Primavera

The document outlines the Enterprise Project Structure (EPS) and Organization Breakdown Structure (OBS) for managing projects within an organization, detailing the hierarchical organization of projects and task distribution. It includes various project activities, their durations, and relationships, such as Finish to Start and Start to Start, along with project calendars. Additionally, it provides examples of project activities and their dependencies, emphasizing the importance of structured project management.

Uploaded by

Fatma Helal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
4 views14 pages

Primavera

The document outlines the Enterprise Project Structure (EPS) and Organization Breakdown Structure (OBS) for managing projects within an organization, detailing the hierarchical organization of projects and task distribution. It includes various project activities, their durations, and relationships, such as Finish to Start and Start to Start, along with project calendars. Additionally, it provides examples of project activities and their dependencies, emphasizing the importance of structured project management.

Uploaded by

Fatma Helal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 14

‫)‪(Enterprise Project Structure‬‬

‫الهيكل التفكيكي لمشروعات الشركه‬


‫هيكل مشروعات المؤسسه هو التنظيم الهرمى لكل المشروعات الموجوده بالمؤسسه حيث ان‬
‫البرنامج مصمم ليتعامل مع الرؤيه الشامله للمؤسسه ‪.‬‬
‫‪Enterprise → Enterprise Project Structure → Add.‬‬

‫‪Eng. Ahmed Hamouda / Primavera For Project Management‬‬ ‫‪Page 1‬‬


Examples:

Eng. Ahmed Hamouda / Primavera For Project Management Page 2


Eng. Ahmed Hamouda / Primavera For Project Management Page 3
‫)‪(Organization Breakdown Structure‬‬
‫الهيكل التفكيكي و التنظيمي لوظائف الشركه‬
‫هو عباره عن عمليه توزيع المهام على مشروعات الشركه ‪ EPS‬و يكون موازيا لها لتوزيع‬
‫المهام على الهيئات المختلفه لجميع قطاعات الشركه ‪.‬‬
‫‪Enterprise → OBS → Add.‬‬

‫‪Eng. Ahmed Hamouda / Primavera For Project Management‬‬ ‫‪Page 4‬‬


Examples:

Eng. Ahmed Hamouda / Primavera For Project Management Page 5


Eng. Ahmed Hamouda / Primavera For Project Management Page 6
Networks

Examples:

Activity Activity Code Duration (day)


Preparation for Project Design A 15
Preparation for Project Bidding Documents B 20
Bidding For Project C 30
Construction D 320

Activity Successor ( FS ) Lag


A B 0
B C 0
C D 0
D - -

Calendar : Project Start → 1-6-2022


Non Work → ( Friday)

Eng. Ahmed Hamouda / Primavera For Project Management Page 7


Activity Activity Code Duration (day)
Excavation A 18
Back Filling B 6
Insulation C 9
Shuttering P.C Footing D 4
placing P.C Footing E 2
De Shuttering P.C Footing G 2
Shuttering R.C Footing F 18
Steel Fixing R.C Footing M 22
Placing R.C Footing H 6
De Shuttering R.C Footing N 4

Activity Successor ( FS ) Lag


A D 0
B - -
C B 0
D E 0
E G 2
G F 0
F M 0
M H 0
H N 3
N C 0

Calendar : Project Start → 1-6-2022

Non Work → ( Friday + 10/6 , 15/7 )

Eng. Ahmed Hamouda / Primavera For Project Management Page 8


Activity Activity Code Duration (day)
Shuttering Columns A 9
Steel Fixing Columns B 6
placing Columns C 4
De Shuttering Columns D 2
Shuttering Slab E 12
Steel Fixing Slab G 8
Placing Slab F 4
De Shuttering Slab M 2

Activity Successor ( FS ) Lag


A B 0
B C 0
C D 2
D E 0
E G 0
G F 0
F M 7
M - -

Calendar: Project Start → 20- 6-2022


Non Work → (Saturday + 15/7)

Eng. Ahmed Hamouda / Primavera For Project Management Page 9


Activity Activity Code Duration (day)
Brick Works A 24
Preliminary Carpentry Works B 9
Preliminary Electrical Works C 6
Preliminary Sanitary Works D 7
Plastering E 20
Flooring G 16
Painting F 10
Finishing of Carpentry Works M 3
Finishing of Electrical Works H 3
Finishing of Sanitary Works N 2
Final Finishing J 1

Activity Successor ( FS ) Lag


A B,C,D 0
B E 0
C E 0
D E 0
E G 0
G F 0
F M,H,N 0
M J 0
H J 0
N J 0
J - -
Calendar: Project Start → 10 – 6 – 2022

Non Work → (Friday& Saturday + 25/6, 10/7, 15/8)

Eng. Ahmed Hamouda / Primavera For Project Management Page 10


Relation Ships – Time Lag

• Finish to Start (FS):

. ‫النشاط التالى ال يبدأ إال بعد انتهاء النشاط الحالى‬

• Start to Start (SS):

