302
302
Materials
 1. Finance hours/architectural project
 2. Arbitration
 3. Compilation of tender documents
 4. Specification writing
 5. Condition of contracts (summary standard form)
 6. Contract administration
 7. Building contract administration by Akpabio
 8. Articles of agreement
 9. Conditions of engagement
 10. Standard form building contract
 11. Auf technology
 12. Easement and dilapidation
 13. Project management
 14. Financing for housing and architectural project
 15. Contract administration
 16. Compilation of tender document
 17. Tendering process
Brief
It is statement of intention, what the client want or need,
determine what the client want and extract it needs, relate it
needs and wants to it resource and constraints. Use your
professional knowledge to advice him to determine the best
solution. Once you determine that this is doable, start the design
project and get the approval.
Tendering
Liaise with other consultant in step 4 (stage equal to realization of
the project (construct). These other consultant include (i)
structural Engr, Q.S, mech. Engr. Elect. Engr, facility manager:-
maintain the smooth running of the facility, specialty (centre
A/C/heating)
Modern method:-
(1) formal sectors (2) informal sectors
Cost control: The architect has major role from the design to
construction stage, in order to realizes a complete holistic client
object towards a successful project delivery
Arbitration
Dispute in construction industry is inevitable
An Arbitrator
In construction industry arbitrator is one who has skill in
construction and addition to knowledge in law. They are not
independent exact but they are judges of law as well as facts.
However he will stand disqualify if:
   (1) he has personal interest or
   (2) Bias.
Appointment of an arbitrator
How the architect is appointed: Appointment is in writing.
  (1) NIA ask both parties to supply brief detail of the dispute
       and complete a form.
  (2)   The complete forms are return to the institute and the
        president approaches a competent arch.
The award
  - The judgments of an arbitrator in an arbitral proceeding is
    called an award. After the award the proceeding is
    terminated.
  - Time: The party fixed the time, the umpire makes the award
    within 3 months.
Question (1) What are the procedure for handling over of site to
the contractor.
Answer:
Handling over to contractor
  (1) Agree of the earliest date with the client
  (2) Notify the contractor, client and all other consultant of the
      date and time
  (3) Remind the consultant to prepare set of document to be
      issued to the contractor on that date
  (4) Inclusive of these procedure are following routine
Routine 1:
  (1) General introduction
  (2) Attendance and compilation of all management list
  (3) Introduction of person in charge (contractor/consult/client)
  (4) Submission of two copies of contract drawings and bills
  (5) Issuance of a copy of planning authority drawings and
      approval letter for site reference.
Routine 2:-
  (1) Tour the site to locate the beacon, temporary site office,
      material stock piling, and impediment to setting out right
      of adjourning owners (easement)
Routine 3:
  (1) Outline chain of communication
  (2) Agree on lab for material analysis (concrete, soil, strength,
      Q-Test)
  (3) Source of power and water to site
  (4) periodic of mobilization
  (5) Fix a date for commencement
  (6) Calculate date of completion
Routine 4:-
  (1) Procuring of insurance
  (2) write architect for setting out before excavation
  (3) Preparing programs of works
  (4) Don’t cast any blending until Engr. Approval
  (5) To buy any water until Arc. Approves sample
Question 1b
Procedures for processing of site by the employer or client.
Answer
  (1)   Fix a date
  (2)   Test plumbing works and installation
  (3)   Pre handing over inspection
  (4)   Inclusive of the above are they following:-
Question 3:
Give five reasons for variation and the effects
Answer
  (1) Unavailability of specific material
  (2) Employer instruction to change
  (3) Delay the completion period
  (4) Fluctuation
  (5) Architect instruction
   The effect is that it always necessitates the upward review of
     the contract sum.
Question 4:
Discuss the relationship among          the   Architect,   employer,
contractor and the clerk of works
Answer
The Architect: is the head of the team who also represent the
intent of the employer the right of the employer to appoint the
clerk of work and the contractor is to facilitate his performance
while the clerk of works should be under the directives of the
architect. The clerk of work cannot give instruction. All the
instruction to be confirm in writing by the architect.
