Fidic 2019 - Emerald Book
Fidic 2019 - Emerald Book
ITA was founded in 1974 by the initiative of nineteen Nations. ITA is the leading international
organization promoting the use of tunnels and underground space through knowledge
sharing and application of technology.
Independent nations can become ITA Member Nations through their national organizations.
Corporations and individuals who fulfill the statutory conditions can become Affiliate
Members. Today (2019), ITA counts 75 Member Nations and 300 corporate or individual
Affiliate Members from all parts of the globe.
I TA is governed by its General Assembly, which is regularly hosted by the annual World
Tunnel Congress. ITA’s goals include:
- to encourage new uses of underground space for the benefit of the public, environment
and sustainable development;
- to encourage studies of underground alternatives to surface construction, not only
considering construction costs but also indirect life-cycle costs and savings as well as
social and environmental advantages;
- to stimulate the development of guidelines for a positive public strategy to take
advantage of subsurface potential;
- to encourage the development of better and cheaper methods for planning,
geo-investigation, design, construction, operation, maintenance and safety of
underground structures by using improved methods such as new technical
developments and risk management principles;
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
ITA, to reach its objectives, has set up Working Groups to study and report on specific
topics. In 2019, 14 Working Groups are active, amongst which Working Group 3
“Contractual Practices”. ITA also has the following 4 committees:
I TA has a Young Members Group (ITAym), open to professionals younger than 35 years,
and students.
I TA information on tunnelling, case histories, the ITA awards, other activities and
publications can be found here: www.ita-aites.org.
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
GENERAL CONDITIONS
PREPARATION OF
TENDER DOCUMENTS
AND ANNEXES: TABLE
OF CONTENTS OF
THE GEOTECHNICAL
BASELINE REPORT,
EXAMPLE FORMS
OF SCHEDULE OF
BASELINES, COMPLETION
SCHEDULE, SCHEDULE
OF CONTRACTOR’S KEY
EQUIPMENT
FORMS OF LETTER OF
TENDER, LETTER OF
ACCEPTANCE, CONTRACT
AGREEMENT AND
DISPUTE ADJUDICATION/
AVOIDANCE AGREEMENT
In collaboration with
Users rely on the contents of FIDIC and ITA publications, especially contracts and agreements,
for important business transactions. The use of authentic publications is therefore essential for
safeguarding their interests. FIDIC and ITA discourage modification of their publications, and
only in exceptional circumstances will they authorise modification, reproduction or incorporation
elsewhere. Permission to quote from, incorporate, reproduce or copy all or part of this
publication should be addressed to the FIDIC Secretariat, which will decide upon appropriate
terms in consultation with ITA. To request such permission, please contact FIDIC, P.O. Box 311,
CH-1215 Geneva 15, Switzerland; e-mail: fidic@fidic.org.
A license to prepare a modified or adapted publication will be agreed to under certain conditions.
Specifically the modified or adapted publication must be for internal purposes, and not be
published or distributed commercially.
In the case of FIDIC and ITA contracts and agreements, FIDIC and ITA aim to provide balanced
and equitable conditions of contract by ensuring the integrity of their publications. A purchaser
or authorised user of a FIDIC/ITA contract or agreement is thus granted the right to:
- make a single copy of the purchased document, for personal and private use;
- incorporate in other documents (or electronic files) either the original printed document (or
electronic file) or pages printed from an electronic file supplied by FIDIC for this purpose;
- draw up and distribute internally and/or among partners clearly identified Particular
Conditions or their equivalent using text provided in the FIDIC/ITA publication specifically for
this purpose;
- reproduce, complete and distribute internally and/or among partners any forms, in both
printed and electronic formats, provided for completion by the purchaser or user.
DISCLAIMER
While FIDIC and ITA aim to ensure that this publication represents the best in business practice,
they do not accept or assume any liability or responsibility for any events or the consequences
thereof that derive from the use of this publication. The FIDIC/ITA publication is provided “as is”,
without warranty of any kind, either express or implied, including, without limitation, warranties of
merchantability, fitness for a particular purpose and non-infringement. The FIDIC/ITA publication
is not exhaustive and is only intended to provide general guidance. This should not be relied upon
in a specific situation or issue. Expert legal advice should be obtained whenever appropriate,
and particularly before entering into or terminating a contract.
Acknowledgements
Notes
General Conditions
Contents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . i
Clauses 1 to 21. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
Appendix: General Conditions of Dispute Avoidance/Adjudication
Agreement. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 110
Annex: DAAB Procedural Rules. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 126
Index of Sub-Clauses. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 133
Contents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
Introductory Guidance Notes. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
Particular Conditions Part A – Contract Data . . . . . . . . . . . . . . . . . . . . . . . 3
Particular Conditions Part B – Special Provisions. . . . . . . . . . . . . . . . . . . . 8
Notes on the Preparation of Special Provisions. . . . . . . . . . . . . . . 13
Clauses . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
Advisory Notes to Users of FIDIC Contracts Where the Project Uses
Building Information Modelling Systems. . . . . . . . . . . . . . . . . . . . . . . . . . 58
Annexes: Example Forms of Securities. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 61
1 General Aspects. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 73
2 Central Principles, Underground Works. . . . . . . . . . . . . . . . . . . . . . . . . 77
3 Pre-Contract Actions by the Employer. . . . . . . . . . . . . . . . . . . . . . . . . . 78
4 Employer’s Tender Documents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 79
Appendix A: The Geotechnical Baseline Report. . . . . . . . . . . . . . . . . . . . 85
Annexes: Example Schedule of Baselines, Example Completion Schedule,
Example Schedule of Contractor’s Key Equipment. . . . . . . . . . . . . . . . . . . . . . . . . 91
Letter of Tender . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I
Letter of Acceptance. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . II
Contract Agreement. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . III
Dispute Avoidance/Adjudication Agreement. . . . . . . . . . . . . . . . . . . . . . . . V
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
FIDIC-ITA Task Group 10, “New Form of Contract for Tunnelling and Underground
Works”:
The preparation was carried out under the general direction of the FIDIC Contracts
Committee:
Poland; Kaj Möller, SWECO, Sweden; Siobhan Fahey, Consulting Engineer, Ireland;
Deryl L. Earsom, USA; Mike Roberts, Mott MacDonald, United Kingdom; Matthias
Neuenschwander, Neuenschwander Consulting Engineers Ltd., Switzerland; Enrico
Vink, FIDIC past Managing Director, Switzerland; Christophe Sisto, FIDIC Design &
Publications Manager, Switzerland; together with liaisons to the FIDIC Board:
Aisha Nadar, Advokatfirman Runeland AB, Sweden; Liu Luobing, Shanghai Investment
Consulting Corporation, People’s Republic of China.
The following ITA and FIDIC Special Advisors provided invaluable and continued support
in the various drafting and revision stages:
ITA President Tarcisio Celestino, University of Sao Paulo, Brasil; ITA Vice Presidents
Jinxiu Yan, China Railway Academy Co. Ltd., People’s Republic of China and Alexandre
Gomes, SMEC, Australia; ITA Executive Council members Arnold Dix, ALARP Consulting
Group, Australia and Randall Essex, Mott MacDonald, USA; ITA Executive Director
Oliver Vion, ITA-AITES, France; FIDIC Legal Reviewer Christopher Seppälä, White &
Case LLP, France; assisted by Dimitar Kondev, White & Case LLP, France.
Drafts were reviewed by many persons and organisations, including those listed
below. Their comments were duly studied by Task Group 10 and, where considered
appropriate, have influenced the wording of the clauses:
Gianni Arrigoni, ENGLAW s.r.l., Italy; Ben Beaumont, Barrister and ADR Specialist,
United Kingdom; Federico Blanc, CMC, Italy; Juan Pablo Buritica, Conconcreto,
Colombia; Hervé Chambon, Vinci Construction Grands Projets, France; Luis Chamy
Haddad, Chile; Elena Chiriotti, INCAS Partners, France; Hervé de Trogoff, Accuracy,
United Kingdom; Gonçalo Diniz Vieira, Lisbon General Drainage Plan, Portugal; Christian
Fredrik Grøner, Statkraft AS, Norway; Eivind Grøv, SINTEF Building and Infrastructure,
Norway; Dakus Gunn, Delta Consulting Group, USA; Ulf Håkansson, Skanska AB,
Acknowledgement of all reviewers above does not mean that such persons or
organisations approve the wording of all clauses.
FIDIC and ITA very much appreciate the time and effort devoted by all the above
persons.
The ultimate decision on the form and content of the document rests with FIDIC and
ITA.
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
This First Edition of the “Conditions of Contract for Underground Works” (Emerald Book) is
published by the Fédération Internationale des Ingénieurs-Conseils (FIDIC) in a joint endeavour
with the International Tunnelling and Underground Space Association (ITA-AITES).
Based on the enquiries on international best practice in contracting of tunnelling and underground
construction works conducted by the ITA-AITES during the last fifteen years and on the
ITA-AITES Report 006 (“The ITA Contractual Framework Checklist for Subsurface Construction
Contracts”, April 2011, ISBN 978-2-9700634-7-9), these General Conditions of Contract have
been specifically drafted by a joint FIDIC – ITA Task Group for use in underground works. Their
use may also be appropriate in other types of works that include a significant geotechnical
uncertainty.
The Second Edition of the Conditions of Contract for Plant and Design-Build, 2017 published
by FIDIC (the Yellow Book 2017), was used as the basis for drafting these General Conditions
of Contract. The Sub-Clauses that are new or different from those of the Yellow Book 2017 are
listed below at the end of these introductory notes.
These Conditions include several new concepts in consideration of the risks that are peculiar to
underground works. In particular, they address the risk related to subsurface physical conditions
which are not possible to assess with sufficient precision in advance of the Contract, and
therefore cannot be assigned entirely to the Contractor.
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
These Conditions reflect the fundamental principle which underlies all FIDIC contracts, namely
balanced risk allocation between the parties to the Contract. The joint FIDIC – ITA Task Group
firmly believes that such balanced risk allocation is paramount to a positive project outcome in
contracts for underground works.
Further, there are two other important features that are not unique to Underground Works, but
which are characteristic of all such Works:
- they require extensive investment in contractor’s equipment;
- underground excavation and lining works are very time-consuming.
It is important that the Employer gives careful consideration to all five of the above features,
both before and during the preparation of the tender documents, because they are critical to
the feasibility of successful completion of the Works and tenderers’ ability to meaningfully price
the Works.
The Geotechnical Baseline Report or GBR is defined as the single contractual source of
risk allocation related to subsurface physical conditions to the Parties. Equally important to the
physical conditions of the ground, the GBR addresses the reaction of the ground to excavation
The Time for Completion of the Works, of a Section or any Milestone may largely depend on
the subsurface physical conditions that are encountered during excavation. As the risk related
to these conditions is allocated to the Employer, Time for Completion should be adjusted
by the variation of these conditions within the limits defined by the GBR, insofar as this variation
affects the critical path of the Works, of a Section or any Milestone. In the case that the amount
of more onerous conditions encountered is higher than described in the GBR, the Time for
Completion should be extended, while in the case that the amount of less onerous conditions
is higher than described in the GBR, the Time for Completion should be reduced. Accordingly,
the Contractor’s Tender shall include production rates for each excavation drive or zone, based
upon the conditions described in the GBR. The estimated quantities of the excavation, ground
support, ancillary measures and lining, as well as the corresponding production rates shall be
included in the Schedule of Baselines (Sub-Clause 8.2.2), and the corresponding sequential
logical links between Milestones shall be included in the Completion Schedule (Sub-Clause
8.2.1).
The cost of the Excavation and Lining Works will also largely depend on the subsurface
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
physical conditions and/or ground reaction(s) to such works. These Conditions provide that the
Excavation and Lining Works are to be measured and paid for using rates and prices
set out in the Bill of Quantities. Under these Conditions it is the Contractor that measures the
as-built quantities which are then agreed or determined by the Engineer. All the other Works (for
example, ancillary surface works) are to be paid on a lump sum basis.
Due to the typically long duration of underground works and to the high cost of investment in
equipment, an important portion of the cost to the Contractor, such as i.e., depreciation of and
interest for equipment, overhead charges etc., is time-related, whilst the remainder of the cost
depends on the volume or quantity of the performed works. Hence, the adjustment of Time
for Completion (if any) due to the difference between the contractually agreed and the
encountered subsurface physical conditions should also lead to an adjustment of the
Contractor’s remuneration for time-related charges. The Bill of Quantities for Excavation
and Lining Works should therefore distinguish between time-related rate items, quantity-related
rate items and fixed rate items for the performance of the Works (Sub-Clauses 13.8.2 and 13.8.3).
This publication includes comprehensive guidance for Employers in preparing tender documents
for projects using these Conditions – see the section entitled Guidance for the Preparation
of Tender Documents below. The quality of the tender documents prepared by the Employer
has a strong influence on the quality of the Contract and on the success of the Project. The
tendering of Underground Works requires a high degree of preparation of the Employer’s
reference design, and therefore FIDIC and ITA strongly recommend that the Employer engages
a team with sufficient experience in the design, procurement and management of underground
works, as well as providing the team sufficient time for careful and thorough preparation of the
tender documents.
This publication continues FIDIC’s fundamental principles of balanced risk sharing, while seeking
to build on the substantial experience gained from the use of the FIDIC Yellow Book over the
past 18 years, and from best international practice endorsed by the ITA-AITES.
These Conditions include conditions which are likely to apply to the majority of such contracts.
Essential items of information which are particular to each individual contract are to be included
in the Particular Conditions Part A – Contract Data.
In addition, it is recognized that many Employers, especially governmental agencies, may require
special conditions of contract, or particular procedures, which differ from those included in the
General Conditions. These should be included in Part B – Special Provisions. However, the
amendment of those General Conditions referring in particular to Underground Works is strongly
discouraged, as it may alter the balanced risk allocation that is central to the present Form of
Contract.
It should be noted, that the General Conditions and the Particular Conditions (Part A – Contract
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
Data and Part B – Special Provisions) are all part of the Conditions of Contract.
This publication begins with a series of comprehensive flow charts which typically show, in
visual form, the sequences of activities which characterize the FIDIC Underground Works form
of contract. The charts are illustrative, however, and must not be taken into consideration in the
interpretation of the Conditions of Contract.
This publication also includes a number of sample forms to help both Parties to develop a
common understanding of what is required by the contract and/or by third parties such as
providers of securities and guarantees.
Drafters of contract documents are reminded that the General Conditions of all FIDIC contracts
are protected by copyright and trademark and may not be changed without specific written
consent, usually in the form of a licence to amend, from FIDIC. If drafters wish to amend the
provisions found in the General Conditions, the place for doing this is in the Particular Conditions
Part B – Special Provisions, as mentioned above, and not by making changes in the General
Conditions as published.
FIDIC and ITA consider the official and authentic texts to be the versions in the English language.
1. The Time for Completion is to be stated (in the Contract Data) as a number of days, to which is added any
extensions of time under Sub-Clause 8.5, and subtracted or added, as the case may be, any adjustement
of time under Sub-Clause 13.8.
2. In order to indicate the sequence of events, the diagram below is based upon the example of the Contractor
failing to comply with Sub-Clause 8.2.
3. The Defects Notification Period is to be stated (in the Contract Data) as a number of days, to which is added
any extensions under Sub-Clause 11.3.
4. Depending on the type of Works, Tests after Completion may also be required.
Base Defects
Date 8.2 Time for Notification
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
Completion1 Period3
11 Notifying
Delay of Defects
attributable
to the
Contractor2
4.2.3 Return of
the Performance
Security (subject to
Sub-Clause 11.11)
≤28d ≤56d
14.11.1 Contractor 14.11.2 Contractor submits 14.13 Engineer issues 14.7 Employer
submits draft final Final Statement and the Final Payment makes payment
Statement to the Engineer 14.12 discharge Certificate
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
Contractor 21.1 Parties 21.4.1 A Party refers 21.4.4 A Party 21.6 A Party
receives appoint the the Dispute to the may issue may initiate
the Letter of DAAB DAAB a “Notice of arbitration
Acceptance Dissatisfaction”
Scenario 11
Engineer starts Parties’ agreement Notice of error by
performing duties Sub-Clause 3.7.1 a Party/Engineer
Sub-Clause 3.7 Sub-Clause 3.7.4
Sub-Clause 3.7.3
(a), (b) or (c)
Scenario 22
Engineer starts Parties advise the Engineer’s Notice Notice of
performing duties Engineer: no agreement of determination Dissatisfaction
Sub-Clause 3.7 Sub-Clause 3.7.1(b) Sub-Clause 3.7.2 Sub-Clause 3.7.5
No Notice
of error
Scenario 33
Engineer starts No agreement Engineer’s Notice Engineer’s Notice
performing duties between the Parties of determination of corrected
Sub-Clause 3.7 Sub-Clause 3.7.1(a) Sub-Clause 3.7.2 determination
Sub-Clause 3.7.4
1. Agreement is reached within 42 days, error found in the Engineer’s Notice of agreement and corrected.
2. The Parties’ early advice that agreement cannot be reached and so Engineer’s determination is necessary,
no error in Engineer’s determination.
3. No agreement within 42 days, Engineer determines within 42 days, error found in the Engineer’s determination
and corrected.
General Conditions
PREPARATION OF
TENDER DOCUMENTS
AND ANNEXES: TABLE
OF CONTENTS OF
THE GEOTECHNICAL
BASELINE REPORT,
EXAMPLE FORMS
OF SCHEDULE OF
BASELINES, COMPLETION
SCHEDULE, SCHEDULE
OF CONTRACTOR’S KEY
EQUIPMENT
FORMS OF LETTER OF
TENDER, LETTER OF
ACCEPTANCE, CONTRACT
AGREEMENT AND
DISPUTE ADJUDICATION/
AVOIDANCE AGREEMENT
In collaboration with
CONTENTS
FORMS
1 GENERAL PROVISIONS. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
1.1 Definitions
1.2 Interpretation
1.3 Notices and Other Communications
1.4 Law and Language
1.5 Priority of Documents
1.6 Contract Agreement
1.7 Assignment
1.8 Care and Supply of Documents
1.9 Errors in the Employer’s Requirements and/or in the Geotechnical Baseline
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
Report
1.10 Employer’s Use of Contractor’s Documents
1.11 Contractor’s Use of Employer’s Documents
1.12 Confidentiality
1.13 Compliance with Laws
1.14 Joint and Several Liability
1.15 Limitation of Liability
1.16 Contract Risk Register and Contract Risk Management Plan
1.17 Contract Termination
2 THE EMPLOYER . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
3 THE ENGINEER. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19
4 THE CONTRACTOR. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25
GUIDANCE
4.6 Co-operation
4.7 Setting Out
4.8 Health and Safety Obligations
4.9 Quality.Management and Compliance Verification Systems
4.10 Use of Site Data of the Geotechnical Baseline Report and of the Geotechnical
Data Report
4.11 Sufficiency of the Accepted Contract Amount
4.12 Unforeseeable Physical Conditions
4.13 Rights of Way and Facilities
4.14 Avoidance of Interference
4.15 Access Route
4.16 Transport of Goods
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
5 DESIGN. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 42
CONDITIONS
GENERAL
6.1 Engagement of Staff and Labour
6.2 Rates of Wages and Conditions of Labour
6.3 Recruitment of Persons
6.4 Labour Laws
6.5 Working Hours
GUIDANCE
6.6 Facilities for Staff and Labour
6.7 Health and Safety of Personnel
6.8 Contractor’s Superintendence
6.9 Contractor’s Personnel
6.10 Contractor’s Records
6.11 Disorderly Conduct
FORMS
6.12 Key Personnel
7.8 Royalties
9 TESTS ON COMPLETION. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 60
CONDITIONS
14.7 Payment
GENERAL
14.8 Delayed Payment
14.9 Release of Retention Money
14.10 Statement at Completion
14.11 Final Statement
14.12 Discharge
GUIDANCE
14.13 Issue of FPC
14.14 Cessation of Employer’s Liability
14.15 Currencies of Payment
15 TERMINATION BY EMPLOYER. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 91
FORMS
15.1 Notice to Correct
15.2 Termination for Contractor’s Default
15.3 Valuation after Termination for Contractor’s Default
15.4 Payment after Termination for Contractor’s Default
15.5 Termination for Employer’s Convenience
15.6 Valuation after Termination for Employer’s Convenience
15.7 Payment after Termination for Employer’s Convenience
20.1 Claims
20.2 Claims For Payment and/or EOT
APPENDIX . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 117
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
1
General Provisions
GUIDANCE
1.1
Definitions In the Contract the following words and expressions shall have the meanings stated,
except where the context requires otherwise
1.1.1 “Accepted Contract Amount” means the amount accepted in the Letter of
Acceptance for the execution of the Works in accordance with the Contract.
FORMS
1.1.2 “Advance Payment Certificate” means a Payment Certificate issued
by the Engineer for advance payment under Sub-Clause 14.2.2 [Advance
Payment Certificate].
1.1.4 “Base Date” means the date 28 days before the latest date for submission
of the Tender.
1.1.6 “Claim” means a request or assertion by one Party to the other Party for
an entitlement or relief under any Clause of these Conditions or otherwise
in connection with, or arising out of, the Contract or the execution of the
Works.
1.1.7 “Commencement Date” means the date as stated in the Engineer’s Notice
issued under Sub-Clause 8.1 [Commencement of Works].
1.1.11 “Contract” means the Contract Agreement, the Letter of Acceptance, the
Letter of Tender, any addenda referred to in the Contract Agreement, these
Conditions, the Employer’s Requirements, the Geotechnical Baseline Report,
the Schedules, the Contractor’s Proposal, the JV Undertaking (if applicable)
and the further documents (if any) including the Contract Risk Management
Plan, the Contract Risk Register and the Geotechnical Data Report, which
are listed in the Contract Agreement or in the Letter of Acceptance.
1.1.12 “Contract Agreement” means the agreement entered into by both Parties
in accordance with Sub-Clause 1.6 [Contract Agreement].
1.1.14 “Contract Price” means the price defined in Sub-Clause 14.1 [The Contract
Price].
1.1.15 “Contract Risk Management Plan” means the document entitled contract
risk management plan (as may be updated and/or revised from time to time)
GUIDANCE
1.1.16 “Contract Risk Register” means the document entitled contract risk
register required under Sub-Clause 1.16 [Contract Risk Register and
Contract Risk Management Plan] (as may be updated and/or revised from
time to time) which identifies relevant risks, and the actions which are to be
FORMS
1.1.20 “Contractor’s Key Equipment” means the items (if any) of the Contractor’s
Equipment that are stated in the Schedule of Contractor’s Key Equipment.
1.1.21 “Contractor’s Key Personnel” means the positions (if any) of the
Contractor’s Personnel, other than the Contractor’s Representative, that are
specified in the Employer’s Requirements.
1.1.23 “Contractor’s Proposal” means the part of the Tender stated or implied
as being the Contractor’s proposal for execution of the Works, as included
in the Contract. Such documents may include the Contractor’s preliminary
design.
1.1.25 “Cost” means all expenditure reasonably incurred (or to be incurred) by the
Contractor in performing the Contract, whether on or off the Site, including
CONDITIONS
Contractor is entitled under a Sub-Clause of these Conditions to payment of
GENERAL
Cost, it shall be added to the Contract Price.
1.1.26 “Cost Plus Profit” means Cost plus the applicable percentage for profit
stated in the Contract Data (if not stated, five percent (5%)). Such percentage
shall only be added to Cost, and Cost Plus Profit shall only be added to the
Contract Price, where the Contractor is entitled under a Sub-Clause of these
GUIDANCE
Conditions to payment of Cost Plus Profit.
1.1.27 “Country” means the country in which the Site (or most of it) is located,
where the Permanent Works are to be executed.
FORMS
appointed under Sub-Clause 21.1 [Constitution of the DAAB] or Sub-Clause
21.2 [Failure to Appoint DAAB Member(s)].
1.1.29 “DAAB Agreement” means the agreement signed or deemed to have been
signed by both Parties and the sole member or each of the three members
(as the case may be) of the DAAB in accordance with Sub-Clause 21.1
[Constitution of the DAAB] or Sub-Clause 21.2 [Failure to Appoint DAAB
Member(s)], incorporating by reference the General Conditions of Dispute
Avoidance/Adjudication Agreement contained in the Appendix to these
General Conditions with such amendments as are agreed.
1.1.30 “Date of Completion” means the date stated in the Taking-Over Certificate
issued by the Engineer; or, if the last paragraph of Sub-Clause 10.1 [Taking
Over the Works and Sections] applies, the date on which the Works or Section
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
are deemed to have been completed in accordance with the Contract; or, if
Sub-Clause 10.2 [Taking Over Parts] or Sub-Clause 10.3. [Interference with
Tests on Completion] applies, the date on which the Works or Section or
Part are deemed to have been taken over by the Employer, or, if Sub-Clause
4.25 [Milestones] applies, the date stated in the Milestone Certificate issued
by the Engineer.
1.1.32 “Daywork Schedule” means the document entitled daywork schedule (if
any) included in the Contract, showing the amounts and manner of payments
to be made to the Contractor for labour, materials and equipment used for
daywork under Sub-Clause 13.5 [Daywork].
1.1.33 “Defects Notification Period” or “DNP” means the period for notifying
defects and/or damage in the Works or a Section or a Part (as the case
may be) under Sub-Clause 11.1 [Completion of Outstanding Work and
Remedying Defects], as stated in the Contract Data (if not stated, one year),
and as may be extended under Sub-Clause 11.3 [Extension of Defects
Notification Period]. This period is calculated from the Date of Completion of
the Works or Section or Part.
1.1.34 “Delay Damages” means the damages for which the Contractor shall be
liable under Sub-Clause 8.8 [Delay Damages] for failure to comply with
Sub-Clause 8.2 [Time for Completion].
(a) one Party makes a claim against the other Party (which may be a
Claim, as defined in these Conditions, or a matter to be determined
(b) the other Party (or the Engineer under Sub-Clause 3.7.2 [Engineer’s
GENERAL
the circumstances, the DAAB or the arbitrator(s), as the case may be, deem
it reasonable for it to do so.
1.1.36 “Employer” means the person named as the employer in the Contract Data
and the legal successors in title to this person.
1.1.41 “Engineer” means the person named in the Contract Data appointed by
the Employer to act as the Engineer for the purposes of the Contract, or
any replacement appointed under Sub-Clause 3.6 [Replacement of the
Engineer].
CONDITIONS
Completion under Sub-Clause 8.5 [Extension of Time for Completion].
GENERAL
1.1.46 “FIDIC” means the Fédération Internationale des Ingénieurs-Conseils, the
International Federation of Consulting Engineers.
GUIDANCE
1.1.48 “Final Statement” means the Statement defined in Sub-Clause 14.11.2
[Agreed Final Statement].
1.1.49 “Foreign Currency” means a currency in which part (or all) of the Contract
Price is payable, but not the Local Currency.
FORMS
1.1.50 “General Conditions” means this document entitled “Conditions of
Contract for Underground Works”, as published by FIDIC.
1.1.56 “JV Undertaking” means the letter provided to the Employer as part of the
Tender setting out the legal undertaking between the two or more persons
constituting the Contractor as a JV. This letter shall be signed by all the
persons who are members of the JV, shall be addressed to the Employer
and shall include:
1.1.59 “Letter of Tender” means the letter of tender, signed by the Contractor,
GUIDANCE
stating the Contractor’s offer to the Employer for the execution of the Works.
1.1.60 “Lining” means the Works required to permanently line and support the
excavated space for the Underground Works, whether constructed at the
same time or at a later stage, including waterproofing, contact grouting and
backfill (in each case if any).
FORMS
1.1.62 “Materials” means things of all kinds (other than Plant), whether on the Site
or otherwise allocated to the Contract and intended to form or forming part
of the Permanent Works, including the supply-only materials (if any) to be
supplied by the Contractor under the Contract.
1.1.63 “Milestone” means any event in the project defined as a milestone in the
Completion Schedule. The completion of the Excavation and the completion
of the Lining shall be deemed to be Milestones.
1.1.64 “Milestone Certificate” means the certificate issued by the Engineer under
Sub-Clause 4.25 [Milestones].
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
1.1.66 “No-objection” means that the Engineer has no objection to the Contractor’s
Documents, or other documents submitted by the Contractor under these
Conditions, and such Contractor’s Documents or other documents may be
used for the Works.
1.1.68 “Notice of Dissatisfaction” or “NOD” means the Notice one Party may give
to the other Party if it is dissatisfied, either with an Engineer’s determination
under Sub-Clause 3.7 [Agreement or Determination] or with a DAAB’s
decision under Sub-Clause 21.4 [Obtaining DAAB’s Decision].
1.1.69 “Part” means a part of the Works or part of a Section (as the case may be)
which is used by the Employer and deemed to have been taken over under
Sub-Clause 10.2 [Taking Over Parts].
1.1.71 “Party” means the Employer or the Contractor, as the context requires.
“Parties” means both the Employer and the Contractor.
CONDITIONS
(or deemed to be issued) under Sub-Clause 11.9 [Performance Certificate].
GENERAL
1.1.74 “Performance Damages” means the damages to be paid by the Contractor
to the Employer, for the failure to achieve the guaranteed performance of the
Plant and/or the Works or any part of the Works (as the case may be), as set
out in the Schedule of Performance Guarantees.
GUIDANCE
1.1.75 “Performance Security” means the security under Sub-Clause 4.2
[Performance Security].
1.1.76 “Permanent Works” means the works of a permanent nature which are to
be executed by the Contractor under the Contract.
1.1.77 “Plant” means the apparatus, equipment, machinery and vehicles (including
FORMS
any components) whether on the Site or otherwise allocated to the Contract
and intended to form or forming part of the Permanent Works.
1.1.79 “Provisional Sum” means a sum (if any) which is specified in the Contract
by the Employer as a provisional sum, for the execution of any part of the
Works or for the supply of Plant, Materials or services under Sub-Clause
13.4 [Provisional Sums].
1.1.81 “Retention Money” means the accumulated retention moneys which the
Employer retains under Sub-Clause 14.3 [Application for Interim Payment]
and pays under Sub-Clause 14.9 [Release of Retention Money].
1.1.88 “Schedule of Rates and Prices” means the document(s) entitled schedule
of rates and prices included in the Contract.
1.1.89 “Section” means a part of the Works specified in the Contract Data as a
Section (if any).
FORMS
1.1.90 “Site” means the places where the Permanent Works are to be executed
and to which Plant and Materials are to be delivered, and any other places
specified in the Contract as forming part of the Site.
1.1.91 “Special Provisions” means the document (if any), entitled special
provisions which constitutes Part B of the Particular Conditions.
1.1.95 “Temporary Works” means all temporary works of every kind (other than
Contractor’s Equipment) required on Site for the execution of the Works.
1.1.96 “Tender” means the Letter of Tender, the Contractor’s Proposal, the JV
Undertaking (if applicable), and all other documents which the Contractor
submitted with the Letter of Tender, as included in the Contract.
1.1.97 “Tests after Completion” means the tests (if any) which are stated in the
Employer’s Requirements and which are carried out in accordance with the
Special Provisions after the Works or a Section (as the case may be) are
taken over under Clause 10 [Employer’s Taking Over].
1.1.98 “Tests on Completion” means the tests which are specified in the Contract
or agreed by both Parties or instructed as a Variation, and which are carried
out under Clause 9 [Tests on Completion] before the Works or a Section (as
the case may be) are taken over under Clause 10 [Employer’s Taking Over].
1.1.99 “Time for Completion” means the time for completing the Works, a
Section or a Milestone (as the case may be) under Sub-Clause 8.2 [Time for
Completion] as stated in the Completion Schedule, and as may be extended
CONDITIONS
Sub-Clause 13.8.3 [Adjustment of Time for Completion], calculated from the
GENERAL
Commencement Date.
1.1.100 “Underground Works” means all Works located beneath the natural or
man-made surface of the earth, including ancillary surface works.
GUIDANCE
contractor by the Base Date. Notwithstanding the foregoing, all subsurface
physical conditions described in the GBR are deemed to be foreseeable, and
all subsurface physical conditions outside the scope of conditions defined in
the GBR are deemed to be Unforeseeable.
FORMS
Adjustments].
1.1.103 “Works” mean the Permanent Works and the Temporary Works, or either of
them as appropriate.
1.2
Interpretation In the Contract, except where the context requires otherwise:
(a) words indicating one gender include all genders; and “he”, “his” and
“himself” shall be read as “he/she”, “his/her” and “himself/herself”
respectively;
(b) words indicating the singular also include the plural and words
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
In any list in these Conditions, where the second-last item of the list is
followed by “and” or “or” or “and/or” then all of the list items going before
General Conditions © FIDIC & ITA 2019
9
this item shall also be read as if they are followed by “and” or “or” or “and/or”
CONDITIONS
The marginal words and other headings shall not be taken into consideration
in the interpretation of these Conditions.
1.3
Notices and
GUIDANCE
Other Communications Wherever these Conditions provide for the giving of a Notice (including
a Notice of Dissatisfaction) or the issuing, providing, sending, submitting
or transmitting of another type of communication (including acceptance,
acknowledgement, advising, agreement, approval, certificate, Claim,
consent, decision, determination, discharge, instruction, No-objection,
record(s) of meeting, permission, proposal, record, reply, report, request,
Review, Statement, statement, submission or any other similar type of
FORMS
All Notices, and all other types of communication as referred to above, shall
not be unreasonably withheld or delayed.
CONDITIONS
Law and Language The Contract shall be governed by the law of the country (or other jurisdiction)
GENERAL
stated in the Contract Data (if not stated, the law of the Country), excluding
any conflict of law rules.
The ruling language of the Contract shall be that stated in the Contract Data
(if not stated, the language of these Conditions). If there are versions of any
part of the Contract which are written in more than one language, the version
GUIDANCE
which is in the ruling language shall prevail.
The language for communications shall be that stated in the Contract Data.
If no language is stated there, the language for communications shall be the
ruling language of the Contract.
1.5
FORMS
Priority of Documents The documents forming the Contract are to be taken as mutually explanatory
of one another. If there is any conflict, ambiguity or discrepancy, the priority
of the documents shall be in accordance with the following sequence:
1.6
Contract Agreement The Parties shall sign a Contract Agreement within 35 days after the
Contractor receives the Letter of Acceptance, unless they agree otherwise.
The Contract Agreement shall be based on the form annexed to the Particular
Conditions. The costs of stamp duties and similar charges (if any) imposed
by law in connection with entry into the Contract Agreement shall be borne
by the Employer.
1.7
Assignment Neither Party shall assign the whole or any part of the Contract or any benefit
or interest in or under the Contract. However, either Party:
Party; and
GENERAL
1.8
GUIDANCE
The Contractor shall keep at all times, on the Site, a copy of:
The Employer’s Personnel shall have right of access to all these documents
during all normal working hours, or as otherwise agreed with the Contractor.
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
1.9
Errors in the Employer’s
Requirements and/or in the
Geotechnical Baseline Report If the Contractor finds an error, fault or defect in the Employer’s Requirements
and/or the Geotechnical Baseline Report as a result of scrutinising them
under Sub-Clause 5.1 [General Design Obligations], the Contractor shall
give a Notice to the Engineer within the period stated in the Contract Data (if
not stated, 42 days) calculated from the Commencement Date.
If, after expiry of this period, the Contractor finds an error, fault or defect in
the Employer’s Requirements and/or in the Geotechnical Baseline Report,
the Contractor shall also give a Notice to the Engineer describing the error,
fault or defect.
CONDITIONS
• when examining the Site and the Employer’s Requirements and
GENERAL
before submitting the Tender; or
• if the Contractor’s Notice is given after the expiry of the period
stated in the first paragraph of this Sub-Clause, when scrutinising
the Employer’s Requirements and the Geotechnical Baseline
Report under Sub-Clause 5.1 [General Design Obligations]; and
GUIDANCE
(c) what measures (if any) the Contractor is required to take to rectify the
error, fault or defect.
For the purpose of Sub-Clause 3.7.3 [Time limits], the date the Engineer
receives the Contractor’s Notice under this Sub-Clause shall be the date of
commencement of the time limit for agreement under Sub-Clause 3.7.3.
FORMS
the Geotechnical Baseline Report under sub-paragraph (b) above, and if an
experienced contractor would not have discovered the error, fault or other
defect:
The Contractor shall be deemed (by signing the Contract Agreement) to give
to the Employer a non-terminable transferable non-exclusive royalty-free
licence to copy, use and communicate the Contractor’s Documents and
such other design documents, including making and using modifications of
them. This licence shall:
Employer for purposes other than those permitted under this Sub-Clause.
1.11
Contractor’s Use of
Employer’s Documents As between the Parties, the Employer shall retain the copyright and other
intellectual property rights in the Employer’s Requirements and other
FORMS
documents made by (or on behalf of) the Employer. The Contractor may, at
the Contractor’s cost, copy, use and communicate these documents for the
purposes of the Contract.
These documents (in whole or in part) shall not, without the Employer’s
prior consent, be copied, used or communicated to a third party by the
Contractor, except as necessary for the purposes of the Contract.
1.12
Confidentiality The Contractor shall disclose all such confidential and other information
as the Engineer may reasonably require in order to verify the Contractor’s
compliance with the Contract.
The Contractor shall treat all documents forming the Contract as confidential,
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
The Employer and the Engineer shall treat all information provided by the
Contractor and marked “confidential”, as confidential. The Employer shall
not disclose or permit to be disclosed any such information to third parties,
except as may be necessary when exercising the Employer’s rights under
Sub-Clause 15.2 [Termination for Contractor’s Default].
1.13
Compliance with Laws The Contractor and the Employer shall, in performing the Contract,
comply with all applicable Laws. Unless otherwise stated in the Employer’s
Requirements:
(a) the Employer shall have obtained (or shall obtain) the planning,
zoning or building permit or similar permits, permissions, licences
and/or approvals for the Permanent Works, and any other permits,
CONDITIONS
Requirements as having been (or being) obtained by the Employer.
GENERAL
The Employer shall indemnify and hold the Contractor harmless
against and from the consequences of any delay or failure to do so,
unless the failure is caused by the Contractor’s failure to comply with
sub-paragraph (c) below;
(b) the Contractor shall give all notices, pay all taxes, duties and fees,
and obtain all other permits, permissions, licences and/or approvals,
GUIDANCE
as required by the Laws in relation to the execution of the Works. The
Contractor shall indemnify and hold the Employer harmless against and
from the consequences of any failure to do so unless the failure is caused
by the Employer’s failure to comply with Sub-Clause 2.2 [Assistance];
(c) within the time(s) stated in the Employer’s Requirement’s the
Contractor shall provide such assistance and all documentation, as
described in the Employer’s Requirements or otherwise reasonably
FORMS
required by the Employer, so as to allow the Employer to obtain any
permit, permission, licence or approval under sub-paragraph (a)
above; and
(d) the Contractor shall comply with all permits, permissions, licences and/
or approvals obtained by the Employer under sub-paragraph (a) above.
If, having complied with sub-paragraph (c) above, the Contractor suffers
delay and/or incurs Cost as a result of the Employer’s delay or failure to
obtain any permit, permission, licence or approval under sub-paragraph (a)
above, the Contractor shall be entitled subject to Sub-Clause 20.2 [Claims
For Payment and/or EOT] to EOT and/or payment of such Cost Plus Profit.
to comply with:
1.14
Joint and Several Liability If the Contractor is a Joint Venture:
(a) the members of the JV shall be jointly and severally liable to the
Employer for the performance of the Contractor’s obligations under
the Contract;
(b) the JV leader shall have authority to bind the Contractor and each
member of the JV; and
(c) neither the members nor (if known) the scope and parts of the Works to
be carried out by each member nor the legal status of the JV shall be
altered without the prior consent of the Employer (but such consent shall
not relieve the altered JV from any liability under sub-paragraph (a) above).
1.15
Limitation of Liability Neither Party shall be liable to the other Party for loss of use of any Works,
loss of profit, loss of any contract or for any indirect or consequential loss
or damage which may be suffered by the other Party in connection with the
Contract, other than under:
Convenience];
GENERAL
and
(iv) under the first paragraph of Sub-Clause 17.4 [Indemnities by
Contractor],
shall not exceed the sum stated in the Contract Data or (if a sum is not so
stated) the Accepted Contract Amount.
This Sub-Clause shall not limit liability in any case of fraud, gross negligence,
deliberate default or reckless misconduct by the defaulting Party.
1.16
Contract Risk Register and
Contract Risk Management Plan The Contractor shall complete and maintain the Contract Risk Register and
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
shall prepare and maintain the Contract Risk Management Plan to manage
and control the risks identified in the Contract Risk Register. The Contractor
shall submit his initial Contract Risk Register and Contract Risk Management
Plan to the Engineer for Review, with a Notice in accordance with Sub-Clause
5.2.2 [Review by Engineer] within 28-days of the Commencement Date, and
thereafter updated Contract Risk Registers and Contract Risk Management
Plans shall be submitted at regular intervals (if not specified otherwise,
every 3 months), and promptly after the occurrence of any event requiring a
revision or update.
The Contract Risk Register and Contract Risk Management Plan shall
comply with requirements, if any, stated in the Employer’s Requirements and
shall include the Contractor’s procedures to ensure that:
(a) Contract Risk Management meetings are held regularly to review and
update the Contract Risk Register and Contract Risk Management
Plan, and
(b) actions are taken – including issuing advance warning notices under
Sub-Clause 8.4 [Advance Warning] and/or meetings are called under
Sub-Clause 3.8 [Meetings], whenever a known, probable or uncertain
future event is likely to have one of the effects listed in Sub-Clause 8.4
[Advance Warning].
1.17
Contract Termination Subject to any mandatory requirements under the governing law of the
Contract, termination of the Contract under any Sub-Clause of these
Conditions shall require no action of whatsoever kind by either Party other
than as stated in the Sub-Clause.
CONDITIONS
GENERAL
2.1
Right of Access to the Site The Employer shall give the Contractor right of access to, and possession
or the necessary right of use of, all parts of the Site within the time (or times)
stated in the Contract Data. The right and possession may not be exclusive
to the Contractor. If, under the Contract, the Employer is required to give
GUIDANCE
(to the Contractor) possession of any foundation, structure, plant or means
of access, the Employer shall do so in the time and manner stated in the
Employer’s Requirements. However, the Employer may withhold any such
right or possession until the Performance Security has been received.
If no such time is stated in the Contract Data, the Employer shall give the
Contractor right of access to, and possession of, those parts of the Site
FORMS
within such times as may be required to enable the Contractor to proceed
in accordance with the Programme or, if there is no Programme at that time,
the initial programme submitted under Sub-Clause 8.3 [Programme].
However, if and to the extent that the Employer’s failure was caused by
any error or delay by the Contractor, including an error in, or delay in the
submission of, any of the applicable Contractor’s Documents, the Contractor
shall not be entitled to such EOT and/or Cost Plus Profit.
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
If, under the Contract, the Employer is required to give to the Contractor
possession of any foundation, structure, plant or means of access in
accordance with Contractor’s Documents, the Contractor shall submit such
Contractor’s Documents to the Engineer in the time and manner stated in
the Employer’s Requirements.
2.2
Assistance If requested by the Contractor, the Employer shall promptly provide
reasonable assistance to the Contractor so as to allow the Contractor to
obtain:
(a) copies of the Laws of the Country which are relevant to the Contract
but are not readily available; and
(b) any permits, permissions, licences or approvals required by the Laws
of the Country (including information required to be submitted by the
Contractor in order to obtain such permits, permissions, licences or
approvals):
(i) which the Contractor is required to obtain under Sub-Clause
1.13 [Compliance with Laws];
(ii) for the delivery of Goods, including clearance through customs;
and
(iii) for the export of Contractor’s Equipment when it is removed from
the Site.
2.3
Employer’s Personnel and
Other Contractors The Employer shall be responsible for ensuring that the Employer’s Personnel
and the Employer’s other contractors (if any) on or near the Site:
[Co-operation]; and
GENERAL
(b) comply with the same obligations which the Contractor is required to
comply with under sub-paragraphs (a) to (e) of Sub-Clause 4.8 [Health
and Safety Obligations] and under Sub-Clause 4.18 [Protection of the
Environment].
2.4
Employer’s Financial
Arrangements The Employer’s arrangements for financing the Employer’s obligations under
FORMS
If the Employer intends to make any material change (affecting the Employer’s
ability to pay the part of the Contract Price remaining to be paid at that time
as estimated by the Engineer) to these financial arrangements, or has to do
so because of changes in the Employer’s financial situation, the Employer
shall immediately give a Notice to the Contractor with detailed supporting
particulars.
If the Contractor:
2.5
Site Data and
Items of Reference The Employer shall have made available to the Contractor for information,
before the Base Date, all relevant data in the Employer’s possession on the
topography of the Site, on hydrological, climatic and environmental conditions
at the Site and adjacent property, and on the geological, geotechnical and
hydrogeological data of the subsurface of the Site.
In particular, the Employer shall have made available to the Contractor, prior
to the Base Date:
CONDITIONS
Employer-Supplied Materials
GENERAL
and Employer’s Equipment If Employer-Supplied Materials and/or Employer’s Equipment are listed in
the Employer’s Requirements for the Contractor’s use in the execution of the
Works, the Employer shall make such materials and/or equipment available
to the Contractor in accordance with the details, times, arrangements, rates
and prices stated in the Employer’s Requirements.
GUIDANCE
The Contractor shall be responsible for each item of Employer’s Equipment
whilst any of the Contractor’s Personnel is operating it, driving it, directing it,
using it, or in control of it.
3
The Engineer
FORMS
3.1
The Engineer The Employer shall appoint the Engineer, who shall carry out the duties
assigned to the Engineer in the Contract.
The Engineer shall be vested with all the authority necessary to act as the
Engineer under the Contract.
The Engineer (or, if a legal entity, the natural person appointed to act on its
behalf) shall be:
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
Where the Engineer is a legal entity, the Engineer shall give a Notice to the
Parties of the natural person (or any replacement) appointed and authorised
to act on its behalf. The authority shall not take effect until this Notice has
been received by both Parties. The Engineer shall similarly give a Notice of
any revocation of such authority.
