Workmanship Standards
for
                                    Licensed Contractors
                                        FEBRUARY 2007
                                        WITH FEBRUARY 2008 REVISIONS
        MAIN OFFICE
  3838 N. Central Ave., Ste. 400
    Phoenix, AZ 85012-1946
        (602) 542-1525
      TDD (602) 542-1588
    Or Toll Free Within Arizona
1-877-MY AZROC (1-877-692-9762)
       Visit Our Website at
         www.azroc.gov
                                        JANET NAPOLITANO
                                           GOVERNOR
                                        FIDELIS V. GARCIA
                                            DIRECTOR
                                STATE OF ARIZONA
                    REGISTRAR OF CONTRACTORS
                                  FIELD OFFICES
FLAGSTAFF OFFICE                                  SHOW LOW OFFICE
2901 Shamrell Blvd., Ste. 100                     581 E. Old Linden Rd., Ste. C
Flagstaff, AZ 86001-1829                          Show Low, AZ 85901-4819
(928) 526-2325                                    (928) 537-8842
KINGMAN OFFICE                                    SIERRA VISTA OFFICE
715 Main St., Suite C                             333 W. Wilcox, Ste. 104
Kingman, AZ 86401-6220                            Sierra Vista, AZ 85635-1756
(928) 753-4220                                    (520) 459-5119
LAKE HAVASU CITY OFFICE                           TUCSON OFFICE
231 Swanson Ave., Ste. 100                        400 W. Congress, Ste. 212
Lake Havasu City, AZ 86403-0966                   Tucson, AZ 85701-1311
(928) 855-2144                                    (520) 628-6345
PRESCOTT OFFICE                                   YUMA OFFICE
240 S. Montezuma St., Ste. 202B                   Crescent Center
Prescott, AZ 86303-3028                           2540 S. 4th Ave., Ste. 117
(928) 445-5710                                    Yuma, AZ 85364-8557
                                                  (928) 344-6900
                          PHOENIX MAIN OFFICE
                           3838 N. Central Ave., Ste. 400
                             Phoenix, AZ 85012-1946
                    (602) 542-1525 or Toll Free Within Arizona
                       1-877-MY AZROC (1-877-692-9762)
                               TDD (602) 542-1588
                        Visit Our Website at www.azroc.gov
THE MISSION OF THE REGISTRAR OF CONTRACTORS
IS TO PROMOTE QUALITY CONSTRUCTION BY
ARIZONA CONTRACTORS THROUGH A LICENSING
AND REGULATORY SYSTEM DESIGNED TO PROTECT
THE HEALTH, SAFETY, AND WELFARE OF THE PUBLIC.
               Visit our Website at
              http://www.azroc.gov
             AN EQUAL EMPLOYMENT OPPORTUNITY
            REASONABLE ACCOMMODATION AGENCY
    THIS DOCUMENT IS AVAILABLE IN ALTERNATIVE FORMATS BY
            CONTACTING OUR ADA COORDINATOR AT
                 (602) 542-1525 TDD (602) 542-1588
                                   INDEX
INTRODUCTION                                        1
RULE 4-9-108 WORKMANSHIP STANDARDS                  1
DEFINITIONS                                         2
GENERAL STATEMENTS                                  3
Air Conditioning and Heating                        3
Cabinets and Vanities                               5
Carpentry
    Finish - (Exterior)                             5
    Finish - (Interior)                             7
    Framing                                         8
Carpet                                              10
Concrete                                            11
    Efflorescence                                   11
    Natural Concrete – Color and Shade Variations   12
    Post Tension                                    12
    Freeze (or Frost) Lines Zones 2 + 3             12
Countertops
    Laminated                                       16
    Cultured Marble                                 17
    Countertops & Walls (Stone Slab)                18
                                          I
Electrical Systems                                19
Fireplace                                         20
Glass                                             20
Gypsum Wall Board                                 21
Hardwood Floors                                   22
Insulation                                        22
Interlocking Pavers                               22
Landscaping                                       24
Masonry                                           25
Painting                                          26
Plumbing                                          27
Resilient Floor Covering                          28
Roofs                                             29
     Asphalt and Fiberglass Composition (3) Tab   30
     Flat Built-up                                31
     Foam                                         34
     Lightweight Aggregate Concrete               36
     Tile                                         37
     Wood Shingles and Shakes                     39
Septic Tank Systems                               40
Siding (Exterior)                                 41
                                      II
Site Work                                       42
Solar Hot Water Systems                         43
Sprinklers, Bubblers and Drip Systems           43
Stucco                                          45
Swimming Pools                                  46
    Coping                                      46
    Decks
             Concrete                           46
             Equipment                          47
             Wood                               48
    Electrical                                  48
    Interior Finish
             Fiberglass/Acrylic                 49
             Fiberglass/Acrylic/Painted         49
             Plaster                            49
             Vinyl Liner                        51
    Mechanical                                  52
              Site Work                         54
              Solar Heaters                     55
                      Mechanical                56
                      On the Building           56
              Structure                         57
                                          III
               Tile                                 58
               Water Quality                        58
Tile
       Ceramic Floor and Natural Stone Floor Tile   59
       Ceramic and Natural Stone Wall Tile          61
       Saltillo Tile and Unglazed Clay Pavers       62
Vents, Louvers and Turbines                         65
Walls, Curbs, Fences, Etc.                          65
Waterproofing and Vapor Barriers                    65
Weather Strip and Thresholds                        66
                                          IV
                                    INTRODUCTION
     These standards cover performance of those construction items of major concern to
the buyer for the first two years of ownership, unless otherwise specified. The contractor
should stand behind the product, but the buyer should be responsible for owner-
maintenance items. Contractor responsibility under these standards should not extend to
items which have been subject to owner neglect, modification or abnormal use.