Question 5
Write short note on the following
  (1) Cost-in-Use
  (2) Replacement east
  (3) Cost overrun
  (4) Contract document
  (5) Total contract sun
  (6) Most ferrous project
  (7) B.O. T (Build Operate Transfer)
  (8) R.O. & T (Rent Operate & Transfer)
  (9) As built drawings
  (10) Maintenance manual
Answer
Contract document: includes the following: all workings drawings,
article of agreement, condition of contract, bill of quantity
specification document
Question 6
Is an Architect a part of the contract agreement? Explain
Answer
No! This is a form of agreement to be filled and signed by
employer and contract with their witness
Question 7:-
What is the role of Architect in the execution of project?
Answer
  (1) Head of building team
  (2)   He bridge gap between the employer and contractor
  (3)   He represent the interest of the employer
  (4)   All instruction are given and confirm by him
  (5)   He supervises the project to ensure that works are in line
        with the approval plan.
Question 8
Mention reasons for the determination of contract by the
contractor
Answer
Determination = termination
(1) if the client is not honoring the certification of payment as at
    when due.
(2) Non-payment of Architect certificate within the agreed period
    and continue refusal 7 days after the contractor written
    request.
(3) Interfering or obstruction of any certificate by the employer.
(4) Suspending whole or part of the work beyond the agree
    period due the following reasons:
(1) Force majeure
(2) Lost or damage
(3) Civil or unrest
(4) Delay in receiving information from the Architect
Question
What cumulating effect could a low completion period at the time
of tender have eventually on the owner, contractor, consultant,
what provision does condition of contract make to give relief to
these parties
Answer
The owner/client
  (1) He has a claim to liquidated ascertained damages
  (2)   He gets shoddy jobs (rubbish job)
Question
Relief for the consultant:
Question:
What is a program of works? What are the various types?
Answer
It is a chart used for planning, monitoring and evaluation of
contractors works, using a bar chart prepare by the contractor.
Parts:
  (1) Items of works: personnel and labor
  (2) Period of work: time and days
Question 2b
Explain the critical part analysis with respect to problem
resolution in contract.
Answer
Critical part analysis is a method of identifying a relationship
between task, establishing the direction, preparing schedule and
determining the C.P this helps to analysis C.P and how to resolve
them for effective progress of the contract. It accommodate the
limitation of a bar chart by showing task interrelationship and
highlight these issue that could create problems of delay.
Question
Explain the following as relate to the Architect duties
  (a) Normal services
  (b) Architect liability
Answer
Normal services: Stage 1 to 5
Stage 3: phase 5
Phase 5: tendering and award
Stage 4: phase
Phase 6: construction
Stage 5: phase 7
Phase 7: post construction.
Answer b part
Architect liability: it is the overall responsibility of the Architect to
administer the contract in the following.
  (1)  Handling up site contractor in commencement of work
  (2)  Approving contractors programs of works
  (3)  Checking and confirmation of setting out
  (4)  Coordination of consultant and site activities
  (5)  Site inspection at least once a month
  (6)  Holding site meeting
  (7)  Issuing interim payment certificate
  (8)  Submission to employee of quarterly progress report
  (9)  Given instruction on matters which he is empowered by
       the contract
  (10) Handling over of completed or practical complete project
       to the employee
  (11) Final inspection/completion certificate/ final account/ final
       payment certificate
Question 5
Explain the following
  (1) Professional indemnity
  (2) Negligence
  (3) Tort
  (4) Agency
Answer
  (1) Professional indemnity: it is the professional insurance
      as to relate to building contract with regards damage or
      loses.
  (2) Negligence: leaving everything to chance which leads to
      shoddy job cost overrun and delay
  (3) Tort: it is a legal process that comes from a contract
      agreement as relate to claiming damages.
  (4) Agency: it implys the relationship which comes into being
      when one party (the agent) is employ by another (the
      principal) to enter into contractual objection with a third
       party on the principal behalf e.g, the Architect relationship
       between client and contract
Question 6
Your client as approach you to raise the funds from the capital
market. What are the options open to you.
Answer
Mortgage banks, commercial banks, merchant bank and special
banks
Question
How do you convince the financier on accelerated completion at a
higher cost?
Answer
  (1) Viability of the project
  (2) Feasibility study
  (3) Accelerated programs of works.
Question
What is arbitration: it is a form of conflict resolution which by it
format is expected to resolve conflict fast between two or more
person and yet bring about reconciliation so that rancor and strive
are eliminated, by referring than to third party for a binding
decision/award.