3.2
Engineer’s Duties
and Authority 3.2.1 Engineer’s General Duties and Authority
The Engineer shall have no authority to amend the Contract or, except as
otherwise stated in these Conditions, to relieve either Party of any duty,
obligation or responsibility under or in connection with the Contract.
3.2.2 Engineer’s Specific Duties and Authority for Excavation and Lining Works
The Engineer shall monitor and record progress of the execution of the
Excavation and Lining Works, for compliance with the Contractor’s obligations
under Sub-Clause 4.24 [Excavation and Lining Works].
Such records shall state whether the measures taken under Sub-Clause 4.24
[Excavation and Lining Works] were jointly agreed between the Engineer and
the Contractor, and if not, the Engineer’s reasons for disagreement.
The Engineer shall provide a copy of such records to the Contractor within
a time that shall be mutually agreed (in the absence of agreement, within 14
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
days of the execution of the Works being recorded). The Contractor shall
examine the records and be deemed to have accepted them unless within 7
days from receipt of the records the Contractor gives a Notice to the Engineer
that the records are asserted as being inaccurate.
After receiving this Notice, the Engineer shall review the records and either
confirm or amend them within 14 days, failing which the records shall be
deemed confirmed as corrected by the Contractor’s Notice. In performing
this task, the Engineer shall proceed under Sub-Clause 3.7 [Agreement or
Determination] and, for the purpose of Sub-Clause 3.7.3 [Time limits], the
date the Engineer receives the Contractor’s Notice under this Sub-Clause
shall be the date of commencement of the time limit for agreement under
Sub-Clause 3.7.3.
If the Engineer fails properly to record progress of the execution of the
Excavation and Lining Works, or to provide the records to the Contractor
within the agreed period, and such failure causes delay and/or additional
Cost, the Contractor shall be entitled subject to Sub-Clause 20.2 [Claims For
Payment and/or EOT] to EOT and/or payment of such Cost Plus Profit.
3.3
The Engineer’s
Representative The Engineer may appoint an Engineer’s Representative and delegate to
him/her in accordance with Sub-Clause 3.4 [Delegation by the Engineer] the
authority necessary to act on the Engineer’s behalf at the Site, except to
replace the Engineer’s Representative.
CONDITIONS
the Engineer’s Representative is to be temporarily absent from the Site
GENERAL
during the execution of the Works, an equivalently qualified, experienced
and competent replacement shall be appointed by the Engineer, and the
Contractor shall be given a Notice of such replacement.
3.4
Delegation by
GUIDANCE
the Engineer The Engineer may from time to time assign duties and delegate authority to
assistants, and may also revoke such assignment or delegation, by giving
a Notice to the Parties, describing the assigned duties and the delegated
authority of each assistant. The assignment, delegation or revocation shall
not take effect until this Notice has been received by both Parties. However,
the Engineer shall not delegate the authority to:
FORMS
(a) act under Sub-Clause 3.7 [Agreement or Determination]; and/or
(b) issue a Notice to Correct under Sub-Clause 15.1 [Notice to Correct].
Each assistant, to whom duties have been assigned or authority has been
delegated, shall only be authorised to issue instructions to the Contractor
to the extent defined by the Engineer’s Notice of delegation under this
Sub-Clause. Any act by an assistant, in accordance with the Engineer’s
Notice of delegation, shall have the same effect as though the act had been
an act of the Engineer. However, if the Contractor questions any instruction
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
3.5
Engineer’s Instructions The Engineer may issue to the Contractor (at any time) instructions which
may be necessary for the execution of the Works, all in accordance with the
Contract. The Contractor shall only take instructions from the Engineer, or
from the Engineer’s Representative (if appointed) or an assistant to whom
the appropriate authority to give instruction has been delegated under
Sub-Clause 3.4 [Delegation by the Engineer].
to the instruction, give a Notice to the Engineer with reasons. If the Engineer
GENERAL
does not respond within 7 days after receiving this Notice, by giving a Notice
confirming, reversing or varying the instruction, the Engineer shall be deemed
to have revoked the instruction. Otherwise the Contractor shall comply with
and be bound by the terms of the Engineer’s response.
3.6
GUIDANCE
Replacement of
the Engineer If the Employer intends to replace the Engineer, the Employer shall, not less
than 42 days before the intended date of replacement, give a Notice to the
Contractor of the name, address and relevant experience of the intended
replacement Engineer.
If the Contractor does not respond within 14 days after receiving this Notice,
FORMS
The Employer shall not replace the Engineer with a person (whether a
legal entity or a natural person) against whom the Contractor has raised
reasonable objection by a Notice under this Sub-Clause.
3.7
Agreement or Determination When carrying out his/her duties under this Sub-Clause, the Engineer shall
act neutrally between the Parties and shall not be deemed to act for the
Employer.
Whenever these Conditions provide that the Engineer shall proceed under
this Sub-Clause to agree or determine any matter or Claim, the following
procedure shall apply:
The Engineer shall consult with both Parties jointly and/or separately, and
shall encourage discussion between the Parties in an endeavour to reach
agreement. The Engineer shall commence such consultation promptly
to allow adequate time to comply with the time limit for agreement under
Sub-Clause 3.7.3 [Time limits]. Unless otherwise proposed by the Engineer
and agreed by both Parties, the Engineer shall provide both Parties with a
record of the consultation.
If agreement is achieved within the time limit for agreement under Sub-Clause
3.7.3 [Time limits] the Engineer shall give a Notice to both Parties of the
agreement, which agreement shall be signed by both Parties. This Notice
shall state that it is a “Notice of the Parties’ Agreement” and shall include a
copy of the agreement.
If:
CONDITIONS
Sub-Clause 3.7.3 [Time limits]; or
GENERAL
(b) both Parties advise the Engineer that no agreement can be achieved
within this time limit
whichever is the earlier, the Engineer shall give a Notice to the Parties
accordingly and shall immediately proceed under Sub-Clause 3.7.2
[Engineer’s Determination].
GUIDANCE
3.7.2 Engineer’s Determination
Within the time limit for determination under Sub-Clause 3.7.3 [Time limits],
FORMS
the Engineer shall give a Notice to both Parties of his/her determination.
This Notice shall state that it is a “Notice of the Engineer’s Determination”,
and shall describe the determination in detail with reasons and detailed
supporting particulars.
The Engineer shall give the Notice of his/her determination within 42 days or
within such other time limit as may be proposed by the Engineer and agreed
by both Parties (the “time limit for determination” in these Conditions), after
the date corresponding to his/her obligation to proceed under the last
paragraph of Sub-Clause 3.7.1 [Consultation to reach agreement].
If the Engineer does not give the Notice of agreement or determination within
the relevant time limit:
one Party to the other Party, the Contractor shall include such an amount
in the next Statement and the Engineer shall include such amount in the
Payment Certificate that follows that Statement.
If, within 14 days after giving or receiving the Engineer’s Notice of agreement
or determination, any error of a typographical or clerical or arithmetical nature
is found:
FORMS
(a) by the Engineer: then he/she shall immediately advise the Parties
accordingly; or
(b) by a Party: then that Party shall give a Notice to the Engineer, stating
that it is given under this Sub-Clause 3.7.4 and clearly identifying the
error. If the Engineer does not agree there was an error, he/she shall
immediately advise the Parties accordingly.
The Engineer shall within 7 days of finding the error, or receiving a Notice
under sub-paragraph (b) above (as the case may be), give a Notice to
both Parties of the corrected agreement or determination. Thereafter, the
corrected agreement or determination shall be treated as the agreement or
determination for the purpose of these Conditions.
(a) the dissatisfied Party may give a NOD to the other Party, with a copy
to the Engineer;
(b) this NOD shall state that it is a “Notice of Dissatisfaction with the
Engineer’s Determination” and shall set out the reason(s) for
dissatisfaction;
(c) this NOD shall be given within 28 days after receiving the Engineer’s
Notice of the determination under Sub-Clause 3.7.2 [Engineer’s
Determination] or, if applicable, his/her Notice of the corrected
determination under Sub-Clause 3.7.4 [Effect of the agreement or
determination] (or, in the case of a deemed determination rejecting
the Claim, within 28 days after the time limit for determination under
Sub-Clause 3.7.3 [Time limits] has expired); and
(d) thereafter, either Party may proceed under Sub-Clause 21.4 [Obtaining
DAAB’s Decision].
CONDITIONS
deemed to be severable from the remainder of the determination; and
GENERAL
(iii) the remainder of the determination shall become final and binding on
both Parties as if the NOD had not been given.
In the event that a Party fails to comply with an agreement of the Parties under
this Sub-Clause 3.7 or a final and binding determination of the Engineer, the
other Party may, without prejudice to any other rights it may have, refer
GUIDANCE
the failure itself directly to arbitration under Sub-Clause 21.6 [Arbitration] in
which case the first and the third paragraphs of Sub-Clause 21.7 [Failure
to Comply with DAAB’s Decision] shall apply to such reference in the same
manner as these paragraphs apply to a final and binding decision of the
DAAB.
3.8
FORMS
Meetings The Engineer or the Contractor’s Representative may require the other to
attend a management meeting to discuss arrangements for future work and/
or other matters in connection with execution of the Works.
The Engineer shall keep a record of each management meeting and supply
copies of the record to those attending and to the Employer. At any such
meeting, and in the record, responsibilities for any actions to be taken shall
be in accordance with the Contract.
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
4.1
Contractor’s
4
The Contractor
General Obligations The Contractor shall execute the Works in accordance with the Contract.
When completed, the Works (or Section or Part or major item of Plant, if any)
shall be fit for the purpose(s) for which they are intended, as defined and
described in the Employer’s Requirements (or, where no purpose(s) are so
defined and described, fit for their ordinary purpose(s)).
The Contractor shall provide the Plant (and spare parts, if any) and
Contractor’s Documents specified in the Employer’s Requirements, and
all Contractor’s Personnel, Goods, consumables and other things and
services, whether of a temporary or permanent nature, required to fulfil the
Contractor’s obligations under the Contract.
The Works shall include any work which is necessary to satisfy the Employer’s
Requirements, Contractor’s Proposal and Schedules, or is implied by the
Contract, and all works which (although not mentioned in the Contract) are
necessary for stability or for the completion, or safe and proper operation, of
the Works.
The Contractor shall be responsible for the adequacy, stability and safety
of all the Contractor’s operations and activities, of all of the Contractor’s
methods of construction, and of all the Works.
and methods shall be made without this alteration having been submitted to
GENERAL
the Engineer.
4.2
Performance Security The Contractor shall obtain (at the Contractor’s cost) a Performance Security
to secure the Contractor’s proper performance of the Contract, in the
amount and currencies stated in the Contract Data. If no amount is stated in
GUIDANCE
within a country (or other jurisdiction) to which the Employer gives consent
and shall be in the form annexed to the Particular Conditions, or in another
form agreed by the Employer (but such consent and/or agreement shall not
relieve the Contractor from any obligation under this Sub-Clause).
The Contractor shall ensure that the Performance Security remains valid and
enforceable until the issue of the Performance Certificate and the Contractor
has complied with Sub-Clause 11.11 [Clearance of Site]. If the terms of
the Performance Security specify an expiry date, and the Contractor has
not become entitled to receive the Performance Certificate by the date 28
days before the expiry date, the Contractor shall extend the validity of the
Performance Security until the issue of the Performance Certificate and the
Contractor has complied with Sub-Clause 11.11 [Clearance of Site].
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
The Employer shall not make a claim under the Performance Security, except
for amounts to which the Employer is entitled under the Contract in the event
of:
CONDITIONS
given under Sub-Clause 15.1 [Notice to Correct] within 42 days
GENERAL
or other time (if any) stated in the Notice;
(d) circumstances which entitle the Employer to terminate the
Contract under Sub-Clause 15.2 [Termination for Contractor’s
Default], irrespective of whether a Notice of termination has been
given; or
(e) if under Sub-Clause 11.5 [Remedying of Defective Work off Site]
GUIDANCE
the Contractor removes any defective or damaged Plant from the
Site, failure by the Contractor to repair such Plant, return it to the
Site, reinstall it and retest it by the date of expiry of the relevant
duration stated in the Contractor’s Notice (or other date agreed
by the Employer).
The Employer shall indemnify and hold the Contractor harmless against and
FORMS
from all damages, losses and expenses (including legal fees and expenses)
resulting from a claim under the Performance Security to the extent that the
Employer was not entitled to make the claim.
18.6 [Release from Performance under the Law] (as the case may be).
(a) within 21 days after the issue of the Performance Certificate and the
Contractor has complied with Sub-Clause 11.11 [Clearance of Site];
or
(b) promptly after the date of termination if the Contract is terminated
in accordance with Sub-Clause 15.5 [Termination for Employer’s
Convenience], Sub-Clause 16.2 [Termination by Contractor],
Sub-Clause 18.5 [Optional Termination] or Sub-Clause 18.6 [Release
from Performance under the Law].
4.3
Contractor’s
Representative The Contractor shall appoint the Contractor’s Representative and shall give
him/her all authority necessary to act on the Contractor’s behalf under the
Contract, except to replace the Contractor’s Representative.
Representative, the Contractor shall similarly submit the name and particulars
of another suitable replacement for such appointment. If the Engineer does
not respond within 28 days after receiving this submission, by giving a
Notice to the Contractor objecting to the proposed person or replacement,
the Engineer shall be deemed to have given his/her consent.
GUIDANCE
The Contractor shall not, without the Engineer’s prior consent, revoke the
appointment of the Contractor’s Representative or appoint a replacement
(unless the Contractor’s Representative is unable to act as a result of death,
illness, disability or resignation, in which case his/her appointment shall be
deemed to have been revoked with immediate effect and the appointment
of a replacement shall be treated as a temporary appointment until the
Engineer gives his/her consent to this replacement, or another replacement
FORMS
The Contractor’s Representative shall be based at the Site for the whole
time that the Works are being executed at the Site. If the Contractor’s
Representative is to be temporarily absent from the Site during the execution
of the Works, a suitable replacement shall be temporarily appointed, subject
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
(a) the authority to issue and receive Notices and other communications
under Sub-Clause 1.3 [Notices and Other Communications]; and
(b) the authority to receive instructions under Sub-Clause 3.5 [Engineer’s
Instructions]),
to any suitably competent and experienced person and may at any time
revoke the delegation. Any delegation or revocation shall not take effect until
the Engineer has received a Notice from the Contractor’s Representative,
naming the person, specifying the powers, functions and authority being
delegated or revoked, and stating the timing of the delegation or revocation.
All these persons shall be fluent in the language for communications defined
in Sub-Clause 1.4 [Law and Language].
4.4
Subcontractors The Contractor shall not subcontract:
(a) works with a total accumulated value greater than the percentage
of the Accepted Contract Amount stated in the Contract Data (if not
stated, the whole of the Works); or
(b) any part of the Works for which subcontracting is not permitted as
stated in the Contract Data.
The Contractor shall be responsible for the work of all Subcontractors, for
managing and coordinating all the Subcontractors’ works, and for the acts
CONDITIONS
as if they were the acts or defaults of the Contractor.
GENERAL
The Contractor shall obtain the Engineer’s prior consent to all proposed
Subcontractors, except:
GUIDANCE
Where the Contractor is required to obtain the Engineer’s consent to a
proposed Subcontractor, the Contractor shall submit the name, address,
detailed particulars and relevant experience of such Subcontractor and the
work intended to be subcontracted to the Engineer and further information
which the Engineer may reasonably require. If the Engineer does not
respond within 14 days after receiving this submission (or further information
FORMS
if requested), by giving a Notice objecting to the proposed Subcontractor,
the Engineer shall be deemed to have given his/her consent.
The Contractor shall give a Notice to the Engineer not less than 28 days
before the intended date of the commencement of each Subcontractor’s
work, and of the commencement of such work on the Site.
4.5
Nominated
Subcontractors In this Sub-Clause, “nominated Subcontractor” means a Subcontractor named
as such in the Employer’s Requirements or whom the Engineer, under Sub-Clause
13.4 [Provisional Sums], instructs the Contractor to employ as a Subcontractor.
(a) there are reasons to believe that the nominated Subcontractor does
not have sufficient competence, resources or financial strength;
(b) the subcontract does not specify that the nominated Subcontractor
shall indemnify the Contractor against and from any negligence or
misuse of Goods by the nominated Subcontractor, the nominated
Subcontractor’s agents and employees; or
(c) the subcontract does not specify that, for the subcontracted work
(including design, if any), the nominated Subcontractor shall:
(i) undertake to the Contractor such obligations and liabilities
as will enable the Contractor to discharge the Contractor’s
corresponding obligations and liabilities under the Contract; and
(ii) indemnify the Contractor against and from all obligations and
liabilities arising under or in connection with the Contract and
from the consequences of any failure by the Subcontractor to
perform these obligations or to fulfil these liabilities.
The Contractor shall pay to the nominated Subcontractor the amounts due
Thereafter, the Engineer shall give a Notice to the Contractor stating the
amount paid directly to the nominated Subcontractor by the Employer and,
in the next IPC after this Notice, shall include this amount as a deduction
under sub-paragraph (b) of Sub-Clause 14.6.1 [The IPC].
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
4.6
Co-operation The Contractor shall, as specified in the Employer’s Requirements or
as instructed by the Engineer, co-operate with and allow appropriate
opportunities for carrying out work by:
CONDITIONS
Setting Out The Contractor shall set out the Works in relation to the items of reference
GENERAL
under Sub-Clause 2.5 [Site Data and Items of Reference].
4.7.1 Accuracy
GUIDANCE
(a) verify the accuracy of all these items of reference before they are used
for the Works;
(b) promptly deliver the results of each verification to the Engineer;
(c) rectify any error in the positions, levels, dimensions or alignment of the
Works; and
(d) be responsible for the correct positioning of all parts of the Works.
FORMS
4.7.2 Errors
If the Contractor finds an error in any items of reference, the Contractor shall
give a Notice to the Engineer describing it:
(a) within the period stated in the Contract Data (if not stated, 28 days)
calculated from the Commencement Date, if the items of reference
are specified in the Employer’s Requirements; or
(b) as soon as practicable after receiving the items of reference, if they
are issued by the Engineer under Sub-Clause 2.5 [Site Data and Items
of Reference].
4.8
Health and Safety
Obligations The Contractor shall:
(a) comply with all applicable health and safety regulations and Laws;
GUIDANCE
(b) comply with all applicable health and safety obligations specified in
the Contract;
(c) comply with all directives issued by the Contractor’s health and
safety officer (appointed under Sub-Clause 6.7 [Health and Safety of
Personnel]);
(d) take care of the health and safety of all persons entitled to be on the
FORMS
Site and other places (if any) where the Works are being executed;
(e) keep the Site, Works (and the other places (if any) where the Works
are being executed) clear of unnecessary obstruction so as to avoid
danger to these persons;
(f) provide fencing, lighting, safe access, guarding and watching of:
(i) the Works, until the Works are taken over under Clause 10
[Employer’s Taking Over]; and
(ii) any part of the Works where the Contractor is executing
outstanding works or remedying any defects during the DNP;
and
(g) provide any Temporary Works (including but not limited to, roadways,
footways, guards and fences) which may be necessary, because of
the execution of the Works, for the use and protection of the public
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
The health and safety manual shall set out all the health and safety
requirements:
CONDITIONS
the Engineer may reasonably require, maintain records and make reports
GENERAL
(in compliance with the applicable health and safety regulations and Laws)
concerning the health and safety of persons and any damage to property.
4.9
Quality Management and
Compliance Verification
GUIDANCE
Systems 4.9.1 Quality Management System
FORMS
The QM System shall be in accordance with the details stated in the Employer’s
Requirements (if any) and shall include the Contractor’s procedures:
(a) to ensure that all Notices and other communications under Sub-Clause
1.3 [Notices and Other Communications], Contractor’s Documents,
as-built records, O&M Manuals, and contemporary records can be
traced, with full certainty, to the Works, Goods, work, workmanship
or test to which they relate;
(b) to ensure proper coordination and management of interfaces between
the stages of execution of the Works, and between Subcontractors;
and
(c) for the submission of Contractor’s Documents to the Engineer for
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
Review.
The Engineer may Review the QM System and may give a Notice to the
Contractor stating the extent to which it does not comply with the Contract.
Within 14 days after receiving this Notice, the Contractor shall revise the QM
System to rectify such non-compliance. If the Engineer does not give such
a Notice within 21 days of the date of submission of the QM System, the
Engineer shall be deemed to have given a Notice of No-objection.
The Engineer may, at any time, give a Notice to the Contractor stating the
extent to which the Contractor is failing to correctly implement the QM
System to the Contractor’s activities under the Contract. After receiving this
Notice, the Contractor shall immediately remedy such failure.
The Contractor shall carry out internal audits of the QM System regularly, and
at least once every 6 months. The Contractor shall submit to the Engineer
a report listing the results of each internal audit within 7 days of completion.
Each report shall include, where appropriate, the proposed measures to
improve and/or rectify the QM System and/or its implementation.
The Contractor shall prepare and submit to the Engineer a complete set
of compliance verification documentation for the Works or Section (as the
case may be), fully compiled and collated in the manner described in the
Employer’s Requirements or, if not so described, in a manner acceptable to
the Engineer.
FORMS
4.10
Use of Site Data, of the
Geotechnical Baseline
Report and of the
Use of Site Data 4.10.1
Geotechnical Data Report
Subject to the provisions of Sub-Clause 4.10.2 [Use of Geotechnical Baseline
Report], the Contractor shall be responsible for interpreting all data referred
to under Sub-Clause 2.5 [Site Data and Items of Reference].
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
Subject to the provisions of Sub-Clause 4.10.2 [Use of Geotechnical
Baseline Report] and to the extent which was practicable (taking account of
time and cost and access to the Site and its surroundings), the Contractor
shall be deemed to have obtained all necessary information as to risks,
contingencies and other circumstances which may influence or affect the
Tender or Works. To the same extent, the Contractor shall be deemed to
have inspected and examined the Site, its surroundings, the above data and
other available information, and to have been satisfied before submitting the
Tender as to all matters relevant to the execution of the Works, including:
(a) the form and nature of the Site and adjacent structures or
developments;
(b) the hydrological and climatic conditions, and the effects of climatic
conditions at the Site;
(c) the extent and nature of the work and Goods necessary for the
execution of the Works;
(d) the Laws, procedures and labour practices of the Country; and
(e) the Contractor’s requirements for access, accommodation, facilities,
personnel, power, transport, water and any other utilities or services.
The Contractor shall be deemed to have based the Tender and the
Contractor’s Proposal for the Excavation and Lining Works on the subsurface
physical conditions and ground reactions described in the GBR, irrespective
of any discrepancy or ambiguity that may be found between such conditions
and/or reactions and the conditions described in any data made available
under Sub-Clause 2.5 [Site Data and Items of Reference].
CONDITIONS
GENERAL
If an alternative construction method for the Excavation and/or Lining Works
is agreed between the Parties, and if the GBR is silent on one or more
parameters that are relevant to such alternative method, reference shall be
made to the GDR to integrate or amend the GBR accordingly.
4.11
GUIDANCE
Sufficiency of the
Accepted Contract Amount The Contractor shall be deemed to:
FORMS
interpretations, necessary information, inspections, examinations and
satisfaction as to all relevant matters described in Sub-Clause 4.10
[Use of Site Data and Geotechnical Baseline and Geotechnical Data
Report] and any further data relevant to the Contractor’s design.
4.12
Unforeseeable Physical
Conditions In this Sub-Clause, “physical conditions” means natural physical conditions,
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
However the impact on progress and/or Cost of any conditions that are
described in the Geotechnical Baseline Report shall not be assessed under
this Sub-Clause but under Sub-Clause 13.8. [Measurement of Excavation
and Lining Works and Adjustment of Time for Completion and Contract
Price].
(a) be given as soon as practicable and in good time to give the Engineer
opportunity to inspect and investigate the physical conditions promptly
and before they are disturbed;
(b) describe the physical conditions, so that they can be inspected and/
or investigated promptly by the Engineer;
(c) set out the reasons why the Contractor considers the physical
conditions to be Unforeseeable; and
The Engineer shall inspect and investigate the physical conditions (subject to
the safety of access) immediately or within a period of days as agreed with
the Contractor, after receiving the Contractor’s Notice.
The Contractor shall continue execution of the Works, using such proper
and reasonable measures as are appropriate for the physical conditions and
to enable the Engineer to inspect and investigate them.
FORMS
The Contractor shall comply with any instructions which the Engineer may give
for dealing with the physical conditions and, if such an instruction constitutes a
Variation, Sub-Clause 13.3.1 [Variation by Instruction] shall apply.
If and to the extent that the Contractor suffers delay and/or incurs Cost due
to these physical conditions, having complied with Sub-Clauses 4.12.1 to
4.12.3 above, the Contractor shall be entitled subject to Sub-Clause 20.2
[Claims For Payment and/or EOT] to EOT and/or payment of such Cost.
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
The Engineer may also review whether other physical conditions in similar
parts of the Works (if any) were at the Base Date reasonably foreseeable by
an experienced contractor (or, as regards subsurface physical conditions
described in the GBR, were more favourable than those described in the
GBR), it being understood that such conditions that have given rise to an
adjustment under Sub-Clause 13.8.3 [Adjustment of Time for Completion]
would not be considered for this purpose. If and to the extent that these more
favourable conditions were encountered, the Engineer may take account of
the reductions in Cost which were due to these conditions in calculating the
additional Cost to be agreed or determined under this Sub-Clause 4.12.5.
However, the net effect of all additions and reductions under this Sub-Clause
4.12.5 shall not result in a net reduction in the Contract Price.
CONDITIONS
[Fully detailed Claim], but shall not be bound by any such evidence.
GENERAL
4.13
Rights of Way and Facilities The Contractor shall bear all costs and charges for special and/or temporary
rights-of-way which may be required for the purposes of the Works, including
those for access to the Site.
GUIDANCE
The Contractor shall also obtain, at the Contractor’s risk and cost, any additional
facilities outside the Site which may be required for the purposes of the Works.
4.14
Avoidance of Interference The Contractor shall not interfere unnecessarily or improperly with:
FORMS
(b) the access to and use and occupation of all roads and footpaths,
irrespective of whether they are public or in the possession of the
Employer or of others.
The Contractor shall indemnify and hold the Employer harmless against and
from all damages, losses and expenses (including legal fees and expenses)
resulting from any such unnecessary or improper interference.
4.15
Access Route The Contractor shall be deemed to have been satisfied, at the Base Date,
as to the suitability and availability of the access routes to the Site. The
Contractor shall take all necessary measures to prevent any road or bridge
from being damaged by the Contractor’s traffic or by the Contractor’s
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
(a) the Contractor shall (as between the Parties) be responsible for repair
of any damage caused to, and any maintenance which may be
required for the Contractor’s use of, access routes;
(b) the Contractor shall provide all necessary signs or directions along
access routes, and shall obtain any permissions or permits which
may be required from the relevant authorities, for the Contractor’s use
of routes, signs and directions;
(c) the Employer shall not be responsible for any third party claims which
may arise from the Contractor’s use or otherwise of any access route;
(d) the Employer does not guarantee the suitability or availability of
particular access routes; and
(e) all Costs due to non-suitability or non-availability, for the use required
by the Contractor, of access routes shall be borne by the Contractor.
(a) give a Notice to the Engineer not less than 21 days before the date on
which any Plant, item of Contractor’s Key Equipment, or a major item
of other Goods (as specified in the Employer’s Requirements), will be
delivered to the Site;
(b) be responsible for packing, loading, transporting, receiving, unloading,
GUIDANCE
storing and protecting all Goods and other things required for the
Works;
(c) be responsible for customs clearance, permits, fees and charges
related to the import, transport and handling of all Goods, including
all obligations necessary for their delivery to the Site; and
(d) indemnify and hold the Employer harmless against and from all
damages, losses and expenses (including legal fees and expenses)
FORMS
resulting from the import, transport and handling of all Goods, and
shall negotiate and pay all third party claims arising from their import,
transport and handling.
4.17
Contractor’s Equipment The Contractor shall be responsible for all Contractor’s Equipment. When
brought on to the Site, Contractor’s Equipment shall be deemed to be
exclusively intended for the execution of the Works. The Contractor’s Key
Equipment shall be designated as such in the Schedule of Contractor’s
Key Equipment including its conforming characteristics as specified in the
Employer’s Requirements.
The date of delivery to the Site of each item of the Contractor’s Key
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
Equipment, and the duration of its presence on the Site, shall be consistent
with the Completion Schedule
The Contractor shall not remove from the Site or any other agreed location
any items of the Contractor’s Key Equipment and/or any other major items
of the Contractor’s Equipment, without the Engineer’s consent. However,
consent shall not be required for vehicles transporting Goods or Contractor’s
Personnel off Site.
4.18
Protection of
the Environment The Contractor shall take all necessary measures to;
CONDITIONS
discharges, effluent and any other pollutants from the Contractor’s activities
GENERAL
shall exceed neither the values indicated in the Employer’s Requirements nor
those prescribed by applicable Laws.
4.19
Temporary Utilities The Contractor shall, except as stated below, be responsible for the provision
of all temporary utilities, including electricity, gas, telecommunications, water
GUIDANCE
and any other services the Contractor may require for the execution of the
Works.
The following provisions of this Sub-Clause shall only apply if, as stated
in the Employer’s Requirements, the Employer is to provide utilities for the
Contractor’s use. The Contractor shall be entitled to use, for the purposes
of the Works, the utilities on the Site for which details and prices are given
FORMS
in the Employer’s Requirements. The Contractor shall, at the Contractor’s
risk and cost, provide any apparatus necessary for the Contractor’s use of
these services and for measuring the quantities consumed. The apparatus
provided for measuring quantities consumed shall be subject to the
Engineer’s consent. The quantities consumed (if any) during each period
of payment stated in the Contract Data (if not stated, each month) shall be
measured by the Contractor, and the amount to be paid by the Contractor
for such quantities (at the prices stated in the Employer’s Requirements)
shall be included in the relevant Statement.
4.20
Progress Reports Monthly progress reports, in the format stated in the Employer’s Requirements
(if not stated, in a format acceptable to the Engineer), shall be prepared by
the Contractor and submitted to the Engineer. Each progress report shall be
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
Reporting shall continue until the Date of Completion of the Works or, if
outstanding work is listed in the Taking-Over Certificate, the date on which
such outstanding work is completed. Unless otherwise stated in the
Employer’s Requirements, each progress report shall include:
4.21
Security of the Site The Contractor shall be responsible for the security of the Site, and:
4.22
Contractor’s Operations
on Site The Contractor shall confine the Contractor’s operations to the Site, and
to any additional areas which may be obtained by the Contractor and
acknowledged by the Engineer as working areas. The Contractor shall take
all necessary precautions to keep Contractor’s Equipment and Contractor’s
Personnel within the Site and these additional areas, and to keep them off
adjacent land.
At all times, the Contractor shall keep the Site free from all unnecessary
obstruction, and shall properly store or remove from the Site any Contractor’s
Equipment (subject to Sub-Clause 4.17 [Contractor’s Equipment]) and/or
surplus materials. The Contractor shall promptly clear away and remove
from the Site any wreckage, rubbish, hazardous waste and Temporary
Works which are no longer required.
4.23
Archaeological and
Geological Findings All fossils, coins, articles of value or antiquity, and structures and other
remains or items of geological or archaeological interest found on the Site
CONDITIONS
shall take all reasonable precautions to prevent Contractor’s Personnel or
GENERAL
other persons from removing or damaging any of these findings.
GUIDANCE
instructions for dealing with it.
If the Contractor suffers delay and/or incurs Cost from complying with the
Engineer’s instructions, the Contractor shall be entitled subject to Sub-Clause
20.2 [Claims For Payment and/or EOT] to EOT and/or payment of such
Cost.
FORMS
4.24
Excavation and Lining Works The Contractor shall take whatever measures are necessary for the execution
of, and/or are necessary for the safety, stability and timely progress of, the
Excavation and Lining Works in accordance with the Contract. The Contractor
shall submit to the Engineer on a daily basis his/her interpretations of the
subsurface and surface monitoring results, if any.
The Contractor and the Engineer shall use all reasonable endeavours to
agree such necessary measures.
Any adjustment to the Contract Price arising from such necessary measures,
shall be in accordance with Sub-Clause 13.8.4 [Adjustment of the Contract
Price],or Sub-Clause 4.12.5 [Agreement or Determination of Delay and/or
Cost] as the case may be.
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
4.25
Milestones The Contractor shall complete the part of the design and/or of Works
required to achieve each Milestone (including all work which is stated in
the Employer’s Requirements as being required for the Milestone to be
considered complete) within the Time for Completion of the Milestone, as
stated in the Completion Schedule, calculated from the Commencement
Date and subject to any Extension of Time under Sub-Clause 8.5 [Extension
of Time for Completion] and/or adjustment under Sub-Clause 13.8.3
[Adjustment of Time for Completion].
(a) issue the Milestone Certificate to the Contractor, stating the date on which
the Milestone was completed in accordance with the Contract, except for
any minor outstanding work and defects (as shall be listed in the Milestone
Certificate); or
(b) reject the application, giving reasons and specifying the work required to be
done and defects required to be remedied by the Contractor to enable the
Milestone Certificate to be issued.
Sub-Clause.
5.1
5
Design
GUIDANCE
General Design Obligations The Contractor shall carry out, and be responsible for, the design of the
Works to the extent specified in the Employer’s Requirements, and, where
applicable, in accordance with the Geotechnical Baseline Report.
The Contractor warrants that the Contractor, the Contractor’s designers and
design Subcontractors have the experience, capability and competence
necessary for the design. The Contractor undertakes that the designers
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
5.2
Contractor’s
Documents The Contractor’s Documents shall comprise the documents:
CONDITIONS
Sub-Clause 1.4 [Law and Language].
GENERAL
The Contractor shall prepare all Contractor’s Documents, and any other
documents necessary to complete and implement the design during
execution of the Works and to instruct the Contractor’s Personnel. The
Employer’s Personnel shall have the right to inspect the preparation of
all these documents (including any investigation, modelling and testing),
GUIDANCE
wherever they are being prepared.
FORMS
otherwise stated in the Employer’s Requirements, calculated from the
date on which the Engineer receives a Contractor’s Document and a
Contractor’s Notice;
- “Contractor’s Document” excludes any of the Contractor’s Documents
which are not specified in the Employer’s Requirements or these
Conditions as being required to be submitted for Review, but includes
all documents on which a specified Contractor’s Document relies for
completeness; and
- “Contractor’s Notice” means the Notice which shall state that the
relevant Contractor’s Document is considered by the Contractor to
be ready for Review under this Sub-Clause 5.2.2 and for use, and that
it complies with the Employer’s Requirements and these Conditions,
or the extent to which it does not do so.
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
The Engineer shall, within the Review Period, give a Notice to the Contractor:
If the Engineer gives no Notice within the Review Period, the Engineer shall
be deemed to have given a Notice of No-objection to the Contractor’s
Document (provided that all other Contractor’s Documents on which that
Contractor’s Document relies (if any) have been given, or are deemed to
have been given, a Notice of No-objection).
If the Engineer gives a Notice under sub-paragraph (b) above, the Contractor
shall:
5.2.3 Construction
5.3
Contractor’s
Undertaking The Contractor undertakes that the design, the Contractor’s Documents,
the execution of the Works and the completed Works will be in accordance
with:
5.4
Technical Standards
and Regulations The Contractor’s Documents, the execution of the Works and the completed
Works (including defects remedied by the Contractor) shall comply with the
Country’s technical standards, building, construction and environmental
Laws, Laws applicable to the product being produced from the Works, and
other standards specified in the Employer’s Requirements, applicable to the
Works, or defined by applicable Laws.
All these technical or other standards and Laws shall, in respect of the
Works, and each Section and Part, be those in force when the Works or
Section or Part are taken over under Clause 10 [Employer’s Taking Over].
CONDITIONS
to be references to the edition applicable on the Base Date, unless stated
GENERAL
otherwise. If changed or new applicable standards come into force in the
Country after the Base Date, the Contractor shall promptly give a Notice
to the Engineer and (if appropriate or requested by the Engineer) submit
proposals for compliance. To the extent that:
GUIDANCE
compliance requires change(s) to the execution of the Works; and
(b) the Contractor’s proposals for compliance constitute a Variation;
5.5
FORMS
Training The Contractor shall carry out training of employees of the Employer (and/or
other personnel identified in the Employer’s Requirements) in the operation
and maintenance of the Works, and any other aspect of the Works, to the
extent specified in the Employer’s Requirements.
5.6
As-Built Records The Contractor shall prepare, and keep up-to-date, a complete set of
“as-built” records of the execution of the Works, showing the exact as-built
locations, sizes and details of the work as executed by the Contractor.
The format, referencing system, system of electronic storage and other
relevant details of the as-built records shall be as stated in the Employer’s
Requirements (if not stated, as acceptable to the Engineer). These records
shall be kept on the Site and shall be used exclusively for the purposes of
this Sub-Clause.
The Contractor shall submit to the Engineer under Sub-Clause 5.2.2 [Review
by Engineer]:
(a) the as-built records for the Works or Section (as the case may be)
before the commencement of the Tests on Completion; and
(b) updated as-built records to the extent that any work is executed by
the Contractor:
(i) during and/or after the Tests on Completion, before the issue of
any Taking-Over Certificate under Sub-Clause 10.1 [Taking Over
the Works and Sections]; and
(ii) after taking over under Sub-Clause 10.1 [Taking Over the Works
and Sections], before the issue of the Performance Certificate.
Maintenance Manuals The Contractor shall prepare, and keep up-to-date, a complete set of
operation and maintenance manuals for the Works (the “O&M Manuals” in
these Conditions).
The format and other relevant details of the O&M Manuals shall be as stated
in the Employer’s Requirements and, in any case, these manuals shall:
GUIDANCE
If during the Tests on Completion any error or defect is found in the provisional
O&M Manuals, the Contractor shall promptly rectify the error or defect at the
Contractor’s risk and cost.
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
5.8
Design Error If errors, omissions, ambiguities, inconsistencies, inadequacies or other defects
are found in the Contractor’s design and/or the Contractor’s Documents, they
and the Works shall be corrected in accordance with Sub-Clause 7.5 [Defects
and Rejection]. If such Contractor’s Documents were previously the subject of
a Notice of No-objection given (or deemed to be given) by the Engineer under
Sub-Clause 5.2.2 [Review by Engineer], the provisions of Sub-Clause 5.2.2
shall apply as if the Engineer had given a Notice in respect of the Contractor’s
Documents under sub-paragraph (b) of Sub-Clause 5.2.2.
6.1
6
Staff and Labour
Engagement of
Staff and Labour Except as otherwise stated in the Employer’s Requirements, the Contractor
shall make arrangements for the engagement of all Contractor’s Personnel,
and for their payment, accommodation, feeding, transport and welfare.
CONDITIONS
Rates of Wages and
GENERAL
Conditions of Labour The Contractor shall pay rates of wages, and observe conditions of labour,
which comply with all applicable Laws and are not lower than those
established for the trade or industry where the work is carried out.
GUIDANCE
level of wages and conditions observed locally by employers whose trade or
industry is similar to that of the Contractor.
6.3
Recruitment of Persons The Contractor shall not recruit, or attempt to recruit, staff and labour from
amongst the Employer’s Personnel.
FORMS
Neither the Employer nor the Engineer shall recruit, or attempt to recruit, staff
and labour from amongst the Contractor’s Personnel.
6.4
Labour Laws The Contractor shall comply with all the relevant labour Laws applicable
to the Contractor’s Personnel, including Laws relating to their employment
(including wages and working hours), health, safety, welfare, immigration
and emigration, and shall allow them all their legal rights.
The Contractor shall require the Contractor’s Personnel to obey all applicable
Laws, including those concerning health and safety at work.
6.5
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
Working Hours No work shall be carried out on the Site on locally recognised days of rest,
or outside the normal working hours stated in the Contract Data, unless:
6.6
Facilities for
Staff and Labour Except as otherwise stated in the Employer’s Requirements, the Contractor
shall provide and maintain all necessary accommodation and welfare facilities
for the Contractor’s Personnel.
6.7
Health and Safety
of Personnel In addition to the requirements of Sub-Clause 4.8 [Health and Safety
Obligations], the Contractor shall at all times take all necessary precautions to
(a) medical staff, first aid facilities, sick bay, ambulance services and
any other medical services stated in the Employer’s Requirements
are available at all times at the Site and at any accommodation for
Contractor’s and Employer’s Personnel; and
(b) suitable arrangements are made for all necessary welfare and hygiene
GUIDANCE
The Contractor shall appoint a health and safety officer at the Site, responsible
for maintaining health, safety and protection against accidents. This officer shall:
the health and safety of all personnel authorised to enter and/or work
on the Site and to take protective measures to prevent accidents.
Throughout the execution of the Works, the Contractor shall provide whatever
is required by this person to exercise this responsibility and authority.
6.8
Contractor’s
Superintendence From the Commencement Date until the issue of the Performance Certificate,
the Contractor shall provide all necessary superintendence to plan, arrange,
direct, manage, inspect, test and monitor the execution of the Works.
(a) who are fluent in or have adequate knowledge of the language for
communications (defined in Sub-Clause 1.4 [Law and Language]); and
(b) who have adequate knowledge of the operations to be carried out
(including the methods and techniques required, the hazards likely to
be encountered and methods of preventing accidents),
6.9
Contractor’s Personnel The Contractor’s Personnel (including Key Personnel, if any) shall be
appropriately qualified, skilled, experienced and competent in their respective
trades or occupations.
The Engineer may require the Contractor to remove (or cause to be removed)
any person employed on the Site or Works, including the Contractor’s
Representative and Key Personnel (if any), who:
CONDITIONS
appointed) a suitable replacement. In the case of the replacement of the
GENERAL
Contractor’s Representative, Sub-Clause 4.3 [Contractor’s Representative]
shall apply. In the case of the replacement of Key Personnel (if any),
Sub-Clause 6.12 [Key Personnel] shall apply.
6.10
Contractor’s Records Unless otherwise proposed by the Contractor and agreed by the Engineer,
GUIDANCE
in each progress report under Sub-Clause 4.20 [Progress Reports], the
Contractor shall include records of:
FORMS
(c) the types of Temporary Works used;
(d) the types of Plant installed in the Permanent Works; and
(e) the quantities and types of Materials used
for each work activity shown in the Programme, at each work location and
for each day of work.
6.11
Disorderly Conduct The Contractor shall at all times take all necessary precautions to prevent
any unlawful, riotous or disorderly conduct by or amongst the Contractor’s
Personnel, and to preserve peace and protection of persons and property
on and near the Site.
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
6.12
Key Personnel If no Key Personnel are specified in the Employer’s Requirements this
Sub-Clause shall not apply.
The Contractor shall appoint the natural persons named in the Tender to the
positions of Key Personnel. If not so named, or if an appointed person fails
to act in the relevant position of Key Personnel, the Contractor shall submit
to the Engineer for consent the name and particulars of another person the
Contractor proposes to appoint to such position. If consent is withheld or
subsequently revoked, the Contractor shall similarly submit the name and
particulars of a suitable replacement for such position.
If the Engineer does not respond within 14 days after receiving any such
submission, by giving a Notice stating his/her objection to the appointment
of such person (or replacement) with reasons, the Engineer shall be deemed
to have given his/her consent.
The Contractor shall not, without the Engineer’s prior consent, revoke the
appointment of any of the Key Personnel or appoint a replacement (unless
the person is unable to act as a result of death, illness, disability or resignation,
in which case the appointment shall be deemed to have been revoked with
immediate effect and the appointment of a replacement shall be treated as
a temporary appointment until the Engineer gives his/her consent to this
replacement, or another replacement is appointed, under this Sub-Clause).
All Key Personnel shall be based at the Site (or, where Works are being
executed off the Site, at the location of the Works) for the whole time that the
Works are being executed. If any of the Key Personnel is to be temporarily
absent during execution of the Works, a suitable replacement shall be
temporarily appointed, subject to the Engineer’s prior consent.
7.1
7
Plant, Materials and Workmanship
GUIDANCE
Manner
of Execution The Contractor shall carry out the manufacture, supply, installation, testing
and commissioning and/or repair of Plant, the production, manufacture,
supply and testing of Materials, and all other operations and activities during
the execution of the Works:
7.2
Samples The Contractor shall submit the following samples of Materials, and relevant
information, to the Engineer for consent prior to using the Materials in or for
the Works:
Each sample shall be labelled as to origin and intended use in the Works.
7.3
Inspection The Employer’s Personnel shall, during all the normal working hours stated
in the Contract Data and at all other reasonable times:
(a) have full access to all parts of the Site and to all places from which
natural Materials are being obtained;
(b) during production, manufacture and construction (at the Site and
elsewhere), be entitled to:
(i) examine, inspect, measure and test (to the extent stated in the
Employer’s Requirements) the Materials, Plant and workmanship,
(ii) check the progress of manufacture of Plant and production and
manufacture of Materials, and
(iii) make records (including photographs and/or video recordings);
and
(c) carry out other duties and inspections, as specified in these Conditions
and the Employer’s Requirements.
The Contractor shall give the Employer’s Personnel full opportunity to carry
out these activities, including providing safe access, facilities, permissions
and safety equipment.
The Contractor shall give a Notice to the Engineer whenever any Materials,
Plant or work is ready for inspection, and before it is to be covered up, put
out of sight, or packaged for storage or transport. The Employer’s Personnel
shall then either carry out the examination, inspection, measurement or
CONDITIONS
Notice to the Contractor that the Employer’s Personnel do not require to do
GENERAL
so. If the Engineer gives no such Notice and/or the Employer’s Personnel do
not attend at the time stated in the Contractor’s Notice (or such time as may
be agreed with the Contractor), the Contractor may proceed with covering
up, putting out of sight or packaging for storage or transport.
GUIDANCE
the Contractor shall, if and when required by the Engineer, uncover the work
and thereafter reinstate and make good, all at the Contractor’s risk and cost.