     The effective date for the start of coverage of these standards should begin when the
buyer occupies the structure or the date of discovery, whichever occurs first or as otherwise
noted.
     Defects in appliances and plumbing and electrical fixtures properly installed by the
contractor should be limited to the manufacturer's warranty.
     These standards are subject to revision as methods of construction or materials used
in construction continue to change.     If there is any conflict between the workmanship
standards and building code requirements, the latter should prevail.
                   RULE 4-9-108 WORKMANSHIP STANDARDS
   A. A contractor shall perform all work in a professional and workmanlike manner.
   B. A contractor shall perform all work in accordance with any applicable building codes
and professional industry standards.
   C. All work performed by a contractor in a county, city, or town that has not adopted
building codes or where any adopted building codes do not contain specific provisions
applicable to that aspect of construction work shall be performed in accordance with
professional industry standards.
                                             1
                                     DEFINITIONS
    The following standards are expressed in terms of permissible tolerances. The format
is designed for easy comprehension as follows:
    PD Possible deficiency
         A brief statement of the problem to be considered.
    AT Acceptable tolerance
         A statement in measurable terms above which repair may be required and below
         which the condition is considered to be acceptable.      “None” means that the
         possible deficiency identified is completely unacceptable and no tolerance is
         allowed.
    CR Contractor responsibility
         A statement of the corrective action needed to correct the deficiency or damage.
    A.C.I. means American Concrete Institute.
    CMU means concrete masonry unit.
    Substantial completion for swimming pools and spa interior cementitious finishes
    means 30 days from the day the pool/spa is filled with water and the equipment is in
    operation.
    All other items on the pool equipment, such as decks, tile, pumps, etc., substantial
    completion means the date of the initial pool start-up.
                                             2
                               GENERAL STATEMENTS
     Contractor’s responsibility on all manufactured surfaces is valid only if the damaged
surface is indicated to the contractor or contractor’s representative within 10 days after
move-in.
     Owner maintenance items include:
     1.    Adjustment of doors, windows and weather-stripping after the first year of
           occupancy.
     2.    Interior and exterior caulking (excluding roofing sealant) after the first year of
           occupancy.
     3.    Drips and leaks at faucets, hose bibs and other plumbing fixtures after the first
           year of occupancy or the expiration of manufacturer's warranty (whichever is
           longer) caused by normal wear of washers, seats or "O" rings.
     4.    Normal wear of the finish of household appliances, fixtures, painted surfaces or
           floor coverings.
When it is shown that any of the above items have been aggravated by the actions or
inaction of the contractor, the contractor should assume responsibility for repair or
replacement of these items.
                            AIR CONDITIONING AND HEATING
1.   PD         Inadequate heat.
     AT         Heating system should be capable of producing an indoor temperature of
                70º as measured in center of room at 5' height under local outdoor winter
                design conditions as specified in ASHRAE Handbook (see J Manual tests
                as specified in ARI standards).
     CR         Contractor should correct the heating to provide the specified temperatures.
                The contractor should be responsible for balancing dampers, registers, and
                other minor adjustments one time for one season. Deficiencies caused by
                malfunction of system equipment or appliances are subject to the terms of
                the manufacturer's warranty unless workmanship by the contractor is
                involved.
                                              3
2.   PD   Excessive noise from ducts.
     AT   Ducts should not rattle or "oilcan".
     CR   Contractor should determine cause and make necessary repairs.
3.   PD   Inadequate combustion air vent.
     AT   Combustion air should be according to manufacturer's specifications.
     CR   Contractor should make necessary repairs.
4.   PD   Unit too close to door.
     AT   As established by code or manufacturer.
     CR   Contractor should make necessary repairs to provide clearance specified by
          code or as recommended by the manufacturer of unit.
5.   PD   Improper clearance to change filters.
     AT   Filter should be easily accessible.
     CR   Contractor should make corrections to allow easy removal of filter.
6.   PD   Air conditioner does not adequately cool structure.
     AT   Unit should cool structure 30º (32º in Scottsdale) lower than outside air
          temperature when measured in center of room at 5' height. Minimum indoor
          temperature should be 78º.
     CR   Contractor should make proper repairs or adjustments to meet temperature
          conditions.
7.   PD   Equipment fails.
     AT   None.
     CR   Contractor should correct deficiency if within one year or within limits of
          manufacturer's warranty.
8.   PD   Condensate lines broken, incomplete or improperly routed.
     AT   None.
     CR   Contractor should make necessary repairs.
                                         4
9.   PD        Water leaking into distribution system, return air or supply system.
     AT        None.
     CR        Contractor should make necessary repairs.
                               CABINETS AND VANITIES
     It should be noted that it is not unusual for the color of installed cabinets to be slightly
different from the samples shown at the time of selection. Color can differ with wood grain
variations and stain lots. Excessive variation is not acceptable.
1.   PD        Cabinet malfunctions.
     AT        Cabinet doors, drawers and other operating parts should function properly.