Question
 What are provision for arbitration in the standard condition of
contract
Answer
  (1)   Dispute to be settle by arbitration
  (2)   NIA president to appoint the arbitrator
  (3)   Award of arbitration in final
  (4)   Law of arbitration is law of Nigeria
Question 3:
Explain the following.
  (1) Variation
  (2) Liquidated and ascertain damages
  (3) Architect certificate
  (4) Extension of time
  (5) Find certificate
  (6) Attendance
  (7) Contract document
Answer
  (1) Variation: is the alteration/modification of the design,
      quality and quantity of works as shown upon in the
      contract drawings, as describe by or referred to in the
      contract bills.
  (2) Liquidated and ascertained damages: this is the
      agree amount the contractor will pay for every week of
      default incompletion, as fixed in the appendix, an
      employer may deduct the calculated sum from the money
      due or is to become due to the contractor.
  (3) Architect certificate: is a document issued by the
      Architect at different stage of the construction work,
      certifying work done and valuation which will include
      (1) Interim payment certificate
      (2) Certificate of making good defect
      (3) Practical completion certificate
      (4) Final certificate
  (4)    Extending of time: it is a process for requesting off
        addition time by contractor due to the delay of program of
        works as a result of the following
        (1) Force – majeure
        (2) Inclement weather not expected by the seen
        (3) Civil commotion
        (4) Architect instruction
        (5) Delayed in issuance of detail
        (6) Delays by nominated by sub-contractor
        (7) Delay in payment of certificate by employer
Arbitration
Dispute arise when one party fails to do the work properly
Three method of dispute resolution
  (1) Arbitration
  (2) Litigation
  (3) Conciliation
  (4) Gangstarism
Arbitration:   is a fun of conflict resolution which by this format
               is expected to resolve conflict fast between two or
               more person and yet bring about reconciliation so
               that rancor and strive are eliminated by referring
               them to a third party for binding decision or
               award.
Feature of Arbitration:
              (1) There must be a real dispute either to litigate
                   or arbitration (to war-war or JAW-JAW)
              (2) There must be an argument between the two
                   parties to refer the dispute to specially
                   nominated person for hearing and settlement
              (3) It is an alternative to litigation
An arbitrator:
              In construction industry arbitrator is someone who
              has skills in construction and having knowledge in
              law or undergone training as a lay arbitrator.
              Knowledge in law of contract, tort event of civil
              proceeding.
Advantage of Arbitration
  (1) Dispute can be settle quicker than in court action
  (2) less expensive than in court action
  (3) Time and place can be arrange for convince to suit all
      parties involve
  (4) Less expensive than litigation
  (5) The award must be property executed
  (6) It has simply rules
Disadvantage
  (1)   The arbitrator is paid the judge is not
  (2)   Venue is hire court is not
  (3)   Arbitration can be very lengthily
Note
Clause 35 of contract agreement provide for dispute to the
referred to arbitration
Sep 2009
Question 1
Mention the scope of service of an Architect as enshrine in the
condition of engagement
Answer
Scope of the service of the Architect include
  (1) Normal services
  (2) Additional services
  (3) Partial services
B4
Normal service: include stages 1 & 2 & 3, but according to
condition of engagement sept 2011 is now stage 1 to 5.
Design stage 1: phase 1 & phase 2
Phase 1: commission and issuance of letter of commission
Phase 2: concept design
Design stage 2: phase 3 & phase 4
Phase 3: coordinated detail design
Phase 4: all construction document
Stage 3: phase 5
Phase 5: tendering & award
Stage 4: phase 6
Phase 6: construction
Stage 5: phase 7
Phase 7: post construction
Additional services:
  (1) Feasibility study
  (2) Sites and buildings
  (3) Special drawings and models
  (4) Development plans
  (5) Special meetings
  (6) Redesign
  (7) Interior design
  (8) Furniture and fittings
  (9) Litigation and arbitration
(Stage 1 to 5)
Question 1b
List the various methods of arriving at the fee payable to the
consulting architect.