7.4
Testing by the Contractor This Sub-Clause shall apply to all tests specified in the Contract, other than
the Tests after Completion (if any).
FORMS
The Contractor shall provide all apparatus, assistance, documents and
other information, temporary supplies of electricity and water, equipment,
fuel, consumables, instruments, labour, materials, and suitably qualified,
experienced and competent staff, as are necessary to carry out the specified
tests efficiently and properly. All apparatus, equipment and instruments shall
be calibrated in accordance with the standards specified in the Employer’s
Requirements or defined by applicable Laws and, if requested by the
Engineer, the Contractor shall submit calibration certificates before carrying
out testing.
The Contractor shall give a Notice to the Engineer, stating the time and place
for the specified testing of any Plant, Materials and other parts of the Works.
This Notice shall be given in reasonable time, having regard to the location
of the testing, for the Employer’s Personnel to attend.
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
The Engineer may, under Clause 13 [Variations and Adjustments], vary the
location or timing or details of specified tests, or instruct the Contractor
to carry out additional tests. If these varied or additional tests show that
the tested Plant, Materials or workmanship is not in accordance with the
Contract, the Cost and any delay incurred in carrying out this Variation shall
be borne by the Contractor.
The Engineer shall give a Notice to the Contractor of not less than 72 hours
of his/her intention to attend the tests. If the Engineer does not attend at
the time and place stated in the Contractor’s Notice under this Sub-Clause,
the Contractor may proceed with the tests, unless otherwise instructed
by the Engineer, which tests shall then be deemed to have been made in
the Engineer’s presence. If the Contractor suffers delay and/or incurs Cost
from complying with any such instruction or as a result of a delay for which
the Employer is responsible, the Contractor shall be entitled subject to
Sub-Clause 20.2 [Claims For Payment and/or EOT] to EOT and/or payment
of Cost Plus Profit.
The Contractor shall promptly forward to the Engineer duly certified reports
of the tests. When the specified tests have been passed, the Engineer shall
endorse the Contractor’s test certificate, or issue a test certificate to the
Contractor, to that effect. If the Engineer has not attended the tests, he/she
shall be deemed to have accepted the readings as accurate.
Plant, Materials and other parts of the Works fails to pass a specified test.
GENERAL
7.5
Defects and Rejection If, as a result of an examination, inspection, measurement or testing, any
Plant, Materials, design or workmanship is found to be defective or otherwise
not in accordance with the Contract, the Engineer shall give a Notice to the
Contractor describing the item of Plant, Materials, design or workmanship
GUIDANCE
that has been found to be defective. The Contractor shall then promptly
prepare and submit a proposal for necessary remedial work.
The Engineer may Review this proposal, and may give a Notice to the
Contractor stating the extent to which the proposed work, if carried out,
would not result in the Plant, Materials, design or workmanship complying
with the Contract. After receiving such a Notice the Contractor shall
FORMS
If the Contractor fails to promptly submit a proposal (or revised proposal) for
remedial work, or fails to carry out the proposed remedial work to which the
Engineer has given (or is deemed to have given) a Notice of No-objection,
the Engineer may:
7.6
Remedial Work In addition to any previous examination, inspection, measurement or testing,
or test certificate or Notice of No-objection by the Engineer, at any time
before the issue of the Taking-Over Certificate for the Works the Engineer
may instruct the Contractor to:
(a) repair or remedy (if necessary, off the Site), or remove from the Site
and replace any Plant or Materials which are not in accordance with
the Contract;
(b) repair or remedy, or remove and re-execute, any other work which is
not in accordance with the Contract; and
(c) carry out any remedial work which is urgently required for the safety
of the Works, whether because of an accident, unforeseeable event
or otherwise.
The Contractor shall comply with the instruction as soon as practicable and
not later than the time (if any) specified in the instruction, or immediately if
urgency is specified under sub-paragraph (c) above.
CONDITIONS
Sub-Clause, except to the extent that any work under sub-paragraph (c)
GENERAL
above is attributable to:
(i) any act by the Employer or the Employer’s Personnel. If the Contractor
suffers delay and/or incurs Cost in carrying out such work, the Contractor
shall be entitled subject to Sub-Clause 20.2 [Claims For Payment and/or
EOT] to EOT and/or payment of such Cost Plus Profit; or
GUIDANCE
(ii) an Exceptional Event, in which case Sub-Clause 18.4 [Consequences
of an Exceptional Event] shall apply.
If the Contractor fails to comply with the Engineer’s instruction, the Employer
may (at the Employer’s sole discretion) employ and pay other persons to
carry out the work. Except to the extent that the Contractor would have
been entitled to payment for work under this Sub-Clause, the Employer
FORMS
shall be entitled subject to Sub-Clause 20.2 [Claims For Payment and/or
EOT] to payment by the Contractor of all costs arising from this failure. This
entitlement shall be without prejudice to any other rights the Employer may
have, under the Contract or otherwise.
7.7
Ownership of Plant
and Materials Each item of Plant and Materials shall, to the extent consistent with the
mandatory requirements of the Laws of the Country, become the property of
the Employer at whichever is the earlier of the following times, free from liens
and other encumbrances:
7.8
Royalties Unless otherwise stated in the Employer’s Requirements, the Contractor
shall pay all royalties, rents and other payments for:
8.1
8
Commencement, Delays and Suspension
Commencement of Works The Engineer shall give a Notice to the Contractor stating the Commencement
Date, not less than 14 days before the Commencement Date. Unless
otherwise stated in the Particular Conditions, the Commencement Date shall
be within 42 days after the Contractor receives the Letter of Acceptance.
The Contractor shall commence the execution of the Works on, or as soon
as is reasonably practicable after, the Commencement Date and shall then
proceed with the Works with due expedition and without delay.
The Contractor shall complete the whole of the Works, each Section (if any),
GENERAL
and each Milestone, within the applicable Time for Completion for the Works,
Section and Milestone (as the case may be), including completion of all work
which is stated in the Contract as being required for the Works or Sections to be
considered to be completed for the purposes of taking over under Sub-Clause
10.1 [Taking Over the Works and Sections]. The Time for Completion shall be
subject to adjustments according to Sub-Clause 13.8.3 [Adjustment of Time for
GUIDANCE
Completion], if any.
The Completion Schedule shall demonstrate the Time for Completion of the
Milestones, based on the sequential logical links between the Milestones with
Times for Completion that are based on and consistent with the production
FORMS
rates provided by the Contractor in the Baseline Schedule for the Excavation
and Lining Works, and with the Times for Completion of the other Works.
The Schedule of Baselines sets out the anticipated activities or items of work for
the Excavation and Lining Works and their corresponding quantities consistent
with the conditions described in the GBR, corresponding to each drive and/
or other area of work within the Sections and/or Milestones in the Completion
Schedule.
8.3
Programme The Contractor shall submit an initial programme for the execution of the
Works to the Engineer within 28 days after receiving the Notice under
Sub-Clause 8.1 [Commencement of Works]. This initial programme
shall be consistent with the Completion Schedule and with the activities,
quantities and production rates stated in the Schedule of Baselines. This
programme shall be prepared to include the level of detail and using the
programming software stated in the Employer’s Requirements (if not stated,
the programming software acceptable to the Engineer). The Contractor
shall also submit a revised programme which accurately reflects the actual
progress of the Works, whenever any programme ceases to reflect actual
progress or is otherwise inconsistent with the Contractor’s obligations.
(a) the Commencement Date and the Time for Completion of the Works,
of each Section (if any) and any other Milestone;
(b) the date right of access to and possession of (each part of) the Site
is to be given to the Contractor in accordance with the time (or times)
CONDITIONS
requires the Employer to give right of access to and possession of
GENERAL
(each part of) the Site;
(c) the order in which the Contractor intends to carry out the Works,
including the anticipated timing of each stage of design, preparation
and submission of Contractor’s Documents, procurement, manufacture,
inspection, delivery to Site, construction, erection, installation, work to be
undertaken by any nominated Subcontractor (as defined in Clause 4.5
GUIDANCE
[Nominated Subcontractors]), testing, commissioning and trial operation;
(d) the Review periods under Sub-Clause 5.2.2 [Review by Engineer],
and periods for Review for any other submissions specified in the
Employer’s Requirements or required under these Conditions;
(e) the sequence and timing of inspections and tests specified in, or
required by, the Contract;
FORMS
(f) for a revised programme: the sequence and timing of the remedial
work (if any) to which the Engineer has given a Notice of No-objection
under Sub-Clause 7.5 [Defects and Rejection] and/or the remedial
work (if any) instructed under Sub-Clause 7.6 [Remedial Work];
(g) all activities (to the level of detail specified in the Employer’s
Requirements), logically linked and showing the earliest and latest
start and finish dates for each activity, the float (if any), and the critical
path(s);
(h) the dates of all locally recognised days of rest and holiday periods (if
any);
(i) all key delivery dates of Plant and Materials;
(j) for a revised programme and for each activity: the actual progress
to date, any delay to such progress and the effects of such delay on
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
The Engineer shall Review the initial programme and each revised programme
submitted by the Contractor and may give a Notice to the Contractor stating
the extent to which it does not comply with the Contract or ceases to reflect
actual progress or is otherwise inconsistent with the Contractor’s obligations.
If the Engineer gives no such Notice:
After the Engineer has (or is deemed to have) given a Notice of No-Objection
to the Contractor’s initial programme, the Programme shall be taken to
General Conditions © FIDIC & ITA 2019
55
have superseded the Completion Schedule and every reference in these
CONDITIONS
Programme”.
The Contractor shall proceed in accordance with the Programme, subject to the
Contractor’s other obligations under the Contract. The Employer’s Personnel
shall be entitled to rely on the Programme when planning their activities.
GUIDANCE
If, at any time, the Engineer gives a Notice to the Contractor that the
Programme fails (to the extent stated) to comply with the Contract or ceases
to reflect actual progress or is otherwise inconsistent with the Contractor’s
FORMS
obligations, the Contractor shall within 14 days after receiving this Notice
submit a revised programme to the Engineer in accordance with this
Sub-Clause.
8.4
Advance Warning Each Party shall advise the other and the Engineer, and the Engineer shall
advise the Parties, in advance of any known or probable future events or
circumstances which may:
8.5
Extension of Time
for Completion The Contractor shall be entitled subject to Sub-Clause 20.2 [Claims
For Payment and/or EOT] to Extension of Time if and to the extent that
completion for the purposes of Sub-Clause 10.1 [Taking Over the Works and
Sections] is or will be delayed by any of the following causes:
CONDITIONS
and/or EOT], the Engineer shall review previous determinations under
GENERAL
Sub-Clause 3.7 [Agreement or Determination] and may increase, but shall
not decrease, the total EOT.
GUIDANCE
accordance with the rules and procedures stated in the Special Provisions (if
not stated, as appropriate taking due regard of all relevant circumstances).
Notwithstanding the foregoing provisions of this Sub-Clause, any adjustment
to the Time for Completion arising out of the measurement of Excavation
and Lining Works shall be determined pursuant to Sub-Clause 13.8
[Measurement of Excavation and Lining Works and Adjustment of Time for
FORMS
Completion and Contract Price] only.
8.6
Delays Caused
by Authorities If:
(a) the Contractor has diligently followed the procedures laid down by the
relevant legally constituted public authorities or private utility entities in
the Country;
(b) these authorities or entities delay or disrupt the Contractor’s work;
and
(c) the delay or disruption was Unforeseeable,
then this delay or disruption will be considered as a cause of delay under
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
8.7
Rate of Progress If, at any time:
(a) actual progress is too slow to complete the Works, a Section, and/or
any Milestone within the relevant Time for Completion; and/or
(b) progress has fallen (or will fall) behind the Programme (or the initial
programme if it has not yet become the Programme) under Sub-Clause
8.3 [Programme],
other than as a result of a cause listed in Sub-Clause 8.5 [Extension of Time
for Completion], then the Engineer may instruct the Contractor to submit,
under Sub-Clause 8.3 [Programme], a revised programme describing
the revised methods which the Contractor proposes to adopt in order to
expedite progress and complete the Works, a Section and/or any Milestone
within the relevant Time for Completion.
Unless the Engineer gives a Notice to the Contractor stating otherwise, the
Contractor shall adopt these revised methods, which may require increases
in the working hours and/or in the numbers of Contractor’s Personnel and/or
the Goods, at the Contractor’s risk and cost. If these revised methods cause
the Employer to incur additional costs, the Employer shall be entitled subject
to Sub-Clause 20.2 [Claims For Payment and/or EOT] to payment of these
costs by the Contractor, in addition to Delay Damages (if any).
If the Contractor fails to comply with Sub-Clause 8.2 [Time for Completion],
GENERAL
not exceed the maximum amount of Delay Damages (if any) stated in the
Contract Data.
These Delay Damages shall be the only damages due from the Contractor for
the Contractor’s failure to comply with Sub-Clause 8.2 [Time for Completion],
other than in the event of termination under Sub-Clause 15.2 [Termination for
Contractor’s Default] before completion of the Works. These Delay Damages
FORMS
shall not relieve the Contractor from the obligation to complete the Works,
or from any other duties, obligations or responsibilities which the Contractor
may have under or in connection with the Contract.
This Sub-Clause shall not limit the Contractor’s liability for Delay Damages
in any case of fraud, gross negligence, deliberate default or reckless
misconduct by the Contractor.
8.9
Employer’s Suspension The Engineer may at any time instruct the Contractor to suspend progress
of part or all of the Works, which instruction shall state the date and cause
of the suspension.
During such suspension, the Contractor shall protect, store and secure such part
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
or all of the Works and the Contractor’s Key Equipment against any deterioration,
loss or damage.
To the extent that the cause of such suspension is the responsibility of the
Contractor, Sub-Clauses 8.10 [Consequences of Employer’s Suspension],
8.11 [Payment for Plant and Materials after Employer’s Suspension] and
8.12 [Prolonged Suspension] shall not apply.
8.10
Consequences of
Employer’s Suspension If the Contractor suffers delay and/or incurs Cost from complying with an
Engineer’s instruction under Sub-Clause 8.9 [Employer’s Suspension] and/
or from resuming the work under Sub-Clause 8.13 [Resumption of Work],
the Contractor shall be entitled subject to Sub-Clause 20.2 [Claims For
Payment and/or EOT] to EOT and/or payment of such Cost Plus Profit.
CONDITIONS
Payment for Plant and Materials
GENERAL
after Employer’s Suspension The Contractor shall be entitled to payment of the value (as at the date of
suspension instructed under Sub-Clause 8.9 [Employer’s Suspension]) of
Plant and/or Materials which have not been delivered to Site, if:
(a) the work on Plant, or delivery of Plant and/or Materials, has been
suspended for more than 28 days and
GUIDANCE
(i) the Plant and/or Materials were scheduled, in accordance with
the Programme, to have been completed and ready for delivery
to the Site during the suspension period; and
(ii) the Contractor provides the Engineer with reasonable evidence
that the Plant and/or Materials comply with the Contract; and
(b) the Contractor has marked the Plant and/or Materials as the
Employer’s property in accordance with the Engineer’s instructions.
FORMS
8.12
Prolonged Suspension If the suspension under Sub-Clause 8.9 [Employer’s Suspension] has
continued for more than 84 days, the Contractor may give a Notice to the
Engineer requesting permission to proceed.
If the Engineer does not give a Notice under Sub-Clause 8.13 [Resumption
of Work] within 28 days after receiving the Contractor’s Notice under this
Sub-Clause, the Contractor may either:
(a) agree to a further suspension, in which case the Parties may agree
the EOT and/or Cost Plus Profit (if the Contractor incurs Cost), and/or
payment for suspended Plant and/or Materials, arising from the total
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
period of suspension;
or (and if the Parties fail to reach agreement under this sub-paragraph (a))
(b) after giving a (second) Notice to the Engineer, treat the suspension
as an omission of the affected part of the Works (as if it had been
instructed under Sub-Clause 13.3.1 [Variation by Instruction])
with immediate effect including release from any further obligation
to protect, store and secure under Sub-Clause 8.9 [Employer’s
Suspension]. If the suspension affects the whole of the Works, the
Contractor may give a Notice of termination under Sub-Clause 16.2
[Termination by Contractor].
8.13
Resumption of Work The Contractor shall resume work as soon as practicable after receiving a
Notice from the Engineer to proceed with the suspended work.
At the time stated in this Notice (if not stated, immediately after the Contractor
receives this Notice), the Contractor and the Engineer shall jointly examine
the Works and the Plant and Materials affected by the suspension. The
Engineer shall record any deterioration, loss, damage or defect in the Works
or Plant or Materials which has occurred during the suspension and shall
provide this record to the Contractor. The Contractor shall promptly make
good all such deterioration, loss, damage or defect so that the Works, when
completed, shall comply with the Contract.
Tests on Completion
GENERAL
9.1
Contractor’s Obligations The Contractor shall carry out the Tests on Completion in accordance with
this Clause and Sub-Clause 7.4 [Testing by the Contractor], after submitting
the documents under Sub-Clause 5.6 [As-Built Records] and Sub-Clause
5.7 [Operation and Maintenance Manuals].
GUIDANCE
The Contractor shall submit to the Engineer, not less than 42 days before
the date the Contractor intends to commence the Tests on Completion,
a detailed test programme showing the intended timing and resources
required for these tests.
The Engineer may Review the proposed test programme and may give a Notice
FORMS
to the Contractor stating the extent to which it does not comply with the Contract.
Within 14 days after receiving this Notice, the Contractor shall revise the test
programme to rectify such non-compliance. If the Engineer gives no such Notice
within 14 days after receiving the test programme (or revised test programme), the
Engineer shall be deemed to have given a Notice of No-objection. The Contractor
shall not commence the Tests on Completion until a Notice of No-objection is
given (or is deemed to have been given) by the Engineer.
In addition to any date(s) shown in the test programme, the Contractor shall
give a Notice to the Engineer, of not less than 21 days, of the date after which
the Contractor will be ready to carry out each of the Tests on Completion.
The Contractor shall commence the Tests on Completion within 14 days
after this date, or on such day or days as the Engineer shall instruct, and
shall proceed in accordance with the Contractor’s test programme to which
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
the Engineer has given (or is deemed to have given) a Notice of No-objection.
(a) pre-commissioning tests (on or off the Site, as appropriate), which shall
include the appropriate inspections and (“dry” or “cold”) functional
tests to demonstrate that each item of the Works or Section can
safely undertake the next stage under sub-paragraph (b) below;
(b) commissioning tests, which shall include the operational tests
specified in the Employer’s Requirements to demonstrate that the
Works or Section can be operated safely and as specified in the
Employer’s Requirements, under all available operating conditions;
and
(c) trial operation (to the extent possible under available operating
conditions), which shall demonstrate that the Works or Section
perform reliably and in accordance with the Contract.
The tests of each stage described in sub-paragraphs (b) and (c) above shall not
be commenced until the Works or Section have passed the previous stage.
During trial operation, when the Works or Section (as the case may be) are
operating under stable conditions, the Contractor shall give a Notice to the
Engineer that they are ready for any other Tests on Completion, including
performance tests. Performance tests shall be carried out to demonstrate
whether the Works or Section comply with the performance criteria specified in
the Employer’s Requirements and with the Schedule of Performance Guarantees.
CONDITIONS
trial operation under this Sub-Clause shall be the property of the Employer.
GENERAL
As soon as the Works or Section have, in the Contractor’s opinion, passed
each stage of the Tests on Completion described in sub-paragraphs (a) to
(c) above, the Contractor shall submit a certified report of the results of these
tests to the Engineer. The Engineer shall Review each such report and may
give a Notice to the Contractor stating the extent to which the results of the
GUIDANCE
tests do not comply with the Contract. If the Engineer does not give such
a Notice within 14 days after receiving the results of the tests, the Engineer
shall be deemed to have given a Notice of No-objection.
FORMS
9.2
Delayed Tests If the Contractor has given a Notice under Sub-Clause 9.1 [Contractor’s
Obligations] that the Works or Section (as the case may be) are ready for
Tests on Completion, and these tests are unduly delayed by the Employer’s
Personnel or by a cause for which the Employer is responsible, Sub-Clause
10.3 [Interference with Tests on Completion] shall apply.
If the Tests on Completion are unduly delayed by the Contractor, the Engineer
may by giving a Notice to the Contractor require the Contractor to carry
out the tests within 21 days after receiving the Notice. The Contractor shall
carry out the tests on such day or days within this period of 21 days as the
Contractor may fix, for which the Contractor shall give a prior Notice to the
Engineer of not less than 7 days.
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
If the Contractor fails to carry out the Tests on Completion within this period
of 21 days:
(a) after a second Notice is given by the Engineer to the Contractor, the
Employer’s Personnel may proceed with the tests;
(b) the Contractor may attend and witness these tests;
(c) within 28 days of these tests being completed, the Engineer shall
send a copy of the test results to the Contractor; and
(d) if the Employer incurs additional costs as a result of such testing,
the Employer shall be entitled subject to Sub-Clause 20.2 [Claims
For Payment and/or EOT] to payment by the Contractor of the costs
reasonably incurred.
9.3
Retesting If the Works, or a Section, fail to pass the Tests on Completion, Sub-Clause
7.5 [Defects and Rejection] shall apply. The Engineer or the Contractor may
require these failed tests, and the Tests on Completion on any related work,
to be repeated under the same terms and conditions. Such repeated tests
shall be treated as Tests on Completion for the purposes of this Clause.
9.4
Failure to Pass Tests
on Completion If the Works, or a Section, fail to pass the Tests on Completion repeated
under Sub-Clause 9.3 [Retesting], the Engineer shall be entitled to:
General Conditions © FIDIC & ITA 2019
61
(a) order further repetition of Tests on Completion under Sub-Clause 9.3
CONDITIONS
[Retesting];
GENERAL
(b) reject the Works if the effect of the failure is to deprive the Employer
of substantially the whole benefit of the Works, in which event
the Employer shall have the same remedies as are provided in
sub-paragraph (d) of Sub-Clause 11.4 [Failure to Remedy Defects];
(c) reject the Section if the effect of the failure is that the Section cannot
be used for its intended purpose(s) under the Contract, in which
GUIDANCE
In the event of sub-paragraph (d) above, the Contractor shall then proceed in
accordance with all other obligations under the Contract, and the Employer
shall be entitled subject to Sub-Clause 20.2 [Claims For Payment and/or
FORMS
10.1
10
Employer’s Taking Over
Tests on Completion], the Works shall be taken over by the Employer when:
(a) the Works have been completed in accordance with the Contract,
including the passing of the Tests on Completion and except as
allowed in sub-paragraph (i) below;
(b) the Engineer has given (or is deemed to have given) a Notice of
No-objection to the as-built records submitted under sub-paragraph
(a) of Sub-Clause 5.6 [As-Built Records];
(c) the Engineer has given (or is deemed to have given) a Notice of
No-objection to the provisional O&M Manuals for the Works submitted
under Sub-Clause 5.7 [Operation and Maintenance Manuals];
(d) the Contractor has carried out the training (if any) as described under
Sub-Clause 5.5 [Training]; and
(e) a Taking-Over Certificate for the Works has been issued, or is deemed
to have been issued in accordance with this Sub-Clause.
If any Part of the Works is taken over under Sub-Clause 10.2 [Taking Over
Parts], the remaining Works or Section shall not be taken over until the
conditions described in sub-paragraphs (a) to (e) above have been fulfilled.
The Engineer shall, within 28 days after receiving the Contractor’s Notice, either:
(i) issue the Taking-Over Certificate to the Contractor, stating the date
on which the Works or Section were completed in accordance with
CONDITIONS
listed in the Taking-Over Certificate) which will not substantially affect
GENERAL
the safe use of the Works or Section for their intended purpose (either
until or whilst this work is completed and these defects are remedied);
or
(ii) reject the application by giving a Notice to the Contractor, with
reasons. This Notice shall specify the work required to be done, the
defects required to be remedied and/or the documents required to
GUIDANCE
be submitted by the Contractor to enable the Taking-Over Certificate
to be issued. The Contractor shall then complete this work, remedy
such defects and/or submit such documents before giving a further
Notice under this Sub-Clause.
If the Engineer does not issue the Taking-Over Certificate or reject the
Contractor’s application within this period of 28 days, and if the conditions
FORMS
described in sub-paragraphs (a) to (d) above have been fulfilled, the Works
or Section shall be deemed to have been completed in accordance with the
Contract on the fourteenth day after the Engineer receives the Contractor’s
Notice of application and the Taking-Over Certificate shall be deemed to
have been issued.
10.2
Taking Over Parts The Engineer may, at the sole discretion of the Employer, issue a Taking-Over
Certificate for any part of the Permanent Works.
The Employer shall not use any part of the Works (other than as a temporary
measure, which is either specified in the Employer’s Requirements or with the
prior agreement of the Contractor) unless and until the Engineer has issued a
Taking-Over Certificate for this part. However, if the Employer does use any
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
part of the Works before the Taking-Over Certificate is issued the Contractor
shall give a Notice to the Engineer identifying such part and describing such
use, and:
(a) that Part shall be deemed to have been taken over by the Employer
as from the date on which it is used;
(b) the Contractor shall cease to be liable for the care of such Part as
from this date, when responsibility shall pass to the Employer; and
(c) the Engineer shall immediately issue a Taking-Over Certificate for this
Part, and any outstanding work to be completed (including Tests
on Completion) and/or defects to be remedied shall be listed in this
certificate.
After the Engineer has issued a Taking-Over Certificate for a Part, the
Contractor shall be given the earliest opportunity to take such steps as
may be necessary to carry out the outstanding work (including Tests on
Completion) and/or remedial work for any defects listed in the certificate.
The Contractor shall carry out these works as soon as practicable and, in
any case, before the expiry date of the relevant DNP.
If the Contractor incurs Cost as a result of the Employer taking over and/
or using a Part, the Contractor shall be entitled subject to Sub-Clause 20.2
[Claims For Payment and/or EOT] to payment of such Cost Plus Profit.
If the Engineer issues a Taking-Over Certificate for any part of the Works, or
if the Employer is deemed to have taken over a Part under sub-paragraph (a)
above, for any period of delay after the date under sub-paragraph (a) above,
the Delay Damages for completion of the remainder of the Works shall be
reduced. Similarly, the Delay Damages for the remainder of the Section (if
shall be calculated as the proportion which the value of the Part (except
GENERAL
10.3
Interference with
Tests on Completion If the Contractor is prevented, for more than 14 days (either a continuous
FORMS
period, or multiple periods which total more than 14 days), from carrying
out the Tests on Completion by the Employer’s Personnel or by a cause for
which the Employer is responsible (including any performance test that is not
possible due to available operating conditions during trial operation):
(a) the Contractor shall give a Notice to the Engineer describing such
prevention;
(b) the Employer shall be deemed to have taken over the Works or Section
(as the case may be) on the date when the Tests on Completion would
otherwise have been completed; and
(c) the Engineer shall immediately issue a Taking-Over Certificate for the
Works or Section (as the case may be).
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
After the Engineer has issued this Taking-Over Certificate, the Contractor
shall carry out the Tests on Completion as soon as practicable and, in any
case, before the expiry date of the DNP. The Engineer shall give a Notice to
the Contractor, of not less than 14 days, of the date after which the Contractor
may carry out each of the Tests on Completion. Thereafter, Sub-Clause 9.1
[Contractor’s Obligations] shall apply.
10.4
Surfaces Requiring
Reinstatement Except as otherwise stated in the Taking-Over Certificate, a certificate for a
Section or Part of the Works shall not be deemed to certify completion of
any ground or other surfaces requiring reinstatement.
11.1
11
Defects after Taking Over
CONDITIONS
Completion, within the time(s) stated in the Taking-Over Certificate or
GENERAL
such other reasonable time as is instructed by the Engineer; and
(b) execute all work required to remedy defects or damage, of which a
Notice is given to the Contractor by (or on behalf of) the Employer on
or before the expiry date of the DNP for the Works or Section or Part
(as the case may be).
GUIDANCE
If a defect appears or damage occurs during the relevant DNP, a Notice shall
be given to the Contractor accordingly, by (or on behalf of) the Employer.
Promptly thereafter:
(i) the Contractor and the Employer’s Personnel shall jointly inspect the
defect or damage;
(ii) the Contractor shall then prepare and submit a proposal for necessary
FORMS
remedial work; and
(iii) the second, third and fourth paragraphs of Sub-Clause 7.5 [Defects
and Rejection] shall apply.
11.2
Cost of Remedying
Defects All work under sub-paragraph (b) of Sub-Clause 11.1 [Completion of
Outstanding Work and Remedying Defects] shall be executed at the risk and
cost of the Contractor, if and to the extent that the work is attributable to:
(a) the design of the Works, other than a part of the design for which the
Employer is responsible (if any);
(b) Plant, Materials or workmanship not being in accordance with the
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
Contract;
(c) improper operation or maintenance which was attributable to matters
for which the Contractor is responsible (under Sub-Clause 5.5
[Training], Sub-Clause 5.6 [As-Built Records] and/or Sub-Clause 5.7
[Operation and Maintenance Manuals] or otherwise); or
(d) failure by the Contractor to comply with any other obligation under the
Contract.
If the Contractor considers that the work is attributable to any other cause,
the Contractor shall promptly give a Notice to the Engineer and the Engineer
shall proceed under Sub-Clause 3.7 [Agreement or Determination] to agree
or determine the cause (and, for the purpose of Sub-Clause 3.7.3 [Time
limits], the date of this Notice shall be the date of commencement of the time
limit for agreement under Sub-Clause 3.7.3). If it is agreed or determined
that the work is attributable to a cause other than those listed above,
Sub-Clause 13.3.1 [Variation by Instruction] shall apply as if such work had
been instructed by the Engineer.
11.3
Extension of Defects
Notification Period The Employer shall be entitled to an extension of the DNP for the Works, or
a Section or a Part:
(a) if and to the extent that the Works, Section, Part or a major item of
Plant (as the case may be, and after taking over) cannot be used for
the intended purpose(s) by reason of a defect or damage which is
attributable to any of the matters under sub-paragraphs (a) to (d) of
Sub-Clause 11.2 [Cost of Remedying Defects]; and
However, a DNP shall not be extended by more than a period of two years
after the expiry of the DNP stated in the Contract Data.
by Contractor], the Contractor’s obligations under this Clause shall not apply to any
defects or damage occurring more than two years after the DNP for the Works, of
which the Plant and/or Materials form part, would otherwise have expired.
11.4
Failure to Remedy Defects If the remedying of any defect or damage under Sub-Clause 11.1 [Completion
of Outstanding Works and Remedying Defects] is unduly delayed by the
FORMS
If the Contractor fails to remedy the defect or damage by the date stated
in this Notice and this remedial work was to be executed at the cost of
the Contractor under Sub-Clause 11.2 [Cost of Remedying Defects], the
Employer may (at the Employer’s sole discretion):
(a) carry out the work or have the work carried out by others (including
any retesting), in the manner required under the Contract and at the
Contractor’s cost, but the Contractor shall have no responsibility for
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
CONDITIONS
above shall be without prejudice to any other rights the Employer may have,
GENERAL
under the Contract or otherwise.
11.5
Remedying of Defective
Work off Site If, during the DNP, the Contractor considers that any defect or damage in
any Plant cannot be remedied expeditiously on the Site the Contractor shall
GUIDANCE
give a Notice, with reasons, to the Employer requesting consent to remove
the defective or damaged Plant off the Site for the purposes of repair. This
Notice shall clearly identify each item of defective or damaged Plant, and
shall give details of:
FORMS
repair;
(c) the transportation to be used (and insurance cover for such
transportation);
(d) the proposed inspections and testing off the Site;
(e) the planned duration required before the repaired Plant shall be
returned to the Site; and
(f) the planned duration for reinstallation and retesting of the repaired
Plant (under Sub-Clause 7.4 [Testing by the Contractor] and/or
Clause 9 [Tests on Completion] if applicable).
The Contractor shall also provide any further details that the Employer may
reasonably require.
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
When the Employer gives consent (which consent shall not relieve the
Contractor from any obligation or responsibility under this Clause), the
Contractor may remove from the Site such items of Plant as are defective
or damaged. As a condition of this consent, the Employer may require the
Contractor to increase the amount of the Performance Security by the full
replacement cost of the defective or damaged Plant.
11.6
Further Tests after
Remedying Defects Within 7 days of completion of the work of remedying of any defect or
damage, the Contractor shall give a Notice to the Engineer describing the
remedied Works, Section, Part and/or Plant and the proposed repeated tests
(under Clause 9 [Tests on Completion] or Clause 12 [Tests after Completion],
as applicable).
Within 7 days after receiving this Contractor’s Notice, the Engineer shall give
a Notice to the Contractor either:
If the Contractor fails to give such a Notice within the 7 days, the Engineer
may give a Notice to the Contractor, within 14 days after the defect or
damage is remedied, instructing the repeated tests that are necessary to
demonstrate that the remedied Works, Section, Part and/or Plant comply
with the Contract.
with the terms applicable to the previous tests, except that they shall be
GENERAL
carried out at the risk and cost of the Party liable, under Sub-Clause 11.2
[Cost of Remedying Defects], for the cost of the remedial work.
11.7
Right of Access
after Taking Over Until the date 28 days after issue of the Performance Certificate, the
GUIDANCE
Contractor shall have the right of access to all parts of the Works and to
records of the operation, maintenance and performance of the Works,
except as may be inconsistent with the Employer’s reasonable security
restrictions.
Whenever the Contractor intends to access any part of the Works or such
records during the relevant DNP:
FORMS
(a) the Contractor shall request access by giving a Notice to the Employer,
describing the parts of the Works and/or records to be accessed,
the reasons for such access, and the Contractor’s preferred date
for access. This Notice shall be given in reasonable time in advance
of the preferred date for access, taking due regard of all relevant
circumstances including the Employer’s security restrictions; and
(b) within 7 days after receiving the Contractor’s Notice, the Employer
shall give a Notice to the Contractor either:
(i) stating the Employer’s consent to the Contractor’s request; or
(ii) proposing reasonable alternative date(s), with reasons. If the
Employer fails to give this Notice within the 7 days, the Employer
shall be deemed to have given consent to the Contractor’s
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
11.8
Contractor to Search The Contractor shall, if instructed by the Engineer, search for the cause of
any defect, under the direction of the Engineer. The Contractor shall carry
out the search on the date(s) stated in the Engineer’s instruction or other
date(s) agreed with the Engineer.
If the Contractor fails to carry out the search in accordance with this
Sub-Clause, the search may be carried out by the Employer’s Personnel.
The Contractor shall be given a Notice of the date when such a search will
be carried out and the Contractor may attend at the Contractor’s own cost. If
the defect is to be remedied at the cost of the Contractor under Sub-Clause
11.2 [Cost of Remedying Defects], the Employer shall be entitled subject
to Sub-Clause 20.2 [Claims For Payment and/or EOT] to payment by the
Contractor of the costs of the search reasonably incurred by the Employer.
CONDITIONS
Performance Certificate Performance of the Contractor’s obligations under the Contract shall not
GENERAL
be considered to have been completed until the Engineer has issued the
Performance Certificate to the Contractor, stating the date on which the
Contractor fulfilled the Contractor’s obligations under the Contract.
The Engineer shall issue the Performance Certificate to the Contractor (with
a copy to the Employer and to the DAAB) within 28 days after the latest of
GUIDANCE
the expiry dates of the Defects Notification Periods, or as soon thereafter as
the Contractor has:
(a) supplied all the Contractor’s Documents, and the Engineer has
given (or is deemed to have given) a Notice of No-objection to the
as-built records under sub-paragraph (b) of Sub-Clause 5.6 [As-Built
Records]; and
FORMS
(b) completed and tested all the Works (including remedying any defects)
in accordance with the Contract.
If the Engineer fails to issue the Performance Certificate within this period of
28 days, the Performance Certificate shall be deemed to have been issued
on the date 28 days after the date on which it should have been issued, as
required by this Sub-Clause.
11.10
Unfulfilled Obligations After the issue of the Performance Certificate, each Party shall remain liable
for the fulfilment of any obligation which remains unperformed at that time.
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
However in relation to Plant, the Contractor shall not be liable for any defects
or damage occurring more than two years after expiry of the DNP for the
Plant except if prohibited by law or in any case of fraud, gross negligence,
deliberate default or reckless misconduct.
11.11
Clearance of Site Promptly after the issue of the Performance Certificate, the Contractor shall:
If the Contractor fails to comply with sub-paragraphs (a), (b) and/or (c) above
within 28 days after the issue of the Performance Certificate, the Employer
may sell (to the extent permitted by applicable Laws) or otherwise dispose
of any remaining items and/or may reinstate and clean the Site (as may be
necessary) at the Contractor’s cost.
12.1
Procedure for Tests
after Completion If Tests after Completion are specified in the Employer’s Requirements, this
Clause shall apply.
GUIDANCE
(a) provide all electricity, water, sewage (if applicable), equipment, fuel,
consumables, instruments, labour, materials, and suitably qualified,
experienced and competent staff, as are necessary to carry out the
Tests after Completion efficiently and properly; and
(b) carry out the Tests after Completion in accordance with:
FORMS
The timing of the Tests after Completion shall be as stated in the Employer’s
Requirements (if not stated, as soon as is reasonably practicable) after
the Works or Section (as the case may be) have been taken over under
Clause 10 [Employer’s Taking Over]. The Engineer shall give a Notice to the
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
Contractor, of not less than 21 days, of the date on which and place at which
the Tests after Completion will be carried out. This Notice shall also include a
test programme showing the estimated timing for each of such tests. Unless
otherwise agreed with the Contractor, these tests shall be carried out on this
date.
If the Contractor does not attend at the time and place stated in the Engineer’s
Notice (or otherwise agreed with the Contractor), the Employer may proceed
with the Tests after Completion, which shall be deemed to have been made
in the Contractor’s presence, and the Contractor shall be deemed to have
accepted the readings as accurate.
The results of the Tests after Completion shall be compiled and evaluated
by both Parties. Appropriate account shall be taken of the effect of the
Employer’s prior use of the Works.
12.2
Delayed Tests If the Contractor incurs Cost as a result of any unreasonable delay by the
Employer in carrying out the Tests after Completion, the Contractor shall be
entitled subject to Sub-Clause 20.2 [Claims For Payment and/or EOT] to
payment of such Cost Plus Profit.
If, for reasons not attributable to the Contractor, a Test after Completion on
the Works or any Section cannot be completed during the DNP (or any other
period agreed by both Parties), then the Works or Section shall be deemed
to have passed this Test after Completion.
CONDITIONS
Retesting Subject to Sub-Clause 12.4 [Failure to Pass Tests after Completion], if the
GENERAL
Works, or a Section, fail to pass the Tests after Completion:
GUIDANCE
If and to the extent that this failure and retesting are attributable to any of
the matters listed in sub-paragraphs (a) to (d) of Sub-Clause 11.2 [Cost of
Remedying Defects] and cause the Employer to incur additional costs, the
Employer shall be entitled subject to Sub-Clause 20.2 [Claims For Payment
and/or EOT] to payment of these costs by the Contractor.
FORMS
12.4
Failure to Pass Tests
after Completion If:
(a) the Works, or a Section, fail to pass any or all of the Tests after
Completion; and
(b) applicable Performance Damages are set out in the Schedule of
Performance Guarantees
the Employer shall be entitled subject to Sub-Clause 20.2 [Claims For
Payment and/or EOT] to payment of these Performance Damages by the
Contractor in full satisfaction of this failure. If the Contractor pays these
Performance Damages to the Employer during the DNP, then the Works or
Section shall be deemed to have passed these Tests after Completion.
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
If the Works, or a Section, fail to pass a Test after Completion and, by giving
a Notice to the Employer, the Contractor proposes to make adjustments or
modifications to the Works or such Section (including an item of Plant):
13.1
Right to Vary Variations may be initiated by the Engineer under Sub-Clause 13.3 [Variation
Procedure] at any time before the issue of the Taking-Over Certificate for the
Works.
GUIDANCE
(a) the varied work was Unforeseeable having regard to the scope and
nature of the Works described in the Employer’s Requirements;
(b) the Contractor cannot readily obtain the Goods required for the
Variation;
(c) it will adversely affect the Contractor’s ability to comply with
Sub-Clause 4.8 [Health and Safety Obligations] and/or Sub-Clause
4.18 [Protection of the Environment];
(d) it will have an adverse impact on the achievement of the Schedule of
Performance Guarantees; or
(e) it may adversely affect the Contractor’s obligation to complete the
Works so that they shall be fit for the purpose(s) for which they are
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
Promptly after receiving this Notice, the Engineer shall respond by giving a
Notice to the Contractor cancelling, confirming or varying the instruction.
Any instruction so confirmed or varied shall be taken as an instruction under
Sub-Clause 13.3.1 [Variation by instruction].
13.2
Value Engineering The Contractor may, at any time, submit to the Engineer a written proposal
which (in the Contractor’s opinion) will, if adopted:
The proposal shall be prepared at the cost of the Contractor and shall
include the details as stated in sub-paragraphs (a) to (c) of Sub-Clause
13.3.1 [Variation by Instruction].
CONDITIONS
comments, the Engineer shall then instruct a Variation. Thereafter:
GENERAL
(i) the Contractor shall submit any further particulars that the Engineer
may reasonably require; and
(ii) then the third paragraph of Sub-Clause 13.3.1 [Variation by Instruction]
shall apply, which shall include consideration by the Engineer of the
sharing (if any) of the benefit, costs and/or delay between the Parties
GUIDANCE
stated in the Particular Conditions.
13.3
Variation Procedure Subject to Sub-Clause 13.1 [Right to Vary], Variations shall be initiated by the
Engineer in accordance with either of the following procedures:
FORMS
The Engineer may instruct a Variation by giving a Notice (describing the
required change and stating any requirements for the recording of Costs) to
the Contractor in accordance with Sub-Clause 3.5 [Engineer’s Instructions].
The Contractor shall proceed with execution of the Variation and shall, within
28 days (or other period proposed by the Contractor and agreed by the
Engineer) of receiving the Engineer’s instruction, submit to the Engineer
detailed particulars including:
time limit for agreement under Sub-Clause 3.7.3). The Contractor shall be
GENERAL
entitled to such EOT and/or adjustments to the Contract Price, without any
requirement to comply with Sub-Clause 20.2 [Claims For Payment and/or
EOT].
For each item of work forming part (or all) of a Variation, the appropriate rate
or price for the item shall be the rate or price specified for such item in the
Schedule of Rates and Prices or, if there is no such item, the rate or price
specified for similar work. However, a new rate or price shall be appropriate
for an item of work if no rate or price for this item is specified in the Schedule
of Rates and Prices and no specified rate or price is appropriate because
FORMS
the item of work is not of similar character, or is not executed under similar
conditions, as any item in the Contract.
Each new rate or price shall be derived from any relevant rates or prices
in the Schedule of Rates and Prices, with reasonable adjustments taking
account of all relevant circumstances. If no rates or prices are relevant for the
derivation of a new rate or price, it shall be derived from the Cost Plus Profit
of executing the work.
Until such time as the adjustments under sub-paragraph (ii) above are
agreed or determined, the Engineer shall assess a provisional rate or price
for the purposes of Interim Payment Certificates.
If the Engineer does not give consent to the proposal, with or without
comments, and if the Contractor has incurred Cost as a result of submitting
it, the Contractor shall be entitled subject to Sub-Clause 20.2 [Claims For
Payment and/or EOT] to payment of such Cost.
CONDITIONS
Provisional Sums Each Provisional Sum shall only be used, in whole or in part, in accordance
GENERAL
with the Engineer’s instructions, and the Contract Price shall be adjusted
accordingly. The total sum paid to the Contractor shall include only such
amounts for the work, supplies or services to which the Provisional Sum
relates, as the Engineer shall have instructed.
GUIDANCE
(a) work to be executed (including Plant, Materials or services to be
supplied) by the Contractor, and for which adjustments to the
Contract Price and the Schedule of Payments (if any) shall be agreed
or determined under Sub-Clause 13.3.1 [Variation by Instruction];
and/or
(b) Plant, Materials, works or services to be purchased by the Contractor,
FORMS
from a nominated Subcontractor (as defined in Sub-Clause 4.5
[Nominated Subcontractors]) or otherwise, and for which there shall
be included in the Contract Price:
(i) the actual amounts paid (or due to be paid) by the Contractor;
and
(ii) a sum for overhead charges and profit, calculated as a percentage
of these actual amounts by applying the relevant percentage rate
(if any) stated in the applicable Schedule. If there is no such rate,
the percentage rate stated in the Contract Data shall be applied.
all (or some) of the items of the work to be executed or Plant, Materials,
works or services to be purchased. Thereafter, the Engineer may respond
by giving a Notice either instructing the Contractor to accept one of these
quotations (but such an instruction shall not be taken as an instruction under
Sub-Clause 4.5 [Nominated Subcontractors]) or revoking the instruction. If
the Engineer does not so respond within 7 days of receiving the quotations,
the Contractor shall be entitled to accept any of these quotations at the
Contractor’s discretion.
Each Statement that includes a Provisional Sum shall also include all
applicable invoices, vouchers and accounts or receipts in substantiation of
the Provisional Sum.
13.5
Daywork If a Daywork Schedule is not included in the Contract, this Sub-Clause shall
not apply.
For work of a minor or incidental nature, the Engineer may instruct that a
Variation shall be executed on a daywork basis. The work shall then be valued
in accordance with the Daywork Schedule, and the following procedure shall
apply.
Before ordering Goods for such work (other than any Goods priced in the
Daywork Schedule), the Contractor shall submit one or more quotations from
the Contractor’s suppliers and/or subcontractors to the Engineer. Thereafter,
the Engineer may instruct the Contractor to accept one of these quotations
(but such an instruction shall not be taken as an instruction under Sub-Clause
4.5 [Nominated Subcontractors]). If the Engineer does not so instruct the
Contractor within 7 days of receiving the quotations, the Contractor shall be
entitled to accept any of these quotations at the Contractor’s discretion.
is not due, the Contractor shall deliver each day to the Engineer accurate
GENERAL
One copy of each statement shall, if correct and agreed, be signed by the
Engineer and promptly returned to the Contractor. If not correct or agreed, the
GUIDANCE
In the next Statement, the Contractor shall then submit priced statements
FORMS
Unless otherwise stated in the Daywork Schedule, the rates and prices in
the Daywork Schedule shall be deemed to include taxes, overheads and
profit.