               A warp of 1/8" in 30" is considered acceptable.
     CR        Contractor should repair, adjust or replace operating parts as required within
               first year.
2.   PD        Cabinet doors not at same height.
     AT        Tops of cabinet doors must be in the same horizontal plane, within 1/8".
     CR        Contractor should adjust doors to meet above standard once within first
               year.
3.   PD        Voids or open knots on outside of cabinet.
     AT        Voids or open knots should not be on outside of cabinet unless special
               effect is requested.
     CR        Contractor should repair or replace.
                                       CARPENTRY
                         CARPENTRY - FINISH - (EXTERIOR)
     Due to varying moisture conditions throughout Arizona, wood products will continue to
expand and contract. This action is normal and beyond the contractors control.
                                               5
1.   PD   Crooked, warped facias.
     AT   Excessively crooked or warped facias are unacceptable.
     CR   Contractor should repair or replace one time within first year.
2.   PD   Wavy or improperly supported soffits.
     AT   Soffits should be reasonably straight, properly supported and nailed.
     CR   Contractor should make necessary repairs.
3.   PD   Trim omitted at juncture of soffit to wall when specified.
     AT   None.
     CR   Contractor should install proper trim per plans and specifications.
4.   PD   Shingle mold crooked, improperly nailed.
     AT   Shingle mold should follow line of facia and be nailed securely to facia.
     CR   Contractor should make necessary repairs.
5.   PD   Door casing, window casing or brick mold loose, out of square or does not
          fit.
     AT   Door, window trim and brick mold should fit, be square and securely
          attached.
     CR   Contractor should make necessary repairs.
6.   PD   Corner boards too short or loose.
     AT   Corner boards should be of proper length and securely attached.
     CR   Contractor should make necessary repairs.
7.   PD   Hammer marks on trim.
     AT   Un-repaired hammer marks are unacceptable.
     CR   Contractor should make necessary repairs.
8.   PD   Spliced barge rafters.
     AT   Long barge rafters may be spliced by approved methods, but splice should
          not separate or sag more than 1/8".
     CR   Contractor should make necessary repairs.
                                         6
9.   PD   Exterior (including garage doors) warping, splintering, shrinking and
          exposing unfinished areas.
     AT   Exterior doors should be sealed on all six sides and finished per
          specifications.
     CR   Contractor should repair and refinish as necessary one time within the first
          year.
                   CARPENTRY - FINISH - (INTERIOR)
1.   PD   Poor workmanship on interior trim.
     AT   All joints on molding, casing, etc., should fit and be securely attached, as
          well as properly filled and sanded.
     CR   Contractor should make necessary repairs.
2.   PD   Pocket door rubs against frame or casing.
     AT   Door units should be installed square and plumb with proper guides, hang
          evenly in frame and work smoothly.
     CR   Contractor should adjust pocket door one time within the first year.
3.   PD   Bypass sliding doors uneven.
     AT   Bypass door units should be installed square and plumb with proper guides,
          hang evenly in frame and work smoothly.
     CR   Contractor should repair and/or adjust properly, one time within the first
          year.
4.   PD   Exposed nails on trim.
     AT   Nails on trim should be installed properly.
     CR   Contractor should make necessary repairs.
5.   PD   Doors bind or rub against jamb.
     AT   Doors should clear 1/8" at top and sides.
     CR   Contractor should make necessary repairs one time within first year.
                                         7
6.   PD       Door will not stand open.
     AT       Doors should not move to open or closed when 45º to opening.
     CR       Contractor should make necessary repairs.
7.   PD       Interior or exterior door warped.
     AT       Warping more than 1/4" when measured in any direction is unacceptable.
     CR       Contractor should replace warped door and finish to match existing doors
              one time within first year.
                               CARPENTRY - FRAMING
     Framing lumber should meet lumber industry standards.
1.   PD       Floors squeak or sub-floor appears loose.
     AT       Floors and subfloors should not have excessive squeaks or be loose.
     CR       Contractor should make necessary repairs.
2.   PD       Wood or metal framed floors uneven or out of level.
     AT       Unevenness of floor should not exceed 3/16" in 48". Floors should be level
              within 1/2" in any 12'.
     CR       Contractor should make necessary repairs.
3.   PD       Walls not straight or not plumb.
     AT       Walls should be straight within 1/4" and plumb within 1/4" measured from
              floor to ceiling at corners.
     CR       Contractor should make necessary repairs.
4.   PD       Walls not 90º angles to each other.
     AT       Walls should be perpendicular within 1/4" in 10'.
     CR       Contractor should make necessary repairs.
                                             8
5.   PD   Rough openings for doors and windows are not properly dimensioned,
          plumb and level.
     AT   The rough openings should satisfy the manufacturer's recommendations.
     CR   Contractor should repair to assure that openings are structurally sound,
          plumb, level and properly sized.
6.   PD   Warped or twisted studs or ceiling joists.
     AT   Stud walls and ceilings should be flat and not bulge more than 3/8" in 8'.
     CR   Contractor should make necessary repairs.
7.   PD   Twisted or warped interior and exterior posts or beams.
     AT   Beams or posts should not twist more than 1/16" per foot of 4" x 12"
          descending ratio as follows:
          4" x 12", 1/16" twist per foot, 1 1/4" total allowable
          4" x 6", 1/32" twist per foot, 9/16" total allowable
          4" x 4", 1/40" twist per foot, 1/2" total allowable
          Warpage or twisting should not damage beam pocket.
