Mechanical Completion:
Valves
M-31A Page 1 of 1
*50000037687* *50000037687*
Unique ID: 30-XY-8102B-M-31A_V1 Item/Tag No. 30-XY-8102B
Project Name: KU-TWK-026 CS Migration System No. 30-CSM-01
Tag Name: 30-XY-8102B
Sub-System No. CSM-07 Job Card: ~
Primary Drawing Ref: Date Printed: 30-Mar-18
Secondary Drawing Ref: Location:
Initial / Punch list
No. Description of Check / Action to be made Results
Signature item No.
Confirm that Valve nameplate complies with Data Sheet and nameplate
1
securely attached
2 Confirm valve location & orientation is correct to detail drawings
Check and confirm Installation and bolting arrangement is in accordance with
3
required specification drawing and manufacturers instructions.
Check access for operation is acceptable and there is sufficient clearance for
4
maintenance removal etc.
Confirm that inlet and outlet piping to valve mating flanges are in parallel and
5 angular alignment with the correct gaskets installed. Complete ITR M-27A.
Ensure that on tightening bolts no imposed stress is applied to valve.
Check all PSVs installed, undamaged and seals intact – complete ITR form
6
M-28A for PSVs
Confirm that valve lubrication is completed to the required specification
7
(Record Type / details of valve lubricant in Remarks below)
Ensure that handwheel, lever or geared actuator is fitted and that valve can be
8
operated without undue strain across complete operating range.
Confirm that valve actuator is installed satisfactory and that any interlock
9 mechanisms associated are fitted correctly.
Ensure interlock keys are safely stored.
10 Check Earth bonding Strap if required is installed.
11 Hand operated valves are to be stroked (open/closed) to confirm that valve is
not tight or seized.
Remarks / Comments :
ITR Input to Data
Completed By Approved By Accepted By
Base
Company
Signature
Print Name
Date of signing