13.6
Adjustments for
Changes in Laws Subject to the following provisions of this Sub-Clause, the Contract Price
shall be adjusted to take account of any increase or decrease in Cost
resulting from a change in:
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
(a) the Laws of the Country (including the introduction of new Laws and
the repeal or modification of existing Laws);
(b) the judicial or official governmental interpretation or implementation of
the Laws referred to in sub-paragraph (a) above;
(c) any permit, permission, license or approval obtained by the Employer
or the Contractor under sub-paragraph (a) or (b), respectively, of
Sub-Clause 1.13 [Compliance with Laws]; or
(d) the requirements for any permit, permission, licence and/or approval
to be obtained by the Contractor under sub-paragraph (b) of
Sub-Clause 1.13 [Compliance with Laws],
made and/or officially published after the Base Date, which affect the
Contractor in the performance of obligations under the Contract. In
this Sub-Clause “change in Laws” means any of the changes under
sub-paragraphs (a), (b), (c) and/or (d) above.
CONDITIONS
(ii) the Engineer shall promptly give a Notice to the Contractor
GENERAL
(with detailed supporting particulars).
GUIDANCE
13.7
Adjustments for
Changes in Cost If Schedule(s) of cost indexation are not included in the Contract, this
Sub-Clause shall not apply.
The amounts payable to the Contractor shall be adjusted for rises or falls in
FORMS
the cost of labour, Goods and other inputs to the Works, by the addition or
deduction of the amounts calculated in accordance with the Schedule(s) of
cost indexation.
To the extent that full compensation for any rise or fall in Costs is not covered
by this Sub-Clause or other Clauses of these Conditions, the Accepted
Contract Amount shall be deemed to have included amounts to cover the
contingency of other rises and falls in costs.
Until such time as each current cost index is available, the Engineer shall use a
provisional index for the issue of Interim Payment Certificates. When a current
cost index is available, the adjustment shall be recalculated accordingly.
If the Contractor fails to complete the Works within the Time for Completion,
adjustment of prices thereafter shall be made using either:
(a) each index or price applicable on the date 49 days before the expiry
of the Time for Completion of the Works; or
(b) the current index or price
whichever is more favourable to the Employer.
13.8
Measurement of Excavation and
Lining Works and Adjustment of
Time for Completion and
Contract Price Unless otherwise stated in the Contract, only the Excavation and Lining Works
shall be subject to measurement, and the Accepted Contract Amount shall
be deemed to cover all other Underground Works and all things necessary
for the proper execution and completion thereof in accordance with the
Contract.
The Contract Price and Time for Completion shall be adjusted following
such measurement, and the Parties shall be entitled to such adjustments
without the need to submit a Statement or any formal Notice (including any
requirement to comply with Sub-Clause 20.2 [Claims For Payment and/or
Extension of Time]).
The method of measurement for the Schedule of Baselines and for the Bill of
Quantities shall be as stated in the Contract Data.
FORMS
After receiving the measurement records, the Engineer shall proceed under
Sub-Clause 3.7 [Agreement or Determination] to agree or determine the
measurement, and, for the purpose of Sub-Clause 3.7.3 [Time limit], the
date when the Engineer receives the measurement records shall be the date
of commencement of the time limit under Sub-Clause 3.7.3 [Time limit].
The Bill of Quantities sets out the quantities, units of measurement and
applicable unit rates and prices for all Excavation and Lining Works.
CONDITIONS
availability and maintenance of the fixed rate items in sub-paragraph
GENERAL
(a) above, all expressed, unless otherwise specified, in units for an
extension or reduction for a calendar day.
(c) Quantity-related rate items for the Excavation and Lining Works, and
Plant supply and installation for the relevant portion of the Works.
(d) Unless provided otherwise in the Particular Conditions, value-related
charges for compliance with contractual provisions such as, without
GUIDANCE
limitation, insurance, securities, permits and levies for the relevant
portion of the Excavation and Lining Works, shall be included as
percentage additions in the rates described in (a), (b) and/or (c) above.
The unit rates and prices referred to in this Sub-Clause 13.8.2 [Bill of
Quantities for Excavation and Lining Works] shall not vary with changes in
measured quantities and shall be deemed to cover the entire remuneration
FORMS
of the Contractor for such Excavation and Lining Works.
Based on this reassessment, and if and to the extent that the Time for
Completion of the Works, Section or other Milestone is or will be impacted,
an adjustment (reduction or extension) shall be calculated for such Time
for Completion based only on the logical sequential links provided in the
Completion Schedule and/or the Programme, as the case may be.
(a) by valuing each item of the Excavation and Lining Works by applying the
measurement agreed or determined in accordance with Sub-Clause
13.8.1 [Responsibility for Measurement], and the appropriate rate or
price for the item in the Bill of Quantities; and
(b) by applying the rates for time-related rate items in the Bill of Quantities
to the adjusted Time for Completion under Sub-Clause 13.8.3
[Adjustment of Time for Completion].
14.1
The Contract Price
14
Contract Price and Payment
(a) the Contract Price shall be the Accepted Contract Amount and be
subject to adjustments, additions (including Cost or Cost Plus Profit
to which the Contractor is entitled under these Conditions) and/or
deductions in accordance with the Contract;
by the Contractor under the Contract, and the Contract Price shall not
GENERAL
(d) any quantities or production rates or price data which may be set out
in the Bill of Quantities or in the Schedule of Baselines or in any other
Schedule shall be used for the purposes stated in the Schedule and
may be inapplicable for other purposes.
14.2
Advance Payment If no amount of advance payment is stated in the Contract Data, this
Sub-Clause shall not apply.
After receiving the Advance Payment Certificate, the Employer shall make an
advance payment, as an interest-free loan for mobilisation and design. The
amount of the advance payment and the currencies in which it is to be paid
shall be as stated in the Contract Data.
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
The Contractor shall obtain (at the Contractor’s cost) an Advance Payment
Guarantee in amounts and currencies equal to the advance payment, and
shall submit it to the Employer with a copy to the Engineer. This guarantee
shall be issued by an entity and from within a country (or other jurisdiction)
to which the Employer gives consent, and shall be in the form annexed to
the Particular Conditions or on another form agreed by the Employer (but
such consent and/or agreement shall not relieve the Contractor from any
obligation under this Sub-Clause).
The Contractor shall ensure that the Advance Payment Guarantee is valid
and enforceable until the advance payment has been repaid, but its amount
may be progressively reduced by the amount repaid by the Contractor as
stated in the Payment Certificates.
If the terms of the Advance Payment Guarantee specify its expiry date, and
the advance payment has not been repaid by the date 28 days before the
expiry date:
(a) the Contractor shall extend the validity of this guarantee until the
advance payment has been repaid;
(b) the Contractor shall immediately submit evidence of this extension to
the Employer, with a copy to the Engineer; and
(c) if the Employer does not receive this evidence 7 days before the
expiry date of this guarantee, the Employer shall be entitled to claim
under the guarantee the amount of advance payment which has not
been repaid.
CONDITIONS
include an application (in the form of a Statement) for the advance payment.
GENERAL
14.2.2 Advance Payment Certificate
The Engineer shall issue an Advance Payment Certificate for the advance
payment within 14 days after:
GUIDANCE
(a) the Employer has received both the Performance Security and the
Advance Payment Guarantee, in the form and issued by an entity
in accordance with Sub-Clause 4.2.1 [Contractor’s Obligations] and
Sub-Clause 14.2.1 [Advance Payment Guarantee] respectively; and
(b) the Engineer has received a copy of the Contractor’s application for
the advance payment under Sub-Clause 14.2.1 [Advance Payment
Guarantee].
FORMS
14.2.3 Repayment of Advance Payment
(a) deductions shall commence in the IPC in which the total of all certified
interim payments in the same currency as the advance payment
(excluding the advance payment and deductions and release of
retention moneys) exceeds ten percent (10%) of the portion of the
Accepted Contract Amount payable in that currency less Provisional
Sums; and
(b) deductions shall be made at the amortisation rate of one quarter
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
If the advance payment has not been repaid before the issue of the
Taking-Over Certificate for the Works, or before termination under Clause
15 [Termination by Employer], Clause 16 [Suspension and Termination by
Contractor] or Clause 18 [Exceptional Events] (as the case may be), the
whole of the balance then outstanding shall immediately become due and
payable by the Contractor to the Employer.
14.3
Application for
Interim Payment The Contractor shall submit a Statement to the Engineer after the end of the
period of payment stated in the Contract Data (if not stated, after the end of
each month). Each Statement shall:
The Statement shall include the following items, as applicable, which shall be
expressed in the various currencies in which the Contract Price is payable, in
the sequence listed:
General Conditions © FIDIC & ITA 2019
81
(i) the estimated contract value of the Works executed, and the
CONDITIONS
(v) any amounts to be added and/or deducted for the advance payment
and repayments under Sub-Clause 14.2 [Advance Payment];
(vi) any amounts to be added and/or deducted for Plant and Materials
under Sub-Clause 14.5 [Plant and Materials intended for the Works];
(vii) any other additions and/or deductions which have become due under
the Contract or otherwise, including those under Sub-Clause 3.7
[Agreement or Determination];
(viii) any amounts to be added for Provisional Sums under Sub-Clause
13.4 [Provisional Sums];
(ix) any amount to be added for release of Retention Money under
Sub-Clause 14.9 [Release of Retention Money];
(x) any amount to be deducted for the Contractor’s use of utilities provided
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
14.4
Schedule of Payments If the Contract includes a Schedule of Payments specifying the instalments
in which the Contract Price will be paid then, unless otherwise stated in this
Schedule:
The Schedule of Payments shall include, as applicable, payments due
on completion of Milestones and other payments consistent with the
corresponding data in the Schedule of Rates and Prices, the Schedule of
82 © FIDIC & ITA 2019 Conditions of Contract for Underground Works
Baselines, the Completion Schedule and/or the Programme, and in the
CONDITIONS
method of measurement pursuant to Sub-Clause 13.8.2 [Bill of Quantities
GENERAL
for Excavation and Lining Works].
GUIDANCE
estimates shall be submitted at intervals of 3 months, until the issue of the
Taking-Over Certificate for the Works.
14.5
Plant and Materials
intended for the Works If no Plant and/or Materials are listed in the Contract Data for payment when
shipped and/or payment when delivered, this Sub-Clause shall not apply.
FORMS
The Contractor shall include, under sub-paragraph (v) of Sub-Clause 14.3
[Application for Interim Payment]:
and Materials if the following conditions are fulfilled (and, for the purpose of
Sub-Clause 3.7.3 [Time limits], the date these conditions are fulfilled shall be
the date of commencement of the time limit for agreement under Sub-Clause
3.7.3):
(b)
the relevant Plant and Materials:
(i) are those listed in the Contract Data for payment when shipped;
(ii) have been shipped to the Country, en route to the Site, in
accordance with the Contract; and
(iii) are described in a clean shipped bill of lading or other evidence
of shipment, which has been submitted to the Engineer together
with:
• evidence of payment of freight and insurance;
• any other documents reasonably required by the Engineer;
and
General Conditions © FIDIC & ITA 2019
83
• a written undertaking by the Contractor that the Contractor
CONDITIONS
which payment will become due when the contract value is included under
sub-paragraph (i) of Sub-Clause 14.3 [Application for Interim Payment]. At
that time, the Payment Certificate shall include the applicable amount to
be deducted which shall be equivalent to, and in the same currencies and
proportions as, this additional amount for the relevant Plant and Materials.
14.6
Issue of IPC No amount will be certified or paid to the Contractor until:
(a) the Employer has received the Performance Security in the form, and
issued by an entity, in accordance with Sub-Clause 4.2.1[Contractor’s
obligations]; and
(b) the Contractor has appointed the Contractor’s Representative in
accordance with Sub-Clause 4.3 [Contractor’s Representative].
The Engineer shall, within 28 days after receiving a Statement and supporting
documents, issue an IPC to the Employer, with a copy to the Contractor:
(a) stating the amount which the Engineer fairly considers to be due; and
(b) including any additions and/or deductions which have become due
under Sub-Clause 3.7 [Agreement or Determination] or under the
Contract or otherwise,
with detailed supporting particulars (which shall identify any difference
between a certified amount and the corresponding amount in the Statement
and give the reasons for such difference).
CONDITIONS
GENERAL
Before the issue of the Taking-Over Certificate for the Works, the Engineer
may withhold an IPC in an amount which would (after retention and other
deductions) be less than the minimum amount of IPC (if any) stated in the
Contract Data. In this event, the Engineer shall promptly give a Notice to the
Contractor accordingly.
GUIDANCE
An IPC shall not be withheld for any other reason, although:
FORMS
obligation in accordance with the Contract, the value of this work
or obligation may be withheld until the work or obligation has been
performed. In this event, the Engineer shall promptly give a Notice
to the Contractor describing the failure and with detailed supporting
particulars of the value withheld; and/or
(c) if the Engineer finds any significant error or discrepancy in the
Statement or supporting documents, the amount of the IPC may take
account of the extent to which this error or discrepancy has prevented
or prejudiced proper investigation of the amounts in the Statement until
such error or discrepancy is corrected in a subsequent Statement.
For each amount so withheld, in the supporting particulars for the IPC the
Engineer shall detail his/her calculation of the amount and state the reasons
for it being withheld.
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
If the Contractor considers that an IPC does not include any amounts to
which the Contractor is entitled, these amounts shall be identified in the next
Statement (the “identified amounts” in this paragraph). The Engineer shall
then make any correction or modification that should properly be made in
the next Payment Certificate. Thereafter, to the extent that:
(a) the Contractor is not satisfied that this next Payment Certificate
includes the identified amounts; and
(b) the identified amounts do not concern a matter for which the
Engineer is already carrying out his/her duties under Sub-Clause 3.7
[Agreement or Determination]
the Contractor may, by giving a Notice, refer this matter to the Engineer
and Sub-Clause 3.7 [Agreement or Determination] shall apply (and, for the
purpose of Sub-Clause 3.7.3 [Time limits], the date the Engineer receives this
Notice shall be the date of commencement of the time limit for agreement
under Sub-Clause 3.7.3).
(a) the amount certified in each Advance Payment Certificate within the
period stated in the Contract Data (if not stated, 21 days) after the
Employer receives the Advance Payment Certificate;
(b) the amount certified in each IPC issued under:
(i) Sub-Clause 14.6 [Issue of IPC], within the period stated in the
GUIDANCE
Contract Data (if not stated, 56 days) after the Engineer receives
the Statement and supporting documents; or
(ii) Sub-Clause 14.13 [Issue of FPC], within the period stated in the
Contract Data (if not stated, 28 days) after the Employer receives
the IPC; and
(c) the amount certified in the FPC within the period stated in the Contract
Data (if not stated, 56 days) after the Employer receives the FPC.
FORMS
Payment of the amount due in each currency shall be made into the bank
account, nominated by the Contractor, in the payment country (for this
currency) specified in the Contract.
14.8
Delayed Payment If the Contractor does not receive payment in accordance with Sub-Clause
14.7 [Payment], the Contractor shall be entitled to receive financing charges
compounded monthly on the amount unpaid during the period of delay.
This period shall be deemed to commence on the expiry of the time for
payment specified in Sub-Clause 14.7 [Payment], irrespective (in the case
of sub-paragraph (b) of Sub-Clause 14.7) of the date on which any IPC is
issued.
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
Unless otherwise stated in the Contract Data, these financing charges shall
be calculated at the annual rate of three percent (3%) above:
(a) the average bank short-term lending rate to prime borrowers prevailing
for the currency of payment at the place for payment, or
(b) where no such rate exists at that place, the same rate in the country
of the currency of payment, or
(c) in the absence of such a rate at either place, the appropriate rate fixed
by the law of the country of the currency of payment.
(i) the need for the Contractor to submit a Statement or any formal
Notice (including any requirement to comply with Sub-Clause 20.2
[Claims For Payment and/or EOT]) or certification; and
(ii) prejudice to any other right or remedy.
14.9
Release of
Retention Money After the issue of the Taking-Over Certificate for:
(a) the Works, the Contractor shall include the first half of the Retention
Money in a Statement; or
(b) for a Section, the Contractor shall include the relevant percentage of
the first half of the Retention Money in a Statement.
CONDITIONS
the Contractor shall include the second half of the Retention Money in a
GENERAL
Statement promptly after such latest date. If a Taking-Over Certificate was
(or was deemed to have been) issued for a Section, the Contractor shall
include the relevant percentage of the second half of the Retention Money in
a Statement promptly after the expiry date of the DNP for the Section.
In the next IPC after the Engineer receives any such Statement, the Engineer
GUIDANCE
shall certify the release of the corresponding amount of Retention Money.
However, when certifying any release of Retention Money under Sub-Clause
14.6 [Issue of IPC], if any work remains to be executed under Clause
11 [Defects after Taking Over] or Clause 12 [Tests after Completion], the
Engineer shall be entitled to withhold certification of the estimated cost of
this work until it has been executed.
FORMS
The relevant percentage for each Section shall be the percentage value of the
Section as stated in the Contract Data. If the percentage value of a Section is
not stated in the Contract Data, no percentage of either half of the Retention
Money shall be released under this Sub-Clause in respect of such Section.
14.10
Statement at Completion Within 84 days after the Date of Completion of the Works, the Contractor
shall submit to the Engineer a Statement at completion with supporting
documents, in accordance with Sub-Clause 14.3 [Application for Interim
Payment], showing:
(a) the value of all work done in accordance with the Contract up to the
Date of Completion of the Works;
b) any further sums which the Contractor considers to be due at the
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
The Engineer shall then issue an IPC in accordance with Sub-Clause 14.6
[Issue of IPC].
14.11
Final Statement Submission by the Contractor of any Statement under the following
provisions of this Sub-Clause shall not be delayed by reason of any referral
under Sub-Clause 21.4 [Obtaining DAAB’s Decision] or any arbitration under
Sub-Clause 21.6 [Arbitration].
Within 56 days after the issue of the Performance Certificate the Contractor
shall submit to the Engineer a draft final Statement.
Except for any amount under sub-paragraph (iii) above, if the Engineer
disagrees with or cannot verify any part of the draft final Statement, the
Engineer shall promptly give a Notice to the Contractor. The Contractor shall
then submit such further information as the Engineer may reasonably require
within the time stated in this Notice, and shall make such changes in the
draft as may be agreed between them.
However, if:
14.12
Discharge When submitting the Final Statement or the Partially Agreed Final Statement
(as the case may be), the Contractor shall submit a discharge which confirms
that the total of such Statement represents full and final settlement of all
moneys due to the Contractor under or in connection with the Contract.
This discharge may state that the total of the Statement is subject to any
payment that may become due in respect of any Dispute for which a
DAAB proceeding or arbitration is in progress under Clause 21 [Disputes
and Arbitration] and/or that it becomes effective after the Contractor has
received:
CONDITIONS
(b) the Performance Security.
GENERAL
If the Contractor fails to submit this discharge, the discharge shall be deemed
to have been submitted and to have become effective when the conditions
of sub-paragraphs (a) and (b) have been fulfilled.
A discharge under this Sub-Clause shall not affect either Party’s liability
GUIDANCE
or entitlement in respect of any Dispute for which a DAAB proceeding or
arbitration is in progress under Clause 21 [Disputes and Arbitration].
14.13
Issue of FPC Within 28 days after receiving the Final Statement or the Partially Agreed
Final Statement (as the case may be), and the discharge under Sub-Clause
14.12 [Discharge], the Engineer shall issue to the Employer (with a copy to
FORMS
the Contractor), the Final Payment Certificate which shall state:
(a) the amount which the Engineer fairly considers is finally due, including
any additions and/or deductions which have become due under
Sub-Clause 3.7 [Agreement or Determination] or under the Contract
or otherwise; and
(b) after giving credit to the Employer for all amounts previously paid by
the Employer and for all sums to which the Employer is entitled, and
after giving credit to the Contractor for all amounts (if any) previously
paid by the Contractor and/or received by the Employer under the
Performance Security, the balance (if any) due from the Employer to
the Contractor or from the Contractor to the Employer, as the case
may be.
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
If the Contractor has not submitted a draft final Statement within the time
specified under Sub-Clause 14.11.1 [Draft Final Statement], the Engineer
shall request the Contractor to do so. Thereafter, if the Contractor fails to
submit a draft final Statement within a period of 28 days, the Engineer shall
issue the FPC for such an amount as the Engineer fairly considers to be due.
If:
14.14
Cessation of
Employer’s Liability The Employer shall not be liable to the Contractor for any matter or thing
under or in connection with the Contract or execution of the Works, except
to the extent that the Contractor shall have included an amount expressly for
it in:
the FPC within 56 days of receiving a copy of the FPC, the Contractor shall
be deemed to have accepted the amounts so certified. The Employer shall
then have no further liability to the Contractor, other than to pay the amount
due under the FPC and return the Performance Security to the Contractor.
However, this Sub-Clause shall not limit the Employer’s liability under the
GUIDANCE
14.15
Currencies of Payment The Contract Price shall be paid in the currency or currencies named in the
Contract Data. If more than one currency is so named, payments shall be
FORMS
made as follows:
CONDITIONS
Termination by Employer
GENERAL
15.1
Notice to Correct If the Contractor fails to carry out any obligation under the Contract the
Engineer may, by giving a Notice to the Contractor, require the Contractor
to make good the failure and to remedy it within a specified time (“Notice to
Correct” in these Conditions).
GUIDANCE
The Notice to Correct shall:
FORMS
which shall be reasonable, taking due regard of the nature of the
failure and the work and/or other action required to remedy it.
The time specified in the Notice to Correct shall not imply any extension of
the Time for Completion.
15.2
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
Termination for
Contractor’s Default Termination of the Contract under this Clause shall not prejudice any other
rights of the Employer under the Contract or otherwise.
15.2.1 Notice
The Employer shall be entitled to give a Notice (which shall state that it is
given under this Sub-Clause 15.2.1) to the Contractor of the Employer’s
intention to terminate the Contract or, in the case of sub-paragraph (f), (g) or
(h) below a Notice of termination, if the Contractor:
15.2.2 Termination
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
CONDITIONS
GENERAL
After termination under this Sub-Clause, the Employer may complete the
Works and/or arrange for any other entities to do so. The Employer and/or
these entities may then use any Goods, Contractor’s Documents and other
design documents made by or on behalf of the Contractor to complete the
Works.
GUIDANCE
After such completion of the Works, the Employer shall give another Notice
to the Contractor that the Contractor’s Equipment and Temporary Works
will be released to the Contractor at or near the Site. The Contractor shall
then promptly arrange their removal, at the risk and cost of the Contractor.
However, if by this time the Contractor has failed to make a payment due to
the Employer, these items may be sold (to the extent permitted by applicable
Laws) by the Employer in order to recover this payment. Any balance of the
FORMS
proceeds shall then be paid to the Contractor.
15.3
Valuation after Termination
for Contractor’s Default After termination of the Contract under Sub-Clause 15.2 [Termination
for Contractor’s Default], the Engineer shall proceed under Sub-Clause
3.7 [Agreement or Determination] to agree or determine the value of the
Permanent Works, Goods and Contractor’s Documents, and any other
sums due to the Contractor for work executed in accordance with the
Contract (and, for the purpose of Sub-Clause 3.7.3 [Time limits], the date
of termination shall be the date of commencement of the time limit for
agreement under Sub-Clause 3.7.3).
This valuation shall include any additions and/or deductions, and the balance
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
due (if any), by reference to the matters described in sub-paragraphs (a) and
(b) of Sub-Clause 14.13 [Issue of FPC].
This valuation shall not include the value of any Contractor’s Documents,
Materials, Plant and Permanent Works to the extent that they do not comply
with the Contract.
15.4
Payment after Termination
for Contractor’s Default The Employer may withhold payment to the Contractor of the amounts
agreed or determined under Sub-Clause 15.3 [Valuation after Termination for
Contractor’s Default] until all the costs, losses and damages (if any) described
in the following provisions of this Sub-Clause have been established.
(a) the additional costs of execution of the Works, and all other costs
reasonably incurred by the Employer (including costs incurred
in clearing, cleaning and reinstating the Site as described under
Sub-Clause 11.11 [Clearance of Site]), after allowing for any sum due
to the Contractor under Sub-Clause 15.3 [Valuation after Termination
for Contractor’s Default];
(b) any losses and damages suffered by the Employer in completing the
Works; and
(c) Delay Damages, if the Works or a Section have not been taken over
under Sub-Clause 10.1 [Taking Over the Works and Sections] and
for Completion of the Works or Section (as the case may be). Such
Delay Damages shall be paid for every day that has elapsed between
these two dates.
15.5
Termination for
GUIDANCE
Employer’s Convenience The Employer shall be entitled to terminate the Contract at any time for the
Employer’s convenience, by giving a Notice of such termination to the Contractor
(which Notice shall state that it is given under this Sub-Clause 15.5).
After giving a Notice to terminate under this Sub-Clause, the Employer shall
immediately:
FORMS
Termination under this Sub-Clause shall take effect 28 days after the later
of the dates on which the Contractor receives this Notice or the Employer
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
returns the Performance Security. Unless and until the Contractor has
received payment of the amount due under Sub-Clause 15.6 [Valuation after
Termination for Employer’s Convenience], the Employer shall not execute
(any part of) the Works or arrange for (any part of) the Works to be executed
by any other entities.
15.6
Valuation after Termination
for Employer’s Convenience After termination under Sub-Clause 15.5 [Termination for Employer’s
Convenience] the Contractor shall, as soon as practicable, submit detailed
supporting particulars (as reasonably required by the Engineer) of:
CONDITIONS
determined, without the need for the Contractor to submit a Statement.
GENERAL
15.7
Payment after Termination
for Employer’s Convenience The Employer shall pay the Contractor the amount certified in the Payment
Certificate under Sub-Clause 15.6 [Valuation after Termination for Employer’s
Convenience] within 112 days after the Engineer receives the Contractor’s
GUIDANCE
submission under that Sub-Clause.
16.1
16
Suspension and Termination by Contractor
FORMS
Suspension by Contractor If:
(a) the Engineer fails to certify in accordance with Sub-Clause 14.6 [Issue
of IPC];
(b) the Employer fails to provide reasonable evidence in accordance with
Sub-Clause 2.4 [Employer’s Financial Arrangements];
(c) the Employer fails to comply with Sub-Clause 14.7 [Payment]; or
(d) the Employer fails to comply with:
(i) a binding agreement, or final and binding determination under
Sub-Clause 3.7 [Agreement or Determination]; or
(ii) a decision of the DAAB under 21.4 [Obtaining DAAB’s Decision]
(whether binding or final and binding)
and such failure constitutes a material breach of the Employer’s
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
16.2
Termination by Contractor Termination of the Contract under this Clause shall not prejudice any other
rights of the Contractor, under the Contract or otherwise.
16.2.1 Notice
The Contractor shall be entitled to give a Notice (which shall state that it is
given under this Sub-Clause 16.2.1) to the Employer of the Contractor’s
(a) the Contractor does not receive the reasonable evidence within 42
days after giving a Notice under Sub-Clause 16.1 [Suspension by
Contractor] in respect of a failure to comply with Sub-Clause 2.4
[Employer’s Financial Arrangements];
(b) the Engineer fails, within 56 days after receiving a Statement and
GUIDANCE
16.2.2 Termination
CONDITIONS
14 days, the Contractor shall be entitled subject to Sub-Clause 20.2 [Claims
GENERAL
For Payment and/or EOT] to EOT and/or payment of such Cost Plus Profit.
16.3
Contractor’s Obligations
After Termination After termination of the Contract under Sub-Clause 15.5 [Termination for
Employer’s Convenience], Sub-Clause 16.2 [Termination by Contractor] or
GUIDANCE
Sub-Clause 18.5 [Optional Termination], the Contractor shall promptly:
(a) cease all further work, except for such work as may have been
instructed by the Engineer for the protection of life or property or for
the safety of the Works. If the Contractor incurs Cost as a result of
carrying out such instructed work the Contractor shall be entitled
subject to Sub-Clause 20.2 [Claims For Payment and/or EOT] to be
FORMS
paid such Cost Plus Profit;
(b) deliver to the Engineer all Contractor’s Documents, Plant, Materials
and other work for which the Contractor has received payment; and
(c) remove all other Goods from the Site, except as necessary for safety,
and leave the Site.
16.4
Payment after
Termination by Contractor After termination under Sub-Clause 16.2 [Termination by Contractor], the
Employer shall promptly:
17.1
Responsibility for
17
Care of the Works and Indemnities
Care of the Works Unless the Contract is terminated in accordance with these Conditions or
otherwise, subject to Sub-Clause 17.2 [Liability for Care of the Works] the
Contractor shall take full responsibility for the care of the Works, Goods and
Contractor’s Documents from the Commencement Date until the issue of
the Taking-Over Certificate for the Works, when responsibility for the care of
the Works shall pass to the Employer. If a Taking-Over Certificate is issued
(or is deemed to be issued) for any Section or Part, responsibility for the care
of the Section or Part shall then pass to the Employer.
the Works], the Contractor shall rectify the loss or damage at the Contractor’s
GENERAL
risk and cost, so that the Works, Goods, or Contractor’s Documents (as the
case may be) comply with the Contract.
17.2
Liability for
Care of the Works The Contractor shall be liable for any loss or damage caused by the
GUIDANCE
(i) any of the events described in sub-paragraphs (a) to (f) above, and
(ii) a cause for which the Contractor is liable,
CONDITIONS
and/or damage, the Contractor shall subject to Sub-Clause 20.2 [Claims for
GENERAL
Payment and/or EOT] be entitled to a proportion of EOT and/or Cost Plus
Profit to the extent that any of the above events have contributed to such
delays and/or Cost.
17.3
Intellectual and Industrial
GUIDANCE
Property Rights In this Sub-Clause, “infringement” means an infringement (or alleged
infringement) of any patent, registered design, copyright, trademark, trade
name, trade secret or other intellectual or industrial property right relating to
the Works; and “claim” means a third party claim (or proceedings pursuing a
third party claim) alleging an infringement.
Whenever a Party receives a claim but fails to give Notice to the other Party
FORMS
of the claim within 28 days of receiving it, the first Party shall be deemed to
have waived any right to indemnity under this Sub-Clause.
The Employer shall indemnify and hold the Contractor harmless against and
from any claim (including legal fees and expenses) alleging an infringement
which is or was:
unless such use was disclosed to the Contractor before the Base
Date or is stated in the Contract.
The Contractor shall indemnify and hold the Employer harmless against
and from any other claim (including legal fees and expenses) alleging an
infringement which arises out of or in relation to:
17.4
Indemnities by Contractor The Contractor shall indemnify and hold harmless the Employer, the
Employer’s Personnel, and their respective agents, against and from all
third party claims, damages, losses and expenses (including legal fees and
expenses) in respect of:
(b) damage to or loss of any property, real or personal (other than the
Works), to the extent that such damage or loss:
(i) arises out of or in the course of or by reason of the Contractor’s
execution of the Works, and
(ii) is attributable to any negligence, wilful act or breach of the
Contract by the Contractor, the Contractor’s Personnel, their
GUIDANCE
The Contractor shall also indemnify and hold harmless the Employer against
all acts, errors or omissions by the Contractor in carrying out the Contractor’s
design obligations that result in the Works (or Section or Part or major item of
Plant, if any), when completed, not being fit for the purpose(s) for which they
FORMS
17.5
Indemnities by Employer The Employer shall indemnify and hold harmless the Contractor, the
Contractor’s Personnel, and their respective agents, against and from all
third party claims, damages, losses and expenses (including legal fees and
expenses) in respect of:
Works), to the extent that such damage or loss arises out of any event
described under sub-paragraphs (a) to (f) of Sub-Clause 17.2 [Liability
for Care of the Works].
17.6
Shared Indemnities The Contractor’s liability to indemnify the Employer, under Sub-Clause 17.4
[Indemnities by Contractor] and/or under Sub-Clause 17.3 [Intellectual and
Industrial Property Rights], shall be reduced proportionately to the extent
that any event described under sub-paragraphs (a) to (f) of Sub-Clause 17.2
[Liability for Care of the Works] may have contributed to the said damage,
loss or injury.
18.1
18
Exceptional Events
100 © FIDIC & ITA 2019 Conditions of Contract for Underground Works
(iii) having arisen, such Party could not reasonably have avoided or
CONDITIONS
overcome; and
GENERAL
(iv) is not substantially attributable to the other Party.
An Exceptional Event may comprise but is not limited to any of the following
events or circumstances provided that conditions (i) to (iv) above are satisfied:
GUIDANCE
foreign enemies;
(b) rebellion, terrorism, revolution, insurrection, military or usurped power,
or civil war;
(c) riot, commotion or disorder by persons other than the Contractor’s
Personnel and other employees of the Contractor and Subcontractors;
(d) strike or lockout not solely involving the Contractor’s Personnel and
other employees of the Contractor and Subcontractors;
FORMS
(e) encountering munitions of war, explosive materials, ionising radiation
or contamination by radio-activity, except as may be attributable
to the Contractor’s use of such munitions, explosives, radiation or
radio-activity; or
(f) natural catastrophes such as earthquake, tsunami, volcanic activity,
hurricane or typhoon.
18.2
Notice of
an Exceptional Event If a Party is or will be prevented from performing any obligations under the
Contract due to an Exceptional Event (the “affected Party” in this Clause),
then the affected Party shall give a Notice to the other Party of such an
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
This Notice shall be given within 14 days after the affected Party became
aware, or should have become aware, of the Exceptional Event, and
the affected Party shall then be excused performance of the prevented
obligations from the date such performance is prevented by the Exceptional
Event. If this Notice is received by the other Party after this period of 14
days, the affected Party shall be excused performance of the prevented
obligations only from the date on which this Notice is received by the other
Party.
However, the obligations of either Party to make payments due to the other
Party under the Contract shall not be excused by an Exceptional Event.
18.3
Duty to Minimise Delay Each Party shall at all times use all reasonable endeavours to minimise any
delay in the performance of the Contract as a result of an Exceptional Event.
If the Exceptional Event has a continuing effect, the affected Party shall give
further Notices describing the effect every 28 days after giving the first Notice
under Sub-Clause 18.2 [Notice of an Exceptional Event].
Party fails to do so, the other Party may give a Notice to the affected Party
stating that the other Party considers that the affected Party’s performance
is no longer prevented by the Exceptional Event, with reasons.
18.4
Consequences of
GUIDANCE
an Exceptional Event If the Contractor is the affected Party and suffers delay and/or incurs Cost
by reason of the Exceptional Event of which he/she gave a Notice under
Sub-Clause 18.2 [Notice of an Exceptional Event], the Contractor shall be
entitled subject to Sub-Clause 20.2 [Claims For Payment and/or EOT] to:
18.5
Optional Termination If the execution of substantially all the Works in progress is prevented for a
continuous period of 84 days by reason of an Exceptional Event of which
Notice has been given under Sub-Clause 18.2 [Notice of an Exceptional
Event], or for multiple periods which total more than 140 days due to the
same Exceptional Event, then either Party may give to the other Party a
Notice of termination of the Contract.
In this event, the date of termination shall be the date 7 days after the Notice is
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
received by the other Party, and the Contractor shall proceed in accordance
with Sub-Clause 16.3 [Contractor’s Obligations After Termination].
(a) the amounts payable for any work carried out for which a price is
stated in the Contract;
(b) the Cost of Plant and Materials ordered for the Works which have
been delivered to the Contractor, or of which the Contractor is liable
to accept delivery. This Plant and Materials shall become the property
of (and be at the risk of) the Employer when paid for by the Employer,
and the Contractor shall place the same at the Employer’s disposal;
(c) any other Cost or liability which in the circumstances was reasonably
incurred by the Contractor in the expectation of completing the
Works;
(d) the Cost of removal of Temporary Works and Contractor’s Equipment
from the Site and the return of these items to the Contractor’s place
of business in the Contractor’s country (or to any other destination(s)
at no greater cost); and
(e) the Cost of repatriation of the Contractor’s staff and labour employed
wholly in connection with the Works at the date of termination.
102 © FIDIC & ITA 2019 Conditions of Contract for Underground Works
The Engineer shall issue a Payment Certificate, under Sub-Clause 14.6
CONDITIONS
[Issue of IPC], for the amount so agreed or determined, without the need for
GENERAL
the Contractor to submit a Statement.
18.6
Release from Performance
under the Law In addition to any other provision of this Clause, if any event arises outside the
control of the Parties (including, but not limited to, an Exceptional Event) which:
GUIDANCE
(a) makes it impossible or unlawful for either Party or both Parties to fulfil
their contractual obligations; or
(b) under the law governing the Contract, entitles the Parties to be
released from further performance of the Contract,
and if the Parties are unable to agree on an amendment to the Contract that
FORMS
would permit the continued performance of the Contract, then after either
Party gives a Notice to the other Party of such event:
(i) the Parties shall be discharged from further performance, and without
prejudice to the rights of either Party in respect of any previous breach
of the Contract; and
(ii) the amount payable by the Employer to the Contractor shall be the
same as would have been payable under Sub-Clause 18.5 [Optional
Termination], and such amount shall be certified by the Engineer, as if
the Contract had been terminated under that Sub-Clause.
19
Insurance
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
19.1
General Requirements Without limiting either Party’s obligations or responsibilities under the
Contract, the Contractor shall effect and maintain all insurances for which
the Contractor is responsible with insurers and in terms, both of which shall
be subject to consent by the Employer. These terms shall be consistent
with terms (if any) agreed by both Parties before the date of the Letter of
Acceptance.
The insurances required to be provided under this Clause are the minimum
required by the Employer, and the Contractor may, at the Contractor’s own
cost, add such other insurances that the Contractor may deem prudent.
If the Contractor fails to effect and keep in force any of the insurances
required under Sub-Clause 19.2 [Insurances to be provided by Contractor]
then, and in any such case, the Employer may effect and keep in force such
insurances and pay any premium as may be necessary and recover the
same from the Contractor from time to time by deducting the amount(s) so
paid from any moneys due to the Contractor or otherwise recover the same
as a debt from the Contractor. The provisions of Clause 20 [Employer’s and
Contractor’s Claims] shall not apply to this Sub-Clause.
If either the Contractor or the Employer fails to comply with any condition of
the insurances effected under the Contract, the Party so failing to comply
General Conditions © FIDIC & ITA 2019
103
shall indemnify the other Party against all direct losses and claims (including
CONDITIONS
The permitted deductible limits allowed in any policy shall not exceed the
amounts stated in the Contract Data (if not stated, the amounts agreed with
the Employer).
Where there is a shared liability the loss shall be borne by each Party in
FORMS
19.2
Insurance to be provided
by the Contractor The Contractor shall provide the following insurances:
The Contractor shall insure and keep insured in the joint names of the
Contractor and the Employer from the Commencement Date until the date
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
(a) the Works and Contractor’s Documents, together with Materials and
Plant for incorporation in the Works, for their full replacement value.
The insurance cover shall extend to include loss and damage of any
part of the Works as a consequence of failure of elements defectively
designed or constructed with defective material or workmanship; and
(b) an additional amount of fifteen percent (15%) of such replacement
value (or such other amount as may be specified in the Contract Data)
to cover any additional costs incidental to the rectification of loss or
damage, including professional fees and the cost of demolition and
removal of debris.
The insurance cover shall cover the Employer and the Contractor against all
loss or damage from whatever cause arising until the issue of the Taking-Over
Certificate for the Works. Thereafter, the insurance shall continue until the
date of the issue of the Performance Certificate in respect of any incomplete
work for loss or damage arising from any cause occurring before the date
of the issue of the Taking-Over Certificate for the Works, and for any loss or
damage occasioned by the Contractor in the course of any operation carried
out by the Contractor for the purpose of complying with the Contractor’s
obligations under Clause 11 [Defects after Taking Over] and Clause 12 [Tests
after Completion].
However, the insurance cover provided by the Contractor for the Works may
exclude any of the following:
(i) the cost of making good any part of the Works which is defective
(including defective material and workmanship) or otherwise does not
comply with the Contract, provided that it does not exclude the cost
104 © FIDIC & ITA 2019 Conditions of Contract for Underground Works
of making good any loss or damage to any other part of the Works
CONDITIONS
attributable to such defect or non-compliance;
GENERAL
(ii) indirect or consequential loss or damage including any reductions in
the Contract Price for delay;
(iii) wear and tear, shortages and pilferages; and
(iv) unless otherwise stated in the Contract Data, the risks arising from
Exceptional Events.
GUIDANCE
19.2.2 Goods
The Contractor shall insure, in the joint names of the Contractor and the
Employer, the Goods and other things brought to Site by the Contractor
to the extent specified and/or amount stated in the Contract Data (if not
specified or stated, for their full replacement value including delivery to Site).
FORMS
The Contractor shall maintain this insurance from the time the Goods are
delivered to the Site until they are no longer required for the Works.
To the extent that the Contractor is responsible for the design of the
Permanent Works, and consistent with the indemnities specified in Clause
17 [Care of the Works and Indemnities]:
The Contractor shall maintain this insurance for the period specified in the
Contract Data.
The Contractor shall insure, in the joint names of the Contractor and the
Employer, against liabilities for death or injury to any person, or loss of or
damage to any property (other than the Works) arising out of the performance
of the Contract and occurring before the issue of the Performance Certificate,
other than loss or damage caused by an Exceptional Event.
The insurance policy shall include a cross liability clause such that the
insurance shall apply to the Contractor and the Employer as separate
insureds.
Such insurance shall be effected before the Contractor begins any work on
the Site and shall remain in force until the issue of the Performance Certificate
and shall be for not less than the amount stated in the Contract Data (if not
stated, the amount agreed with the Employer).
The Contractor shall effect and maintain insurance against liability for claims,
damages, losses and expenses (including legal fees and expenses) arising
out of the execution of the Works in respect of injury, sickness, disease or
death of any person employed by the Contractor or any of the Contractor’s
other personnel.
GUIDANCE
The Employer and the Engineer shall also be indemnified under the policy
of insurance, except that this insurance may exclude losses and claims to
the extent that they arise from any act or neglect of the Employer or of the
Employer’s Personnel.
The insurance shall be maintained in full force and effect during the whole
time that the Contractor’s Personnel are assisting in the execution of the
FORMS
The Contractor shall provide all other insurances required by the Laws of
the countries where (any part of) the Works are being carried out, at the
Contractor’s own cost.
20
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
(a) if the Employer considers that the Employer is entitled to any additional
payment from the Contractor (or reduction in the Contract Price) and/
or to an extension of the DNP;
(b) if the Contractor considers that the Contractor is entitled to any
additional payment from the Employer and/or to EOT; or
(c) if either Party considers that he/she is entitled to another entitlement
or relief against the other Party. Such other entitlement or relief
may be of any kind whatsoever (including in connection with any
certificate, determination, instruction, Notice, opinion or valuation
of the Engineer) except to the extent that it involves any entitlement
referred to in sub-paragraphs (a) and/or (b) above.
In the case of a Claim under sub-paragraph (c) above, where the other Party
or the Engineer has disagreed with the requested entitlement or relief (or is
deemed to have disagreed if he/she does not respond within a reasonable
time), a Dispute shall not be deemed to have arisen but the claiming Party
may by giving a Notice refer the Claim to the Engineer and Sub-Clause 3.7
[Agreement or Determination] shall apply. This Notice shall be given as soon
as practicable after the claiming Party becomes aware of the disagreement
106 © FIDIC & ITA 2019 Conditions of Contract for Underground Works
(or deemed disagreement) and shall include details of the claiming Party’s
CONDITIONS
case and the other Party’s or the Engineer’s disagreement (or deemed
GENERAL
disagreement).
20.2
Claims For Payment
and/or EOT If either Party considers that he/she is entitled to any additional payment by
the other Party (or, in the case of the Employer, a reduction in the Contract
GUIDANCE
Price) and/or to EOT (in the case of the Contractor) or an extension of the
DNP (in the case of the Employer) under any Clause of these Conditions or
otherwise in connection with the Contract, the following Claim procedure
shall apply:
FORMS
The claiming Party shall give a Notice to the Engineer, describing the event
or circumstance giving rise to the cost, loss, delay or extension of DNP for
which the Claim is made as soon as practicable, and no later than 28 days
after the claiming Party became aware, or should have become aware, of
the event or circumstance (the “Notice of Claim” in these Conditions).
If the claiming Party fails to give a Notice of Claim within this period of 28
days, the claiming Party shall not be entitled to any additional payment,
the Contract Price shall not be reduced (in the case of the Employer as the
claiming Party), the Time for Completion (in the case of the Contractor as
the claiming Party) or the DNP (in the case of the Employer as the claiming
Party) shall not be extended, and the other Party shall be discharged from
any liability in connection with the event or circumstance giving rise to the
Claim.
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
If the Engineer considers that the claiming Party has failed to give the Notice
of Claim within the period of 28 days under Sub-Clause 20.2.1 [Notice of
Claim] the Engineer shall, within 14 days after receiving the Notice of Claim,
give a Notice to the claiming Party accordingly (with reasons).
If the Engineer does not give such a Notice within this period of 14 days,
the Notice of Claim shall be deemed to be a valid Notice. If the other Party
disagrees with such deemed valid Notice of Claim the other Party shall give
a Notice to the Engineer which shall include details of the disagreement.
Thereafter, the agreement or determination of the Claim under Sub-Clause
20.2.5 [Agreement or determination of the Claim] shall include a review by
the Engineer of such disagreement.
If the claiming Party receives a Notice from the Engineer under this Sub-Clause
and disagrees with the Engineer or considers there are circumstances which
justify late submission of the Notice of Claim, the claiming Party shall include
in its fully detailed Claim under Sub-Clause 20.2.4 [Fully detailed claim]
details of such disagreement or why such late submission is justified (as the
case may be).