     CR   Contractor should make necessary repairs.
8.   PD   Cracked interior beams.
     AT   Cracks in finished interior beams, which do not affect structural integrity, are
          acceptable if repaired.
     CR   Contractor should make necessary repairs.
9.   PD   Improper crickets.
     AT   None - Crickets must be constructed to provide proper drainage.
     CR   Contractor should make necessary repairs.
10. PD    Roof holds water.
     AT   Minor ponding (up to 1/2" deep in small areas equivalent to no more than
          1/3 of span) is acceptable providing roof is dry within 48 hours after rainfall.
     CR   Contractor should make necessary repairs.
                                          9
11. PD         Scuppers installed too high.
     AT        Scuppers should be installed low enough to drain roof.
     CR        Contractor should be responsible for repairing or replacing improperly
               installed scuppers.
                                          CARPET
     Tackless carpets should be tightly stretched and securely attached to the tack strip at
all perimeters. Bubbles or ripples should not be visible in the carpet.
     Seams should be of a good appearance from a standing position; however, seams
normally have some visibility.
     Some of the contributing factors to seam visibility are:
     Peaking - Due to the additional thickness of the seam tape and the action of the heat
from the seaming iron, slight peaking can occur at the seam. This will be particularly
apparent in lower profile and velvet type textures.
     Textures - Various textures have an effect on seam visibility. Loop pile, loop pile
berber and dense velvet finishes will generally create more visible seams than other
textures.
     Contractors who install carpeting should resolve problems regarding manufacturing
defects with the manufacturer on behalf of the owner if the contractor was responsible for
the sale and or selection of the carpeting.
1.   PD        Pile crushing in new installations.
     AT        Some pile crushing is not uncommon when the installation is new. This will
               normally self correct within 90 days.
     CR        If severe crushing persists after 90 days, carpet should be replaced.
2.   PD        Excessively visible seams.
     AT        Seams should be tightly fitted with no gaps or overlaps in the seam.
     CR        Contractor should remake seam if gaps or overlaps are present.
                                              10
3.   PD        Defective materials.
     AT        None.
     CR        Defective materials should be replaced.
4.   PD        Carpet seams placed in "T" configuration.
     AT        Carpet seams placed in "T" configuration are unacceptable except where
               other methods are impractical.
     CR        Contractor should correct seam or replace affected area.
                                        CONCRETE
      This section applies to standard steel troweled or light broom finishes. Specialty
finishes are not included.
     Settling or heaving of soils under concrete caused by alteration of grades by owner or
owner’s agent, which create excessive ponding or moisture adjacent to concrete
foundations, walks, drives, slabs, or patios, should not be considered the contractor’s
responsibility providing the contractor has met all the conditions called for in the contract,
plans, specifications, and all code requirements.
     The contractor should be responsible to correct or ensure correction of settling or
heaving if compaction is not according to the licensed soils engineer’s report or if no
alterations have been made by owner or owner’s agent.
     All concrete should be placed in compliance with applicable codes and standards. This
will apply to design strengths, testing, dimensions, frost lines, and reinforcement along with
items not specifically contained in the codes, such as proper placement in a good and
workmanlike manner to achieve appearance and function of the finished product.
                             CONCRETE – EFFLORESCENCE
     The potential for efflorescence exists in all portland cement-based products.
Efflorescence is a salt that is left on the surface of concrete upon drying and is generally of
only cosmetic concern in nature. It often dissipates with contact with water or the passage
of time. Efflorescence that is severe, recurring, or accompanied by degradation of the
concrete surface may indicate the application of excessive moisture, an elevated
concentration of salts in the applied water, numerous cycles of wetting and drying and/or a
more substantial presence of salts within the surrounding environment.
                                              11
           NATURAL CONCRETE – COLOR AND SHADE VARIATIONS
    Color and shade variations are inherent in all portland cement-based products. These
variations may occur and are generally acceptable. These differences can be attributed to a
wide variety of causes. Some causes include variable jobsite conditions and changes in
aggregate source, age, degree of curing, and specified slab substrate.
                                     POST – TENSION
    Cracking in a post-tensioned slab is normal, and often post-tensioned slabs exhibit
fewer cracks in number but, hairline cracks are not uncommon. The purpose of the steel
cable is to improve the structural performance of the slab and foundation system, per the
structural engineer’s design, often to improve performance on expansive or weaker soils.
The post-tensioned slab and foundation system is designed to act as an integral unit,
distributing its own weight and the loads it carries uniformly into the supporting soils.
              CONCRETE - FREEZE (OR FROST) LINES ZONE 2 + 3
     In areas above 3000’, ft. elevation concrete should be air entrained according to A.C.I.
specifications for the aggregate size of the concrete being placed. It is recommended that
denser concrete be placed to offset the effects of freeze and thaw along with placing the
concrete below the freeze line. The freeze line will vary with the elevation. Recommended
depths are as follows:
                   Elevation             3000-4999 Ft.                   18”
                   Elevation             5000-6999 Ft.                   24”
                   Elevation             7000-8000 Ft.                   36”
Check with local building officials for required depth in the area where the construction is
planned.