Answer
  (1) Professional fee base on government approve scale of
      fees for consultant in C.I (conditional of engagement and
      remuneration for professional architect services sept
      2011)
  (2) time rates or man-month-rate base on years of experience
  (3) Negotiations fee
Question 1c
Old fee
Answer
Stage 1:
Assumption
12 years = N92,400/month
20 days = 1month
92,400    = N4,620 per days
20 days
40 days for stage 1 = 40
X 4,620 = N184,800
Stage 2
N4,620 per day
60 days to do stage 2
60 x N4,620 = N277,200
Therefore my rate for stage 1 & 2 equal
184,800 stage 1
277,200 stage 2
Question 2a
Short note on the following
  (1) Prime consultant
  (2) Project management
  (3) Multi-farrous project
Answer
  (1) Prime consultant: is the leader of the consultants on a
      project, he concise and initiate projects, produce the
      guiding design and sketch coordinate and in some cases
      manages the project.
  (2)   Project manager: coordinate the logistic of the project
        and activities of other consultants as they relate to the
        clients. He does not take responsibility for the
        performance of any other consultants. He is employed on
        complex or large project to eliminate any unnecessary
        financing burden on the client.
  (3)   Multi-farrous: they are project which has more than one
        prime-consultant with the following characteristics
  (1)   Diversity of use
  (2)   Substantial infrastructures
Answer
2b What are the features of multi-farrous project
  (1) More than 1 prime consultant
  (2) Diversity of use
  (3) Substantial infrastructure
Answer
2c 5 examples of multifarious project
  (1) Teaching/general hospital complex
  (2) Campus for secondary/university institution
  (3) Major housing estate (not) less than 5 hectare
  (4) Industrial complex
  (5) Substantial and power distribution
Answer to d qstn
  (1) On a complex or large project
  (2) On a multifarious project
2e
Answer
Additional services: are services beyond the normal services and
contract period. They includes the following
   (1) Feasibility
  (2)   Sites and buildings
  (3)   Special drawings and model
  (4)   Development plans
  (5)   Special meetings
  (6)   Redesign
  (7)   Interior design
  (8)   Furniture and fittings
  (9)   Litigation and arbitration
Question 3a
What are Architect instructions
Answer
Is a written statement by the Architect to the contractors as
stipulate to the contract which is binding on the contractor and
must comply within 5 working days
Question 3A
Discuss procedure for insuring the instructions
Answer
Procedure include the following
i.   It must be in writing
ii.  It must be issue by Architect
iii. Contractor must comply within 5 working days
iv. Verbal instructions needs to be regularize within 5 working
days
v.   Additional instruction from the client.
Question 3b
Write brief note on the following
i.   Determination of contract
ii.  Force-majour
iii. Arbitration
iv. Practical completion
v.   Deflect liability period
vi.   Reimbursable
Answer
1.   Determination of contracts: all parties of building contract
have right to end the contract if it is breach and damage, also
which normal remedy does not work. Determination is
termination of contract which can arise due to the following
(a) Client not honouring certificate of payment as at when due
(b) Non-payment of Architect certificate within agree period and
continuous refusal 7 days after contract written request.
(c) Interference or obstruction of any certificate by the employer
Arc            =    40%
Mech. Engr.         =   10%
Elect. Engr         =   10%
Str. Engr      =    15%
Q.5            =    15%
Geo-Tech. Engr      =   5
Building       =    5
                        100% of (1% of Provisional sum in
contract bill)
 Question
March 2011
You are coming for an industrial part in Lagos, the complex
consists of 8 prototypes warehouse, with sum internal office value
N80million each. The cost of sub-structure of each is of 20% of
the cost. In addition there is cost of external work estimated to be
N40million
1.   Calculate your percent fee as the prime contractor
2.   Calculate your post contract fee when has reach 50% stage
Steps: ANALYSIS
Clause 23: 1.1 for any body work the architect is = prime
consultant
Step 2
Applying sliding schedule table
Cost of project Arc % of payable amount
Up to 5m        4.75%    237,500
      10m       4.5%450,00
      15m            4.25%     637,000
      45m            4.0%1,800.000
      75m       3.5 2,625,000
     150m            3.0 4,500.000
     200m            2.5 5,000,000
Balance        180m            1.75%   13,150,000
                18,400,000
Question 2
You are just been commission to up with a proposal of a 2
bedroom flat (house) on a plot in a choose area in Ilorin, using
(time rate) compute fees for stages 1 & 2
Answer
Assuming project cost = N80,000,000 E.T.C
Stage (1) = 4.75% of 80million
Phase (1) = 15% (4.75% of E.T.C)
                = 15% of 3,800.000
Phase (2) = 20% of 3.800.000
Question 2
What are the essential part of project management which the
Architect should plan for so as to have successful project. are the
other professionals, the architect has to relate in the process.