Without admitting the Employer’s liability, the Engineer may monitor the
Contractor’s contemporary records and/or instruct the Contractor to
keep additional contemporary records. The Contractor shall permit the
Engineer to inspect all these records during normal working hours (or at
other times agreed by the Contractor), and shall if instructed submit copies
GUIDANCE
includes:
The Costs claimed under this Sub-Clause 20.2.4 and relating to Excavation
and Lining Works shall be calculated by reference to the rates and prices in
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
the Bill of Quantities, to the extent that the unit rates and the respective items
of work are comparable as stated under Sub-Clause 13.8 [Measurement of
Excavation and Lining Works and Adjustment of Time for Completion].
Within either:
(i) 84 days after the claiming Party became aware, or should have
become aware, of the event or circumstance giving rise to the Claim,
or
(ii) such other period (if any) as may be proposed by the claiming Party
and agreed by the Engineer
the claiming Party shall submit to the Engineer a fully detailed Claim.
If within this time limit the claiming Party fails to submit the statement under
sub-paragraph (b) above, the Notice of Claim shall be deemed to have
lapsed, it shall no longer be considered as a valid Notice, and the Engineer
shall, within 14 days after this time limit has expired, give a Notice to the
claiming Party accordingly.
If the Engineer does not give such a Notice within this period of 14 days,
the Notice of Claim shall be deemed to be a valid Notice. If the other Party
disagrees with such deemed valid Notice of Claim the other Party shall give
a Notice to the Engineer which shall include details of the disagreement.
Thereafter, the agreement or determination of the Claim under Sub-Clause
20.2.5 [Agreement or determination of the Claim] shall include a review by
the Engineer of such disagreement.
If the claiming Party receives a Notice from the Engineer under this Sub-Clause
20.2.4 and if the claiming Party disagrees with such Notice or considers
108 © FIDIC & ITA 2019 Conditions of Contract for Underground Works
there are circumstances which justify late submission of the statement under
CONDITIONS
sub-paragraph (b) above, the fully detailed claim shall include details of the
GENERAL
claiming Party’s disagreement or why such late submission is justified (as the
case may be).
If the event or circumstance giving rise to the Claim has a continuing effect,
Sub-Clause 20.2.6 [Claims of continuing effect] shall apply.
GUIDANCE
20.2.5 Agreement or determination of the Claim
After receiving a fully detailed Claim under Sub-Clause 20.2.4 [Fully detailed
Claim], or an interim or final fully detailed Claim (as the case may be) under
Sub-Clause 20.2.6 [Claims of continuing effect], the Engineer shall proceed
under Sub-Clause 3.7 [Agreement or Determination] to agree or determine:
FORMS
(a) the additional payment (if any) to which the claiming Party is entitled
or the reduction of the Contract Price (in the case of the Employer as
the claiming Party); and/or
(b) the extension (if any) of the Time for Completion (before or after its
expiry) under Sub-Clause 8.5 [Extension of Time for Completion] (in
the case of the Contractor as the claiming Party), or the extension (if
any) of the DNP (before its expiry) under Sub-Clause 11.3 [Extension
of Defects Notification Period] (in the case of the Employer as the
claiming Party),
(i) he/she shall promptly give a Notice to the claiming Party, describing
the additional particulars and the reasons for requiring them;
(ii) he/she shall nevertheless give his/her response on the contractual or
other legal basis of the Claim, by giving a Notice to the claiming Party,
within the time limit for agreement under Sub-Clause 3.7.3 [Time
limits];
(i) above, the claiming Party shall submit the additional particulars;
GENERAL
and
(iv) the Engineer shall then proceed under Sub-Clause 3.7 [Agreement or
Determination] to agree or determine the matters under sub-paragraphs
(a) and/or (b) above (and, for the purpose of Sub-Clause 3.7.3 [Time
limits], the date the Engineer receives the additional particulars from
the claiming Party shall be the date of commencement of the time
GUIDANCE
(a) the fully detailed Claim submitted under Sub-Clause 20.2.4 [Fully
detailed Claim] shall be considered as interim;
(b) in respect of this first interim fully detailed Claim, the Engineer shall
give his/her response on the contractual or other legal basis of the
Claim, by giving a Notice to the claiming Party, within the time limit for
agreement under Sub-Clause 3.7.3 [Time limits];
(c) after submitting the first interim fully detailed Claim the claiming Party
shall submit further interim fully detailed Claims at monthly intervals,
giving the accumulated amount of additional payment claimed (or the
reduction of the Contract Price, in the case of the Employer as the
claiming Party), and/or extension of time claimed (in the case of the
Contractor as the claiming Party) or extension of the DNP (in the case
of the Employer as the claiming Party); and
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
(d) the claiming Party shall submit a final fully detailed Claim within 28 days
after the end of the effects resulting from the event or circumstance,
or within such other period as may be proposed by the claiming Party
and agreed by the Engineer. This final fully detailed claim shall give
the total amount of additional payment claimed (or the reduction of
the Contract Price, in the case of the Employer as the claiming Party)
and/or extension of time claimed (in the case of the Contractor as the
claiming Party) or extension of the DNP (in the case of the Employer
as the claiming Party).
After receiving the Notice of Claim, and until the Claim is agreed or determined
under Sub-Clause 20.2.5 [Agreement or determination of the Claim], in each
Payment Certificate the Engineer shall include such amounts for any Claim
as have been reasonably substantiated as due to the claiming Party under
the relevant provision of the Contract.
The Employer shall only be entitled to claim any payment from the Contractor
and/or to extend the DNP, or set off against or make any deduction from any
amount due to the Contractor, by complying with this Sub-Clause 20.2.
110 © FIDIC & ITA 2019 Conditions of Contract for Underground Works
21
CONDITIONS
Disputes and Arbitration
GENERAL
21.1
Constitution of the DAAB Disputes shall be decided by a DAAB in accordance with Sub-Clause 21.4
[Obtaining DAAB’s Decision]. The Parties shall jointly appoint the member(s)
of the DAAB within the time stated in the Contract Data (if not stated, 28
days) after the date the Contractor receives the Letter of Acceptance.
GUIDANCE
The DAAB shall comprise, as stated in the Contract Data, either one suitably
qualified member (the “sole member”) or three suitably qualified members
(the “members”). If the number is not so stated, and the Parties do not agree
otherwise, the DAAB shall comprise three members.
The sole member or three members (as the case may be) shall be selected
FORMS
from those named in the list in the Contract Data, other than anyone who is
unable or unwilling to accept appointment to the DAAB.
If the DAAB is to comprise three members, each Party shall select one
member for the agreement of the other Party. The Parties shall consult both
these members and shall agree the third member, who shall be appointed to
act as chairperson.
The DAAB shall be deemed to be constituted on the date that the Parties
and the sole member or the three members (as the case may be) of the
DAAB have all signed a DAAB Agreement.
The terms of the remuneration of either the sole member or each of the
three members, including the remuneration of any expert whom the DAAB
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
consults, shall be mutually agreed by the Parties when agreeing the terms of
the DAAB Agreement. Each Party shall be responsible for paying one-half of
this remuneration.
If at any time the Parties so agree, they may appoint a suitably qualified
person or persons to replace any one or more members of the DAAB.
Unless the Parties agree otherwise, a replacement DAAB member shall be
appointed if a member declines to act or is unable to act as a result of death,
illness, disability, resignation or termination of appointment. The replacement
member shall be appointed in the same manner as the replaced member was
required to have been selected or agreed, as described in this Sub-Clause.
Unless otherwise agreed by both Parties, the term of the DAAB (including
the appointment of each member) shall expire either:
(a) on the date the discharge shall have become, or deemed to have
become, effective under Sub-Clause 14.12 [Discharge]; or
(b) 28 days after the DAAB has given its decision on all Disputes, referred
to it under Sub-Clause 21.4 [Obtaining DAAB’s Decision] before such
discharge has become effective,
whichever is later.
whichever is earlier.
GUIDANCE
21.2
Failure to Appoint
DAAB Member(s) If any of the following conditions apply, namely:
(a) if the DAAB is to comprise a sole member, the Parties fail to agree the
appointment of this member by the date stated in the first paragraph
of Sub-Clause 21.1 [Constitution of the DAAB]; or
FORMS
(b) if the DAAB is to comprise three persons, and if by the date stated in
the first paragraph of Sub-Clause 21.1 [Constitution of the DAAB]:
(i) either Party fails to select a member (for agreement by the other
Party);
(ii) either Party fails to agree a member selected by the other Party;
and/or
(iii) the Parties fail to agree the appointment of the third member (to
act as chairperson) of the DAAB;
(d) if, after the Parties have agreed the appointment of the member(s)
or replacement, such appointment cannot be effected because
one Party refuses or fails to sign a DAAB Agreement with any such
member or replacement (as the case may be) within 14 days of the
other Party’s request to do so,
then the appointing entity or official named in the Contract Data shall, at the
request of either or both Parties and after due consultation with both Parties,
appoint the member(s) of the DAAB (who, in the case of sub-paragraph (d)
above, shall be the agreed member(s) or replacement). This appointment
shall be final and conclusive.
(i) the monthly services fee and daily fee shall be as stated in the terms
of the appointment; and
(ii) the law governing the DAAB Agreement shall be the governing law of
the Contract defined in Sub-Clause 1.4 [Law and Language].
112 © FIDIC & ITA 2019 Conditions of Contract for Underground Works
21.3
CONDITIONS
Avoidance of Disputes If the Parties so agree, they may jointly request (in writing, with a copy to
GENERAL
the Engineer) the DAAB to provide assistance and/or informally discuss and
attempt to resolve any issue or disagreement that may have arisen between
them during the performance of the Contract. If the DAAB becomes aware
of an issue or disagreement, it may invite the Parties to make such a joint
request.
GUIDANCE
Such joint request may be made at any time, except during the period that
the Engineer is carrying out his/her duties under Sub-Clause 3.7 [Agreement
or Determination] on the matter at issue or in disagreement unless the Parties
agree otherwise.
Such informal assistance may take place during any meeting, Site visit or
otherwise. However, unless the Parties agree otherwise, both Parties shall
FORMS
be present at such discussions. The Parties are not bound to act on any
advice given during such informal meetings, and the DAAB shall not be
bound in any future Dispute resolution process or decision by any views or
advice given during the informal assistance process, whether provided orally
or in writing.
21.4
Obtaining DAAB’s Decision If a Dispute arises between the Parties then either Party may refer the Dispute
to the DAAB for its decision (whether or not any informal discussions have
been held under Sub-Clause 21.3 [Avoidance of Disputes]) and the following
provisions shall apply.
The reference of a Dispute to the DAAB under this Sub-Clause shall, unless
prohibited by law, be deemed to interrupt the running of any applicable
statute of limitation or prescription period.
Both Parties shall promptly make available to the DAAB all information,
access to the Site, and appropriate facilities, as the DAAB may require for
the purposes of making a decision on the Dispute.
Unless the Contract has already been abandoned or terminated, the Parties
shall continue to perform their obligations in accordance with the Contract.
However, if at the end of this period, the due date(s) for payment of any
GUIDANCE
DAAB member’s invoice(s) has passed but such invoice(s) remains unpaid,
the DAAB shall not be obliged to give its decision until such outstanding
invoice(s) have been paid in full, in which case the DAAB shall give its
decision as soon as practicable after payment has been received.
The decision shall be given in writing to both Parties with a copy to the
Engineer, shall be reasoned, and shall state that it is given under this
FORMS
Sub-Clause.
The decision shall be binding on both Parties, who shall promptly comply
with it whether or not a Party gives a NOD with respect to such decision
under this Sub-Clause. The Employer shall be responsible for the Engineer’s
compliance with the DAAB decision.
but only if there are reasonable grounds for the DAAB to believe that
the payee will be unable to repay such amount in the event that the
decision is reversed under Sub-Clause 21.6 [Arbitration], require
the payee to provide an appropriate security (at the DAAB’s sole
discretion) in respect of such amount.
(a) such Party may give a NOD to the other Party, with a copy to the
DAAB and to the Engineer;
(b) this NOD shall state that it is a “Notice of Dissatisfaction with the
DAAB’s Decision” and shall set out the matter in Dispute and the
reason(s) for dissatisfaction; and
(c) this NOD shall be given within 28 days after receiving the DAAB’s
decision.
If the DAAB fails to give its decision within the period stated in Sub-Clause
21.4.3 [The DAAB’s decision], then either Party may, within 28 days after
this period has expired, give a NOD to the other Party in accordance with
sub-paragraphs (a) and (b) above.
114 © FIDIC & ITA 2019 Conditions of Contract for Underground Works
shall be entitled to commence arbitration of a Dispute unless a NOD in
CONDITIONS
respect of that Dispute has been given in accordance with this Sub-Clause
GENERAL
21.4.4.
If the DAAB has given its decision as to a matter in Dispute to both Parties,
and no NOD under this Sub-Clause 21.4.4 has been given by either Party
within 28 days after receiving the DAAB’s decision, then the decision shall
become final and binding on both Parties.
GUIDANCE
If the dissatisfied Party is dissatisfied with only part(s) of the DAAB’s decision:
FORMS
(iii) the remainder of the decision shall become final and binding on both
Parties as if the NOD had not been given.
21.5
Amicable Settlement Where a NOD has been given under Sub-Clause 21.4 [Obtaining DAAB’s
Decision], both Parties shall attempt to settle the Dispute amicably before
the commencement of arbitration. However, unless both Parties agree
otherwise, arbitration may be commenced on or after the twenty-eighth
(28th) day after the day on which this NOD was given, even if no attempt at
amicable settlement has been made.
21.6
Arbitration Unless settled amicably, and subject to Sub-Clause 3.7.5 [Dissatisfaction
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
(a) the Dispute shall be finally settled under the Rules of Arbitration of the
International Chamber of Commerce;
(b) the Dispute shall be settled by one or three arbitrators appointed in
accordance with these Rules; and
(c) the arbitration shall be conducted in the ruling language defined in
Sub-Clause 1.4 [Law and Language].
The arbitrator(s) shall have full power to open up, review and revise any
certificate, determination (other than a final and binding determination),
instruction, opinion or valuation of the Engineer, and any decision of the DAAB
(other than a final and binding decision) relevant to the Dispute. Nothing shall
disqualify the Engineer from being called as a witness and giving evidence
before the arbitrator(s) on any matter whatsoever relevant to the Dispute.
In any award dealing with costs of the arbitration, the arbitrator(s) may take
account of the extent (if any) to which a Party failed to cooperate with the
other Party in constituting a DAAB under Sub-Clause 21.1 [Constitution of
the DAAB] and/or Sub-Clause 21.2 [Failure to Appoint DAAB Member(s)].
obligations of the Parties, the Engineer and the DAAB shall not be altered by
GENERAL
reason of any arbitration being conducted during the progress of the Works.
21.7
Failure to Comply
with DAAB’s Decision In the event that a Party fails to comply with any decision of the DAAB, whether
binding or final and binding, then the other Party may, without prejudice to
any other rights it may have, refer the failure itself directly to arbitration under
Sub-Clause 21.6 [Arbitration] in which case Sub-Clause 21.4 [Obtaining
DAAB’s Decision] and Sub-Clause 21.5 [Amicable Settlement] shall not
FORMS
In the case of a binding but not final decision of the DAAB, such interim or
provisional measure or award shall be subject to the express reservation that
the rights of the Parties as to the merits of the Dispute are reserved until they
are resolved by an award.
relief.
21.8
No DAAB In Place If a Dispute arises between the Parties in connection with, or arising out of,
the Contract or the execution of the Works and there is no DAAB in place
(or no DAAB is being constituted), whether by reason of the expiry of the
DAAB’s appointment or otherwise:
116 © FIDIC & ITA 2019 Conditions of Contract for Underground Works
APPENDIX
CONDITIONS
GENERAL
General Conditions of DAAB Agreement
1
Definitions 1.1 “General Conditions of Dispute Avoidance/Adjudication Agreement”
GUIDANCE
or “GCs” means this document entitled “General Conditions of Dispute
Avoidance/Adjudication Agreement”, as published by FIDIC.
1.2 In the DAAB Agreement (as defined below) and in the GCs, words and
expressions which are not otherwise defined shall have the meanings
assigned to them in the Contract (as defined in the DAAB Agreement).
FORMS
1.3 “DAAB Agreement” is as defined under the Contract and is a tripartite
agreement by and between:
1.3 “DAAB’s Activities” means the activities carried out by the DAAB in
accordance with the Contract and the GCs, including all Informal Assistance,
meetings (including meetings and/or discussions between the DAAB
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
1.4 “DAAB Rules” means the document entitled “DAAB Procedural Rules”
published by FIDIC which are annexed to, and form part of, the GCs.
1.5 “Informal Assistance” means the informal assistance given by the DAAB
to the Parties when requested jointly by the Parties under Sub-Clause 21.3
[Avoidance of Disputes] of the Conditions of Contract.
1.6 “Term of the DAAB” means the period starting on the Effective Date (as
defined in Sub-Clause 2.1 below) and finishing on the date that the term of
the DAAB expires in accordance with Sub-Clause 21.1 [Constitution of the
DAAB] of the Conditions of Contract.
1.7 “Notification” means a notice in writing given under the GCs, which shall
be:
2
General Provisions 2.1 The DAAB Agreement shall take effect:
GUIDANCE
(a) in the case of a sole-member DAAB, on the date when the Employer,
the Contractor and the DAAB Member have each signed (or, under
the Contract, are deemed to have signed) the DAAB Agreement; or
(b) in the case of a three-member DAAB, on the date when the Employer,
the Contractor, the DAAB Member and the Other Members have each
signed (or under the Contract are deemed to have signed) a DAAB
Agreement.
FORMS
2.2 Immediately after the Effective Date, either or both Parties shall give a
Notification to the DAAB Member that the DAAB Agreement has come into
effect. If the DAAB Member does not receive such a notice within 182 days
after entering into the DAAB Agreement, it shall be void and ineffective.
3
Warranties 3.1 The DAAB Member warrants and agrees that he/she is, and will remain at
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
all times during the Term of the DAAB, impartial and independent of the
Employer, the Contractor, the Employer’s Personnel and the Contractor’s
Personnel (including in accordance with Sub-Clause 4.1 below).
3.2 If, after signing the DAAB Agreement (or after he/she is deemed to have
signed the DAAB Agreement under the Contract), the DAAB Member
becomes aware of any fact or circumstance which might:
3.3 When appointing the DAAB Member, each Party relies on the DAAB
Member’s representations that he/she is:
4
Independence and
Impartiality 4.1 Further to Sub-Clauses 3.1 and 3.2 above, the DAAB Member shall:
118 © FIDIC & ITA 2019 Conditions of Contract for Underground Works
(a) have no financial interest in the Contract, or in the project of which the
CONDITIONS
Works are part, except for payment under the DAAB Agreement;
GENERAL
(b) have no interest whatsoever (financial or otherwise) in the Employer, the
Contractor, the Employer’s Personnel or the Contractor’s Personnel;
(c) in the ten years before signing the DAAB Agreement, not have
been employed as a consultant or otherwise by the Employer, the
Contractor, the Employer’s Personnel or the Contractor’s Personnel;
GUIDANCE
(d) not previously have acted, and shall not act, in any judicial or arbitral
capacity in relation to the Contract;
(e) have disclosed in writing to the Employer, the Contractor and the
Other Members (if any), before signing the DAAB Agreement (or
before he/she is deemed to have signed the DAAB Agreement under
the Contract) and to his/her best knowledge and recollection, any:
(i) existing and/or past professional or personal relationships with
FORMS
any director, officer or employee of the Employer, the Contractor,
the Employer’s Personnel or the Contractor’s Personnel (including
as a dispute resolution practitioner on another project),
(ii) facts or circumstances which might call into question his/her
independence or impartiality, and
(iii) previous involvement in the project of which the Contract forms
part;
(f) not, while a DAAB Member and for the Term of the DAAB:
(i) be employed as a consultant or otherwise by, and/or
(ii) enter into discussions or make any agreement regarding future
employment with
the Employer, the Contractor, the Employer’s Personnel or the
Contractor’s Personnel, except as may be agreed by the Employer,
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
5
General Obligations
of the DAAB Member 5.1 The DAAB Member shall:
(a) comply with the GCs, the DAAB Rules and the Conditions of Contract
that are relevant to the DAAB’s Activities;
(b) not give advice to the Employer, the Contractor, the Employer’s
Personnel or the Contractor’s Personnel concerning the conduct of
the Contract, except as required to carry out the DAAB’s Activities;
(c) ensure his/her availability during the Term of the DAAB (except in
exceptional circumstances, in which case the DAAB Member shall
give a Notification without delay to the Parties and the Other Members
(if any) detailing the exceptional circumstances) for all meetings, Site
visits, hearings and as is necessary to comply with sub-paragraph (a)
above;
(d) become, and shall remain for the duration of the Term of the DAAB,
knowledgeable about the Contract and informed about:
(i) the Parties’ performance of the Contract;
(ii) the Site and its surroundings; and
(iii) the progress of the Works (and of any other parts of the project
of which the Contract forms part)
all documents received from either Party under Rule 4.3 of the DAAB
GENERAL
6
GUIDANCE
General Obligations
of the Parties 6.1 Each Party shall comply with the GCs, the DAAB Rules and the Conditions
of Contract that are relevant to the DAAB’s Activities. The Employer and the
Contractor shall be responsible for compliance with this provision by the
Employer’s Personnel and the Contractor’s Personnel, respectively.
6.2 Each Party shall cooperate with the other Party in constituting the DAAB,
FORMS
6.4 The Parties, the Employer’s Personnel and the Contractor’s Personnel shall
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
not request advice from or consultation with the DAAB Member regarding
the Contract, except as required for the DAAB Member to carry out the
DAAB’s Activities.
6.5 At all times when interacting with the DAAB, each Party shall not compromise
the DAAB’s warranty of independence and impartiality under Sub-Clause
3.1 above.
6.6 In addition to providing documents under Rule 4.3 of the DAAB Rules, each
Party shall ensure that the DAAB Member remains informed as is necessary
to enable him/her to comply with sub-paragraph (d) of Sub-Clause 5.1
above.
7
Confidentiality 7.1 Subject to Sub-Clause 7.4 below, the DAAB Member shall treat the details
of the Contract, all the DAAB’s Activities and the documents provided under
Rule 4.3 of the DAAB Rules as private and confidential, and shall not publish
or disclose them without the prior written consent of the Parties and the
Other Members (if any).
7.2 Subject to Sub-Clause 7.4 below, the Employer, the Contractor, the
Employer’s Personnel and the Contractor’s Personnel shall treat the details
of all the DAAB’s Activities as private and confidential.
120 © FIDIC & ITA 2019 Conditions of Contract for Underground Works
(b) becomes generally available to the public through no breach of the
CONDITIONS
GCs; or
GENERAL
(c) is lawfully obtained by the person from a third party which is not
bound by an obligation of confidentiality.
7.4 If a DAAB Member is replaced under the Contract, the Parties and/or the
Other Members (if any) shall disclose details of the Contract, the documents
provided under Rule 4.3 of the DAAB Rules and previous DAAB’s Activities
GUIDANCE
(including decisions, if any) to the replacement DAAB Member as is necessary
in order to:
FORMS
8
The Parties’ undertaking
and indemnity 8.1 The Employer and the Contractor undertake to each other and to the DAAB
Member that the DAAB Member shall not:
8.2 The Employer and the Contractor hereby jointly and severally indemnify and
hold the DAAB Member harmless against and from all damages, losses and
expenses (including legal fees and expenses) resulting from any claim from
which he/she is relieved from liability under Sub-Clause 8.1 above.
9
Fees and Expenses 9.1 The DAAB Member shall be paid as follows, in the currency named in the
DAAB Agreement:
(a) a monthly fee, which shall be a fixed fee as payment in full for:
(i) being available on 28-days’ notice for all meetings, Site visits and
hearings under the DAAB Rules (and, in the event of a request
under Rule 3.6 of the DAAB Rules, being available for an urgent
meeting or Site visit);
(ii) becoming and remaining knowledgeable about the Contract,
informed about the progress of the Works and maintaining
a current working file of documents, in accordance with
sub-paragraph (d) of Clause 5.1 above;
(iii) all office and overhead expenses including secretarial services,
photocopying and office supplies incurred in connection with his/
her duties; and
(iv) all services performed hereunder except those referred to in
sub-paragraphs (b) and (c) of this Clause.
This fee shall be paid monthly with effect from the last day of the month
in which the Effective Date occurs until the end of the month in which
the Term of the DAAB expires, or the DAAB Member declines to act
or is unable to act as a result of death, illness, disability, resignation or
termination of his/her DAAB Agreement.
General Conditions © FIDIC & ITA 2019
121
If no monthly fee is stated in the DAAB Agreement, the matters
CONDITIONS
(d) any taxes properly levied in the Country on payments made to the
DAAB Member (unless a national or permanent resident of the
Country) under this Sub-Clause 9.1.
9.2 Subject to Sub-Clause 9.3 below, the amounts of the DAAB Member’s
monthly fee and daily fee, under Sub-Clause 9.1 above, shall be as specified
in the DAAB Agreement signed (or, under the Contract, deemed to have
been signed) by the Parties and the DAAB Member.
9.3 If the Parties and the DAAB Member have agreed all other terms of the DAAB
Agreement but fail to jointly agree the amount of the monthly fee or the daily
fee in the DAAB Agreement (the “non-agreed fee” in this Sub-Clause):
122 © FIDIC & ITA 2019 Conditions of Contract for Underground Works
(e) thereafter, after giving credit to the Parties for all amounts previously
CONDITIONS
paid in respect of the non-agreed fee, the balance (if any) due from
GENERAL
the DAAB Member to the Parties or from the Parties to the DAAB
Member, as the case may be, shall be paid.
9.4 The DAAB Member shall submit invoices for payment of the monthly fee
and air fares quarterly in advance. Invoices for other expenses and for daily
fees shall be submitted following the conclusion of a meeting, Site visit or
GUIDANCE
hearing; and following the giving of a decision or an informal written note
(under Rule 2.1 of the DAAB Rules). All invoices shall be accompanied by
a brief description of the DAAB’s Activities performed during the relevant
period and shall be addressed to the Contractor.
9.5 The Contractor shall pay each of the DAAB Member’s invoices in full within
28 days after receiving each invoice. Thereafter, the Contractor shall apply
FORMS
to the Employer (in the Statements under the Contract) for reimbursement of
one-half of the amounts of these invoices. The Employer shall then pay the
Contractor in accordance with the Contract.
9.6 If the Contractor fails to pay to the DAAB Member the amount to which
he/she is entitled under the DAAB Agreement within the period of 28
days stated at Sub-Clause 9.5 above, the DAAB Member shall inform the
Employer who shall promptly pay the amount due to the DAAB Member
and any other amount which may be required to maintain the function of
the DAAB. Thereafter the Employer shall, by written request, be entitled to
payment from the Contractor of:
and
(b) financing charges calculated at the rate specified in Sub-Clause 14.9
[Delayed Payment] of the Conditions of Contract.
The Employer shall be entitled to such payment from the Contractor without
any requirement to comply with Sub-Clause 20.2 [Claims For Payment and/
or EOT] of the Conditions of Contract, and without prejudice to any other
right or remedy.
9.7 If the DAAB Member does not receive payment of the amount due within 56
days after submitting a valid invoice, the DAAB Member may:
(a) not less than 7 days after giving a Notification to the Parties and the
Other Members (if any), suspend his/her services until the payment is
received; and/or
(b) resign his/her appointment by giving a Notification under Sub-Clause
10.1 below.
10
Resignation
and Termination 10.1 The DAAB Member may resign at any time for any reason, by giving a
Notification of not less than 28 days (or other period as may be agreed by the
Parties) to the Parties and to the Other Members (if any). During this period the
Parties shall take the necessary steps to appoint, without delay, a replacement
DAAB Member in accordance with Sub-Clause 21.1 [Constitution of the
DAAB] of the Conditions of Contract (and, if applicable, Sub-Clause 21.2
[Failure to Appoint DAAB Member(s)] of the Conditions of Contract).
10.3 At any time the Parties may jointly terminate the DAAB Agreement by giving
a Notification of not less than 42 days to the DAAB Member.
10.4 If the DAAB Member fails, without justifiable excuse, to comply with
Sub-Clause 5.1 above, the Parties may, without prejudice to their other
FORMS
10.5 If either Party fails, without justifiable excuse, to comply with Clause 6 above,
the DAAB Member may, without prejudice to his/her other rights or remedies,
terminate the DAAB Agreement by giving a Notification to the Parties. This
notice shall take effect when received by both Parties.
10.6 Any resignation or termination under this Clause shall be final and binding
on the Parties and the DAAB Member. However, a notice given under
Sub-Clause 10.3 or 10.4 above by either the Employer or the Contractor,
but not by both, shall be of no effect.
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
10.9 Subject to any mandatory requirements under the governing law of the DAAB
Agreement, termination of the DAAB Agreement under this Clause shall
require no action of whatsoever kind by the Parties or the DAAB Member (as
the case may be) other than as stated in this Clause.
11
Challenge 11.1 The Parties shall not object against the DAAB Member, except that either
Party, or in the case of a three-member DAAB the Other Members jointly,
shall be entitled to do so for an alleged lack of independence or impartiality or
otherwise in which case Rule 10 Objection Procedure and Rule 11 Challenge
Procedure of the DAAB Rules shall apply.
11.2 The decision issued under Rule 11 of the DAAB Rules (the “Decision on the
Challenge” in the GCs) shall be final and conclusive.
124 © FIDIC & ITA 2019 Conditions of Contract for Underground Works
11.3 At any time before the Decision on the Challenge is issued, the challenged
CONDITIONS
DAAB Member may resign under Sub-Clause 10.1 above and, in such case,
GENERAL
the challenging Party shall inform the International Chamber of Commerce
(ICC). However, Sub-Clause 10.2 shall not apply to such resignation and the
resigning DAAB Member’s DAAB Agreement shall terminate with immediate
effect.
11.4 Unless the challenged DAAB Member has resigned, or his/her DAAB
GUIDANCE
Agreement has been terminated under Sub-Clause 10.3 above, the DAAB
Member and the Other Members (if any) shall continue with the DAAB’s
Activities until the Decision on the Challenge is issued.
FORMS
Agreement, shall be deemed to have been terminated with immediate
effect on the date of the notification of the Decision on the Challenge by
ICC;
(b) the challenged DAAB Member shall not be entitled to any fees or
expenses under his/her DAAB Agreement from the date of the
notification of the Decision on the Challenge by ICC;
(c) any decision under Sub-Clause 21.4.3 [The DAAB’s decision] of the
Conditions of Contract, given by the DAAB:
(i) after the challenge was referred under Rule 11 of the DAAB
Rules; and
(ii) before the resignation (if any) of the challenged DAAB Member
under Sub-Clause 11.3 above, or his/her DAAB Agreement is
terminated under sub-paragraph (a) above or under Sub-Clause
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
10.3 above
shall become void and ineffective. In the case of a sole-member
DAAB, all other DAAB’s Activities during this period shall also become
void and ineffective. In the case of a three-member DAAB, all other
DAAB’s Activities during this period shall remain unaffected by the
Decision on the Challenge except if there has been a challenge to all
three members of the DAAB and such challenge is successful;
(d) the successfully challenged DAAB Member shall be removed from the
DAAB; and
(e) the Parties shall, without delay, appoint a replacement DAAB Member
in accordance with Sub-Clause 21.1 [Constitution of the DAAB] of the
Conditions of Contract.
12
Disputes under
the DAAB Agreement Any dispute arising out of or in connection with the DAAB Agreement, or the
breach, termination or invalidity thereof, shall be finally settled by arbitration
under the Rules of Arbitration of the International Chamber of Commerce
2017 by one arbitrator appointed in accordance with these Rules of
Arbitration, and Article 30 and the Expedited Procedure Rules at Appendix
VI of these Rules of Arbitration shall apply.
Rule 1
Objectives 1.1 The objectives of these Rules are:
Rule 2
FORMS
Avoidance of Disputes 2.1 Where Sub-Clause 21.3 [Avoidance of Disputes] of the Conditions of Contract
applies, the DAAB (in the case of a three-member DAAB, all three DAAB
Members acting together) may give Informal Assistance during discussions
at any meeting with the Parties (whether face-to-face or by telephone or by
video conference) or at any Site visit or by an informal written note to the
Parties.
Rule 3
Meetings and Site Visits 3.1 The purpose of meetings with the Parties and Site visits by the DAAB is to
enable the DAAB to:
(b) become aware of, and remain informed about, any actual or potential
issue or disagreement between the Parties; and
(c) give Informal Assistance if and when jointly requested by the Parties.
3.2 As soon as practicable after the DAAB is appointed, the DAAB shall convene
a face-to-face meeting with the Parties. At this meeting, the DAAB shall
establish a schedule of planned meetings and Site visits in consultation with
the Parties, which schedule shall reflect the requirements of Rule 3.3 below
and shall be subject to adjustment by the DAAB in consultation with the
Parties.
3.3 The DAAB shall hold face-to-face meetings with the Parties, and/or visit the
Site, at regular intervals and/or at the written request of either Party. The
frequency of such meetings and/or Site visits shall be:
3.4 In addition to the face-to-face meetings referred to in Rules 3.2 and 3.3
above, the DAAB may also hold meetings with the Parties by telephone or
video conference as agreed with the Parties (in which case each Party bears
the risk of interrupted or faulty telephone or video conference transmission
and reception).
126 © FIDIC & ITA 2019 Conditions of Contract for Underground Works
3.5 At times of critical construction events (which may include suspension of
CONDITIONS
the Works or termination of the Contract), the DAAB shall visit the Site at
GENERAL
the written request of either Party. This request shall describe the critical
construction event. If the DAAB becomes aware of an upcoming critical
construction event, it may invite the Parties to make such a request.
3.6 Either Party may request an urgent meeting or Site visit by the DAAB. This
shall be a written request and shall give reasons for the urgency of the
GUIDANCE
meeting or Site visit. If the DAAB agrees that such a meeting or Site visit is
urgent, the DAAB Members shall use all reasonable endeavours to:
FORMS
to respond to or oppose this request) the DAAB agrees that a Site visit is
necessary, visit the Site within 14 days after the date of this meeting.
3.7 The time of, and agenda for, each meeting and Site visit shall be set by the
DAAB in consultation with the Parties.
3.8 Each meeting and Site visit shall be attended by the Employer, the Contractor
and the Engineer.
3.9 Each meeting and Site visit shall be co-ordinated by the Contractor in
co-operation with the Employer and the Engineer. The Contractor shall
ensure the provision of appropriate:
(a) personal safety equipment, security controls (if necessary) and site
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
3.10 At the conclusion of each meeting and Site visit and, if possible before
leaving the venue of the face-to-face meeting or the Site (as the case may
be) but in any event within 7 days, the DAAB shall prepare a report on its
activities during the meeting or Site visit and shall send copies of this report
to the Parties and the Engineer.
Rule 4
Communications
and Documentation 4.1 The language to be used:
(a) in all communications to and from the DAAB and the Parties (and, in
the case of a three-member DAAB, between the DAAB Members);
(b) in all reports and decisions issued by the DAAB; and
(c) during all Site visits, meetings and hearings relating to the DAAB’s
Activities
4.2 All communications and/or documents sent between the DAAB and a
Party shall simultaneously be copied to the other Party. In the case of a
4.3 The Parties shall provide the DAAB with a copy of all documents which the
DAAB may request, including:
and any other document relevant to the performance of the Contract and/
or necessary to enable the DAAB to become and remain informed about the
matters described in sub-paragraphs (d)(i) to (d)(iii) of Sub-Clause 5.1 of the GCs.
Rule 5
Powers of the DAAB 5.1 In addition to the powers granted to the DAAB under the Conditions of
Contract, the General Conditions of the DAAB Agreement and elsewhere in
these Rules, the Parties empower the DAAB to:
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
CONDITIONS
powers granted to the DAAB, under the Conditions of Contract, the GCs
GENERAL
and these Rules, may be exercised.
Rule 6
Disputes 6.1 If any Dispute is referred to the DAAB in accordance with Sub-Clause
21.4.1 [Reference of a Dispute to the DAAB] of the Conditions of Contract,
the DAAB shall proceed in accordance with Sub-Clause 21.4 [Obtaining
GUIDANCE
DAAB’s Decision] of the Conditions of Contract and these DAAB Rules, or
as otherwise agreed by the Parties in writing.
6.2 The DAAB shall act fairly and impartially between the Parties and, taking due
regard of the period under Sub-Clause 21.4.3 [The DAAB’s decision] of the
Conditions of Contract and other relevant circumstances, the DAAB shall:
FORMS
(a) give each Party a reasonable opportunity (consistent with the
expedited nature of the DAAB proceeding) of putting forward its case
and responding to the other Party’s case; and
(b) adopt a procedure in coming to its decision that is suitable to the
Dispute, avoiding unnecessary delay and/or expense.
Rule 7
Hearings 7.1 In addition to the powers under Rule 5.1 above, and except as otherwise
agreed in writing by the Parties, the DAAB shall have power to:
(a) decide on the date and place for any hearing, in consultation with the
Parties;
(b) decide on the duration of any hearing;
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
(c) request that written documentation and arguments from the Parties
be submitted to it prior to the hearing;
(d) adopt an inquisitorial procedure during any hearing:
(e) request the production of documents, and/or oral submissions by
the Parties, at any hearing that the DAAB considers may assist in
exercising the DAAB’s power under sub-paragraph (g) of Rule 5.1
above;
(f) request the attendance of persons at any hearing that the DAAB
considers may assist in exercising the DAAB’s power under
sub-paragraph (g) of Rule 5.1 above;
(g) refuse admission to any hearing, or audience at any hearing, to any
persons other than representatives of the Employer, the Contractor
and the Engineer;
(h) proceed in the absence of any party who the DAAB is satisfied
received timely notice of the hearing;
(i) adjourn any hearing as and when the DAAB considers further
investigation by one Party or both Parties would benefit resolution
of the Dispute, for such time as the investigation is carried out, and
resume the hearing promptly thereafter.
7.2 The DAAB shall not express any opinions during any hearing concerning the
merits of any arguments advanced by either Party in respect of the Dispute.
7.3 The DAAB shall not give any Informal Assistance during a hearing, but if the
Parties request Informal Assistance during any hearing:
(a) the hearing shall be adjourned for such time as the DAAB is giving
Informal Assistance;
Rule 8
GUIDANCE
The DAAB’s Decision 8.1 The DAAB shall make and give its decision within the time allowed under
Sub-Clause 21.4 [Obtaining DAAB’s Decision] of the Conditions of Contract,
or other time as may be proposed by the DAAB and agreed by the Parties in
writing.
(a) it shall meet in private (after the hearing, if any) in order to have
discussions and to start preparation of its decision;
(b) the DAAB Members shall use all reasonable endeavours to reach a
unanimous decision;
(c) if it is not possible for the DAAB Members to reach a unanimous
decision, the applicable decision shall be made by a majority of
the DAAB Members, who may require the minority DAAB Member
to prepare a separate written report (with reasons and supporting
particulars) which shall be issued to the Parties; and
(d) if a DAAB Member fails to:
(i) attend a hearing (if any) or a DAAB Members’ meeting; or
(ii) fulfil any required function (other than agreeing to a unanimous
decision)
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
8.4 If, within 14 days of receiving a decision from the DAAB, either Party finds
a typographical, clerical or arithmetical error in the decision, that Party may
request the DAAB to correct such error. This shall be a written request and
shall clearly identify the error.
8.5 If, within 14 days of receiving a decision from the DAAB, either Party believes
that such decision contains an ambiguity, that Party may request clarification
from the DAAB. This shall be a written request and shall clearly identify the
ambiguity.
130 © FIDIC & ITA 2019 Conditions of Contract for Underground Works
8.6 The DAAB shall respond to a request under Rule 8.4 or Rule 8.5 above within
CONDITIONS
14 days of receiving the request. The DAAB may decline (at its sole discretion
GENERAL
and with no requirement to give reasons) any request for clarification under
Rule 8.5. If the DAAB agrees (in the case of a three-member DAAB they
agree unanimously or by majority) that the decision did contain the error or
ambiguity as described in the request, it may correct its decision by issuing
an addendum to its original decision in writing to the Parties, in which case
this addendum shall be issued together with the DAAB’s response under this
GUIDANCE
Rule.
8.7 If the DAAB issues an addendum to its original decision under Rule 8.3
or 8.6 above, such an addendum shall form part of the decision and the
period stated in sub-paragraph (c) of Sub-Clause 21.4.4 [Dissatisfaction
with DAAB’s decision] of the Conditions of Contract shall be calculated from
the date the Parties receive this addendum.
FORMS
Rule 9
In the event of
Termination of
DAAB Agreement 9.1 If, on the date of termination of a DAAB Member’s DAAB Agreement arising
from resignation or termination under Clause 10 of the GCs, the DAAB
is dealing with any Dispute under Sub-Clause 21.4 [Obtaining DAAB’s
Decision] of the Conditions of Contract:
(a) the period under Sub-Clause 21.4.3 [The DAAB’s decision] of the
Conditions of Contract shall be temporarily suspended; and
(b) when a replacement DAAB Member is appointed in accordance
with Sub-Clause 21.1 [Constitution of the DAAB] of the Conditions
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
Rule 10
Objection Procedure 10.1 The following procedure shall apply to any objection against a DAAB
Member:
(a) the objecting Party shall, within 7 days of becoming aware of the facts
and/or events giving rise to the objection, give a Notification to the
DAAB Member of its objection. This Notification shall:
(i) state that it is given under this Rule;
(ii) state the reason(s) for the objection;
(iii) substantiate the objection by setting out the facts, and describing
the events, on which the objection is based, with supporting
particulars; and
(iv) be simultaneously copied to the other Party and the Other
Members;
(b) within 7 days after receiving a notice under sub-paragraph (a) above,
the objected DAAB Member shall respond to the objecting Party.
This response shall be simultaneously copied to the other Party and
the Other Members. If no response is given by the DAAB Member
based;
(c) within 7 days after receiving the objected DAAB Member’s response
under sub-paragraph (b) above (or, if there is no such response, after
expiry of the period of 7 days stated in sub-paragraph (b) above) the
objecting Party may formally challenge a DAAB member in accordance
with Rule 11 below;
GUIDANCE
(d) if the challenge is not referred within the period of 7 days stated in
sub-paragraph (c) above, the objecting Party shall be deemed to have
agreed to the DAAB Member remaining on the DAAB and shall not
be entitled to object and/or challenge him/her thereafter on the basis
of any of the facts and/or evidence stated in the notice given under
sub-paragraph (a) above;
Rule 11
FORMS
Challenge Procedure 11.1 If and when the objecting Party challenges a DAAB Member, within 21 days
of learning of the facts upon which the challenge is based, the provisions
of this Rule shall apply. Any challenge is to be decided by the International
Chamber of Commerce (ICC) and administered by the ICC International
Centre for ADR.
11.2 The procedure for such challenge and information on associated charges to
be paid are set out at http://fidic.org and http://iccwbo.org.
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
132 © FIDIC & ITA 2019 Conditions of Contract for Underground Works
INDEX OF SUB-CLAUSES
CONDITIONS
Sub-Clause Page
GENERAL
Accepted Contract Amount, Sufficiency of the 4.11 35
Access after Taking Over, Right of 11.7 68
Access Route 4.15 37
Access to the Site, Right of 2.1 17
GUIDANCE
Adjustments for Changes in Cost 13.7 77
Adjustments for Changes in Laws 13.6 76
Advance Payment 14.2 80
Advance Warning 8.4 56
Agreement, Contract 1.6 11
Agreement or Determination 3.7 22
FORMS
Amicable Settlement 21.5 115
Arbitration 21.6 115
Archaeological and Geological Findings 4.23 40
As-Built Records 5.6 45
Assignment 1.7 11
Assistance 2.2 17
Authorities, Delays Caused by 8.6 57
Avoidance of Interference 4.14 37
Co-operation 4.6 30
GENERAL
134 © FIDIC & ITA 2019 Conditions of Contract for Underground Works
Exceptional Event, Notice of an 18.2 101
CONDITIONS
Exceptional Event, Consequences of an 18.4 102
GENERAL
Extension of Defects Notification Period 11.3 65
Extension of Time of Completion 8.5 56
GUIDANCE
FPC, Issue of 14.13 89
FORMS
Indemnities by Contractor 17.4 99
Indemnities by Employer 17.5 100
Indemnities, Shared 17.6 100
Inspection 7.3 50
Instructions, Engineer’s 3.5 21
Insurance to be provided by the Contractor 19.2 104
Insurance: General Requirements 19.1 103
Intellectual and Industrial Property Rights 17.3 99
Interference, Avoidance of 4.14 37
Interference with Tests on Completion 10.3 64
Interim Payment, Application for 14.3 81
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
Interpretation 1.2 9
Issue of FPC 14.13 89
Issue of IPC 14.6 84
Payment 14.7 86
Payment after Termination by the Contractor 16.4 97
Payment, Currencies of 14.15 90
GUIDANCE
Samples 7.2 50
Schedule of Payments 14.4 82
Search, Contractor to 11.8 68
Security of the Site 4.21 40
Security, Performance 4.2 26
Setting Out 4.7 31
136 © FIDIC & ITA 2019 Conditions of Contract for Underground Works
Site, Clearance of 11.11 69
CONDITIONS
Site, Contractor’s Operations on 4.22 40
GENERAL
Site Data, Use of 4.10 34
Site Data and Items of Reference 2.5 18
Site, Right of Access to the 2.1 17
Site, Security of the 4.21 40
Staff and Labour, Engagement of 6.1 46
GUIDANCE
Staff and Labour, Facilities for 6.6 47
Standards and Regulations, Technical 5.4 44
Statement at Completion 14.10 87
Statement, Final 14.11 87
Subcontractors 4.4 28
Subcontractors, nominated 4.5 29
FORMS
Superintendence, Contractor’s 6.8 48
Surfaces Requiring Reinstatement 10.4 64
Suspension, Consequences of Employer’s 8.10 58
Suspension by Contractor 16.1 95
Suspension, Employer’s 8.9 58
Suspension, Payment for Plant and Materials after Employer’s 8.11 59
Suspension, Prolonged 8.12 59
138 © FIDIC & ITA 2019 Conditions of Contract for Underground Works
GENERAL CONDITIONS
PREPARATION OF
TENDER DOCUMENTS
AND ANNEXES: TABLE
OF CONTENTS OF
THE GEOTECHNICAL
BASELINE REPORT,
EXAMPLE FORMS
OF SCHEDULE OF
BASELINES, COMPLETION
SCHEDULE, SCHEDULE
OF CONTRACTOR’S KEY
EQUIPMENT
FORMS OF LETTER OF
TENDER, LETTER OF
ACCEPTANCE, CONTRACT
AGREEMENT AND
DISPUTE ADJUDICATION/
AVOIDANCE AGREEMENT
In collaboration with
CONDITIONS
GENERAL
for the Preparation of Particular Conditions
CONTENTS
INTRODUCTORY GUIDANCE NOTES. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
GUIDANCE
CONTRACT DATA . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
INTRODUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
FORMS
1 General Provisions. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
2 The Employer. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19
3 The Engineer . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21
4 The Contractor. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
5 Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28
9 Tests on Completion. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 36
15 Termination by Employer . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 47
18 Exceptional Events. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 49
19 Insurance. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 49
Certain Sub-Clauses in the General Conditions require that specific information is provided in the
Contract Data.