PD = Possible Deficiency
AT= Acceptable Tolerance
CR= Contractor Responsibility
                                               12
1.   PD   Cracks in “cast in place” concrete stems..
     AT   Cracks wider than 1/8" should be properly repaired with appropriate
          material. Cracks over 1/4" indicate the possibility of settlement, heaving or
          other failure.
     CR   Contractor should properly fill cracks with appropriate materials over 1/8”
          but less than 1/4". If cracks are 1/4" or wider, contractor should determine
          the cause and make proper repairs. Repairs should be made near the end
          of first year to allow the building to stabilize.
2.   PD   Cracks in basement floors.
     AT   Cracks in excess of 3/32” width and 1/8” vertical displacement or compound
          cracks in excess of 1/16” in width are not acceptable.
     CR   If vertical displacement in excess of 1/8” or compound cracking in excess of
          1/16” in width is present, affected area should be replaced.
3.   PD   Cracking of garage slabs, carports, exterior slabs, patios, driveways and
          sidewalks.
     AT   Cracks in excess of 3/32” width and 1/8” vertical displacement or compound
          cracks in excess of 1/16” in width are not acceptable. Cracks of 3/16” are
          acceptable for sidewalks.
     CR   If vertical displacement in excess of 1/8” or compound cracking in excess of
          1/16” in width is present, affected area should be replaced. Cracks in
          sidewalks which exceed 3/16” will require the affected areas to be replaced.
4.   PD   Patio or carport slab cracking at columns.
     AT   Half moon cracking at column base is unacceptable.
     CR   Contractor should make necessary repairs.
                                          13
5.   PD   Settling or heaving of stoops or steps.
     AT   Settlement or heaving more than 1/4" is unacceptable.
     CR   Contractor should make necessary repairs.
6.   PD   Spalling or pitting of concrete.
     AT   Concrete should not deteriorate to the extent that the aggregate is exposed
          or the aesthetics are destroyed under normal use and weather conditions.
     CR   Contractor should take corrective action necessary to repair or replace
          defective areas. Contractor should not be responsible for damage caused
          by chemicals applied by others.
7.   PD   Ponding or standing water on garages, patios, stoops, carports, walks and
          driveway concrete surfaces.
     AT   Water should drain.         Standing water exceeding 3/32" is unacceptable.
          Standing water exceeding 3/16" on driveways is unacceptable. Flood, wait
          30 minutes and then check for ponding.
     CR   Contractor should make necessary repairs.
8.   PD   Improper expansion and/or control joints in driveways.
     AT   Driveways should have expansion joints at carport or garage and at curb or
          sidewalk. Control joints at least 1/5 the thickness of the slab should be
          placed no more than 10' apart.
     CR   Contractor should correct to provide proper control or expansion joints.
9.   PD   Cracks in control joints.
     AT   Concrete should crack in control joints.        Cracks exceeding 3/8" are
          excessive.
     CR   Contractor should make necessary repairs.
10. PD    Uneven or wavy floors.
     AT   Floors should not vary from flat more than 1/4" over a 10' area provided the
          deviation is gradual. Deviations, dips, or sags over short distances and
          easily visible to the eye may be considered unacceptable.
     CR   Contractor should make necessary repairs.
                                          14
11. PD   Floors not level.
   AT    Floors should be level within 1/4" in any 12' run.
   CR    Contractor should make necessary repairs.
12. PD   Corners chipped or broken during construction.
   AT    Chipped or broken corners in concrete may occur during construction.
         These chips and broken corners are unacceptable at move-in.
   CR    Contractor should make necessary repairs.
13. PD   Different elevations between slabs.
   AT    Vertical displacement between two adjacent slabs should not be a trip
         hazard.
   CR    Contractor should make necessary repairs.
14. PD   Excessive crazing of finished exterior concrete surfaces.
   AT    None.
   CR    Contractor should make necessary repairs.
15. PD   Improper, inadequate, unsightly finishing.
   AT    None.
   CR    Contractor should make necessary repairs.
16. PD   Frozen or frost bitten concrete.
   AT    None.
   CR    Contractor should make necessary repairs.
17. PD   Pop-outs in concrete slabs.
   AT    Minor pop-outs are acceptable if repaired. Slabs with an excessive amount
         of pop-outs are unacceptable.
   CR    Contractor should make necessary repairs.
18. PD   Post-tension cable design.
   AT    Review by designing structural engineer.
   CR    Follow the direction of the structural engineer.
                                       15
                                    COUNTERTOPS
                                       LAMINATED
     High Pressure Decorative Laminate and its substrate are usually wood-based
products, which typically expand and contract with humidity. In order to maintain long
lasting, functional, and aesthetic usage, it is necessary to practice regular maintenance.
Heat-generating appliances should not be placed on or near seams and/or joints. Moisture
should never be allowed to stand on seams and/or joints for more than 24 hours.
1.   PD        Scratches and chips in laminate.
     AT        Scratches that cannot be seen looking straight down at a distance of 12" nor
               felt with fingernail are considered acceptable. Notable scratches or chips
               should be reported on walk thru or within 10 days after move-in.
     CR        Contractor should repair or replace as necessary.
2.   PD       Tops bowed or warped.
     AT        Bow or warp should not exceed 1/16" per lineal foot.
     CR        Contractor should repair or replace as necessary.
3.   PD        Defects or flaws in plastic laminate.
     AT        None.
     CR        Contractor should repair or replace as necessary.
4.   PD        Loose self-edge at laminate edge or splash.
     AT        None - Self-edge should be completely adhered to the substrate.
