lack of oxygen
                 before allowing personnel to enter any confined space or excavation, and he shall then
                 monitor conditions continuously during the period of work. He shall take such
                 measures (e.g. Ventilation, the provision of breathing apparatus, and back-up
                 personnel and equipment) as will avoid any risk of injury to personnel. The Employer
                 may order the withdrawal of personnel if dissatisfied with the Contractor's
                 arrangements.
              A. Cuttings shall be excavated to the lines and levels shown on the Drawings or
                 as directed by the Employer.
              B. Toes to the slopes of cuttings shall only be undercut where Permanent Works
                 necessitate excavation(s). Such excavations shall be restricted in extent and shall
                 remain open only for the minimum period necessary. The Contractor shall submit to
                 the Employer for approval a method statement giving his procedure for carrying out
                 such work.
              3.4.3 Dressing of Formation and Side Slopes of Rock Encountered in Cuttings (IF
                    NEEDED)
              A. Where rock is encountered in cuttings, the side slopes shall be cut to the lines, levels
                 and slopes shown on the Drawings or as directed by the Employer.
                  Shall have a maximum size not greater than one third the thickness to be compacted
                  and not exceeding one third the maximum allowable compacted layer thickness,
                  whichever is the less. The formation so constructed shall be formed to lines and
                  levels shown on the Drawings.
              C. The sloping sides of all permanent cuttings shall be scaled of all rock fragments
                 which are loose or can be prized with a crowbar.
              B. The sides of excavations for structures such as basements and foundations shall
                 be adequately supported at all times and, except where required as shown on the
                 Drawings or allowed by the Employer, shall not be battered. The Contractor shall
                 submit to the Employer proposals for his Temporary Works to ensure stability of the
                 excavation, temporary and Permanent Works, and these proposals shall include
                 detailed drawings and calculations, methods of installation and withdrawal and his
                 means of keeping the Works free of water.
              D. For excavation in soils such as over consolidated clays which are likely to heave and
                 swell, the Contractor shall submit to the Employer for his prior approval a detailed
                 method statement giving his procedure and proposed arrangements for minimizing
                 the effects of heave and swelling.
              Shall be made good with a material approved by the Employer deposited and compacted as
              specified or, if instructed by the Employe.
3.4.6 Proving Formation in Excavation and Dealing with Soft or Unsound Spots
              B. Any soft or unsound spots as may be found, by inspection, testing, proof rolling or
                 compaction or otherwise as may be specified, in the formation or under areas to be
                 filled, shall be excavated as required by the Specification and instructed by the
                 Employer. The resultant excavation shall be backfilled with approved material
                 deposited and compacted as specified for the forming of filled areas or, if instructed
                 by the Employer.
              D. An alternative method treatment using approved rock fill material may be permitted
                 or required by the Employer. If so it shall be placed directly on the naturally occurring
                 soft soil and compacted to such total depth that on completion of compaction
                 negligible deflection of the surface occurs by the passage of vehicles hauling in the
                 rock. The rock fill material shall be deposited and compacted as specified above.
3.5 FILLING
              B. Haulage of material to areas of filling shall proceed only when sufficient spreading
                 and compaction plant is operating at the place of deposition.
              D. All earthworks placed in or below embankments and other areas of fill such as
                 backfill to trenches, pits and structures such as retaining walls and basements, or
                 elsewhere in the Works, shall be deposited and compacted, as soon as practicable
                 after excavation, in layers of thickness appropriate to the compaction plant used, but
                 not exceeding 250 mm compacted thickness, unless otherwise permitted in the
                 appropriate clause or otherwise specified, or otherwise agreed by the Employer.
              E. If there is a deficit in the 'cut-fill' balance of acceptable materials from excavations the
                 deficiency shall be made good by importation of acceptable material. In this case the
                 Contractor shall propose a source or sources of such material for the Employer
                 approval (refer to Part 2 - Products).
              G. Where non-cohesive material, on excavation, is too wet or too dry for satisfactory
                 compaction the Contractor shall raise or lower the moisture content until satisfactory
                 compaction is achieved and approved by the Employer.
              H. Where for any reason the moisture content of acceptable material changes to a
                 value unacceptable for compaction, the Contractor shall raise or lower the
                 moisture content until satisfactory compaction is achieved and approved by the
                 Employer.
              I.   Areas of general fill and embankments shall be built up evenly over the full width,
                   and with side slopes not greater at any time than shown on the Drawings or directed
                   by the Employer. Areas of fill shall be kept free of water in compliance with the
                   “Workmanship” section of this specification. During construction of areas of general
                   fill and embankments the Contractor shall control and direct construction traffic
                   uniformly over their full width. Damage to compacted layers by constructional traffic
                   shall be made good by the Contractor.