The Employer should amend as appropriate and complete all data and should insert “Not Applicable”
in the space next to any Sub-Clause which the Employer does not wish to use.
FORMS
The Employer should insert “Tenderer to Complete” in the space next to any Sub-Clause which
the Employer wishes Contract Data to be completed by the tenderers. Except where indicated
“Tenderer to Complete” tenderers shall not amend the Contract Data as provided by the Employer.
All italicised text and any enclosing square brackets are for use in preparing the Contract Data and
should be deleted from the final version of the Contract Data.
Failure by the Employer to provide the information and details required in the Contract Data could
mean either that the documents forming the Contract are incomplete with vital information missing,
or that the fall-back provisions to be found in some of the Sub-Clauses in the General Conditions
will automatically take effect.
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
CONDITIONS
GENERAL
Sub-Clause Data to be given Data
GUIDANCE
percentage profit to be added to the Cost:..................... ________ %
FORMS
1.1.41.......... Engineer’s name and address:........................................ ___________________
___________________
___________________
___________________
percent:................................................................ ________ %
currency:.............................................................. ___________________
4.7.2............ period for notification of errors in the items of reference.. ________ days
CONDITIONS
GENERAL
14.2............. Currency or currencies of Advance Payment.................. ___________________
___________________
14.2.3.......... percentage deductions for the repayment of the Advance
Payment......................................................................... ________ %
GUIDANCE
14.3(b).......... number of additional paper copies of Statements........... ________
FORMS
Contract Amount)........................................................... ________ %
___________________ ___________________
___________________ ___________________
19.2.3(b)....... insurance required against liability for fitness for purpose. yes / no
(delete as appropriate)
CONDITIONS
GENERAL
19.2.6.......... other insurances required by Laws and by local practice
(give details).................................................................... ___________________
GUIDANCE
21.1............. list of proposed members of DAAB
- proposed by Employer................................................. 1.__________________
2.__________________
3.__________________
FORMS
- proposed by Contractor............................................... 1.__________________
2.__________________
3.__________________
(Unless otherwise
stated here, it shall be
the President of FIDIC
or a person appointed
by the President)
* These percentages shall also be applied to each half of the Retention Money under Sub-Clause 14.9.
Definition of Milestones:
Description of the event that does not correspond Time for Completion Delay Damages
with the whole of the Works or with any Section and (Calculated from the (Sub-Clause 8.8)
is designated a Milestone for the purposes of the Commencement Date)
Contract (Sub-Clause1.1.99)
Maximum amount of delay damages for Milestones (percent of final Contract Price) ….. ____ %
INTRODUCTION
The terms of the Conditions of Contract for Underground Works have been prepared by the
Fédération Internationale des Ingénieurs-Conseils (FIDIC) in collaboration with the International
GUIDANCE
Tunnelling and Underground Space Association (ITA-AITES) and are recommended for general use
for the execution of Underground Works, where tenders are invited on an international basis.
Modifications to the General Conditions may well be required to account for local legal requirements,
particularly if they are to be used on domestic contracts.
Under the usual arrangements for these types of contract, the Contractor is responsible for the
FORMS
execution (design and construction) of underground works, in accordance with the requirements
of the Employer. These Conditions are based on the premise that the Employer shall include a
Geotechnical Baseline Report together with a Schedule of Baselines and a Completion Schedule, a
Bill of Quantities, Employer’s Requirements and an outline reference design for the Works, but they
are not intended for use where the Contractor is to construct the Works in accordance with a detailed
design provided by the Employer. In this latter case, it is recommended that the Employer consider
using FIDIC’s Conditions of Contract for Construction, Second Edition 2017; with appropriate
Particular Conditions of Contract which are specific to Underground Works which may be based on
the provision of these General Conditions of Contract including in particular a Geotechnical Baseline
Report, a Schedule of Baselines and a Completion Schedule.
The guidance hereafter is intended to assist drafters of the Special Provisions (Particular Conditions
– Part B) by giving options for various sub-clauses where appropriate. In some cases example
wording is included between lines, while in other instances only an aide-memoire is given.
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
FIDIC strongly recommends that the Employer, the Contractor and all drafters of the
Special Provisions take all due regard of the five FIDIC Golden Principles:
GP1: The duties, rights, obligations, roles and responsibilities of all the Contract
Participants must be generally as implied in the General Conditions, and
appropriate to the requirements of the project.
GP3: The Particular Conditions must not change the balance of risk/reward allocation
provided for in the General Conditions.
GP4: All time periods specified in the Contract for Contract Participants to perform
their obligations must be of reasonable duration.
GP5: Unless there is a conflict with the governing law of the Contract, all formal
disputes must be referred to a Dispute Avoidance/Adjudication Board (or a
Dispute Adjudication Board, if applicable) for a provisionally binding decision as a
condition precedent to arbitration.
These FIDIC golden principles are described and explained in the publication FIDIC’s
Golden Principles (http://http://fidic.org/bookshop †), and are necessary to ensure that
modifications to the General Conditions:
- are limited to those necessary for the particular features of the Site and the
project, and necessary to comply with the applicable law;
- do not change the essential fair and balanced character of a FIDIC contract; and
CONDITIONS
ensure that it is wholly suitable for the particular circumstances. Unless it is considered suitable,
GENERAL
example wording should be amended before use.
Where any amendments or additions are made to the General Conditions, great care must be
taken to ensure that the wording does not unintentionally alter the meaning of other clauses in the
Conditions of Contract, does not inadvertently change the obligations assigned to the Parties or the
balance of risks shared between them and/or does not create any ambiguity or misunderstanding in
GUIDANCE
the rest of the Contract documents. In particular, FIDIC and ITA strongly recommend that the drafter
should refrain from modifying any Sub-Clause specifically referring to Underground Works.
Each time period stated in the General Conditions is what FIDIC believes is reasonable, realistic and
achievable in the context of the obligation to which it refers, and reflects the appropriate balance
between the interests of the Party required to perform the obligation, and the interests of the other
Party whose rights are dependent on the performance of that obligation. If consideration is given
FORMS
to changing any such stated time period in the Special Provisions (Particular Conditions – Part B),
care should be taken to ensure that the amended time period remains reasonable, realistic and
achievable in the particular circumstances.
There are a number of Sub-Clauses in the General Conditions which require data to be provided by
the Employer and/or the Contractor and inserted into the Contract Data (Particular Conditions – Part
A). However, there are no Sub-Clauses in the General Conditions which require data or information
to be included in the Special Provisions (Particular Conditions – Part B).
Provisions found in the Contract documents under Special Provisions (Particular Conditions – Part B)
indicate that the General Conditions have been amended or supplemented.
In describing the Conditions of Contract in the tender documents, the following text can be used:
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
“The Conditions of Contract comprise the “General Conditions”, which form part of the
“Conditions of Contract for Underground Works” First Edition 2019 published by the
Fédération Internationale des Ingénieurs-Conseils (FIDIC) in joint endeavour with the
International Tunnelling and Underground Space Association (ITA-AITES), the Contract
Data (Particular Conditions – Part A), and the following “Special Provisions” (Particular
Conditions – Part B) which include amendments and additions to such General
Conditions.”
The provisions of the Special Provisions (Particular Conditions – Part B) will always over-rule and
supersede the equivalent provisions in the General Conditions, and it is important that the changes are
easily identifiable by using the same clause numbers and titles as appear in the General Conditions.
Furthermore, it is necessary to add a statement in the tender documents for a contract that:
“The provisions to be found in the Special Provisions (Particular Conditions – Part B) take
precedence over the equivalent provisions found under the same Sub-Clause number(s)
in the General Conditions, and the provisions of the Contract Data (Particular Conditions
– Part A) take precedence over the Special Provisions (Particular Conditions – Part B).”
†
Please Note: all web links referred to in these guidance notes are up-to-date as of the date of this
publication but it is recommended that users of these guidance notes check online, at the time that
they wish to reference the relevant document, for the most up-to-date version of the document.
As with all FIDIC standard conditions, some Sub-Clauses may require modifications due to local
legal requirements or project specific considerations. Many of the guidance notes provided for the
drafting of the Particular Conditions for various Sub-Clauses for the Conditions of Contract for Plant
and Design Build are applicable for the Particular Conditions for Underground Works. FIDIC and
ITA recommend to avoid modifying the specific Sub-Clauses that FIDIC and ITA have adapted for
Underground Works. The modified Sub-Clauses are the result of extensive deliberation and analysis
by a group of international experts on the subject. Partial modification of the Sub-Clauses could
result in unintended consequences or could make the proposed Contract framework ineffective.
1.1 Definitions
1.1.5 Bill of Quantities
1.1.8 Completion Schedule
1.1.11 Contract
GUIDANCE
Other Sub-Clauses :
1.2 Interpretation
1.5 Priority of Documents
1.9 Errors in the Employer’s Requirements and/or in the Geotechnical Baseline Report
1.16 Contract Risk Register and Contract Risk Management Plan
2.5 Site Data and Items of Reference
3.2 Engineer’s Duties and Authority, Sub-Clauses 3.2.1 and 3.2.2
3.7 Agreement or Determination
4.10 Use of Site Data, of the Geotechnical Baseline Report and of the Geotechnical Data
Report
4.10.1 Use of Site Data
4.10.2 Use of the Geotechnical Baseline Report
4.10.3 Use of the Geotechnical Data Report
4.11 Sufficiency of the Accepted Contract Amount
CONDITIONS
4.12.1 Contractors’ Notice,
GENERAL
4.12.2 Engineer’s inspection and investigation
4.12.5 Agreement or Determination of Delay and/or Cost
4.16 Transport of Goods
4.17 Contractor’s Equipment
GUIDANCE
4.20 Progress Reports
4.24 Excavation and Lining Works
4.25 Milestones
5.1 General Design Obligations
5.2 Contractor’s Documents
FORMS
6.12 Contractor’s Key Personnel
7.1 Manner of Execution
7.7 Ownership of Plant and Materials
8.2 Time for Completion
8.2.1 The Completion Schedule
8.2.2 The Schedule of Baselines
8.3 Programme
8.4 Advance Warning
8.5 Extension of Time for Completion
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
It is very important that Employers (and all drafters of the Special Provisions) work with their
professional advisers to review specific terminology in the General Conditions for compliance and
consistency with accepted practice in the legal jurisdiction they are operating in.
For example:
GUIDANCE
• under a number of legal systems (notably in some common law jurisdictions) the term
“gross negligence” has no clear definition and, as such, is often avoided in legal documents;
and
• under English law, the term “indemnity” or “indemnify” has a specific meaning, entitling
the indemnified party to recover certain losses that may not otherwise be recoverable at
law. For example, a Contractor’s indemnity may be construed to permit the Employer to
recover losses or damages that might otherwise be considered indirect or consequential,
FORMS
whereas for some events which may arise both Parties’ losses or damages are intended
to be limited by Sub-Clause 1.15 [Limitation of Liability] to direct damages only.
The following references and examples show some of the Sub-Clauses in the General Conditions
which may need amending to suit the needs of the project or the requirements of the Employer. The
selected Sub-Clauses and the example wording are included as examples only. They also include,
as an aide-memoire, references to other documents such as the Employer’s Requirements and the
Contract Data, where particular issues may need to be addressed.
The selected Sub-Clauses do not necessarily require changing and the example wording may not
suit the needs of a particular project or Employer. It is the responsibility of the drafter of the Special
Provisions to ensure that the selection of the Sub-Clauses and the choice of wording is appropriate
to the project concerned.
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
Furthermore, there may be other Sub-Clauses, not mentioned below, which need to be amended.
Great care must be taken when amending the wording of Sub-Clauses from the General Conditions,
or adding new provisions, to ensure that the balance of obligations and rights of the Parties are not
unintentionally compromised.
CONDITIONS
Requirements. However, it may also be necessary under other Sub-Clauses for the Employer to give
GENERAL
specific information in the Employer’s Requirements (for example, under Sub-Clause 7.2 [Samples]).
1.8 Care and Supply of Documents
GUIDANCE
2.5 Site Data and Items of Reference
FORMS
4.6 Co-operation
5.5 Training
7.3 Inspection
7.8 Royalties
8.3 Programme
Data (Particular Conditions – Part A). This data must be provided in the tender documents, and
GENERAL
these Conditions of Contract assume that all such data will be provided by the Employer, except as
expressly noted in the example form of Contract Data included in this publication. If the Employer
requires tenderers to provide any of the other information required in the Contract Data, the tender
documents must make this clear.
If the Employer requires tenderers to provide additional data or information, a convenient way of
GUIDANCE
doing this is to provide a suitably worded questionnaire with the tender documents.
The Instructions to Tenderers may need to specify any constraints on the completion of the Contract
Data and/or Schedules, and/or specify the extent of other information which each tenderer is to
include with his/her Tender. If each tenderer is to produce a tender security and/or a parent company
guarantee, these requirements should be included in the Instructions to Tenderers: example forms
are included at the end of this publication.
FORMS
The Instructions to Tenderers may require the tenderer to provide information on the matters referred
to in some or all of the following Sub-Clauses:
4.3 Contractor’s Representative
19 Insurance
It is important for the Parties to understand which of the documents included in the tender dossier,
and which of the documents submitted by tenderers, will form part of the Contract and therefore
have continuing effect. For example, the Instructions to Tenderers are not, by definition, a part of
the Contract. They are simply instructions and information on the preparation and submission of the
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
tender, and they should not contain anything of a binding or contractual nature.
If the design-build contract is to include fixtures, fittings equipment, and other similar items, the
scope of such work must be defined in the Employer’s Requirements. Full consideration should
be given to detailed requirements for these items, such as the extent to which the Works are to be
fully equipped, ready for operation, with spare parts and consumables provided for operation (for
a specified period), typically by the Employer. If the Contractor is required to operate the Works,
either for a few months’ trial operation under sub-paragraph (c) of Sub-Clause 9.1 [Contractor’s
Obligations] or for some years’ operation, this must also be specified and detailed in the Employer’s
Requirements.
If tenderers are required to carry out any preliminary design or study for their proposals, the Employer
should bear in mind that tenderers are understandably often reluctant to incur great expense in the
preparation of tender designs. Therefore, when preparing the Instructions to Tenderers, thought
should be given as to the extent of detail which tenderers can realistically be expected to prepare
and include in their proposals. The extent of detail required should be clearly described in the
Instructions to Tenderers (it should be noted that there can be no description in the documents
which will later constitute the Contract, which only comes into full force and effect when a tenderer’s
proposal is accepted). Employers should also consider remunerating tenderers if, in order to provide
a responsive Tender, they have to undertake studies or carry out preliminary design work.
Finally, when planning the overall programme for the project, Employers must remember to allow a
realistic time for:
- tenderers to prepare and submit a responsive Tender (avoiding time that is either too short
which can reduce competition and result in inadequate submittals, or too long which can
be wasteful to all parties involved); and
- the review and evaluation of tenders and the award of the Contract to the successful
tenderer. This will be the minimum time which tenderers should be asked to hold their
tenders valid and open to acceptance.
CONDITIONS
Sub-Clause 1.1 Definitions
GENERAL
The opening words of Sub-Clause 1.1 mean that the definitions apply, not only to the Conditions
of Contract, but to all the documents of the Contract. Therefore, the Employer should take
care (particularly when drafting the Employer’s Requirements) and the Contractor should take
care (particularly when drafting the Contractor’s Proposal) to use terms in accordance with
those as defined in the definitions.
GUIDANCE
Regarding the “Base Date” under Sub-Clause 1.1.4, if the Employer makes significant data/
information available to tenderers 28 days or less before the due date for submission of
tenders, then it is recommended that the Employer consider extending that date so that such
information is provided before the Base Date for the purposes of the Contract conditions
(including, Sub-Clause 2.5 [Site Data and Items of Reference] and Sub-Clause 4.12
FORMS
[Unforeseeable Physical Conditions]).
The defined term “Site”, under Sub-Clause 1.1.90, is used for a number of different purposes
in the General Conditions (for example: insurances and security) and so, if it is anticipated that
any item(s) of equipment, Plant, Materials and Temporary Works are to be located or stored
in places other than where the Permanent Works are to be executed, it is recommended
that consideration be given to specifying such places in the Contract (by the Employer in the
Employer’s Requirements and/or by the Contractor in the Contractor’s Proposal).
In general, changes should not be made to the definitions as this could have serious
consequences on the interpretation of the documents of the Contract, particularly the
Conditions of Contract.
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
FIDIC and ITA recommend that none of the definitions that refer specifically to Underground
Works be amended.
However, there are limited circumstances where it may be desirable to amend some of the
definitions. For example:
1.1.4 the Base Date could be defined as a particular calendar date with time
zone hour
1.1.42 one particular Foreign Currency may be required
1.1.52 a different currency may be required to be the contract Local Currency
Also, some of the defined terms in the General Conditions may not be appropriate and may
need changing or developing.
For example, if the extent of the Site crosses the border between two countries, it is
recommended that consideration be given to the following changes:
term should be carefully and properly defined, using a clear Sub-Clause numbering system for
GENERAL
the new / additional defined terms. It is recommended that the numbering of new definitions
does not interfere with the numbering as originally included in the General Conditions. For
example:
In some jurisdictions, it may be advisable to add additional definitions to clarify certain terms/
expressions which appear in the General Conditons but are not defined. A typical example
might be:
FORMS
In relation to the meaning of “consent” under sub-paragraph (g), it should be noted that
this does not mean “approve” or “approval” which, under some legal jurisdictions, may be
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
If Notices are only to be given in paper format by post, then consideration may be given to
increasing the particular timescales for Notices in the Conditions of Contract to allow extra
days for the Notice to be delivered to the recipient.
FIDIC and ITA recommend the order of priority of the documents in the General Conditions
remain unaltered.
The form of the Contract Agreement should be included in the tender documents as an annex
to the Special Provisions: an example form is included at the end of this publication (in the
section “Forms”).
CONDITIONS
to recording in the Contract Agreement: the Accepted Contract Amount, the Base Date and/
GENERAL
or the Commencement Date.
Entry into a formal Contract Agreement may be mandatory under the applicable law. In such
a case, the words “unless they agree otherwise” should be deleted from the text.
GUIDANCE
Additional provisions may be required if all rights to particular items of computer software (for
example) are to be assigned to the Employer. These provisions should take account of the
applicable law.
FORMS
For Underground Works involving the supply and installation of Plant, alternative arrangements
may be appropriate:
In respect of sub-paragraphs (b) and (c) of this Sub-Clause, if (in addition to the provisions of
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
Sub-Clause 4.18 [Protection of the Environment]) the applicable law requires the Contractor
to apply for and/or comply with particular environmental permits, these permits should be
clearly described in detail in the Employer’s Requirements together with the Contractor’s
obligations associated with each permit.
If it is likely that one or more of the tenderers will be a Joint Venture, detailed requirements for
the JV may need to be specified in addition to those listed in the definition of “JV Undertaking”
under Sub-Clause 1.1.56. For example, it may be desirable for each member of the JV
to produce a parent company guarantee: an example form is included at the end of this
publication (in the section “Forms”).
The Employer should scrutinise the JV Undertaking carefully and, where relevant, check if the
project’s financing institution(s) has/have to give consent.
If it is required that the limitation of each Party’s liability to the other Party is to include certain
“indirect or consequential loss or damage” and is also to take into account liabilities which
are to be insured under Clause 19 [Insurance], the Contract Data and this Sub-Clause may
be varied:
CONDITIONS
direct loss caused by termination of the Contract
GENERAL
under Sub-Clause 15.5 [Termination for Employer’s
Convenience] and Sub-Clause 16.2 [Termination by
Contractor], the limit shall be twenty percent (20%) of
the Accepted Contract Amount;
(ii) for damage caused by the Employer or Employer’s
Personnel to the Temporary Works or Plant and
GUIDANCE
Materials not included in the Permanent Works, the
limit shall be thirty percent (30%) of the required value
of cover of the insurance under Sub-Clause 19.2.1
[The Works];
(iii) for damage caused by the Employer or Employer’s
Personnel to the Contractor’s Equipment, Materials,
Plant and/or Temporary Works, the limit shall be
FORMS
the required value of cover of the insurance under
Sub-Clause 19.2.2 [Goods];
(iv) for death or injury to the Contractor’s Personnel by a
cause attributable to the Employer the limit shall be
the required value of cover of the insurance under
Sub-Clause 19.2.5 [Injury to employees];
(v) for the Employer’s indemnity to the Contractor for
third party claims under Sub-Clause 17.5 [Indemnities
by Employer], there shall be no limit; and
(vi) for all matters other than those described in
sub-paragraph (i) to (v) above and other than under
Sub-Clause 17.3 [Intellectual and Industrial Property
Rights], the limit shall be in accordance with Sub-Clause
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
It is typically necessary for the Contractor to have early access to the Site for the purposes
of survey and subsurface investigations. The details of such early right of access should be
stated in the Contract Data, including any restrictions on such access and whether or not it
shall be exclusive to the Contractor.
If right of access to, and possession of, the Site cannot be granted by the Employer in the normal
way, details should be given in the Employer’s Requirements and appropriate amendments
made to the first paragraph of this Sub-Clause and, if necessary, to the second paragraph.
If Employer-Supplied Materials are listed in the Employer’s Requirements for the Contractor’s
use in the execution of the Works, the following provisions may be added:
If Employer’s Equipment is listed in the Employer’s Requirements for the Contractor’s use in
the execution of the Works, the following provisions may be added:
CONDITIONS
Goods or Contractor’s Personnel to or from the Site.”
GENERAL
In the last paragraph of Sub-Clause 17.1 [Responsibility for Care of
the Works] after the two instances of “Goods” add:
“, Employer’s Equipment”,
GUIDANCE
Sub-Clause 3.1 The Engineer
In the appointment of the Engineer, it is recommended that the Employer and the Engineer
use the form of agreement FIDIC Clients/Consultants Model Services Agreement fifth Edition,
2017 (http://fidic.org/books/clientconsultant-model-services-agreement-5th-ed-2017-white-
book).
FORMS
Sub-Clause 3.2 Engineer’s Duties and Authority
In performing the Engineer’s duties and in exercising his/her authority under the Contract, the
Engineer should take due regard of:
a) FIDIC’s Code of Ethics for consulting engineers: http://fidic.org/about-fidic/fidic-policies/
fidic-code-ethics†;
and
b) the duty to prevent corruption and bribery as described in the publications:
- FIDIC Guidelines for Integrity Management (FIM) in the consulting
industry, Part 1- Policies and principles first edition, 2011 (http://fidic.
org/books/integrity-management-system-fims-guidelines-1st-ed-
2011-part1† ) and
- FIDIC Guidelines for Integrity Management System in the Consulting
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
EXAMPLE “The Engineer shall obtain the consent of the Employer before
taking action under the following Sub-Clauses of these Conditions:
This list should be extended or reduced as necessary. If the obligation to obtain the Employer’s
consent only applies beyond certain limits, financial or otherwise, the example wording should
be varied accordingly.
It should be noted that any such requirement shall not be applied to any action by the Engineer
under Sub-Clause 3.7 [Agreement or Determination], as stated in Sub-Clause 3.2 [Engineer’s
Duties and Authority] of the General Conditions.
Sub-Clause 3.2.2 Engineer’s Specific Duties and Authority for Excavation and
Lining Works
FIDIC and ITA recommend that Sub-Clause 3.2.2 [Engineer’s Specific Duties and Authority for
Excavation and Lining Works] remain unchanged. These duties are essential to the Contract.
© FIDIC & ITA 2019
21
Sub-Clause 3.4 Delegation by the Engineer
CONDITIONS
GENERAL
The Engineer’s assistants may include: design engineers, other construction professionals,
technicians, inspectors and/or specialist independent engineers and/or inspectors appointed
to monitor and review the execution of the Works (including inspecting and/or testing items
of Plant and/or Materials).
If it is anticipated that the Engineer’s assistants may not all be fluent in the language for
communications defined in Sub-Clause 1.4 [Law and Language], consideration should be
GUIDANCE
“If any assistants are not fluent in this language the Engineer shall
make competent interpreters available during all working hours, in
FORMS
If the applicable law prevents the Contractor from complying with any Engineer’s instruction
that may have an adverse effect on the health and safety of the Contractor’s Personnel,
sub-paragraph (b) of this Sub-Clause may be amended:
“or will adversely affect the health and safety of the Contractor’s
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
Personnel”.
If the Conditions of Contract are to allow for the giving of oral instructions by the Engineer, this
Sub-Clause may be amended:
The Engineer shall not delegate any of his/her duties under this Sub-Clause to the Engineer’s
Representative (if appointed) or to any assistant, as stated under Sub-Clause 3.4 [Delegation
by the Engineer].
The opening words of this Sub-Clause state that the Engineer “shall act neutrally between the
Parties” when carrying out his/her duties under this Sub-Clause and “shall not be deemed
to act for the Employer”. By these statements it is intended that, although the Engineer is
appointed by the Employer and acts for the Employer in most other respects under the
CONDITIONS
in a fair-minded and unbiased manner.
GENERAL
Sub-Clause 3.8 Meetings
GUIDANCE
Clause 4 The Contractor
Sub-Clause 4.1 Contractor’s General Obligations
FIDIC strongly recommends that the Employer ensures that the Employer’s Requirements
contain a clearly identified, defined and described specific purpose or purposes for which the
FORMS
facility will be used when complete, in order that the Contractor can comply with the obligation
to provide Works which are “fit for the purpose(s) for which they are intended” as stated in
this Sub-Clause.
The acceptable form(s) of Performance Security should be included in the tender documents.
Example forms are included at the end of this publication (in the section “Forms”). They
incorporate two sets of Uniform Rules published by the International Chamber of Commerce
(the “ICC”, which is based at 33-43 Avenue du Président Wilson, 75116 Paris, France), which
also publishes guides to these Uniform Rules.
These example forms and the wording of the Sub-Clause may have to be amended to comply
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
The example forms of Performance Security that are included at the end of this publication (in
the section “Forms”) provide for the option to reduce the amount of the Performance Security
following issue of the Taking-Over Certificate for the whole of the Works under Clause 10. If
neither of the example forms is to be used, consideration should be given to adding provisions
for this option to Sub-Clause 4.2.1.
If the Contractor’s Representative is known at the time of submission of the tender, the tenderer
may propose that person in his/her tender. The tenderer may wish to propose alternatives,
especially if the contract award seems likely to be delayed.
The “main engineering discipline applicable to the Works” in which the Contractor’s
Representative is required to be qualified, experienced and competent should be the
engineering discipline of the Works which is of highest value proportionate to the value of the
Works. If it is necessary to stipulate that the Contractor’s Representative shall be qualified,
experienced and competent in a particular engineering discipline in relation to the Works, the
following amendment will need to be made to this Sub-Clause:
© FIDIC & ITA 2019
23
EXAMPLE In the second paragraph of Sub-Clause 4.3 delete “the main
CONDITIONS
If it is permissible that the Contractor’s Representative is not fluent in the language for
communications defined in Sub-Clause 1.4 [Law and Language], consideration should be
given to amending this Sub-Clause:
If it is permissible that the Contractor’s Representative’s delegates are not all fluent in the
language for communications defined in Sub-Clause 1.4 [Law and Language], consideration
should be given to amending this Sub-Clause:
“If any of these persons is not fluent in this language the Contractor
shall make competent interpreters available during all working
hours, in a number sufficient for those persons to properly perform
their delegated powers, functions and/or authority.”
It may be appropriate and/or desirable, taking account of the circumstances and locality of
the project, to encourage the Contractor to employ local contractors in the execution of the
Works:
If no consent by the Engineer to Subcontractors is required, the last three paragraphs of this
Sub-Clause may be deleted. If less consent by the Engineer to Subcontractors is preferable,
this Sub-Clause may be amended:
CONDITIONS
“or
GENERAL
(iii) a Subcontractor where the value of his/her subcontract is less
than one percent (1%) of the Accepted Contract Amount.”
If the Engineer’s consent is required to the suppliers of certain Materials, this Sub-Clause may
GUIDANCE
be amended:
FORMS
____________________________”
(insert details: for example, specific manufactured or prefabricated
items of Materials)
If the Employer requires that all the Contractor’s subcontracts should provide for assignment of
the subcontract to the Employer in the event that Sub-Clause 15.2 [Termination for Contractor’s
Default] applies, the following amendment will need to be made to this Sub-Clause:
Termination].”
If the Employer requires that the Contractor assigns the benefit of the relevant subcontract in
the event that a Subcontractor’s obligations continue after expiry of the DNP relating to that
Subcontractor’s work, the following amendment will need to be made to this Sub-Clause:
Normally the Contractor will select and employ Subcontractor(s), (subject to any constraints
stated in the Contract), but this Sub-Clause provides for the situation where the Employer may
wish to select a particular Subcontractor or Subcontractors to be employed by the Contractor
in the execution of the Works.
If this is the case, it is recommended that the Employer names the particular Subcontractor(s)
in the Employer’s Requirements so that tenderers are aware of this requirement before
submitting their tenders - although this Sub-Clause also makes provision for the Engineer
to instruct the Contractor to employ a Subcontractor or Subcontractors selected by the
Employer after contract award.
© FIDIC & ITA 2019
25
It should be noted that:
CONDITIONS
a) once the Contractor has employed a Subcontractor who has been nominated by the
GENERAL
b) sub-paragraph (b) of Sub-Clause 13.4 [Provisional Sums] should provide for payment
to the Contractor for works or services to be purchased by the Contractor from a
nominated Subcontractor.
GUIDANCE
If the Contractor is sharing occupation of the Site with others, it may not be appropriate for
him/her to provide some of the listed items. In these circumstances:
FORMS
- this Sub-Clause should be amended to specify exactly what health and safety
obligations are the Contractor’s under the Contract, and
- the health and safety obligations which are to be fulfilled by the Employer and/or
others should be specified in the Employer’s Requirements
so that it is clear which Party is responsible for what in respect of the health and safety
obligations for the Site and for the Works.
quality-construction-2004†).
If the Employer requires the Contractor to have a Quality Manager employed on the Site, such
position should be specified in the Employer’s Requirements as one of the positions of Key
Personnel.
If the Employer requires the Contractor to interface with others and/or with the Employer, the
Employer’s Requirements should clearly describe all such interfaces and should specify the
extent in which the Contractor shall allow for such interfaces in the QM System.
FIDIC and ITA recommend that the wording of Clause 4.10 [Use of Site Data and Geotechnical
Baseline Report and Geotechnical Data Report] remain unchanged.
FIDIC and ITA recommend that the wording of Clause 4.12 [Unforeseeable Physical
Conditions] remain unchanged.
In some cases, the Contractor may be required to get permission prior to delivery of Goods
to the Site. In such cases those Goods for which permission is required should be stated in
the Employer’s Requirements, and the following wording may be added to this Sub-Clause:
CONDITIONS
Goods shall be delivered without this permission, which shall not
GENERAL
relieve the Contractor from any duty, obligation or responsibility
under or in connection with the Contract.”
If the Contractor is not to provide all the Contractor’s Equipment necessary to execute
GUIDANCE
the Works, the Employer’s obligations should be specified: please see Sub-Clause 2.6
[Employer-Supplied Materials and Employer’s Equipment] and the guidance notes for
Sub-Clause 2.6 above.
If vesting of Contractor’s Equipment to the Employer is required, and such vesting is consistent
with the Laws of the Country, further paragraphs may be added to this Sub-Clause:
FORMS
EXAMPLE At the end of Sub-Clause 4.17, add the following paragraphs:
If services are to be available on the Site for the Contractor to use, details of such services
should be set out in the Employer’s Requirements, including a description of each utility, the
capacity of each utility that is available for the Contractor’s use, its location and the price per
unit of consumption.
If the Contractor is sharing occupation of the Site with others, it may not be appropriate for the
Contractor to be responsible for its security. In these circumstances, it is recommended that:
a) this Sub-Clause should be amended to specify exactly what security obligations are
the Contractor’s under the Contract,
and
so that it is clear which Party is responsible for what in respect of the security of the Site.
If the Contractor is sharing occupation of the Site with others, it is recommended that this
Sub-Clause is amended by identifying and allocating responsibility for clearance and removal
GUIDANCE
from the Site of any wreckage, rubbish, hazardous waste, temporary works and surplus material.
In respect of any of the Milestones that do not correspond with the whole of the Works or
with any Section and if Delay Damages are to apply for the Contractor’s failure to comply with
Sub-Clause 8.2 [Delay Damages] in respect of those Milestones, the Contract Data should
FORMS
Description of the event that does not correspond Time for Completion Delay Damages
with the whole of the Works or with any Section and (calculated from the (as a percentage of
is designated a Milestone for the purposes of the Commencement final Contract Price
Contract Date) per day of delay)
_____ days __ %
_____ days __ %
_____ days __ %
_____ days __ %
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
Maximum amount of delay damages for Milestones (percent of final Contract Price) ___ %. “
Clause 5 Design
Sub-Clause 5.1 General Design Obligations
It is recommended that the Instructions to Tenderers require tenderers to include the name,
address, detailed particulars and relevant experience of each proposed designer/design
Subcontractor so that the Employer can assess whether and to what extent each tenderer’s
proposed designers/design Subcontractors comply with the three conditions set out in
sub-paragraphs (a) to (c) of this Sub-Clause.
Tenderers should be advised of the extent to which the Employer’s reference design is a
suggestion or a requirement.
It is important that the Employer’s Requirements should clearly specify which Contractor’s
Documents the Employer requires the Contractor to prepare, which may not necessarily
include (for example) all the technical documents which the Contractor’s Personnel will need
in order to execute the Works.
CONDITIONS
specify that the Contractor’s Documents shall include drawings showing how the Plant is to
GENERAL
be installed and any other information required for:
• preparing suitable foundations or other means of support,
• providing suitable access on the Site, for the Plant and any necessary equipment, to
the place where the Plant is to be erected, and/or
GUIDANCE
• making necessary connections to the Plant.
The “Contractor’s Documents” under this Sub-Clause 5.2.2 are the documents that the
Contractor must submit to the Engineer for Review, as specified in the Employer’s Requirements
or as stated in the Conditions of Contract (namely, as-built records under Sub-Clause 5.6
[As-Built Records] and O&M Manuals under Sub-Clause 5.7 [Operation and Maintenance
FORMS
Manuals]). It is important, therefore, that the Employer’s Requirements clearly identify which of
the Contractor’s Documents the Employer requires the Contractor to submit to the Engineer
for Review.
If a different Review Period than that stated under this Sub-Clause 5.2.2 is considered
necessary, or different Review Periods are considered necessary for different (types of)
Contractor’s Documents, taking account of the time required to review the different types
of Contractor’s Documents and/or of the possibility of substantial submissions at particular
stages of the design-build process, such different Review Period(s) should be clearly stated in
the Employer’s Requirements.
In some jurisdictions there may be a requirement under the applicable law for the mandatory
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
It is strongly recommended that the Employer is advised by legal and engineering professionals
with extensive experience in the mandatory review/checking and/or verification process(es)
required by the applicable law when preparing the revised wording of this Sub-clause.
If the Works include Plant that comprises (in whole or in part) new or innovative technology in
the Country or at the Employer’s location, it is recommended that the Parties consider including
© FIDIC & ITA 2019
29
in the Contract provision for training (by the Employer in the Employer’s Requirements and/
CONDITIONS
or by the Contractor in the Contractor’s Proposal) of the Employer’s Personnel at the location
GENERAL
of another plant facility, or at a number of other plant facilities, that are similar in nature to the
Works.
If the Contractor is required to supply spare parts under the Contract, these should be
GUIDANCE
detailed in the Employer’s Requirements, which should also specify the required guarantee
period for these spare parts.
It may be necessary to review and revise this Sub-Clause (or delete it in its entirety) if
the relevant labour Laws applicable to the Contractor’s Personnel and/or the Employer’s
Personnel do not permit any restriction on the right of any worker to seek other positions.
If the Employer plans to make any facilities and/or accommodation (for example, office
accommodation) available for the Contractor’s occupation and/or use, the Employer’s
obligations to do so and details of such facilities and/or accommodation should be specified
in the Employer’s Requirements. See also the guidance under Clause 17 [Care of the Works
and Indemnities] below for the suggested additional sub-clause in respect of responsibility for
care of such facilities and/or accommodation.
If it is permissible that the Contractor’s superintending staff are not all fluent in the language
for communications defined in Sub-Clause 1.4 [Law and Language], then consideration
should be given to amending this Sub-Clause:
If it is permissible that all Key Personnel are not fluent in the language for communications
defined in Sub-Clause 1.4 [Law and Language], then consideration should be given to
amending this Sub-Clause:
CONDITIONS
“If any of the Key Personnel are not fluent in this language the
GENERAL
Contractor shall make competent interpreter(s) available during all
working hours, sufficient for that person to properly perform his/her
duties under the Contract.”
Additional Sub-Clauses
GUIDANCE
It may be necessary, appropriate and/or desirable to include additional sub-clauses to take
account of the circumstances and locality of the Site:
“The Contractor may bring into the Country any foreign personnel who
FORMS
are necessary for the execution of the Works to the extent allowed
by the applicable Laws. The Contractor shall ensure that these
personnel are provided with the required residence visas and work
permits. The Employer shall, if requested by the Contractor, use all
reasonable endeavours in a timely and expeditious manner to assist
the Contractor in obtaining any local, state, national, or government
permission required for bringing in the Contractor’s personnel.
“The Contractor shall not, other than in accordance with the Laws
of the Country, import, sell, give, barter or otherwise dispose of any
alcoholic liquor or drugs, or permit or allow importation, sale, gift,
barter or disposal thereto by the Contractor’s Personnel.”
CONDITIONS
bargaining collectively, and shall not discriminate or retaliate against
GENERAL
the Contractor’s Personnel who participate, or seek to participate,
in such organisations and bargain collectively. The Contractor shall
engage with such workers’ representatives. Workers’ organisations
are expected to fairly represent the workers in the workforce.”
GUIDANCE
“The Contractor shall not make employment decisions on the basis
of personal characteristics unrelated to inherent job requirements.
The Contractor shall base the employment relationship on the
principle of equal opportunity and fair treatment, and shall not
discriminate with respect to aspects of the employment relationship,
including recruitment and hiring, compensation (including wages
FORMS
and benefits), working conditions and terms of employment,
access to training, promotion, termination of employment or
retirement, and discipline. In countries where the relevant labour
Laws provide for non-discrimination in employment, the Contractor
shall comply with such Laws. When the relevant labour Laws are
silent on non-discrimination in employment, the Contractor shall
meet the requirements under this Sub-Clause. Special measures of
protection or assistance to remedy past discrimination or selection
for a particular job based on the inherent requirements of the job
shall not be deemed discrimination.”
If the Contractor is to provide high-value items of Plant and/or Materials under the Contract,
consideration may be given to amending this Sub-Clause:
“No Plant and/or Materials that is the property of the Employer shall
be removed from the Site. If it becomes necessary to:
(i) remove any item of such Plant from the Site for the purposes
of repair, the Contractor shall give a Notice, with reasons, to
the Engineer requesting consent to remove the defective or
damaged item off the Site. This Notice shall clearly identify
the item of defective or damaged Plant, and shall give details
of: the defect or damage to be repaired; the place to which
defective or damaged item of Plant is to be taken for repair;
the transportation to be used (and insurance cover for such
transportation); the proposed inspections and testing off the
Site; and the planned duration required before the repaired
item of Plant shall be returned to the Site. The Contractor
shall also provide any further details that the Employer may
reasonably require; or
(ii). replace any item(s) of such Plant and/or Materials, the
Contractor shall give a Notice, with reasons, to the Engineer
clearly identifying the item(s) of Plant and/or Materials to be
replaced, and giving details of the due date of delivery to the
Site of the replacement item(s).
to the Site, the Contractor shall ensure that such an item is not
moved except for its delivery to the Site.
Additional Sub-Clause
If the Contract is being financed by an institution whose rules or policies require a restriction
FORMS
If the Works are to be completed and taken over in stages it is important that each stage is
defined as a Section, and the Time for Completion of each Section is stated, in the Contract
Data (please also see the guidance below under Sub-Clause 10.1 [Taking Over the Works
and Sections].
It is strongly recommended that the programming software that is preferable to the Engineer
(in his/her monitoring of the Contractor’s progress in executing the Works) be clearly identified
in the Employer’s Requirements, and that such software is drawn to the attention of tenderers
in the Instructions to Tender.
For less complex projects, the Employer may consider simplifying the requirements for the
Contractor’s programme as listed in sub-paragraphs (a) to (k) in this Sub-Clause (for example,
by replacing sub-paragraphs (a) to (k) in this Sub-Clause with sub-paragraphs (a) to (d) as
they appear under Sub-Clause 8.3 [Programme] of FIDIC’s Conditions of Contract for Plant
and Design-Build First Edition 1999).
Sub-paragraph (c) of this Sub-Clause entitles the Contractor to an extension of the Time
for Completion for “exceptionally adverse climatic conditions”. It may be preferable to set
out in the Employer’s Requirements what constitutes an “exceptionally adverse” event -
for example, by reference to available weather statistics and return periods. It may also be
CONDITIONS
the frequency with which events of similar adversity have previously occurred at or near the
GENERAL
Site. For example, an exceptional degree of adversity might be regarded as one which has a
probability of occurrence of once every four or five times the Time for Completion of the Works
(for example, once every eight to ten years for a two-year contract).
The final paragraph of this Sub-Clause provides that the rules and procedures for assessing the
GUIDANCE
Contractor’s entitlement to an EOT where there is concurrency between delays attributable to
both Parties shall be stated in the Special Provisions. This provision has been drafted by FIDIC
in this manner because there is no one standard set of rules/procedures in use internationally
(though, for example the approach given in the Delay and Disruption Protocol published by
the Society of Construction Law (UK):
https://www.scl.org.uk/sites/default/files/SCL_Delay_Protocol_2nd_Edition_Final.pdf† is
increasingly being adopted internationally and different rules/procedures may apply in different
FORMS
legal jurisdictions.)
In preparing the Special Provisions, therefore, it is strongly recommended that the Employer
be advised by a professional with extensive experience in construction programming, analysis
of delays and assessment of extension and reduction of time in the context of the governing
law of the Contract.
Under the laws of many countries or other jurisdictions, the amount of these pre-defined
damages must be a reasonable estimate of the anticipated or actual loss caused to the
Employer by the delay. Therefore if the Delay Damages are fixed at an unreasonably large
amount, they may be unenforceable in common law jurisdictions or subject to downward
adjustment in civil law jurisdictions.
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
If the Accepted Contract Amount is to be quoted as the sum of figures in more than one
currency, it may be preferable to define these damages (per day) as a percentage to be
applied to each of these figures. If the Accepted Contract Amount is expressed in the Local
Currency, the damages per day may either be defined as a percentage or be defined as a
figure in Local Currency: see Sub-Clause 14.15(c).
Additional Sub-Clause
Incentives for early completion may be included (in addition to sub-paragraph (a) of Sub-Clause
13.2 [Value Engineering] which refers to accelerated completion):
The Employer’s Requirements should describe the tests which the Contractor is to carry
out before being entitled to a Taking-Over Certificate. It may also be appropriate for the
Contractor’s Proposal to include detailed arrangements, instrumentation, etc.
GUIDANCE
If the Works are to be tested and taken over in Sections, it is strongly recommended that
consideration be given to testing requirements in the Employer’s Requirements that take due
account of the effect of other parts of the Works being incomplete.
The Employer may wish the Employer’s permanent operating and maintenance personnel
to witness the operational tests and/or trial operation (including during the training of the
FORMS
Employer’s Personnel under Sub-Clause 5.5 [Training]), in which case, this should be clearly
stated in the Employer’s Requirements.
The wording in sub-paragraphs (a) to (c) of this Sub-Clause includes the conditions which are
typically applicable for a plant contract, but otherwise may require amendment. In particular,
sub-paragraph (c) refers to trial operation, during which any product produced by the Works
becomes the property of the Employer. As such, the Employer becomes responsible for
disposing of such product, and entitled to retain the proceeds if the product is sold. If the
product is to be retained by the Contractor, this Sub-Clause should be amended accordingly.
For less complex projects, the Employer may consider simplifying the testing requirements
under this Sub-Clause.
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
If the Works are to be completed and taken over in stages it is important that each stage is
defined as a Section in the Contract Data. Precise geographical definitions are advisable, and
the Contract Data should include a table to also define for each Section:
• the relevant percentage for release of Retention Money,
An example form of such a table is shown in the example form of Contract Data included in
this publication.
Depending on the complexity of the project and the nature of the Works, the Employer may
consider amending the period of “two years” stated at the end of the first paragraph of this
Sub-Clause to be a longer or a shorter period.
It may be necessary to review the effect of this Sub-Clause in relation to the period of liability
imposed by the applicable law.