Question 3
Explains sequentially the step you will take to screen each of the
following contractor’s claims
   (1) Extension of time/completion period
   (2) Fluctuation clam for material
Qstn
Six storey building on a large expanse of land in Abuja, at its
recent board meeting approval to extend at existing building to
accommodate the conference hall. Other structure approved.
   (1) Construction of 10 bedroom guest house: execution unit
   (2) 8 Nos 4 bedroom senior staff quarters
   (3) 2 blocks of 6 No 2 bedroom flat for junior staff.
Answer
Analysis
Office extension           N10 mil
Ten bedroom guest house    N20 mil
8 Nos 4 bedrm          N10 mil
Office Block
E.t.c           N10 mil
Therefore: fee for stage 1 & 2 =    4.75% of E.t.c
                               =    4.75% of 10 mil
                               =    N475,000
1,068,750
2,137,500
1,662,500
 475,000
 950,000
4,631,250.00
Note
Hourly rate
  (1) No the cadal of staff to deploy (1) principal of the firm to
      principal Architect
  (2) Project Architect is an associate Architect
  (3) Drivers
  (4) Secretary
      Principal
Question
State the steps you will take from the point of requesting for
tenders to the point of recommending a contractor to the client.
Answer
  (1) Invite selected contractor to bid
  (2) Purchase of tender forms
  (3) Return tender/making submission
  (4) Arrange a date for opening of bid/tenders
  (5)   Tender analysis report which will take in to cognizes the
        amount bided and time stipulated
  (6)   Recommendation (best 3 in descending order)
Question 2
Provide brief answers to the following question
  (1) Define advance payment bond
  (2) What are working drawings
  (3) A lump sum contract
Answer
   (1) A.P.B = it is a document obtained from the bank/financial
        institution as a guarantee, which transfer all liability/risk
        that may arise from the contractors default.
   (2) What are working drawings: Working drawings are
        contract document that show graphically all works that
        will be carryout or executed in project. It also forms part
        of tender document.
   (3) Lump sum contract: it is a contractor that a fixed figure
        and that does not entertain room for fluctuation.
Question
(4) What is the name given to the statement or drawing which
modify the base contract document, after the letter has be issued
to the bidders but prior to the taken of the bids.
Answer: Addendum
Answer
Insurance is the equitable transfer of a loose from one entity to
another in exchange for payment. It is a form of risk
management.
Type of Insurance:
  (1) All risks insurance: covers all the parties of the contracts
  (2) Professional indemnity insurance; it is a type of insurance
      provided by the consultant, it serve as hedge against
      professional negligent.
Answer
  (1) Partial service
  (2) Normal service
  (3) Resident service
  (4) Additional service
Answer
It is an agree amount the contractor will pay for every week of
default as fix in the appendix
Question 9
What are general conditions?
Answer
Clause that spell out the condition under which the project will be
administered or governed.
Question 10
What is the term given to the diff between the price listed and the
actual priced paid
Answer
Profit margin
Sept 2010
Question
To illustrate your understand write concise shift on the following
  (1) Project tender document
  (2) Variations
  (3) Prime cost (prime cost suns)
  (4) Provisional sum
  (5) Architect instruction
  (6) Prime consultant
  (7) Project manager
  (8) Resident supervision of project
  (9) Architect certificate
  (10) Project clerk of works
The land is shrinking the people are necessary and more water on
the earth surface conflict. In our designs we need to think of to
make the national resources remain in them state.
302
March 2012
Question
You had the commission to reneeler archutator service for the
design of a 10 stiny office building of a gross area of 12,000m 2.
You have now completed this tender doc and your client has
instructed to proceed to tendency process by inxity tender from 6
selected tender contract
Question 2
Short note on the following
  (1) Architect instruction
  (2) Extension of time
  (3) Fluctuation
  (4) Trade preambles
  (5) Contingencies
  (6) Royalties and pertent right
  (7) Sustainability
  (8) Green architecture
  (9) Clerk of work
  (10) Insurances
  (11) Attendance
Answer
  1. Architect instruction: it is a written statement issue by the
     Arc. To the contractor as it relate to the contract which is
     binding on contractor and he most comply within 5 working
     days.