     CR        Contractor should repair or replace as necessary.
5.   PD        Moisture damage at seams, joints or around the sink.
     AT        None - All seams and joints should comply with the American National
               Standard Institute guidelines.
     CR        Contractor should repair or replace as necessary (except where there is
               owner neglect, modification or abnormal use).
                                                16
6.   PD   Cuts - Burns - Abrasions - Stains.
     AT   Cuts, burns, abrasions and/or stains should be reported on walk thru or
          within 10 days after move-in.
     CR   Contractor should repair or replace as necessary.
                  COUNTERTOPS – CULTURED MARBLE
1.   PD   Scratches in marble.
     AT   None - Scratches in marble should be reported to the contractor within 10
          days after move-in.
     CR   Contractor should repair or replace as necessary.
2.   PD   Marble is bowed or warped.
     AT   Bow or warp should not exceed 1/16" per lineal foot in any direction.
     CR   Contractor should make necessary repairs.
3.   PD   Pinhole defects in marble.
     AT   Pinhole defects should be repaired unless excessive.
     CR   Contractor should make necessary repairs. Excessive pinholes may require
          marble replacement.
4.   PD   Tub ledge fails to drain water into tub.
     AT   None.
     CR   Contractor should take appropriate steps to insure that tub ledge drains
          properly.
5.   PD   Marble windowsills in bathrooms or kitchens hold water.
     AT   Marble windowsills in these areas should drain away from window.
     CR   Contractor should make necessary repairs.
6.   PD   Pattern in marble is not continuous.
     AT   Small areas of irregular pattern should be acceptable unless it occurs in a
          prominent location.
     CR   Contractor should replace marble where necessary.
                                          17
                       COUNTERTOPS & WALLS (STONE SLAB)
     When an inadequate or defective substrate is present prior to installation of tile, the
general contractor and/or the owner should be notified in writing by the tile contractor that a
specific surface area is unacceptable for installation. Verifiable documentation that the
potential problem was first submitted to the responsible party may relieve the installer of
responsibility.
1.   PD           Joint width is excessive.
     AT           Joints should not exceed 1/16” in width.
     CR           Contractor should make necessary repairs.
2.   PD           Joint width between countertop and adjacent wall is excessive.
     AT           The width of the caulk joint between the countertop and adjacent wall
                  should not exceed 1/8”.
     CR           Contractor should make necessary repairs.
3.   PD           Countertop is warped or bowed.
     AT           1/16” in 4’ in any direction.
     CR           Contractor should make necessary repairs.
4.   PD           Scratches or chips in polished stone.
     AT           None. Notable scratches or chips should be reported at walk through or
                  within 10 days after move-in. Fissures are natural characteristics of stone
                  and should not be construed as scratching or pitting.
     CR           Contractor should make necessary repairs.
5.   PD           Vein trend.
     AT           In slabs with obvious veining, the slabs should be installed with vein trend
                  running in the same direction.
     CR           Contractor should make necessary repairs.
                                                  18
                           ELECTRICAL SYSTEMS
          POTENTIALLY HAZARDOUS SITUATIONS SHOULD
                       BE CORRECTED IMMEDIATELY.
1.   PD   Malfunctioning of electrical fixtures, switches or outlets.
     AT   None.
     CR   Contractor should make necessary repairs.
2.   PD   Breaker trips with normal use.
     AT   Breaker should operate as intended.
     CR   Contractor    should   replace      defective   breaker   in   accordance   with
          manufacturer’s warranty.
3.   PD   Electrical equipment not level, plumb and true.
     AT   None.
     CR   Contractor should make necessary repairs.
4.   PD   Electrical equipment or materials not secure or adequately supported.
     AT   None.
     CR   Contractor should make necessary repairs.
5.   PD   Switch located behind door.
     AT   All boxes for switches should be located on the side of the doorframe
          opposite the hinge.
     CR   Contractor should make necessary repairs.
6.   PD   Switches or plates span two different materials and are not flush.
     AT   Switches or plates should not span different types of building materials,
          vertically or horizontally, unless specified and then should be flush with both
          materials.
     CR   Contractor should make necessary repairs.
                                         19
                                         FIREPLACE
1.   PD        Unobstructed fireplace chimney does not draw properly.
     AT        None.
     CR        Contractor should make necessary repairs to correct fireplace or chimney to
               function properly.
2.   PD        Damper does not operate properly.
     AT        Damper should have full travel and operate easily.
     CR        Contractor should make necessary repairs.
                                          GLASS
     Glass and mirror defects should be reported to the contractor at the time of the walk-
thru. If no walk-thru has been held, these defects should be reported within 10 days of
occupancy or replacement installation.
1.   PD        Scratches on glass observable in daylight at 15’.
     AT        None.
     CR        Contractor should replace as necessary.
2.   PD        Malfunctioning windows, screens and sliding glass doors.
     AT        Windows, screens and sliding doors should operate smoothly with
               reasonable ease. Contractor should not be held responsible for owner’s
               alterations or abuse to windows, screens and sliding doors.
     CR        Contractor should replace or repair as necessary one time in first year.
3.   PD        Leaks at glazing in windows or doors.
     AT        Minor infiltration of moisture and dust is normal around doors and windows,
               especially during high winds and excessive rain. Excessive infiltration from
               improperly installed doors and windows or poorly fitted weather stripping is
               unacceptable.