CONDITIONS
of the applicable law.
GENERAL
Additional Sub-Clause
If the Works include the Plant that comprises (in whole or in part) new or innovative technology
in the Country or at the Employer’s location, consideration may be given to including in the
Employer’s Requirements a requirement for the Contractor to provide supervisory assistance
GUIDANCE
to the Employer’s permanent operating personnel in the operation and maintenance of the
Plant during the DNP of the Works.
FORMS
be as described in the Employer’s Requirements for the purpose
of supporting the Employer’s operation and maintenance of the
Plant for the period of [insert number of months] after the Date of
Completion.”
The Employer’s Requirements should describe the tests the Employer will carry out, after
taking-over, to verify that the Works fulfil the Employer’s performance requirements. For some
types of Works, these Tests may be the most difficult to specify well, although they are critical
to a successful outcome. It may be appropriate for the Instructions to Tenderers to require
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
the Contractor’s Proposal to include detailed arrangements, and/or to define and allow for
the provision of any instrumentation or other items required in addition to that included in the
Plant, to demonstrate compliance with the Employer’s performance requirements.
The provisions in the General Conditions are based on the Tests after Completion being
carried out by the Employer and the Employer’s operating personnel, with guidance from
the Contractor’s staff. If other arrangements are envisaged, they should be specified in
the Employer’s Requirements, and this Sub-Clause should be amended accordingly. For
example, if the Employer wishes the Contractor to carry out the Tests after Completion
(with the Employer providing all electricity, water, sewage (if applicable), fuel, consumables,
materials for the tests and making personnel and the Plant available), it is recommended that
consideration be given to the provisions of Sub-Clause 12.1 in FIDIC’s Conditions of Contract
for EPC/Turnkey Projects, Second Edition 2017.
If the works of a Section are to be tested under this Sub-Clause, it is strongly recommended
that consideration be given to testing requirements in the Employer’s Requirements that take
due account of the effect of other parts of the Works being incomplete.
measure the performance of the Works or Section against the performance criteria
GENERAL
(b) availability tests – to be carried out during an initial period of the DNP (which period
should be specified in the Employer’s Requirements), to measure the availability of
the Works or Section during that period.
In some jurisdictions there may be a requirement under the applicable law for mandatory
GUIDANCE
testing of the Works after taking-over and before operation. If this is the case, it is essential
that it is drawn to tenderers’ attention in the Instruction to Tenderers, giving details of such
mandatory testing.
If the first paragraph of this Sub-Clause is to apply, the method of calculating the Performance
FORMS
Damages (based on the extent of the failure) should be defined in the Schedule of Performance
Guarantees, which should also clearly specify the minimum acceptable performance criteria.
c) the Engineer may request a proposal from the Contractor under Sub-Clause 13.3.2
[Variation by Request for Proposal].
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
Provisional Sums may be required for parts of the Works which are not required to be priced at
the risk of the Contractor. For example, a Provisional Sum may be necessary to cover goods
or services which the Employer wishes to select after award of the Contract, or to deal with a
major uncertainty regarding subsurface conditions. It is essential to define the scope of each
Provisional Sum (it is recommended that this be included in the Schedule of Rates and Prices
prepared by the Employer), since the amount of each Provisional Sum corresponding to the
defined scope will then be excluded from the other elements of the Accepted Contract Amount.
The provision for adjustments under this Sub-Clause may be required if it would be
unreasonable for the Contractor to bear the risk of escalating costs due to inflation.
If the amounts payable to the Contractor are to be adjusted for rises or falls in the cost of
labour, Goods and other inputs to the Works, for this Sub-Clause to apply it is important that
a Schedule (or Schedules) of cost indexation is (are) included in the Contract and that such
Schedule(s) include a formula or formulae for calculation of the applicable adjustment under
this Sub-Clause.
For a plant contract, it may be preferable to adopt a formula or formulae which is/are more
directly related to the timing of the costs incurred by manufacturers.
CONDITIONS
CHANGE IN COST
GENERAL
Pn = a+b Ln +c En +d Mn +......
Lo Eo Mo
where:
“Pn” is the adjustment multiplier to be applied to the estimated
GUIDANCE
contract value in the relevant currency of the work carried out in
period “n”, this period being a month;
FORMS
Works, such tabulated cost elements may be indicative of resources
such as labour, equipment and materials;
“Ln”, “En”, “Mn”, … are the current cost indices or reference prices
(stated in the Schedule of cost indexation) for period “n”, expressed
in the relevant currency of payment, each of which is applicable to
the relevant tabulated cost element on the date 49 days prior to the
last day of the period (to which the particular Payment Certificate
relates); and
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
“Lo”, “Eo”, “Mo”, … are the base cost indices or reference prices,
expressed in the relevant currency of payment, each of which is
applicable to the relevant tabulated cost element on the Base Date.
a= 0.10 Fixed
b= ____Labour
c=
d=
e=
* These values and dates confirm the definition of each index, but
do not define Base Date indices
FIDIC and ITA recommend that no amendment is made to the provisions of Sub-Clause 13.8
[Measurement of Excavation and Lining Works and Adjustment of Time for Completion and
Contract Price] and/or to any of the Sub-Clauses 13.8.1 to 13.8.4.
The procedures and timing for making payments under this Clause 14 should be checked
to ensure that they are acceptable to both the Employer and any financing institution the
Employer may be using to fund the project.
When writing the Special Provisions, consideration should be given to the amount and timing
of payment(s) to the Contractor. A positive cash flow is clearly of benefit to the Contractor,
and tenderers will take account of the interim payment procedures when preparing their
tenders.
Normally, a plant and/or design-build contract is based on a lump sum price, with little or
no measurement. The Contractor thus takes the risk of changes in cost arising from the
Contractor’s design. The lump sum price may consist of two or more amounts, quoted in the
currencies of payment (which may, but need not, include the Local Currency).
In order to value Variations, tenderers may be required to include in their Tenders detailed price
break-downs, including quantities, unit rates and other pricing information. This information
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
can also be useful for the assessment of interim payments, but may not have been priced
competitively. When the tender documents are being prepared, the Employer must therefore
decide whether he/she will accept being bound by the tenderer’s price break-downs. If not,
the Employer should ensure that the Engineer has the necessary expertise to value any
Variations which may be required.
Additional Sub-Clauses may be required to cover any exceptions to the provisions set out in
Sub-Clause 14.1, and any other matters relating to payment.
If Sub-Clause 14.1(a) is not to apply, the method of determining the Contract Price should
be defined in additional Sub-Clauses, as envisaged in the last sentence of Sub-Clause 14.1.
If payment for any part of the Works is to be made on the basis of measurement, that part
must be defined in the Contract, and the following wording may be considered for one of the
additional Sub-Clauses:
The Engineer shall agree or determine the value of those parts of the
Works which are to be measured, in accordance with Sub-Clause
3.7 [Agreement or Determination]. Measurement shall be made
of the net actual quantities of those parts, notwithstanding local
practice.
CONDITIONS
and place on Site at which the measurement will be made. Unless
GENERAL
otherwise agreed with the Contractor, the measurement on Site shall
be made on this date and the Contractor’s Representative shall:
(a) either attend or send another qualified representative to
assist the Engineer and to endeavour to reach agreement of
the measurement, and
(b) supply any particulars requested by the Engineer.
GUIDANCE
If the Contractor fails to attend or send a representative at the time
and place stated in the Engineer’s Notice (or otherwise agreed with
the Contractor), the measurement made by (or on behalf of) the
Engineer shall be deemed to have been made in the Contractor’s
presence and the Contractor shall be deemed to have accepted
the measurement as accurate.
FORMS
Any part of the Permanent Works that is to be measured from
records shall be identified in the Employer’s Requirements and,
except as otherwise stated in the Contract, such records shall be
prepared by the Engineer. Whenever the Engineer has prepared the
records for such a part, he/she shall give a Notice to the Contractor
of not less than 7 days, stating the date on which and place at
which the Contractor’s Representative shall attend to examine
and agree the records with the Engineer. If the Contractor fails to
attend or send a representative at the time and place stated in
the Engineer’s Notice (or otherwise agreed with the Contractor),
the Contractor shall be deemed to have accepted the records as
accurate.
If, for any part of the Works, the Contractor attends the measurement
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
If the Contractor is not required to pay import duties on Goods imported by the Contractor into
the Country, an additional Sub-Clause should be added and sub-paragraph (b) of Sub-Clause
14.1 [The Contract Price] of the General Conditions should be amended accordingly:
exempt from customs and other import duties, if the Employer’s prior
written approval is obtained for import. The Employer shall endorse
the necessary exemption documents prepared by the Contractor
for presentation in order to clear the Goods through Customs, and
shall also provide the following exemption documents:
(describe the necessary documents, which the Contractor will be
GUIDANCE
unable to prepare)
If exemption is not then granted, the customs duties payable and
paid shall be reimbursed by the Employer.
All imported Goods, which are not incorporated in or expended in
connection with the Works, shall be exported on completion of the
Contract.
FORMS
If expatriate staff are exempted from paying local income tax, a suitable Sub-Clause should
be added and sub-paragraph (b) of Sub-Clause 14.1 [The Contract Price] of the General
Conditions should be amended accordingly. However, advice should be sought from a
qualified tax expert before drafting any such additional Sub-Clause.
When writing the Particular Conditions, consideration should be given to the benefits of the
Employer making an advance payment to the Contractor. Unless this Sub-Clause is not to
apply, the advance payment and the currencies in which it is to be paid must be specified in
CONDITIONS
repayment is achieved before the Contractor’s completion of the Works. The typical figures
GENERAL
in sub-paragraphs (a) and (b) of Sub-Clause 14.2.3 [Repayment of Advance Payment] of the
General Conditions are based on the assumption that the advance payment is less than 22%
of the Accepted Contract Amount.
The acceptable form of Advance Payment Guarantee should be included in the tender
GUIDANCE
documents, annexed to the Particular Conditions: an example form is included at the end of
this publication (in the section “Forms”).
If the Employer wishes to provide the advance payment in instalments, the Contract Data and
this Sub-Clause will need to be amended.
FORMS
- delete the words “14.2 ………. Amount of Advance Payment (percent
of Accepted Contract Amount): ……….” and replace with:
“14.2 ………….Total Advance Payment ___% of the Accepted
Contract Amount
14.2 ………….Number and timing of instalments: ________________”.
“The total amount of the advance payment, the number and timing
of instalments, and the applicable currencies and proportions shall
be as stated in the Contract Data.”.
is entitled to under the Contract, within 14 days after the Engineer has
received the Contractor’s application (in the form of a Statement) for
that instalment of advance payment.”
The General Conditions contains provisions for interim payments to the Contractor, which may
be based on a Schedule of Payments. This Schedule of Payments should be consistent with
the Completion Schedule. If another basis is to be used for determining interim valuations,
FORMS
a) an amount, or percentage of the estimated final Contract Price, for each month
(or other period) during the Time for Completion (but this can prove unreasonable
if the Contractor’s progress differs significantly from the expectation on which the
Schedule was based); or
the Works, which necessitates careful definition of the payment milestones (but
disagreements may arise when the work required for a payment milestone is nearly
achieved but the balance of the work, albeit minor, cannot be completed until some
months later).
The figures inserted by a tenderer in the Schedule of Payments may be compared with his/
her tender Completion Schedule and detail programme (if any), in order to assess whether
they are reasonably consistent with each other.
Alternatively, if the Works consist of only a few different types of operations, a simple
measurement approach for interim valuations may be appropriate.
For the avoidance of doubt, these instructions do not apply to Excavation and Lining Works, for
which payments shall be based upon measurement according to Sub-Clause 13.8 [Measurement
of Underground Works and Adjustment of Time for Completion and Contract Price].
Periods for payment should be long enough for the Employer to meet, but not so long as to
prejudice the Contractor’s positive cash-flow.
CONDITIONS
GENERAL
If part of the Retention Money is to be released and substituted by an appropriate guarantee,
an additional Sub-Clause may be added. The acceptable form(s) of guarantee should be
included in the tender documents, annexed to the Particular Conditions: an example form is
included at the end of this publication (in the section “Forms”). Also, a limit of Retention Money
should be stated in the Contract Data.
GUIDANCE
EXAMPLE SUB-CLAUSE FOR RELEASE OF RETENTION
FORMS
The Contractor shall obtain (at the Contractor’s cost) a guarantee in
amounts and currencies equal to half (50%) of the limit of Retention
Money stated in the Contract Data, and shall submit it to the
Employer with a copy to the Engineer. This guarantee shall be issued
by an entity and from within a country (or other jurisdiction) to which
the Employer gives consent, and shall be based on the sample form
included in the tender documents or on another form agreed by the
Employer (but such consent and/or agreement shall not relieve the
Contractor from any obligation under this Sub-Clause).
If all payments are to be made in Local Currency, this currency must be named in the Letter
of Tender, and this Sub-Clause may be replaced:
Financing Arrangements
For major contracts in some markets, there may be a need to secure finance from entities such
as aid agencies, development banks, export credit agencies, or other international financing
institutions. If financing is to be procured from any of these sources, the Special Provisions
may need to incorporate the financing institution’s special requirements. The exact wording
will depend on the relevant institution, so reference will need to be made to the institution to
ascertain its requirements, and to seek approval of the draft tender documents.
render the eventual contract eligible for financing, and/or additional Sub-Clauses which may
GENERAL
need to be incorporated into the Special Provisions. The following examples indicate some of
the topics which the institution’s requirements may cover:
- prohibition from discrimination against the shipping companies of any one country;
- provision for arbitration under recognised international rules and at a neutral location;
- giving the Contractor the right to suspend/terminate in the event of default under the
financing arrangements;
- specifying that the Contract does not become effective until certain conditions
precedent have been satisfied, including pre-disbursement conditions for the
financing arrangements; and
- obliging the Employer to make payments from his own resources if, for any reason,
the funds under the financing arrangements are insufficient to meet the payments
due to the Contractor, whether due to a default under the financing arrangements or
otherwise.
The financing institution may wish the Contract to include references to the financing
arrangements, especially if funding from more than one source is to be arranged to finance
different elements of supply. It is not unusual for the Special Provisions to include particular
provisions identifying different categories of Works and specifying the documents to be
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
presented to the relevant financing institution to obtain payment. If the financing institution’s
requirements are not met, it may be difficult (or even impossible) to secure suitable financing
for the project, and/or the institution may decline to provide finance for part or all of the
Contract.
Where the financing is not tied to the export of goods and services from any particular country
but is simply provided by commercial banks lending to the Employer, those banks may need
that the Contractor’s rights are very restricted. These banks may prefer the Contract to be
based upon FIDIC’s Conditions of Contract for EPC/Turnkey Projects, Second Edition 2017
(albeit that this may lead to higher tender prices for the Works).
Alternatively, the Contractor may be prepared to initiate financing arrangements for the
Contract and retain responsibility for them, although the Contractor would probably be unable
or unwilling to provide finance from the Contractor’s own resources. The Contractor’s financing
bank’s requirements are then likely to affect the Contractor during contract negotiations. For
example, the financing bank may require the Employer to make interim payments, although
a large proportion of the Contract Price might be withheld until the Works are complete.
Since the Contractor would then have to arrange financing to cover the shortfall between
the payments and the Contractor’s outgoings, the Contractor (and the financing bank) would
probably require some form of security from the Employer, guaranteeing payment when due.
It may be appropriate for the Employer, when preparing the tender documents, to anticipate
the latter requirement by undertaking to provide a guarantee for the element of payment
which the Contractor is to receive when the Works are complete. The acceptable form(s) of
guarantee should be included in the tender documents, annexed to the Particular Conditions:
an example form is included at the end of this publication (in the section “Forms”). The
following Sub-Clause may be added.
CONDITIONS
“The Employer shall obtain (at the Employer’s cost) a payment
GENERAL
guarantee in the amount and currencies, and provided by an
entity, as stated in the Contract Data. The Employer shall deliver
the guarantee to the Contractor within 28 days after both Parties
have entered into the Contract Agreement. The guarantee shall
be in the form annexed to these Special Provisions, or in another
GUIDANCE
form acceptable to the Contractor. Unless and until the Contractor
receives the guarantee, the Engineer shall not give the notice under
Sub-Clause 8.1 [Commencement of Works].
(a) when the Contractor has been paid the Accepted Contract
FORMS
Amount;
(b) when obligations under the guarantee expire or have been
discharged; or
(c) when the Employer has performed all obligations under the
Contract.”
Before inviting tenders, the Employer should verify that the wording of this Sub-Clause, and
each anticipated ground for termination, is consistent with the law governing the Contract.
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
Sub-paragraph (h) in this Sub-Clause is intended to include situations, where the Contractor
or any of the Contractor’s employees, agents, Subcontractors or Contractor’s Personnel gives
or offers to give (directly or indirectly) to any person any bribe, gift, gratuity, commission or
other thing of value, as an inducement or reward for showing or forbearing to show favour or
disfavour to any person in relation to the Contract. However, this is not intended to include
lawful inducements and rewards by the Contractor to the Contractor’s Personnel.
If the Employer has made available any Employer-Supplied Materials and/or Employer’s
Equipment in accordance with Sub-Clause 2.6, consideration should be given to an additional
sub-paragraph under this Sub-Clause:
In many jurisdictions under the applicable law it may not be permissible for the Employer to
terminate the Contract for convenience (termination of the Contract only being permitted
in the event of default on the part of the Contractor and, thereafter, arranging an equitable,
non-discriminatory and transparent procurement process to select a replacement contractor).
Before inviting tenders, the Employer should verify that the wording of this Sub-Clause is
consistent with the law governing the Contract.
Sub-paragraph (j) in this Sub-Clause is intended to include situations, where the Employer
or any of the Employer’s employees, agents or Employer’s Personnel gives or offers to give
(directly or indirectly) to any person any bribe, gift, gratuity, commission or other thing of
FORMS
If the Employer has made available any Employer-Supplied Materials and/or Employer’s
Equipment in accordance with Sub-Clause 2.6, consideration should be given to amending
this Sub-Clause:
(d) remove all other Goods from the Site, except as necessary for
safety, and leave the Site.”
In respect of the Contractor’s obligation to indemnify under the second paragraph of this
Sub-Clause, it should be noted that:
a) as this liability is not excluded under the first paragraph of Sub-Clause 1.15 [Limitation
of Liability], the Contractor has no liability for any indirect or consequential loss or
damage suffered by the Employer as a result of any negligence by the Contractor in
designing the Works to be fit for purpose;
b) as this liability is not excluded under the second paragraph of Sub-Clause 1.15
[Limitation of Liability], it falls within the Contractor’s limitation of liability under
Sub-Clause 1.15; and
c) this liability may be covered by the insurance to be taken out by the Contractor
under Sub-Clause 19.2.3 [Liability for breach of professional duty], in which case a
statement to this effect should be included in the Contract Data.
CONDITIONS
GENERAL
If the Contractor is to be allowed to use and/or occupy any of the Employer’s facilities and/
or accommodation temporarily during the Contract, it is recommended that an additional
sub-clause be added to Clause 17 to cover the responsibility for care of such facilities and/
or accommodation:
GUIDANCE
ACCOMMODATION
“The Contractor shall take full responsibility for the care of the items
of the Employer’s facilities and/or accommodation listed below,
from the date of use and/or occupation by the Contractor until
the date on which such use and/or occupation is re-vested in the
Employer.
FORMS
[List of items and details]
In respect of sub-paragraph (f) of this Sub-Clause, it should be noted that any event of
“exceptionally adverse climatic conditions” is excluded from the definition of what constitutes
an Exceptional Event. While this means that there is no right for either Party to suspend the
Works in the case of an event of “exceptionally adverse climatic conditions”, if this type of
event has the effect of delaying completion and taking-over of the Works or Section the
Contractor shall be entitled to EOT under sub-paragraph (c) of Sub-Clause 8.5 [Extension of
Time].
Clause 19 Insurance
If the Employer wishes to change the insurance provisions of this Clause – for example
by providing some of the insurance cover under the Employer’s own policy(ies) – it will be
necessary to review and revise the relevant Sub-Clause(s) under this Clause 19.
a) the tender documents include details of such insurances as an annex to the Special
Provisions so that tenderers can estimate what other insurances they may wish to
have for their own protection. The details should include the conditions of insurance,
limits, exceptions and deductibles; preferably in the form of a copy of each insurance
policy; and
In respect of any Claim under sub-paragraph (c) of this Sub-Clause, it should be noted that
“another entitlement or relief …or the execution of the Works” may include such matters as:
- access to the Site or to places where the Works are being (or to be) carried out, and/
or
FORMS
Consideration may be given to replacing the words “within a reasonable time” in the last
paragraph of this Sub-Clause by a specified time period.
It is generally accepted that construction projects depend for their success on the avoidance
of Disputes between the Employer and the Contractor and, if Disputes do arise, the timely
resolution of such Disputes.
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
Therefore, the Contract should include the provisions under Clause 21 which, while not
discouraging the Parties from reaching their own agreement on Disputes as the Works
proceed, allow them to bring contentious matters to an independent and impartial dispute
avoidance/adjudication board (“DAAB”) for resolution.
The provisions of this Sub-Clause are intended to provide for the appointment of the DAAB,
and FIDIC strongly recommends that the DAAB be appointed, as a ‘standing DAAB’
– that is, a DAAB that is appointed at the start of the Contract who visits the Site on a regular
basis and remains in place for the duration of the Contract to assist the Parties:
a) in the avoidance of Disputes,
and
It is for this reason that, under the first paragraph of this Sub-Clause, the Parties are under
a joint obligation to appoint the member(s) of the DAAB within 28 days after the Contractor
receives the Letter of Acceptance if no other time is stated in the Contract Data. That said, it
is preferable that the member(s) of the DAAB are appointed before the Letter of Acceptance
is issued.
At an early stage in the Employer’s planning of the project, consideration should be given
as to whether a sole-member DAAB or a three-member DAAB is preferable for a particular
project, taking account of its size, duration and the fields of expertise which will be involved.
CONDITIONS
- a sole-member DAAB of one natural person, who has entered into a tripartite
GENERAL
agreement with both Parties;
or
- a three-member DAAB of three natural persons, each of whom has entered into a
tripartite agreement with both Parties.
GUIDANCE
The tripartite agreement above is referred to as the DAAB Agreement under the Conditions
of Contract. It is recommended that the form of this agreement be one of the two alternative
example forms included at the end of this publication (in the section “Forms”), as appropriate
to the arrangement adopted.
It should be noted that both forms of the DAAB Agreement incorporate (by reference) the General
FORMS
Conditions of Dispute Avoidance/Adjudication Agreement with its Annex DAAB Procedural
Rules, which are included as the Appendix to the General Conditions in this publication.
Under either of these alternative forms of DAAB Agreement, each natural person of the DAAB
is referred to as a DAAB Member.
The Contract Data includes two lists for potential DAAB Members to be named: one for the
Employer to list three names, the other for the Contractor to list three names. This ensures
that both Parties have equal opportunity to put forward (the same number of) names for
potential DAAB Members, and so avoid any question that DAAB Member(s) may be imposed
on one Party by the other Party.
This provides a total of six potential DAAB Members from which the sole member or three
members (as the case may be) can be selected by the Parties. If it is considered necessary to
have a wider selection of DAAB Member(s) to choose from, then provision may be made for
longer lists in the Contract Data for both the Contractor and the Employer to name (the same
number of) additional DAAB Members.
If the Parties cannot agree on any DAAB member, Sub-Clause 21.2 [Failure to Appoint DAAB
Member(s)] applies and the selection and appointment of the DAAB member(s) should be
made by a wholly impartial entity with an understanding of the nature and purpose of a DAAB.
The President of FIDIC is prepared to perform this role if this authority has been delegated in
accordance with the example wording in the Contract Data. FIDIC maintains a list of approved
and experienced adjudicators for this specific purpose: The FIDIC President’s List of Approved
Dispute Adjudicators (http://fidic.org/president-list†).
If no potential DAAB members’ names are given in the Contract Data, consideration should
be given to stating a time period in the Contract Data that is greater than the default period of
28 days stated in the first paragraph of this Sub-Clause.
date of termination + 28 days to give a Notice of Claim under Sub-Clause 20.2.1 [Notice
of Claim]
+ 84 days to submit detailed particulars for the Claim under Sub-Clause 20.2.4 [Fully
detailed Claim]
GUIDANCE
+ 84 days for the Engineer’s agreement/determination of the Claim under Sub-Clause 3.7
[Agreement or Determination]
As noted above, FIDIC strongly recommends that the DAAB be appointed at the start of the
Contract and remain in place for the duration of the Contract. However, as an alternative to the
‘standing DAAB’ envisaged under this Sub-Clause, the Parties may prefer the dispute board
to be appointed on an ‘ad-hoc’ basis. In such case, the dispute board would be appointed
when a Dispute arises, its appointment would be limited to resolution of the Dispute, it would
have no role to play in the avoidance of Disputes between the Parties, and its appointment
would cease when it had given its decision on that Dispute. Should a new Dispute arise, a
new ad-hoc DAAB would be appointed. Given that such a dispute board would have no
role in dispute avoidance, it is more correctly referred to as a “Dispute Adjudication Board”
or “DAB”, If the Parties wish to provide for an ‘ad-hoc DAB’, rather than the recommended
‘standing DAAB’, then the following amendments will be needed:
EXAMPLE Delete the definitions under Sub-Clause 1.1.22 and 1.1.23 and
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
replace with:
CONDITIONS
Employer and the Contractor each avail themselves of the opportunity at the tender stage of
GENERAL
the Contract to name three potential members in the Contract Data.
In circumstances where the DAAB has given its decision but one or both Parties is/are
dissatisfied with the decision, the provisions of this Sub-Clause are intended to encourage the
GUIDANCE
Parties to settle a Dispute amicably, without the need for arbitration.
Rather than considering the 28 day period stated in this Sub-Clause as a ‘cooling-off period’,
FIDIC recommends that the Parties avail themselves of this opportunity to actively engage
with each other with a view to settling their Dispute.
FORMS
Such active engagement may be by, for example:
• direct negotiation by senior executives from each of the Parties;
• expert determination (using, for example, the Expert Rules published by the
International Chamber of Commerce (the “ICC”, which is based at 33-43 Avenue
du Président Wilson, 75116 Paris, France) https://iccwbo.org/publication/icc-expert-
rules-english-version/ †);
Amicable settlement procedures typically depend for their success on the consensual
involvement of both Parties, on confidentiality and on both Parties’ acceptance of the particular
procedure. Therefore, while it is recommended that both Parties engage actively to settle the
Dispute amicably, neither Party should seek to impose the procedure on the other Party.
If the Parties wish to adopt a mediation procedure in their attempt to settle the Dispute
amicably, then consideration may be given to the Mediation Rules, 2017 published by the
International Chamber of Commerce (the “ICC”, which is based at 33-43 Avenue du Président
Wilson, 75116 Paris, France) https://iccwbo.org/dispute-resolution-services/mediation/
mediation-rules/ †
Appointment of Mediator
Once the mediator has been appointed, the Dispute shall immediately
be referred to the mediator by the Parties or by either Party.
that follow below, during the mediation process the Parties shall
engage with the mediator and with each other in co-operation, in
a timely manner and in good faith.
Confidentiality
Mediator’s Opinion
Costs of Mediation
CONDITIONS
or has engaged in the mediation, in a frivolous or vexatious manner,
GENERAL
then the mediator shall have the power to order that Party to pay
the reasonable costs of the other Party for preparing for and
attending the mediation meeting. If these costs cannot be agreed,
they will be assessed by the mediator, whose assessment shall be
binding on the Parties.
GUIDANCE
Sub-Clause 21.6 Arbitration
The Contract should include provisions for the resolution by international arbitration of any
Dispute which is not settled amicably by the Parties. In international contracts, international
commercial arbitration has numerous advantages over litigation in national courts and is likely
to be more acceptable to the Parties.
FORMS
Careful consideration should be given to ensuring that the international arbitration rules that
are chosen are compatible with the provisions of Clause 21 and with the other elements to
be set out in the Contract Data. The Arbitration Rules published by the International Chamber
of Commerce (the “ICC”, which is based at 33-43 Avenue du Président Wilson, 75116 Paris,
France) https://iccwbo.org/dispute-resolution-services/arbitration/rules-of-arbitration/† are
frequently incorporated by reference in international contracts.
It is important that the Parties agree on the number of arbitrators and the language of
arbitration. In the absence of specific stipulations as to the number of arbitrators and the
place of arbitration in the Contract, the International Court of Arbitration of the ICC will decide
these matters.
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
If the arbitration rules published by the United Nations Commission on International Trade Law
(“UNCITRAL” which is based at the Vienna International Centre, A-1400 Vienna, Austria) http://
www.uncitral.org/pdf/english/texts/arbitration/arb-rules-revised/arb-rules-revised-2010-e.
pdf† or other non-ICC arbitration rules are preferred, it may be necessary to designate, in
the Contract Data, an institution to appoint the arbitrators or to administer the arbitration,
unless the institution is named (and their role specified) in the arbitration rules. It may also
be necessary to ensure, before so designating an institution in the Contract Data, that the
institution is prepared to appoint or administer.
For major projects tendered internationally, it is desirable that the place of arbitration be
situated in a country other than that of the Employer or Contractor. This country should have a
modern and liberal arbitration law and should have ratified a bilateral or multilateral convention
(such as the 1958 New York Convention on the Recognition and Enforcement of Foreign
Arbitral Awards), or both, that would facilitate the enforcement of an arbitral award in the
states of the Parties.
It may be considered desirable in some cases for other Parties to be joined into any
arbitration between the Parties or for two or more pending arbitrations to be consolidated,
thereby creating a multi-party arbitration. While the ICC Arbitration Rules address multi-party
arbitration, such arbitration may in some cases be feasible only if the parties have included
multi-party arbitration clauses in their contracts. Such clauses require skilful drafting, and
usually need to be prepared on a case-by-case basis
It is not unusual that the arbitration of a complex dispute is concluded sometime after
performance of the Contractor’s obligations under the Contract have been completed, in
which case it may not be fair and reasonable in the circumstances for any arbitral award which
requires the payment of an amount by one Party to the other Party to be in the currencies
Payment]. For example, the Contractor may no longer have any need for local currency after
GENERAL
completion of the Works; or the local currency may have declined in value in the interim or
be a ‘blocked currency’ that, consequently, cannot be removed from the country concerned.
GUIDANCE
FORMS
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
CONDITIONS
Uses Building Information Modelling Systems
GENERAL
Building Information Modelling (BIM), is a process which is changing many elements of the
design profession, the construction industry and, possibly, even the operation and maintenance
of a facility.
GUIDANCE
BIM is one of the digital data technologies used in all aspects of project planning, investigation,
design, construction and operation. Digital data technologies include systems for: data
acquisition; document management; design and process management; estimating, planning,
and scheduling; contract management; performance management; and building information
modelling.
FORMS
BIM has varying degrees of complexity ranging from rather isolated use of computer aided
design tools to full sharing of models and information by the entire project team. Currently,
BIM is more often used and better understood in developed countries, many of which are
encouraging or even mandating its use to improve quality, accuracy and delivery times for
projects as well as to provide cost savings. BIM has the potential to dramatically improve
productivity in the construction industry and reduce operational costs of facilities as well.
Coordination of goals and effort is essential and is generally achieved by a BIM Protocol and a
BIM Execution Plan, both key documents to access and understand work in this environment.
A designer needs to understand and work to the Levels of Design (or Detail) (LOD) that will be
spelled out in these documents to ensure that there is sufficient detail at each level to allow all
designs to progress efficiently and avoid unnecessary changes.
BIM is founded on a team approach and successful projects utilising BIM encourage
collaboration. FIDIC contracts are designed to be fair to all parties and are considered suitable
for use with projects featuring the use of BIM - providing that the parties recognise the difference
in approach and use the contract appropriately. This starts with proper planning and, unless
an employer has appropriate expertise in house, they are well advised to retain an engineer
who is appropriately qualified to assist them in the solicitation of interest, proposals, selection
and negotiation of contracts with the selected project team. Legal advice is also necessary, of
course, especially during the latter steps. The request for proposal (RFP) must clearly outline
what the client’s (employer’s) expectations of the consultant are. The expectations should
focus on the specific BIM goals and benefits desired. If properly developed, the RFP will
help the proposers be responsive and the employer select the consultant (or in the case of a
design build project, the project team) best qualified to deliver the desired BIM outcome. This
process will in turn help all parties develop appropriate contract terms and conditions. Ideally
the selection process would use FIDIC’s Quality Based Selection (QBS) guideline.
It should be noted that the improved quality of information in projects utilising BIM can result
in a significant reduction in variations. It is worth thinking about how the traditional roles of
contractor and employer fit into this structure. In general, BIM is well suited for integrated
early proactive involvement of the design engineer, contractor and employer are essential. If
GENERAL
advanced levels of BIM are anticipated for the project, the possibility of adding operation and
maintenance elements of the constructed facility might be considered.
For advanced levels of BIM where fully open sharing of information is required, a qualified
individual needs to be assigned the duty of managing the combined model. This should be
separate from the project manager’s role to ensure clear delineation of project responsibilities.
GUIDANCE
This may require special outsourcing, if such skills are not available from the employer or
engineer. Managing the BIM elements of a project may also involve risks that are beyond the
normal coverage of professional indemnity (PI) insurance policies. Specialist advice should be
sought from PI insurers if there is any doubt on coverage for this role. The competence and
responsibilities of this position need to be understood and should include experience in data
back-up and integrity, continuity planning and cyber security.
FORMS
All parties involved in a project utilising BIM should take special care in checking their assigned
scope and contract to ensure that they are aware of their BIM related responsibilities. The
risks that FIDIC has identified in working in a BIM environment arise from these key features:
To manage these and other digital technology related risks, consultants are encouraged to
clearly define adequately their proposed services, addressing such issues as:
- the systems and versions or releases they propose and the management processes
they will adopt
- access rights and limitations of the client, other consultants and contractors
- reliance other parties in the project may place on data in the digital environment
- limitations in terms of uptime and access and potential exclusion of liability for
down-time
- access to the current and previous issues of the combined model and to the
complete audit trail of changes to the model
At the completion of the project the model may need to be brought up to as-built status.
This involves not only the drawing elements but also the embedded data. Experience shows
that this is a significant effort, so responsibilities for completing this task should be clear and
appropriate allowances provided.
The process for the delivery of contractual notices should be checked to determine if this will
be through the common data environment or by more traditional means.
If sub-contractors are to be utilised, they should be bound by the BIM Protocol and Execution
Plan.
CONDITIONS
collaborative nature of the BIM process. Professionals with engineering, construction and
GENERAL
legal expertise should be consulted in this regard.
Legal counsel should review the contract to ensure that it does not create an unintended joint
venture which may be a risk in some jurisdictions.
GUIDANCE
If there is a fitness for purpose clause, make sure that it is clear who is responsible for
ensuring compliance and how responsibility for rectification is spread between participants.
Make sure that audit trails for modifications to the composite or federated model are controlled
by a process which can generate an audit trail that is preserved during and after completion.
The audit trail should be accessible by appropriate parties during and after project completion.
Given that there will be many parties involved in the design and construction effort, ensure
FORMS
that there are appropriate limits of liability in place for each participant and for the project as
a whole.
For subsurface projects involving BIM, in addition to considering the general principles as
introduced above, the following (non-exhaustive) list of Sub-Clauses of the General Conditions
of Contract Underground Works [©FIDIC 2019 First Edition] should be thoroughly reviewed
when drafting the Particular Conditions:
1.1 Definitions
1.3 Notices and Other Communications
1.5 Priority of Documents
1.10 Employer’s Use of Contractor’s Documents
1.11 Contractor’s Use of Employer’s Documents
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
Acceptable form(s) of security should be included in the tender documents: for Annex A and/or
B, in the Instructions to Tenderers; and for Annexes C to G, annexed to the Particular Conditions.
The following example forms, which (except for Annex A) incorporate Uniform Rules published by
the International Chamber of Commerce (the “ICC”, which is based at 33-43 Avenue du Président
GUIDANCE
Wilson, 75116 Paris, France, www.iccwbo.org), need to be carefully reviewed against, and may have
to be amended to comply with, applicable law. Although the ICC publishes guides to these Uniform
Rules, legal advice should be taken before the securities are written. Note that the guaranteed
amounts should be quoted in all the currencies, as specified in the Contract, in which the guarantor
pays the beneficiary.
FORMS
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
CONDITIONS
GUARANTEE
GENERAL
Name of Contract/Contract No.:_________________________________________________________
Name and address of Employer:_________________________________________________________
__________________________________________________ (together with successors and assigns).
GUIDANCE
We have been informed that ____________________________________ (hereinafter called the
“Contractor”) is submitting an offer for such Contract in response to your invitation, and that the
conditions of your invitation require his/her offer to be supported by a parent company guarantee.
In consideration of you, the Employer, awarding the Contract to the Contractor, we (name of
parent company) irrevocably and unconditionally guarantee to you, as a primary obligation, the
due performance of all the Contractor’s obligations and liabilities under the Contract, including the
FORMS
Contractor’s compliance with all its terms and conditions according to their true intent and meaning.
If the Contractor fails to so perform his/her obligations and liabilities and comply with the Contract,
we will indemnify the Employer against and from all damages, losses and expenses (including
legal fees and expenses) which arise from any such failure for which the Contractor is liable to the
Employer under the Contract.
This guarantee shall come into full force and effect when the Contract comes into full force and effect.
If the Contract does not come into full force and effect within a year of the date of this guarantee,
or if you demonstrate that you do not intend to enter into the Contract with the Contractor, this
guarantee shall be void and ineffective. This guarantee shall continue in full force and effect until
all the Contractor’s obligations and liabilities under the Contract have been discharged, when this
guarantee shall expire and shall be returned to us, and our liability hereunder shall be discharged
absolutely.
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
This guarantee shall apply and be supplemental to the Contract as amended or varied by the Employer
and the Contractor from time to time. We hereby authorise them to agree any such amendment or
variation, the due performance of which and compliance with which by the Contractor are likewise
guaranteed hereunder. Our obligations and liabilities under this guarantee shall not be discharged
by any allowance of time or other indulgence whatsoever by the Employer to the Contractor, or by
any variation or suspension of the works to be executed under the Contract, or by any amendments
to the Contract or to the constitution of the Contractor or the Employer, or by any other matters,
whether with or without our knowledge or consent.
This guarantee shall be governed by the law of the same country (or other jurisdiction) as that which
governs the Contract and any dispute under this guarantee shall be finally settled under the Rules
of Arbitration of the International Chamber of Commerce by one or more arbitrators appointed in
accordance with such Rules. We confirm that the benefit of this guarantee may be assigned subject
only to the provisions for assignment of the Contract.
Whether one or more signatories for the parent company are required will depend on the parent
(1)
The Beneficiary (the “Employer”):__________________ [insert name and address of the Beneficiary]
We have been informed that ____________________________________________________ [insert
name and address of the Tenderer] (hereinafter called the “Applicant”) is submitting an offer for such
Contract in response to your invitation, and that the conditions of your invitation (the “Conditions of
Invitation”, which are set out in a document entitled Instructions to Tenderers) require his/her offer to
FORMS
(b) the Applicant has refused to accept the correction of errors in his/her offer in
accordance with such Conditions of Invitation, or
(c) you awarded the Contract to the Applicant and he/she has failed to comply with
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
(d) you awarded the Contract to the Applicant and he/she has failed to comply with
Sub-Clause 4.2.1 of the Conditions of Contract.
Any demand for payment must contain your signature(s) which must be authenticated by your
bankers or by a notary public. The authenticated demand and statement must be received by us
at the following office [insert address of office] on or before ________________________ [insert the
date 35 days after the expiry of the validity of the Letter of Tender], when this guarantee shall expire.
Date:___________________________________
Whether one or more signatories for the bank are required will depend on the bank and/or
(1)
applicable law.
CONDITIONS
- DEMAND GUARANTEE
GENERAL
Guarantee No.:__________________________ [insert guarantee reference number]
The Guarantor:_______________________________________________________________________
[insert name and address of place of issue, unless indicated in the letterhead]
GUIDANCE
Name of Contract/Contract No.: __________________________________________________[insert
reference number or other information identifying the contract between the Applicant and the
Beneficiary on which the guarantee is based]
FORMS
We have been informed that ____________________________________________________ [insert
name and address of the Contractor] (hereinafter called the “Applicant”) is your Contractor under
such Contract, which requires him/her to obtain a Performance Security.
At the request of the Applicant, we __________________________________________ [insert name
of Guarantor] hereby irrevocably undertake to pay you, the Beneficiary/Employer, any sum or sums
not exceeding in total the amount of __________________________________ [insert in figures and
words the maximum amount payable and the currency in which it is payable] (the “Guaranteed
Amount”) upon receipt by us of your demand in writing and your written statement indicating in what
respect the Applicant is in breach of its obligations under the Contract.
[Following receipt by us of an authenticated copy of the Taking-Over Certificate for the whole of the
Works under Clause 10 of the Conditions of Contract, the Guaranteed Amount shall be reduced by
________________ % and we shall promptly notify you that we have received such certificate and
have reduced the Guaranteed Amount accordingly.] (1)
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
(signature) (signature)
GENERAL
________________________________________ ________________________________________
(name) (name)
Date:___________________________________
GUIDANCE
(1)
When drafting the tender documents, the writer should ascertain whether to include the optional
text, shown in parentheses [ ]
(2)
Whether one or more signatories for the bank are required will depend on the bank and/or
applicable law
FORMS
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
CONDITIONS
- SURETY BOND
GENERAL
Name of Contract/Contract No.: ________________________________________________________
Name and address of Beneficiary (the “Employer”): _________________________________________
____________________________________________________________________________________
GUIDANCE
We have been informed that ____________________________________________________ [insert
name of the Contractor] (hereinafter called the “Principal”) is your contractor under such Contract,
which require him/her to obtain a Performance Security.
By this Bond, ________________________________________________________________________
_________________________________________________ [insert name and address of contractor]
FORMS
_________________________________________________________________________ [insert name
and address of Guarantor] as Guarantor are irrevocably held and firmly bound to the Beneficiary in
the total amount of _______________________ [insert in figures and words the maximum amount
payable and the currency in which it is payable] (the “Bond Amount”) for the due performance of all
such Principal’s obligations and liabilities under the above named Contract.
[Such Bond Amount shall be reduced by ________________ % upon the issue of the Taking-Over
Certificate for the whole of the Works under Clause 10 of the Conditions of Contract.](1)
This Bond shall become effective on the Commencement Date defined in the Contract.
Upon Default by the Principal to perform any contractual obligation, or upon the occurrence of
any of the events and circumstances listed in Sub-Clause 15.2.1 of the Conditions of Contract,
the Guarantor shall satisfy and discharge the damages sustained by the Beneficiary due to such
Default, event or circumstances.(2) However, the total liability of the Guarantor shall not exceed the
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
Bond Amount.
The obligations and liabilities of the Guarantor shall not be discharged by any allowance of time or
other indulgence whatsoever by the Beneficiary to the Principal, or by any variation or suspension
of the Works to be executed under the Contract, or by any amendments to the Contract or to the
constitution of the Principal or the Beneficiary, or by any other matters, whether with or without the
knowledge or consent of the Guarantor.
Any claim under this Bond must be received by the Guarantor on or before ____________________
[insert the date six months after the expected expiry of the Defects Notification Period for the Works]
(the “Expiry Date”), when this Bond shall expire and shall be returned to the Guarantor.
The benefit of this Bond may be assigned subject to the provisions for assignment of the Contract,
and subject to the receipt by the Guarantor of evidence of full compliance with such provisions.
This Bond shall be governed by the law of _________________________________ [insert the law
governing the bond] being the same country (or other jurisdiction) as that which governs the
Contract. This Bond incorporates and shall be subject to the Uniform Rules for Contract Bonds,
published as number 524 by the International Chamber of Commerce, and words used in this Bond
shall bear the meanings set out in such Rules.
Whereas this Bond has been issued by the Principal and the Guarantor on ________________ [date]
________________________________________ ________________________________________
GENERAL
(signature) (signature)
________________________________________ ________________________________________
(name) (name)
GUIDANCE
When writing the tender documents, the writer should ascertain whether to include the optional
(1)
Insert: [and shall not be entitled to perform the Principal’s obligations under the Contract.]
(2)
FORMS
Or: [or at the option of the Guarantor (to be exercised in writing within 42 days of receiving the claim
specifying such Default) perform the Principal’s obligations under the Contract.]
Whether one or more signatories for the Principal are required will depend on the Principal and/or
(3)
applicable law.
Whether one or more signatories for the Guarantor are required will depend on the Guarantor and/
(4)
or applicable law.
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
CONDITIONS
GUARANTEE
GENERAL
Guarantee No.: ________________________________________ [insert guarantee reference number]
GUIDANCE
indicated in the letterhead]
FORMS
______________________________________________ [insert name and address of the Beneficiary]
(b) the amount of the advance payment which the Applicant has failed to repay.
This guarantee shall become effective upon receipt [of the first instalment] of the advance payment
by the Applicant. The Guaranteed Amount shall be reduced by the amounts of the advance payment
repaid to you, as evidenced by interim payment certificates issued under Sub-Clause 14.6 of the
Conditions of Contract. Following receipt of a copy of each interim payment certificate, we shall
promptly notify you of the revised Guaranteed Amount accordingly.
Any demand for payment must contain your signature(s) which must be authenticated by your
bankers or by a notary public. The authenticated demand and statement must be received by us
at the following office [insert address of office] on or before ________________________ [insert the
date 70 days after the expected expiry of the Time for Completion] (the “Expiry Date”), when this
guarantee shall expire.
The party liable for the payment of any charges: __________________ [insert the name of the party].
This guarantee shall be governed by the laws of ___________________________[insert the law
governing the guarantee], and shall be subject to the Uniform Rules for Demand Guarantees (URDG)
2010 Revision, ICC Publication No. 758.
Date:___________________________________
Whether one or more signatories for the bank are required will depend on the bank and/or
(1)
applicable law.