              L. Material used for haul roads or running layers shall not be re-used without the
                 permission of the Employer.
              M. The layers of fill shall be graded, levelled and mixed, with water added as necessary,
                 to ensure homogeneous conditions throughout the full depth of the uncompacted
                 layer.
              A. The first 300 mm of main backfill shall be placed in layers not exceeding 100 mm
                 un-compacted thickness with each layer being thoroughly compacted before placing
                 the next layer. Only light compaction equipment subject to the approval of
                 the Employer shall be used. Otherwise mechanical rammers, rollers and the like
                 shall not be used to compact the fill until there is a minimum 600 mm of fill above
                 the top of the pipes.
              B. The main backfill shall then be built up in layers not exceeding 150 mm in compacted
                 thickness. Compaction shall be according to clause 3.6.
              C. As filling proceeds all trenches or pit supports shall be removed in a safe manner and
                 in accordance with the approved method of working.
              D. Particularly under roads or existing works such as pipes, the fill shall be compacted to
                 a minimum relative compaction of 95% or bring it as nearly as possible to the
                 same condition of density and moisture content as that of the undisturbed soil in the
                 trench or pit sides provided the fill is of a similar nature; otherwise a selected material
                 approved by the Employer shall be used.
              E. Unless otherwise specified, filling around manholes shall be as for trenches and shall
                 be carried out as part of the same operation. The fill shall be raised equally all-round
                 the manhole shaft.
              F. Any settlement that occurs shall be made good by the Contractor with the surface
                 construction also being maintained in an acceptable condition.
              B. Fill shall be placed and compacted in accordance with the “Filling” and “Compaction
                 of Earthworks” sections of this specification excepting as otherwise specified in this
                 sub-clause.
              E. Fill within this zone shall not differ in level during construction from the level of the
                 remainder of the adjoining fill to the structure by more than 250mm.
              B. Before filling and compaction works are commenced, and further as may be necessary
                 during the progress of the Works, the Contractor should have carried out
                 classification tests, including natural moisture content and compaction tests in
                 accordance with ECP, as appropriate, on the main types of materials originating
                 from the Site and any proposed to be imported to determine acceptability and
                 optimum compaction requirements.
              C. For materials which are non-plastic and have not more than 10 per cent passing 75
                 microns .
              D. The Employer shall be advised of when the tests are to be undertaken. Two copies of
                 all test results shall be forwarded to him for his approval prior to the commencement
                 of work and thereafter as the occasion arises (refer to the “Testing” section of this
                 specification).
              E. The Contractor shall submit to the Employer his proposals giving the maximum
                 compacted depth of each layer, the type(s) of plant and the number of passes for
                 compaction of each type of material. The Contractor shall demonstrate to the
                 Employer satisfaction that he can achieve the requirements regarding compaction
                 before the Works commence by carrying out compaction trials.
              F. Where compaction is required the Contractor shall submit his method of compaction
                 for each material to the Employer for approval.
              G. Earth-moving plant will not be accepted as compaction equipment under this clause
                 nor shall the use of a lighter category of plant to provide any preliminary compaction
                 to assist the use of heavier plant be taken into account in assessing the amount of
                 compaction required for any layer.
              I.   The frequency of testing the compacted fill shall be sufficient in relation to the
                   volume of particular works, the rate of placing and its purpose, and shall be as
                   agreed with the Employer in accordance with the “Testing” section of this
                   specification.
              J. In case the method of compaction is specified by the Employer the Contractor will
                 be required to carry out tests in accordance with the above and when instructed
                 by the Employer or carry out comparative field density tests determined
                 Specifications which shall be calibrated on material similar to that which is being
                 tested for field density.
              L. Work shall be continued until a state of compaction is reached throughout filled areas,
                 including slopes of embankments, such that dry density tests from the compacted
                 material has a dry density not less than that stated below.
              M. For non-cohesive materials, within the limits of the “Structural Fill’ section of
                 this Specification and for materials with a plasticity index not 10%, the state of
                 compaction shall be such that the compacted material has a dry density not less than
                 95% of maximum dry density and a moisture content within the range of ±3%
                 optimum percentage as determined in ECP.
              N. For intermediate materials the state of compaction shall be such that the compacted
                 material has a dry density not less than the specified percentage of maximum dry
                 density and a moisture content within the specified range related to optimum
                 percentage.