  2. Extension of time: it is a process of requesting for
     additional of time by contractor due to delay of progress of
     work as a result of or more of the following reasons.
(8) negotiated fee: one of the method vrol at aming at at fee due
to the consultant which is usually muc then he sliding scale
Tender document
Tender: is a formal offer to supply good and provide the
statement of price, you or a company will charge
(T.D): are due which are reluctant for tender processes which
include
(1) Drawing and specification
(2) B.O.Q
(3) Schedule of rates
(4) Invitation to tender
(5) Instruction to the person tendency
(6) Information about person tendency
(7) Firm of tender
Answer
Cost-in-use: it is the cost incurred that will make the building for
use: eg electricity, A/C etc
Year
Questions
Messr: ABC Plc commission an Architectural firm for a proposed
multi-story building, the Architectural firm has just the working
drug in his with the normal service dictates, when the unfir
onmetur Architecutral firm with the same brief. These other fun is
the winner of a competition ABC Plc as organize. Analysis the
situation crotial and advise the first architecture fin on the live of
retun to take
Answer
He should be advise to make his clans sure he commission/ fund
engage. He should has letter of communion to make his clams or
inform the president of N.I.A.
Question 3
Write short note on the following
  (1) Total contract sum
  (2) Repetitive project
  (3) Construction cost
  (4) E.t.c
  (5) Reimbursables expenses
  (6) Additional services
  (7) Time charges
  (8) Negotiated fee
  (9) Sliding scale
  (10) Force-major
  (11) Tender document
Answer
  (1) Total Contract Sum (T.C.S): is the actual sun expended on
      the project by the clients
  (2)     Repetitive: shall mean unit(s) of the say design types and
          specification to construction on the same site or other
          sites
  (3)     Construction cost: value of measured work or value of
          builders work
Question
Differentiate among the following set of architecture technology
   (1) renovation
   (2) rehabilitation
   (3) reconstruction
   (4) restoration
   (5) refurbishment
  (6)   schedule of condition
  (7)   schedule of dilapidation
  (8)   schedule of repairs
Answer
(1) Renovate: Makes something like new again, to bring
something back to it formal better state by means of repairs,
redecoration or remodeling.
(2) Rehabilitate: restore a place to a good condition, to restore a
building or part of a town to it formal condition
(3) Restoration: it is the return something to previous condition.
To bring something back to an earlier and better condition
(4) Reconstruct: to put something back together from it
component part, pieces or remains.
(5) Refurbishment: cleaning and decorating of a building,
making it more attractive or better equipped.
(6) Schedule of condition: it is a list of the state or condition of
a building before occupation
(7) Schedule of dilapidation: it is a detail list of faulty or
defective element in a building with remedy and cost implication
(8) Schedule of repairs: it is a detail list of defective element.
Sept 2007
Question
A typical Arc. Interim cert. his number of information on a project,
enumerate 5 of such information and explain their relevance to
the project of construction work.
Answer
Below are some information on the Architect interim certificate
(1)     Value of work completed to date
(2)     Material on site
(3)     Advances, mobilization and amount spent so far
(4)     Variation
(5)        Claims      (reimbursable):   transport,   accommodation,
logistic, office         renters etc
(6) Retentions
Explaining or note
The value of work explain the level of work completed to date
(1) Material on site shows the details of material used and
material on good for the project of work
Advances: Show how mobilization had been paid aid how much
spent so far
Variation: Details of changes that will affect the contract sum
Claims: show reimbursable which will include transport
accommodation logistic, office rental e.t.c
Question 3
In the course of reconstruction project in Question 1 a local
chairman demanded a change in the specification of the entrance
doors from single solid door to double swing doors. Write out the
A.I in these regards.
Answer
To B & C builders                 Jwac KONZULTS
5, Eden Udo Street Uyo       Abuja
Project title: Construction of primary health care in local
government in Nigeria
C/c   10
(1)    Employer
(2)    Q.S
(3)    Clerk of work
(4)    Consultant
Or for address alternatives
To:………………………………………………………
From:………………………………………………….
Project:………………………………………………..
Draw table
Signed:……………………………………………….
Copied:…………………………………………………
Signed architect:…………………………………
Date:…………………………………………………
Question 4
Tender what condition would you recommend extension of time of
a project
Answer
  (1) force-major
  (2) delay in honouring the payment certificate
  (3) delay in issuing detail