GUARANTEE
GENERAL
At any time, our liability under this guarantee shall not exceed the total amount of retention money
released to the Applicant by you, as evidenced by interim payment certificates issued under
Sub-Clause 14.6 of the Conditions of Contract with a copy being submitted to us.
Any demand for payment must contain your signature(s) which must be authenticated by your
bankers or by a notary public. The authenticated demand and statement must be received by us
at the following office [insert address of office] on or before ______________________ [insert the
date 70 days after the expected expiry of the Defects Notification Period for the Works], (the “Expiry
Date”), when this guarantee shall expire.
We have been informed that the Beneficiary may require the Applicant to extend this guarantee if the
Performance Certificate under the Contract has not been issued by the date 28 days prior to such Expiry
Date. We undertake to pay you the Guaranteed Amount upon receipt by us, within such period of 28
days, of your demand in writing and your written statement that the Performance Certificate has not been
issued, for reasons attributable to the Applicant, and that this guarantee has not been extended.
The party liable for the payment of any charges: __________________ [insert the name of the party].
This guarantee shall be governed by the laws of _________________________ [insert the law
governing the guarantee] and shall be subject to the Uniform Rules for Demand Guarantees (URDG)
2010 Revision, ICC Publication No. 758.
Whether one or more signatories for the bank are required will depend on the bank and/or
(1)
applicable law.
CONDITIONS
EMPLOYER
GENERAL
Guarantee No.: ________________________________________ [insert guarantee reference number]
The Guarantor: _______________________________________________________________________
________________________________________ [insert name and address of place of issue, unless
indicated in the letterhead]
GUIDANCE
Name of Contract/Contract No.: ________________________________________________________
_____________________________________________ [insert reference number or other information
identifying the contract between the Applicant and the Beneficiary on which the guarantee is based]
FORMS
We have been informed that ____________________________________________________________
_______________________________________________ [insert name and address of the Employer]
(hereinafter called the “Applicant”) is required to obtain a bank guarantee.
The party liable for the payment of any charges: __________________ [insert the name of the party].
This guarantee shall be governed by the laws of _________________ [insert the law governing
the guarantee] and shall be subject to the Uniform Rules for Demand Guarantees (URDG) 2010
Revision, ICC Publication No. 758.
Whether one or more signatories for the bank are required will depend on the bank and/or
(1)
applicable law.
PREPARATION OF
TENDER DOCUMENTS
AND ANNEXES: TABLE
OF CONTENTS OF
THE GEOTECHNICAL
BASELINE REPORT,
EXAMPLE FORMS
OF SCHEDULE OF
BASELINES, COMPLETION
SCHEDULE, SCHEDULE
OF CONTRACTOR’S KEY
EQUIPMENT
FORMS OF LETTER OF
TENDER, LETTER OF
ACCEPTANCE, CONTRACT
AGREEMENT AND
DISPUTE ADJUDICATION/
AVOIDANCE AGREEMENT
In collaboration with
CONDITIONS
1 General Aspects
GENERAL
When preparing the tender documents and planning the tender process, Employers should consult
the publication FIDIC Procurement Procedures Guide 1st edition 2011 (http://fidic.org/books/
fidic-procurement-procedures-guide-1st-ed-2011) which presents a systematic approach to the
procurement of engineering and building works for projects of all sizes and complexity, and gives
invaluable help and advice on the contents of the tender documents, and the procedures for receiving
GUIDANCE
and evaluating tenders. This publication provides internationally acceptable, comprehensive, best
practice procedures designed to increase the probability of receiving responsive clear and competitive
tenders using FIDIC forms of contract. FIDIC intends to update the FIDIC Procurement Procedures
Guide (planned for publication at a later date) to make specific reference to these Conditions of
Contract for Underground Works, First Edition 2019.
The tender documents issued by the Employer should be prepared by suitably qualified engineers
FORMS
who are familiar with the technical aspects of the required works and the particular requirements and
contractual provisions of a design-build project for Underground Works. Furthermore, a review by
suitably qualified lawyers is advisable.
The tender documents issued to tenderers should normally include the following:
- a letter of invitation to tender
- the Instructions to Tenderers (including advice on any matters which the Employer wishes
tenderers to include in their tenders but which do not form part of the Employer’s Requirements)
and the various base documents forming the Contract in order of priority:
(a) the required forms of agreement (see Sample Contract Agreement);
(b) the Form of Letter of Tender (see Sample Letter of Tender) and required appendices (if
any);
Particular Conditions of Contract:
(c) Particular Conditions Part A - Contract Data and
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
The Instructions to Tenderers may need to specify any constraints on the completion of the Contract
GENERAL
Data and/or Schedules, and/or specify the extent of other information which each tenderer is to
include with the tender. If each tenderer is to produce a tender security and/or a parent company
guarantee, these requirements should be stated in the Instructions to Tenderers: example forms are
included at the end of this publication.
It is important for the Parties to understand which of the documents included in the tender dossier,
and which of the documents submitted by tenderers, will form part of the Contract and therefore
GUIDANCE
have continuing effect (for example, the Instructions to Tenderers are not, by definition, a part of the
Contract. They are simply instructions and information on the preparation and submission of the
tender).
If tenderers are required to carry out any preliminary design or study for their proposals, the Employer
should bear in mind that tenderers are understandably often reluctant to incur great expense in the
preparation of tender designs. Therefore, when preparing the Instructions to Tenderers, thought
FORMS
should be given as to the extent of detail which tenderers can realistically be expected to prepare
and include in their proposals. The extent of detail required should be clearly described in the
Instructions to Tenderers (it should be noted that there can be no description in the documents
which will later constitute the Contract, which only comes into full force and effect when a tenderer’s
proposal is accepted). Employers should also consider remunerating tenderers if, in order to provide
a responsive tender, they have to undertake studies or carry out preliminary design work.
The procedure for award of Contract should be stated clearly in the Instructions to Tenderers.
It is in the interest of the Employer for tenderers to prepare and submit a responsive tender.
Accordingly, the Employer should avoid setting a tender period which is either too short and which
can reduce competition and result in inadequate submittals or too long which can be wasteful to all
parties involved.
The review and evaluation of tenders and the award of the Contract requires time. This will be the
minimum time which tenderers should be asked to hold their tenders valid and open to acceptance.
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
CONDITIONS
effect) includes the Contractor’s Proposal and completed Schedules.
GENERAL
It should be noted that certain documents may need to be amended during the negotiation process,
where permitted by applicable Law, in particular:
- the Geotechnical Baseline Report;
- the Schedule of Baselines;
- the Completion Schedule; and
GUIDANCE
- the Contract Risk Register and associated Schedules
to be consistent with any adoption of a Contractor’s Proposal which differs in detail from the
Employer’s reference design.
Particular Conditions Part A - Contract Data
Many Sub-Clauses in the General Conditions make reference to data being contained in the Contract
Data (Particular Conditions – Part A). This data must be provided in the tender documents, and
FORMS
these Conditions of Contract assume that all such data will be provided by the Employer, except
as expressly noted in the form of Contract Data included in the Guidance for the Preparation of
Particular Conditions before this Guidance.
If the Employer requires tenderers to provide any of the other information required in the Contract
Data, the tender documents must make this clear.
Particular Conditions Part A – Completion Schedule
Please see paragraph 4.2.1 below for guidance on the preparation of the Completion Schedule.
Particular Conditions Part A – Schedule of Baselines
Please see paragraph 2.3 below for guidance on the preparation of the Schedule of Baselines.
Particular Conditions Part B - Special Provisions
Please see the separate section entitled “Guidance for the Preparation of Special Provisions” in this
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
publication above.
The Geotechnical Baseline Report
Each of the tenderers should receive the data referred to in Sub-Clause 2.5 [Site Data and Items of
Reference], including but not limited to the Geotechnical Baseline Report,
Please see paragraph 2.3 and Appendix A below for guidance on the preparation of the GBR.
The General Conditions of Contract
The following Sub-Clauses make express reference to matters to be included in the Employer’s
Requirements:
1.8 Care and Supply of Documents
1.9 Errors in the Employer’s Requirements and/or in the Geotechnical Baseline Report
1.11 Contractor’s Use of Employer’s Documents
1.13 Compliance with Laws
1.16 Contract Risk Register and Contract Risk Management Plan
2.1 Right of Access to the Site
2.5 Site Data and Items of Reference
2.6 Employer-Supplied Materials and Employer’s Equipment
4.1 Contractor’s General Obligations
4.5 Nominated Subcontractors
4.6 Co-operation
4.7 Setting Out
4.8 Health and Safety Obligations
4.9 Quality Management and Compliance Verification Systems
4.10 Use of Site Data, of the Geotechnical Baseline Report and of the Geotechnical Data
Report
4.17 Contractor’s Equipment
4.18 Protection of the Environment
5.5 Training
5.6 As-Built Records
5.7 Operation and Maintenance Manuals
6.1 Engagement of Staff and Labour
6.6 Facilities for Staff and Labour
6.7 Health and Safety of Personnel
6.12 Contractor’s Key Personnel
FORMS
7.3 Inspection
7.4 Testing by the Contractor
7.8 Royalties
8.3 Programme
9.1 Contractor’s Obligations
10.2 Taking Over Parts
11.11 Clearance of Site
12.1 Procedure for Tests after Completion.
13.1 Right to Vary
However, it may also be necessary under other Sub-Clauses for the Employer to give specific
information in the Employer’s Requirements (for example, under Sub-Clause 7.2 [Samples])
The Employer’s Requirements
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
The Employer’s Requirements should specify the particular requirements for the completed Works,
including functional requirements, quality and scope. If the Contractor is required to supply certain
items, such as consumables, these should be listed in a Schedule.
Drafters of the Employer’s Requirements must remember that if any matters are not referred to or
covered, the Contractor may well be relieved of any responsibility in respect of such matters.
If the Works are to include fixtures, fittings equipment, (for example, separated ventilation or utility
ducts, running surfaces, drainage within the Lining Works, and suchlike) and other similar items, the
scope of such work must be defined in the Employer’s Requirements. Full consideration should be
given to detailed requirements for these items, such as the extent to which the Works are to be
fully equipped, ready for operation, with spare parts and consumables provided for operation (for a
specified period), typically by the Employer. If the Contractor is required to operate the Works, either
for a few months’ trial operation under sub-paragraph (c) of Sub-Clause 9.1 [Contractor’s Obligations]
or for some years’ operation, this must also be specified and detailed in the Employer’s Requirements.
Other Schedules
For this type of contract where the Works, except the Excavation and Lining Works, are normally
valued on a lump sum basis, the Schedules may include a Schedule of Payments (as referred to
under Sub-Clause 14.4 [Schedule of Payments] in the General Conditions).
In respect of the Excavation and the Lining Works, which are to be valued by measurement, the Bill
of Quantities in the Schedule of Rates and Prices will be the most important Schedule.
A Daywork Schedule may also be necessary, to cover minor works to be executed at cost.
The Schedule of Contractor’s Key Equipment forms part of the “other Schedules”.
Many Sub-Clauses in the General Conditions make reference to data being contained in such other
Schedules. This data must be provided in the tender documents, and these Conditions of Contract
assume that if such data is not provided by the Employer, then it is provided by the tenderer. Where
the Employer requires tenderers to provide any information in a Schedule, the tender documents
must make this clear by identifying the Schedule and the specific information that the tenderer is to
provide.
CONDITIONS
Please see the guidance given under Sub-Clause 1.14 [Joint and Several Liability] in the separate
GENERAL
section entitled “Guidance for the Preparation of Special Provisions” in this publication above.
Other documents forming part of the Contract
These will include (but not limited to) the Geotechnical Data Report or GDR, the Contract Risk
Management Plan and the Contract Risk Register.
Please see paragraph 3.1.3 below for guidance on the preparation of the Geotechnical Data Report.
GUIDANCE
Please see paragraph 1 of Appendix A below for guidance on the preparation of the Contract Risk
Register and the Contract Risk Management Plan.
FORMS
for Employers to note that the tender documents for Underground Works should include detailed
information about the anticipated subsurface physical conditions, including expected ground and
ground water risks identified by the Employer and the design considerations relating to these risks
that the Employer has taken into consideration when formulating the Employer’s reference design.
While the Employer will suggest preferred method(s) of construction based on the anticipated
subsurface physical conditions and the risks associated therewith, the Employer should allow
tenderers to propose alternative construction methods in line with their proposals for design and
construction of the Works.
Sufficient investigation of the subsurface physical conditions, of the access limitations to the Site and
of the potential influence of the Works on the surrounding ground, ground water table and on the
surface should be carried out by the Employer and the results provided to tenderers in the tender
documents.
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
Also, the preparation of the tender documents requires a dedicated time frame, independent of the
time allocated by the Employer to any previous design stages.
2.3 The Geotechnical Baseline Report GBR and the Schedule of Baselines (Sub-Clauses
2.5, 4.10.2 and 8.2.2)
The reaction of the surrounding ground to the underground excavation and support processes
depends not only on the geotechnical parameters of the ground mass but also on the design
concept proposed by the Employer and the methods of construction for excavation and support.
This information (range of geotechnical parameters plus method of construction for excavation and
support with relevant ground classification system) shall be described in the Geotechnical Baseline
Report (GBR) as the single source of allocation of risks due to subsurface physical conditions.
The anticipated quantities of Excavation and Lining Works included in the GBR shall be itemized in
the Schedule of Baselines. The tenderer shall then enter the corresponding production rate against
each different item of work.
GUIDANCE
The Schedule of Baselines and the GBR shall have high priority amongst the Contract documents.
Due to the overriding issue of Time for Completion, the Schedule of Baselines, which provides the
time link to the Completion Schedule, takes precedence over the GBR.
conditions and on the production rates submitted by the tenderer. As the subsurface physical
conditions are within the risk sphere of the Employer and the production rates are within the risk
sphere of the Contractor, the time available to the Contractor for the Underground Excavation and
Lining Works shall be measured and adjusted against the difference between the subsurface physical
conditions expected (as described in the GBR and as quantified in the Schedule of Baselines) and
the subsurface physical conditions actually encountered.
The adjustment mechanism shall be clearly stated in the tender documents.
No adjustment shall be provided for any difference between the production rates stated in the
Contractor’s Proposal and the performance rates actually achieved for the specified set of subsurface
physical conditions in the Schedule of Baselines.
The Milestones that are relevant to the Employer shall be clearly stated in the Completion Schedule
which shall be compatible with and based on the quantities itemized in the Schedule of Baselines.
Time adjustments and Extensions of Time, if any, shall be calculated and determined by reference
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
2.6 Measurement of Excavation and Lining Works and Adjustment of Time for
Completion and Contract Price (Sub-Clause 13.8)
A major portion of the costs incurred by the Contractor is related to time rather than to the quantities
produced (in particular, technical, commercial and administrative overheads, depreciation and
maintenance of Contractor’s Equipment, leasing costs etc.).
The Bill of Quantities shall consequently provide for time-related rate items which allow for the
corresponding adjustments in the Contract Price according to the adjustments in Time for Completion.
CONDITIONS
should be undertaken.
GENERAL
3.1.2 Access to the Site and Working Areas (Sub-Clauses 2.1, 4.13, 4.14 & 4.15)
Permission for and physical access to the Site as well as the availability of the working areas on- and
off- Site should be investigated prior to issuing the tender documents. Sufficient time, should be
allocated for the related permanent or temporary expropriation and/or possession of the requisite
areas if required.
GUIDANCE
3.1.3 Geology, Hydrogeology, Hydrology and Geotechnics (Sub-Clause 4.10)
The relevant data for the realization of the Works should be collected, analyzed and, if applicable,
monitored. Investigation may include, amongst others, extensive study of available literature and
data, geophysical surveys, destructive and non-destructive probe drilling, down-the-hole testing,
surface testing and laboratory testing, as well as related digital modelling.
Particular attention should be given to investigation and testing with long lead times (deep drilling,
time consuming laboratory tests and long-term monitoring of ground water levels etc.).
FORMS
The data, so collected, shall be identified and described in the Geotechnical Data Report GDR.
3.3 Disposal of Excavated and Waste Materials (Sub-Clause 7.1 & 7.8)
Disposal of excavated Material is crucial to the success of the project because of the large volumes
involved.
Suitable treatment and disposal facilities of Materials to be re-used or removed from the Underground
Works should be explored and secured for the:
a) Material to be excavated and/or re-cycled, including chemical alterations caused by the
excavation and support processes, based on the expected quality of excavation Material;
and
b) typical waste Material removed from the Works during construction including those subjected
to varying degrees of contamination and/or hazardous slurries and water.
3.4 Materials Testing (Sub-Clause 7.2 + 7.4)
Critical parts of Underground Works may be difficult to access after construction. Their durability is
therefore essential. If no long-term performance data is available for the Materials and systems to
be provided for any such part of the Works, either accelerated testing of such Materials should be
undertaken, or access be ensured by particular arrangements. Such situations should be identified
at an early stage in the initial risk assessment of the project.
4 Employer’s Tender Documents
Apart from the mandatory contractual information, the tender documents shall include the following
documents, without limitation, in the following order of priority :
and construction, the times computed in the Schedule of Baselines and the times for construction
GENERAL
of all other items of work specified in the Contract to be executed and completed by the tenderer.
The Completion Schedule shall be based on and compatible with the Schedule of Baselines and
shall include the Employer defined Milestones (Sub-Clause 1.1.63) and drives of the project.
The Programme (Sub-Clause 1.1.78) submitted by the Contractor shall be based on the agreed
Completion Schedule and on the key dates specified in the Contract Data.
GUIDANCE
shall be consistent with the GBR, the characteristics of the proposed Contractor’s Key Equipment
and the experience of the Contractor’s Key Personnel all as described in the relevant Schedules.
The Schedule of Baselines shall be based on the GBR and on the Employer’s reference design.
The Schedule of Baselines shall contain all the activities and their anticipated quantities for the
underground Excavation (Sub-Clause 1.1.43) and Lining (Sub-Clause 1.1.60) Works, typically
allocated by Sections and drives.
The Schedule of Baseliness shall include, if applicable and without limitation, the following information
and/or measures relating to:
a) location, dimensions, nature and characteristics of expected utilities and underground
structures;
b) excavation and support classes as described in the GBR and the Employer’s reference
design;
c) probe drilling and other investigations related to assessing subsurface physical conditions;
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
d) complementary support;
e) advanced ground treatment, such as poor or contaminated ground;
f) consolidation and waterproofing grouting;
g) seepage, water ingress treatment and related hindrances;
h) treatment of geological overbreak and related hindrances;
i) waterproofing;
j) construction of the final Lining;
k) interruptions due to changes in the method of construction for Excavation and Lining Works;
l) interruptions due to Unforeseeable subsurface physical conditions, i.e. those not included
in the GBR (see example Appendix A); and
m) anticipated interruptions and hindrances anticipated due to the Employer or Authorities.
The Schedule of Baselines shall also include other relevant conditions for the Works specified in the
Contract, such as working time per shift/per day/per week, number of shifts per week, number of
working days per week, compulsory holidays etc.
The Schedule of Baselines shall be divided into units (typically individual drives and/or methods
of construction per zone) that reflect a Section or Part of the Works, if applicable, to enable the
computation of the time available to the Contractor for the specific corresponding production times
for the Underground Excavation and Lining of the same.
The corresponding total time available for each unit shall be the sum of all the individual production
times for the realization of the individual items of work itemized in the relevant Schedule of Baselines.
The time for the realization of an individual item of work shall be calculated by dividing the quantity
specified by the Employer by the corresponding production rate submitted by the Contractor taking
into any time for learning curves into account.
4.1.2 The Particular Conditions Part B - Special Provisions (Sub-Clause 1.1.70)
The Special Provisions shall include information and/or instructions about and without limitation on:
a) the decision process affecting the excavation and support measures;
CONDITIONS
sharing and co-operation instructions; provision of permits; temporary rights of way and
GENERAL
conditions for preparing the Sections or Parts for the Taking-Over Certificate);
c) the removal or temporary storage of excavated material, waste treatment and disposal,
including ownership and instructions on recycling (if any);
d) utility requirements (water supply, effluent treatment and disposal, normal and emergency
power supply, telecommunications);
e) facilities and services to be provided for the Employer’s Personnel and/or Contractor’s
GUIDANCE
Personnel; and
f) instructions and/or constraints on logistics to and from Site and inspections off Site (e.g.
factory acceptance tests for Contractor’s Key Equipment, Materials and Plant, etc.).
4.2 The Geotechnical Baseline Report GBR (Sub-Clause 1.1.51 + 4.10.2)
(see also: Appendix A to this Guidance)
The GBR contains the only contractual definition of what is assumed to be encountered in defining
FORMS
the contractual allocation of the risks for subsurface physical conditions between the Parties. The
risk allocation in the GBR depends on the Employer’s preferred risk acceptance. The design concept
chosen by the Employer and the GBR is thus an interpretation of the expected subsurface physical
conditions, adapted to the preferred risk allocation by the Employer. This implies that the GBR may
deviate from factual geological data contained in the GDR (Sub-Clause 1.1.52).
GBR interpretations can also be based on experience and other sources of relevant information on
the subsurface physical conditions. The GBR shall include parameters that focus on the behaviour of
the ground and groundwater caused by or having impact on the method of excavation and support
rather than on pure scientific data.
The GBR shall include instructions on acceptable impacts due to construction on adjacent facilities,
the subsurface and on the surface alike (i.e. permissible settlements, impact on groundwater, etc.).
The assumed subsurface physical conditions stated in the GBR shall include the Employer’s
proposal for the method of construction for each zone for excavation and support, together with the
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
CONDITIONS
The BoQ shall be based on and consistent with the Employer’s reference design.
GENERAL
4.6 Contractor’s Proposal (Sub-Clause 1.1.23)
4.6.1 Compliant Proposal
The Contractor shall submit a compliant proposal with the tender documents issued by the Employer.
4.6.1.1 Completion of the Completion Schedule
GUIDANCE
The Tenderer shall complete the Completion Schedule based on and consistent with
a) the Schedule of Baselines, including the tendered production rates;
b) the Milestones that are independent of the criteria set out in the Schedule of Baselines; and
c) the details of the production rates defined in the Contractor’s Proposal.
The Completion Schedule shall include the logical links between all Sections and Milestones and the
distinct activities comprising the required items of work linked to the Sections and Milestones.
FORMS
4.6.1.2 Method statements
The Contractor’s Proposal shall be structured and describe the manner of execution in the form of
method statements including, but not limited to, detailed information on the:
a) Contractor’s Personnel organization and associated resources;
b) provisions for the Employer’s Personnel on and off Site (if any);
c) software systems intended to be employed for planning, design, records and reporting;
d) execution of the Permanent Works according to Sections as specified in the GBR;
e) execution of the Temporary Works including Site establishment;
f) storage of material and in particular those involving waste and hazardous materials;
g) interface requirements for utility connections at various locations on and around the Site;
h) operation of borrow pits, disposal areas and transport within, or to and from, the Site;
i) Contractor’s Key Equipment and arrangements of installations;
j) management of Health, Safety and Environmental and of Security issues;
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
The Employer shall include all available relevant information in the tender documents as follows,
GENERAL
without limitation:
a) the Contract Risk Register and the Contract Risk Management Plan, to be completed by
the Contractor;
b) the results of the preliminary investigations (i.e. borehole log information and core drillings) and
other factual geological, hydrogeological and geotechnical information in the Geotechnical
GUIDANCE
CONDITIONS
GENERAL
The Geotechnical Baseline Report (GBR)
Introduction
GUIDANCE
1 The Contractual Purpose of the Geotechnical Baseline Report GBR
2 Administration and Reference for Measurement during Contract
3 GBR Content Recommendations
4 The Purpose of the Geotechnical Data Report GDR
5 Example Table of Contents of a GBR
FORMS
Introduction
The Geotechnical Baseline Report describes the subsurface physical conditions to serve as a basis
for the execution of the Excavation and Lining Works, including design and construction methods,
and the reaction of the ground to such methods. The GBR sets out the allocation of the risk between
the Parties for such subsurface physical conditions.
conditions. The GBR is used to design the work, plan and equip the excavation process, and help
adjudicate disputes associated with unforeseen subsurface physical conditions.
The GBR allocates the subsurface condition risks between the Employer and the Contractor for the
elements of work as set out in the Schedule of Baselines.
The design concept selected by the Employer and the interpretations stated in the GBR collectively
represent the Employer’s preferred risk allocation for the subsurface physical conditions. This shall
apply to the Employer’s reference design and any alternative design and method of construction
submitted in the Contractor’s Proposal by a tenderer. The GBR statements may also be based
on previous construction experience or exploration data from other sources of relevant information
on the physical and behavioral conditions of the ground. Because the GBR statements reflect
information beyond the data, they may deviate from the factual geological, hydrogeological and/or
geotechnical data contained in the Geotechnical Data Report or (GDR).
The GBR also serves to convey and highlight the key project constraints and requirements, as well
as latitudes, to enable the tenderers to grasp the key project issues.
The GBR shall include parameters that help to describe the physical characteristics of the ground
and ground water conditions, as well as the most likely ground behaviours to be expected during the
and methods utilized, descriptions of anticipated ground behaviour will be presented within the
GENERAL
Physical and behavioural statements in the GBR shall be described using quantitative terms (with
limits where appropriate e.g water inflow, rate of deformation) to the extent practicable. As far as
possible the selected baseline parameters shall have the ability to be confirmed by the physical or
behavioural conditions encountered quantitively in the field, to reduce ambiguity in the scope of
GUIDANCE
work, avoid delays and potential for disputes, and improve time and cost certainty.
The GBR shall also, where possible, present examples of relevant, local construction projects that
experienced physical conditions similar to those anticipated to be encountered for the proposed
Works.
FORMS
The FIDIC General Conditions of Contract for Underground Works are based on the principles of
fairness and therefore of balanced risk allocation to the Contractor and the Employer. Each risk of
foreseeable subsurface physical conditions shall be allocated in the Geotechnical Baseline Report to
the Party that is best positioned to control it, which leads to more effective risk control. Transparent
and equitable allocation of ground related risks leads to more competitive Tenders and lower outturn
cost of the Works. The Employer should avoid establishing an overly conservative GBR, as this will
render it less effective. Instead, the Employer is advised to provide realistic statements in the GBR
to give the tenderers confidence in the fairness of the Schedule of Baselines as the basis for the
Tender.
The location of the ground for the construction of the Underground Works is selected and made
available by the Employer. Consequently, the Employer’s GBR and reference design need to be
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
compatible with the other Employer’s Requirements as these form the basis for the assumptions in
the Tenders. The Contractor’s Proposal of design methodology, the detailed means and measures
including methods of construction for Excavation and Lining and the associated production rates
for any given set of circumstances, must be then selected by the tenderer and submitted in the
completed Schedule of Baselines consistent with the Employer’s reference design and/or alternative
design (if any).
This difference in the time and cost for Excavation Works is due to the dependency of the means and
measures necessary to excavate and ensure the long term stability of the underground openings
created by the excavation process, taking into consideration everything contained in the ground
such as water, gas, and natural or man-made obstacles.
The time available to the Contractor for Excavation (including all necessary support) and Lining Works
shall be adjusted accordingly based on the variations of the physical and behavioural conditions of
the ground encountered within those stated in the GBR.
Any subsurface physical conditions that are outside the limits stated in the GBR shall be considered
Unforeseeable physical conditions, and accordingly the corresponding Sub-Clause 4.12
[Unforeseeable Physical Conditions] of the General Conditions of Contract shall apply.
The Contractor, when making any claim based on Unforeseeable subsurface physical conditions,
must be able to demonstrate that:
CONDITIONS
ii) the impact of any changes in scope, time, risk allocation or cost was caused by the difference
GENERAL
of the encountered subsurface physical conditions against the limits stated in the GBR.
Purely numerical differences in the physical conditions encountered do not provide sufficient
basis for an adjustment in compensation or Time for Completion (e.g. a permeability outside
the range specified in the GBR is not sufficient, unless the water seepage is higher than the
limit specified in the GBR).
3 GBR Content Recommendations
GUIDANCE
The subsurface conditions stated in the GBR shall be described, and later monitored, measured and
recorded, in terms of the means and measures required for the Excavation and Lining which ensures
the stability of the space created by the Excavation, and the effect on the surrounds including
adjacent property affected by the Excavation. The data should generally be allocated to the different
variations and combinations of homogeneous and heterogeneous zones along the length of the
different drives.
FORMS
Baseline conditions shall be described in terms of the:
i) anticipated methods of construction; and
ii) logistics determining access to the working faces and ensuring suitable working conditions
The parameters contained in the GBR shall focus on ground behaviour and/or ground response
rather than geologically oriented parameters. For example, rather than to establish permeability
parameters for the ground, seepage estimations and grouting requirements should be stated to
the maximum extent possible, using quantitative terms that can be measured and verified during
construction.
The GBR should use a contractual ground classification system that properly reflects the effort
(time and cost) of excavating and supporting the cavity in the expected ground conditions. For this
purpose, the definition of a ground classification system, together with the associated quantitative
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
The nature of the foreseeable subsurface physical conditions and the measures to control them,
will have significant impact on how to define the contractual ground classification system. The use
of geomechanical classification systems as a contractual ground classification system may have to
be integrated with the selected design and construction methodology in order to serve the purpose
of the GBR.
GUIDANCE
- support type;
- grouting methods and sequences;
- groundwater management methods and sequences;
- expected deformations for the ground type and the means to control the deformations;
- expected ranges of ground mass parameters and behaviours that could affect the
productivity and cost of the methods of construction for each type of Excavation and
potential situation during the drive (e.g. abrasivity, bit & cutter wear, drillability, cuttability,
groutability, squeezing, cutterhead jamming, and spalling);
- geotechnical “Hold Points” (i.e. locations where the procedure needs to be reviewed in
particular detail due to lack of information, high risk zones, or where further investigation or
analysis is required) with attention and alert values related to reference values established in
the Employer’s reference design and/or in the Contract Risk Management Plan; and
- required monitoring.
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
In addition to the above contractual ground classification system, the GBR should:
- present the general description of the geology, hydrogeology, and ground stress regime of
the Works;
- include a thorough discussion on anticipated ground water levels, seasonal and/or tidal
(if any) variations, estimated inflows, estimated pumping volumes and rates, anticipated
ground water chemistry and temperature;
- provide referenced baseline statements on:
i) acceptable construction impacts on adjacent property and facilities;
ii) parameters such as maximum/differential settlement, rate and tendency of deformation
etc., on affected property (e.g. structures and buried utilities);
iii) and other known natural geotechnical, hydrogeological, hydrological and/or man-made
sources of potential difficulty or hazard that could impact the construction process
such as:
- natural hazards:
- boulders, cavities and other obstructions, high or low top of bedrock, mixed face physical
conditions, geological contact zones, highly stressed or permeable physical conditions, gas,
coal seams or oil deposits, high temperatures and hot water inflows, intrusions, isolated
aquifers, seismic conditions, etc.;
- man-made hazards:
- other obstructions such as: identified or unidentified deep foundations and/or abandoned
piles, exploratory shafts, pits, wells, boreholes, buried utilities, buried debris, unexploded
ordnance, engineered and/or reclaimed ground, waste tips, contaminated ground and
ground water within the impact zone of the proposed Works alignment etc.;
- items of value and/or Interest according to governing laws; and
- any anticipated items of value or interest described under Sub-Clause 4.23 [Archaeological
and Geological Findings].
CONDITIONS
Baselines.
GENERAL
Design parameters may be included in the GBR, or alternatively, excluded from the GBR and included
in the Employer’s Requirements.
All subsurface physical conditions that are not explicitly included in the scope of the GBR are
GUIDANCE
considered as Unforeseeable physical conditions, see Sub-Clause 1.1.101 [Unforeseeable]
FORMS
The GDR should be issued to the tenderers as part of the Invitation to Tender to enable tenderers to
make their own interpretations and assessment of the risks associated with the referenced baseline
statements in the GBR. The GDR will collate all geotechnical and related data as described under
Sub-Clause 2.5 [Site Data and Items of Reference].
Should the GBR be silent on a particular physical or behavioural condition, or if the Contractor
requires additional basis for a design-related parameter or assumption, information in the GDR may
provide a supplemental basis for interpretation. Such interpretation by the Contractor shall have to be
agreed by the Engineer in order to become contractual. Reference to investigations and assessment
of foundation methods, structural integrity and status etc., which have been analysed and reported
elsewhere should be summarized in the GDR.
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
classes
5.1 Drive D01
5.1.1 Subsurface physical conditions
5.1.1.1 Ground types and relevant geotechnical properties
GUIDANCE
5.8 Shaft S2
5.9 …
5.10 Cross Passage CP1
5.11 …
Appendices to Part A: Project layout, geological map and longitudinal profile, ...
Appendices to Part B:
Appendix B1: Geotechnical-methodological longitudinal sections
Appendix B2: Excavation and support classes, typical cross sections and profiles
Appendix B3: Criteria for attribution of excavation and support class
CONDITIONS
BASELINES, COMPLETION SCHEDULE,
GENERAL
SCHEDULE OF CONTRACTOR’S KEY
EQUIPMENT
GUIDANCE
FORMS
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
Italics = measurement
Baseline Schedule EBT 01
WBS: Emerald Book Tunnel 1 Example Annual production time in WD 313
(EXAMPLE)
Working Phase: Excavation Interruptions to production time
Working time: Shift/WD (EXAMPLE) 2 Winter Break per year in WD 12
GUIDANCE
(EXAMPLE)
hours/shift (EXAMPLE) 9 Summer Break per year in WD 12
(EXAMPLE)
WD/week (EXAMPLE) 6 Other interruptions per year in WD 12
(EXAMPLE)
Work Category (EXAMPLE) Unitit Production rate, Estimation Calculus Valuation
(EXAMPLE) Unit per WD
(EXAMPLE) Quantity Time WD Measured Adjusted
(EXAMPLE) (EXAMPLE) Quantity time
FORMS
E
m
Total 1.82 1000.00 550.00
Total PL 550.00
Hindrances due to (EXAMPLES):
- Excavation of niches in Tunnel 1 (see piece 0.50 5.00 10.00
GBR drawing ZZ)
m 8.00 20.00 2.50
- Reduction of round length, instructed by
the Engineer
AM
- Geological overbreaks
Mucking of geological overbreak m3 500.00 50.00 0.10
Filling with Shotcrete m3 180.00 50.00 0.28
- Other hindrances (SPECIFY) [production rate] [quantity] [WD]
Interruptions for (EXAMPLES):
EX
CONDITIONS
Bold script: calculated
GENERAL
Italics = measurement
Baseline Schedule EBT 011
WBS: Emerald Book Tunnel 1 Example Annual production time in WD 365
(EXAMPLE)
Working Phase: Lining Interruptions to production time
Working time: Shift/WD (EXAMPLE) 3 Winter Break per year in WD 12
GUIDANCE
(EXAMPLE)
hours/shift (EXAMPLE) 8 Summer Break per year in WD 12
(EXAMPLE)
WD/week (EXAMPLE) 7 Other interruptions per year in WD 18
(EXAMPLE)
Work Category (EXAMPLE) Unitit Production rate, Estimation Calculus Valuation
(EXAMPLE) Unit per WD
(EXAMPLE) Quantity Time WD Measured Adjusted
(EXAMPLE) (EXAMPLE) Quantity time
FORMS
Tunnel Cross Section
Lining section 1 (see GBR drawing XX) m 12.00 500.00 41.67
E
m
Total 8.00 1000.00 125.00
Total PL 125.00
Hindrances due to (EXAMPLES):
- Lining of niches in Tunnel 1 (see GBR piece 0.25 5.00 20.00
drawing ZZ)
- Other hindrances (SPECIFY) [unit] [production rate] [quantity] [WD]
Interruptions for (EXAMPLES):
- Survey by Employer day 1.00 5.00 0
AM
GBR conditions
Total Interruptions and hindrances during production time 25.83
Interruptions to production time:
- Winter Break WD 12 0
- Summer Break WD 12 12
EX
- Other interruptions WD 18 9
Total Interruptions to production time (WD): 21.0
Total Interruptions (WD): 46.8
Total Working phase (WD): 171.8
Total Working phase on the critical path (Calendar days): 171.8
Duration lining time month 5.6
week 24.5
year 0.5
Difference between construction time for valuation purposes and planned time WD
week
Milestones (EXAMPLES): Start date, Lining Tunnel 1: 5/12/2021
Completion date, Lining Tunnel 1: 10/30/2021
93
© FIDIC & ITA 2019
Example Completion Schedule
Bold script = Requested by Employer WD = Working Days
Underlined = contractually agreed - initially proposed by Contractor
CONDITIONS
GENERAL
Completion Schedule
Baseline Predecessor
WBS No.
Milestone (EXAMPLE) Schedule
(EXAMPLE) Baseline
(EXAMPLE) Date WBS No. Date Activity [d] Float [d]
Schedule
(EXAMPLE) (EXAMPLE) (EXAMPLE) (EXAMPLE) (EXAMPLE)
(EXAMPLE)
GUIDANCE
E
1.01 Commencement Date 1/1/2019 - - - - -
PL
1.12 End Excavation EBT 01 EBT01 5/11/2021 1.11 EBT01
1.22 End Lining EBT01 EBT011 10/30/2021 1.21 EBT011 5/12/2021 172 -
1.31
Start Electromechanical
Equipment
AM - 7/11/2021 1.21 EBT011 5/12/2021 60 -
End Electromechanical
1.32 - 5/30/2022 1.22 EBT011 10/30/2021 211 -
Equipment
1.32 - 5/30/2022 1.31 - 7/11/2021 211 112*
End, Dismantling Site
1.41 - 7/29/2022 1.32 - 5/30/2022 60 -
EX
Installation
Completion Date proposed by Contractor
1.02 7/29/2022 1.41 - 7/29/2022 - -
and agreed
Completion Date requested
1.02 30/09/20221) 63**
by Employer 1)
1)
Superseded by agreed Completion Date
* Contractor’s Float
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
** Employer’s Float
94
© FIDIC & ITA 2019 Conditions of Contract for Underground Works
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
Equipment Item
Power Energy Departure
Caracteristic Arrival on site Availabilty REMARKS
source from site (EXAMPLE:
BoQ Item No. (Weight,
Year of Number Used for Asset Value
EXAMPLE Brand Model Diameter, electricity/
Type (EXAMPLE) Commissioning [kW] of items WBS Nos. (New/Used)
(EXAMPLE) (EXAMPLE) Bucket diesel/
(EXAMPLE) (EXAMPLE) (EXAMPLE) (EXAMPLE) [date] [weeks] [date] of Equipment)
capacity etc) gasoline/
(EXAMPLE) (EXAMPLE) (EXAMPLE) (EXAMPLE)
other (what)
X A
Example Schedule of Contractor’s Key Equipment
95
FORMS GUIDANCE GENERAL
CONDITIONS
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
GENERAL CONDITIONS
PREPARATION OF
TENDER DOCUMENTS
AND ANNEXES: TABLE
OF CONTENTS OF
THE GEOTECHNICAL
BASELINE REPORT,
EXAMPLE FORMS
OF SCHEDULE OF
BASELINES, COMPLETION
SCHEDULE, SCHEDULE
OF CONTRACTOR’S KEY
EQUIPMENT
FORMS OF LETTER OF
TENDER, LETTER OF
ACCEPTANCE, CONTRACT
AGREEMENT AND
DISPUTE ADJUDICATION/
AVOIDANCE AGREEMENT
In collaboration with
CONDITIONS
GENERAL
NAME OF CONTRACT:
TO:
We have examined the Particular Conditions Part A – Contract Data, the Completion Schedule,
the Schedule of Baselines, the Particular Conditions Part B – Special Provisions, the Geotechnical
GUIDANCE
Baseline Report, the General Conditions, the Employer’s Requirements, the other Schedules, the
Geotechnical Data Report, the Contract Risk Management Plan, the Contract Risk Register and
the Addenda Nos ________________________ for the above-named Contract and the words and
expressions used herein shall have the meanings assigned to them in the Conditions of Contract. We
have examined, understood and checked these documents and have ascertained that they contain
no errors or other defects. We accordingly offer to design, execute and complete the Works and
remedy any defects therein, in conformity with this Tender which includes all these documents and
FORMS
the enclosed Proposal, for the sum of
___________________________________________________________________________
[currency and amount in figures]
___________________________________________________________________________
[currency and amount in words]
We agree to abide by this Tender until ___________________ [date] and it shall remain binding upon
us and may be accepted at any time before that date.
If this offer is accepted, we will provide the specified Performance Security, commence the Works
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
as soon as is reasonably practicable after the Commencement Date, and complete the Works in
accordance with the above-named documents within the Time for Completion. We guarantee that
the Works will then conform with the Schedule of Performance Guarantees.
Unless and until a Contract Agreement is prepared and executed this Letter of Tender, together with
your written acceptance thereof, shall constitute a binding contract between us.
We understand that you are not bound to accept the lowest or any tender you may receive.
Address:___________________________________
Date: ________________________________
i
LETTER OF ACCEPTANCE •
CONDITIONS
GENERAL
NAME OF CONTRACT:______________________
CONTRACT NUMBER:_______________________
TO:_______________________________________
GUIDANCE
Date:______________________________________
Your Reference:_____________________________
Our Reference:_____________________________
FORMS
We thank you for your Tender dated _____________________________________ for the design,
execution and completion of the Works comprising the above-named Contract and remedying of
defects therein so that they are fit for the purposes defined in the Contract, all in conformity with the
terms and conditions contained in the Contract.
We have pleasure in accepting your Tender for the Accepted Contract Amount of:
__________________________________________
[currency and amount in figures]
__________________________________________
[currency and amount in words]
In consideration of you properly and truly performing the Contract, we agree to pay you the Accepted
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
Contract Amount or such other sums to which you may become entitled under the terms of the
Contract, at such times and as prescribed by the Contract.
We acknowledge that this Letter of Acceptance creates a binding Contract between us, and
we undertake to fulfil all our obligations and duties in accordance with the terms of this Contract.
Date:______________________________________
__________________________________________
•
Memoranda (if any) to be annexed [see Sub-Clause 1.1.50]
CONDITIONS
GENERAL
This Agreement made the_________________ day of____________________ __________________
Between____________ of__________________ (hereinafter called “the Employer”) of the one part,
and________________ of__________________ (hereinafter called “the Contractor”) of the other part
Whereas the Employer desires that the Works known as _______________________________ [name
GUIDANCE
and number of the Contract] should be executed by the Contractor, and has accepted a Tender by
the Contractor for the execution and completion of these Works and the remedying of any defects
therein,
1. In this Agreement words and expressions shall have the same meanings as are respectively
assigned to them in the Conditions of Contract hereinafter referred to.
FORMS
2. The following documents shall be deemed to form and be read and construed as part of this
Agreement:
(a) the Letter of Acceptance dated ________________;
(b) the Letter of Tender dated _________________;
(c) the Addenda Nos ___________________;
(d) the Particular Conditions Part A – Contract Data, the Completion Schedule and the
Schedule of Baselines;
(e) the Particular Conditions Part B – Special Provisions;
(f) the Geotechnical Baseline Report;
(g) the General Conditions;
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
4. The Employer hereby covenants to pay the Contractor, in consideration of the design,
execution and completion of the Works and the remedying of defects therein, the Contract
Price at the times and in the manner prescribed by the Contract.
In Witness whereof the parties hereto have caused this Agreement to be executed the day and year
first before written in accordance with their respective laws.
iii
SIGNED by:______________________________ SIGNED by:______________________________
CONDITIONS
for and on behalf of the Employer in the for and on behalf of the Contractor in the
GENERAL
presence of presence of
Witness:_________________________________ Witness:_________________________________
Name:___________________________________ Name:___________________________________
Address:_________________________________ Address:_________________________________
GUIDANCE
Date:____________________________________ Date:____________________________________
FORMS
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
CONDITIONS
GENERAL
[All italicised text and any text within square brackets (except Sub-Clause headings) in this form of
agreement is for use in preparing the form and should be deleted from the final product].
GUIDANCE
This Agreement made the ______day of ______ [month], _____ [year], between
FORMS
Name and contact details of the Contractor_________________________________________ (name)
________________________________________ (address)
______________________________________ (telephone)
_______________________(email / other contact details);
and
Whereas:
A. the Employer and the Contractor have entered (or intend to enter) into the Contract;
B. under the Contract, the “DAAB” or “Dispute Avoidance/Adjudication Board” means the
sole member or three members (as stated in the Contract Data of the Contract) so named in
the Contract, or appointed under Sub-Clause 21.1 [Constitution of the DAAB] or Sub-Clause
21.2 [Failure to Appoint DAAB Members] of the Conditions of Contract;
C. the Employer and the Contractor desire jointly to appoint the above-named DAAB Member
to act on the DAAB as:
(a) the sole member of the DAAB, and where this is the case, all references to the “Other
Members” do not apply; or
(b) one of three members / chairperson [delete the one which is not applicable] of the
DAAB and, where this is the case, the other two persons are:
v
The Employer, Contractor and DAAB Member jointly agree as follows:
CONDITIONS
GENERAL
Second Edition 2017 published by FIDIC (“GCs”), as amended and/or added to by the
following provisions.
3. The DAAB Member shall be paid in accordance with Clause 9 of the GCs. The currency of
FORMS
In respect of Sub-Clauses 9.1 and 9.2 of the GCs, the amounts of the DAAB Member’s
monthly fee and daily fee shall be:
monthly fee___________________ per month, and
daily fee of____________________ per day
(or as otherwise set under Sub-Clause 9.3 of the GCs).
4. In consideration of the above fees, and other payments to be made to the DAAB Member
in accordance with the GCs, the DAAB Member undertakes to act as DAAB Member in
accordance with the terms of this DAAB Agreement.
5. The Employer and the Contractor shall be jointly and severally liable for the DAAB Member’s
© FIDIC 2019 - DISCUSSION PAPER ONLY - NOT FOR CONTRACT USE
fees and other payments to be made to the DAAB Member in accordance with the GCs.
6. This DAAB Agreement shall be governed by the law of _____________ (if not stated, the law
that governs the Contract under Sub-Clause 1.4 of the Conditions of Contract).