. ‫النشاط التالى ال يبدأ إال بعد ابتداء النشاط الحالى‬

Eng. Ahmed Hamouda / Primavera For Project Management Page 11


‫‪• Finish to Finish (FF):‬‬

‫النشاط التالى ال ينتهى إال بعد انتهاء النشاط الحالى ‪.‬‬

‫‪• Start to Finish (SF):‬‬

‫النشاط التالى ال ينتهى إال بعد ابتداء النشاط الحالى ‪.‬‬

‫‪Eng. Ahmed Hamouda / Primavera For Project Management‬‬ ‫‪Page 12‬‬


Activity Original Successors
Activity Name Lag
ID Duration ( FS )
A010 Technical Work Beginning 0 A020 0
A020 Design Building 27 A030&A040 0
A030 Review and Approve Designs 23 A060 0
A040 Prepare Bidding Documents 18 A050 0
A050 Review and Approve Bidding Documents 23 A060 0
A060 Bidding the Project 45 A070 0
A070 Begin Building Construction 0 A080 0
A080 Site Preparation 32 A090 0
A090 Excavation 18 A100&A110 0
A100 Install Under Ground Water Lines 9 A120 0
A110 Install Under Ground Electric Conduit 9 A120 0
A120 Form Concrete Footings 14 A130 0
A130 Pour Concrete Footings 5 A140&A150 0
A140 Concrete Foundation Walls 18 A150 0
A150 Footing Insulation 5 A160 0
A160 Backfill and Compact 3 A170&A180 0
A170 Begin Structural Phase 0 - 0
A180 Form Concrete Columns 14 A190 0
A190 Pour Concrete Columns 5 A200&A210 2&0
A200 Floor Decking 9 A210 0
A210 Form Concrete Roof 18 A220 0
A220 Pour Concrete Roof 5 A230 7
A230 Concrete Basement Slab 18 A240&A250&A300 0
A240 Close-in Phase Begins 0 - -
A250 Brick Walls 45 A260 0
A260 Electrical Works 14 A270&A310 0
A270 Plastering Works 63 A280 0
A280 Erect Door and Window Frames 9 A290 0
A290 Erect Doors and Windows 32 A320&A340 0
A300 Insulation and Finish Roofing. 18 - 0
A310 Plumbing Works 23 A330 0
A320 Finishes Phase Begins 0 - -
A330 Flooring Works 27 A360 3
A340 Painting Building 36 A350&A360&A370 0
A350 Install Lighting Fixtures 5 A380 0
A360 Install Plumbing Fixtures 5 A380 0
A370 Install Floor and Carpeting 9 A390 0
A380 Air Condition 9 A410 0
A390 Finish Carpentry 5 A400 0
A400 Final Finishing 2 A410& B020 0
A410 Building Completed 0 - -
B010 Technical Work Beginning 0 B020 0
B020 Design Building 27 B030&B040 0

Eng. Ahmed Hamouda / Primavera For Project Management Page 13


B030 Review and Approve Designs 23 B060 0
B040 Prepare Bidding Documents 18 B050 0
B050 Review and Approve Bidding Documents 23 B060 0
B060 Bidding the Project 45 B070 0
B070 Begin Building Construction 0 B080 0
B080 Site Preparation 32 B090 0
B090 Excavation 18 B100&B110 0
B100 Install Under Ground Water Lines 9 B120 0
B110 Install Under Ground Electric Conduit 9 B120 0
B120 Form Concrete Footings 14 B130 0
B130 Pour Concrete Footings 5 B140&B150 0
B140 Concrete Foundation Walls 18 B150 0
B150 Footing Insulation 5 B160 0
B160 Backfill and Compact 3 B170&B180 0
B170 Begin Structural Phase 0 - 0
B180 Form Concrete Columns 14 B190 0
B190 Pour Concrete Columns 5 B200&B210 2&0
B200 Floor Decking 9 B210 0
B210 Form Concrete Roof 18 B220 0
B220 Pour Concrete Roof 5 B230 7
B230 Concrete Basement Slab 18 B240&B250&B300 0
B240 Close-in Phase Begins 0 - -
B250 Brick Walls 45 B260 0
B260 Electrical Works 14 B270&B310 0
B270 Plastering Works 63 B280 0
B280 Erect Door and Window Frames 9 B290 0
B290 Erect Doors and Windows 32 B320&B340 0
B300 Insulation and Finish Roofing. 18 - 0
B310 Plumbing Works 23 B330 0
B320 Finishes Phase Begins 0 - -
B330 Flooring Works 27 B360 3
B340 Painting Building 36 B350&B360&B370 0
B350 Install Lighting Fixtures 5 B380 0
B360 Install Plumbing Fixtures 5 B380 0
B370 Install Floor and Carpeting 9 B390 0
B380 Air Condition 9 B410 0
B390 Finish Carpentry 5 B400 0
B400 Final Finishing 2 B410 0
B410 Building Completed 0 - -
Calendar :

Non Work → (Friday + 25/1)

Project Start → 1-1-2022

Eng. Ahmed Hamouda / Primavera For Project Management Page 14