     CR        Contractor should make necessary repairs.
                                            20
4.   PD   Cracked or broken glass.
     AT   None.
     CR   Contractor should make necessary repairs.
5.   PD   Scratches on mirror surfaces observable in daylight at a distance of 3’ or
          more.
     AT   None.
     CR   Contractor should replace mirror.
                           GYPSUM WALL BOARD
1.   PD   Ceiling sags.
     AT   Ceiling should not sag more than 3/8" in 8'.
     CR   Contractor should make necessary repairs.
2.   PD   Visible conditions such as nail pops, cracks and seam lines due to
          expansion and contraction of structure.
     AT   Normal conditions such as hairline cracks where drywall meets a dissimilar
          material should be considered acceptable and can be readily corrected by
          homeowner.
     CR   Contractor should repair nail pops, seam lines and other hairline cracks one
          time within first year of occupancy.
3.   PD   Loose panels, improper nailing.
     AT   Panels should be firmly fastened.
     CR   Contractor should make necessary repairs.
4.   PD   Readily visible flat areas in textured finish.
     AT   None.
     CR   Contractor should make necessary repairs.
5.   PD   Voids at switch and receptacle plates.
     AT   None.
     CR   Contractor should make necessary repairs.
                                         21
                                HARDWOOD FLOORS
1.   PD       Hardwood curls, pops or buckles.
     AT       None - Unless caused by moisture from broken sewer or water pipes, roof
              leaks, spills, etc.    Hardwood floors should be installed according to
              manufacturer’s recommendations.
     CR       Contractor should make necessary repairs.
                                        INSULATION
1.   PD       Insulation not uniform in attic.
     AT       Insulation should meet minimum specified R factor.
     CR       Contractor should make necessary corrections to assure uniform thickness
              and specified R factor.
2.   PD       Insulation not installed properly.
     AT       None.
     CR       Contractor should correct condition as necessary.
3.   PD       Garage area not insulated.
     AT        Normally not done unless specified.
     CR       Contractor should correct only if specified.
                              INTERLOCKING PAVERS
1.   PD Settling or heaving of stoops or steps.
     AT Settling or heaving more than ¼” is unacceptable.
     CR Contractor should make necessary repairs.
2.   PD Spalling, pitting or damage of concrete pavers.
     AT Pavers should not deteriorate to the extent that the aggregate is exposed or the
          aesthetics are destroyed under normal use and weather conditions.
     CR Contractor should take corrective action necessary to replace defective areas.
          Contractor should not be responsible for damage caused by chemicals,
          excessive pressure washing or abuse.
                                             22
3.   PD Ponding or standing water on garages, patios, stoops, carports, walks and
          driveway surfaces.
     AT Water should drain. Standing water exceeding 3/32” is unacceptable. Standing
          water exceeding 3/16” on driveways is unacceptable. Flood, wait 30 minutes and
          check for ponding.
     CR Contractor should make necessary repairs.
4.   PD Shifted or broken edge restraint.
     AT Edge restraints should remain stationary.
     CR Contractor should make necessary repairs
5.   PD Inadequate or excessive leveling sand.
     AT Leveling sand should be a minimum of ¾” and a maximum of 1 ½”.
     CR Contractor should make necessary repairs.
6.   PD Excessive gap between pavers in field and at edges.
     AT No gaps should exceed 3/8” at the edge of the pavers. Joint widths between the
          pavers in the field should be between 1/16" and 3/16 at the base of the pavers
          (tumbled pavers may have a gap appearing larger from the top)
     CR Contractor should fill gaps at the edges greater than 3/8” with cut paver. Pavers
          with a gap greater than 3/16” in the field should be taken up and relayed tight.
7.   PD White substance on pavers (efflorescence).
     AT Efflorescence is the result of a naturally occurring reaction and is not a defect.
     CR No contractor action is required.
8.   PD The elevation of two adjacent pavers is not the same.
     AT There should be no more than 1/8” difference in height between adjacent pavers.
     CR Contractor shall make necessary repairs. If not extreme, re-compaction of the
          area may repair the problem.
9.   PD Uneven or wavy pavers.
     AT Excessive deviations, dips or sags over short distances are considered
          unacceptable.
     CR Contractor should make necessary repairs.
                                             23
10. PD Pavers interfere with drainage.
     AT Pavers should not interfere with drainage.
     CR Contractor should correct as necessary.
                                    LANDSCAPING
1.   PD       Landscaping interferes with drainage.
     AT       Landscaping should not interfere with established drainage.
     CR       Contractor should correct as necessary.
2.   PD       Plants are not size or species specified.
     AT       None.
     CR       Contractor should install proper plants.
3.   PD       Plants dying.
     AT       Plants should be installed in healthy living condition.
     CR       Contractor should replace affected plants within warranty period unless
              condition is caused by owner.
4.   PD       Rocks uneven or spread too thin.
     AT       None.
     CR       Contractor should correct so that proper coverage is achieved.
5.   PD       Grass and weeds growing in rocks.
     AT       Areas should be protected from weed or grass infiltration.
     CR       Contractor should correct condition by appropriate means within 90 days.
6.   PD       Low spots.
     AT       Area should be fine graded and properly compacted.
     CR       Contractor should correct condition.
7.   PD       Damage caused by landscaping equipment.
     AT       None.