              O. Where fill materials have particle sizes exceeding the maximum size allowable in the
                 relevant Test. the procedures for comparing test values with field values shall be
                 agreed with the Employer prior to such fill materials being used.
              A. Before filling, spreading and compacting operations are commenced; materials shall
                 be classified by the Contractor for acceptability in accordance with sub- clauses the
                 “structural fill” and “Unsuitable Materials” section of this specification, and agreed
                 by the Employer.
              B. Fill shall be spread in layers not exceeding 300 mm in thickness unless otherwise
                 specified by the Employer. Spreading shall not be done when the ground or the fill is
                 excessively wet or otherwise in a condition detrimental to the work nor shall it be
                 done during heavy rain.
              B. Fill material in areas of benching shall be carefully and compacted to ensure that no
                 voids occur at the vertical steps of the benching.
              C. Placing and compacting of fill material on a lower bench shall continue to a level one
                 compacted layer thickness above an adjacent higher bench before material is
                 placed upon the latter bench.
              D. Four additional passes of the approved compaction plant shall be made over a
                 width of 2m each side of each vertical face immediately following the compaction of
                 the first layer of material on each bench.
              B. Material used in rock fill shall, except for any specified cover to slopes or near bottom
                 of capping layer or formation level, be of such size that it can be deposited in
                 horizontal layers each not exceeding 800 mm loose depth and extending over the
                 full width of the area or of the embankment. Material shall be spread and
                 levelled by a crawler tractor having a mass of not less than 15 tons and compacted.
                 The top surface and side slopes of embankments as formed shall be thoroughly
                 blinded with approved fine graded material to seal the surface and give a compacted
                 stable surface. Such fine graded material may on side slopes and verges be topsoil
                 except where the final surface may be such as paving or otherwise shown on the
                 Drawings.
              C. Compaction shall be carried out by a vibratory roller with the minimum requirements
                 of ECP
              D. Where rock is used as general fill and has the properties of rock fill it shall be spread
                 and compacted as for rock fill.
              A. The compacted density of the fill shall be equal to or greater than 95% of the
                 maximum dry density as determined. Samples for soil classification, moisture and
                 CBR tests shall be taken prior to incorporating the material in the works. For every
                 completed layer of material, 1 field density test point shall be performed on an area of
                 approximately 500m2 of prepared area.
              A. Preparation and surface treatment of the subgrade shall be carried out only after
                 completion of any subgrade drainage or dewatering and, unless otherwise agreed by
                 the Employer, immediately prior to blinding with concrete or the construction of
                 the Works.
                  1) The surface shall, after reinstatement of any soft areas, be well cleaned and
                     free from mud and slurry.
                  2) The surface shall be compacted by a minimum of 6 passes of a smooth-drum
                     vibrating roller having a minimum dead weight of 10 tons.
                  3) The surface shall be regulated and trimmed within a tolerance of ±20 mm.
                  4) Where the surface is too high it shall be trimmed and re-compacted in
                     accordance with this Specification. If the surface is too low the deficiency shall
                     be corrected by the addition of suitable material of the same classification and
                     moisture content or other approved material laid and compacted to Specification.
3.7 REINSTATEMENT
3.7.1 General
              1) These clauses cover the reinstatement of surfaces which existed before the Works
                 have commenced, which have been disturbed in the course of the Works and which
                 are not finished as part of other works.
              A. Those parts of the site and any areas outside the site disturbed by excavation for
                 service trenches shall be reinstated to the same standard as existed before the works
                 commenced unless otherwise shown on the drawings or instructed by the Employer.
              B. Paved and hard surfaces shall be temporarily reinstated by the Contractor immediately
                 following backfilling and before reopening the disturbed areas to traffic. The
                 materials used shall be appropriate to the adjacent construction. Verges shall be
                 temporarily reinstated to match nearly as possible the adjacent areas.
              C. Unless shown on the drawings or instructed otherwise by the Employer the surfaces
                 over disturbed areas shall be permanently reinstated by the Contractor, within 2
                 months of the temporary reinstatement, in materials and construction similar to the
                 adjoining surfaces and in a manner specified by the Employer to obtain proper
                 integration between these adjoining surfaces. To ensure satisfactory integration
                 between the new and existing construction each layer is to be stepped back beyond
                 the edges of excavation and underlying layers.
              D. Throughout the duration of the Works, the Contractor shall ensure that all vehicle
                 wheels are thoroughly cleaned prior to leaving the site approaches and re-entering
                 public roads. The Contractor shall ensure that points of entry from and exit to public
                 roads are kept clean.