Gantt Chart_x000D_
Project Time line for Bafikot-Khungri 132kV TLP
DURATION in
S.N. TASK NAME SUB TASK NAME STATUS ASSIGNED TO START DATE END DATE COMMENTS
days
For Transmission Line
1 Detail Survey of the transmission line Started Forest Department 4/14/2025 5/29/2025 45 Almost about to complted soon.
2 Soil investigation Not Started Contractor 10/11/2025 3/10/2026 150
3 Land Acqusition of Tower Pad Not Started 11/10/2025 3/10/2026 120
ROW Compensation works and Tree
4 Not Started 3/20/2026 7/18/2026 120
Cutting
5 Detail Design of the Tower Started 6/3/2025 11/30/2025 180
6 Tower Foundation Works Not Started 3/10/2026 11/5/2026 240
7 Stringing Not Started 11/5/2026 1/4/2027 60
8 Testing and Commissionning Not Started 1/4/2027 1/19/2027 15