     CR       Contractor should have proper repairs made to anything damaged during
              landscaping.
                                            24
                                        MASONRY
     Masonry walls should be straight, plumb and level, with uniform mortar joints and
proper grout and vertical horizontal reinforcement. CMU will vary in texture and color;
therefore, care should be used in selection of the material.        Slump block will absorb
moisture and should be sealed to prevent leaks through walls and damage in freeze-thaw
zones.
1.   PD       Crooked, out-of-plumb, out-of-level masonry walls.
     AT       1/4" out of plumb, 1/2" in total length of wall out of level not to exceed 1/4" in
              8'.
     CR       Contractor should make necessary repairs.
2.   PD       Uneven surface of masonry walls.
     AT       Walls should be free of protruding or sunken blocks or bricks, unless called
              for in plans and specifications.
     CR       Contractor should make necessary repairs.
3.   PD       Voids in mortar joints.
     AT       Voids in masonry mortar joints 1/4" or less are acceptable unless they are
              excessive.
     CR       Contractor should make necessary repairs.
4.   PD       Cracks in mortar joints (stair step).
     AT       Stair step cracks in mortar joints can result from normal settlement and do
              not necessarily indicate a structural problem.
     CR       Cracks 1/8" or more should be filled.       If cracks exceed 1/8" or if crack
              extends across the block itself, a structural problem may exist. Contractor
              should determine cause of the crack and make appropriate repairs if
              necessary.
5.   PD       Parapet walls not capped or filled.
     AT       None.
     CR       Parapet walls should be properly capped and filled.
                                             25
6.   PD   Parapet walls not finished on roof side.
     AT   None.
     CR   Parapet walls should be struck on roof side and voids in mortar filled.
7.   PD   Masonry columns out of plumb or out of line.
     AT   Masonry columns should be plumb within 1/4" and in line within 1/4".
     CR   Contractor should make necessary repairs.
8.   PD   Mortar joints not straight, plumb or varies in thickness. (Certain masonry
          products are designed to exhibit an irregular appearance and must be
          evaluated accordingly).
     AT   Mortar joints should be straight and plumb (within 3/16" in adjacent courses)
          and of uniform thickness unless otherwise specified or detailed on plans.
          (Note: The bed joint may vary from these standards to compensate for
          irregularities in the stem wall or footing as allowed by the U.B.C.).
     CR   Contractor should make necessary repairs.
9.   PD   Metal reinforcement (rebar, duo-wire, etc.) not placed in masonry walls and
          fences as specified or as required by the building code.
     AT   None.
     CR   Contractor should reconstruct and provide proper reinforcement.           The
          existing wall or fence material may be reused provided it is undamaged.
                                    PAINTING
1.   PD   Exterior paint or latex stain peels or deteriorates.
     AT   None.
     CR   Contractor should properly prepare and refinish affected areas, matching
          color as closely as possible. Where finish deterioration affects the majority
          of the wall or area, the whole area should be refinished.
                                         26
2.   PD   Painting required as corollary repair because of other work does not match
          surrounding paint.
     AT   Paint should match surrounding areas as closely as possible.
     CR   Contractor should refinish to match surrounding areas as closely as
          possible.
3.   PD   Deterioration of stains, varnish or lacquer finishes.
     AT   Finishes on interior woodwork should not deteriorate during the first year of
          ownership. However, varnish type finishes used on exterior will deteriorate
          rapidly.
     CR   The contractor should correct or repair deteriorating finish one time during
          the first year of occupancy.
4.   PD   Interior paint inadequately covers surface.
     AT   Interior paint should be applied in an amount conforming to manufacturer's
          specifications of coverage and in sufficient quantity to visually cover all
          specified areas.
     CR   The contractor should retouch all surfaces where inadequate paint has been
          applied to cover original surfaces. Paint deterioration caused by normal
          living conditions, such as repeated scrubbing or scouring is a maintenance
          item and should be the responsibility of the owner.
5.   PD   Exterior doors not sealed on all six surfaces.
     AT   None.
     CR   Contractor should make necessary repairs.
                                   PLUMBING
1.   PD   Leakage from any soil, waste, vent, gas or water piping.
     AT   None.
     CR   Contractor should make necessary repairs.
                                         27
2.   PD         Faucet or valve leak.
     AT         No valve or faucet should leak due to defects in material or workmanship.
                Leakage caused by worn washers is considered owner maintenance except
                during manufacturer's warranty period.
     CR         Contractor should repair or replace the leaking faucet or valve unless due to
                owner negligence.
3.   PD         Defective plumbing fixtures or trim fittings.
     AT         None.
     CR         Contractor should replace or repair defective fixture or fitting according to
                manufacturer's warranty unless workmanship is involved, then contractor
                should repair problem. Contractor is not responsible for failure due to owner
                negligence or water impurities.
4.   PD         Stopped up sewers and drains.
     AT         None.
     CR         Contractor should be responsible if caused by workmanship.
5.   PD         Plumbing fixture loose at floor.
     AT         None.
     CR         Contractor should repair as necessary.
6.   PD         Vents or other penetrations located in roof valley.
     AT         Vents or other penetrations should not be located within 18" of valley
                centerline.
     CR         Contractor should relocate vents or other penetrations and have roof
                repaired by properly licensed contractor.
                              RESILIENT FLOOR COVERING
     Some resilient flooring is not recommended for use on concrete slabs. If the buyer
specifies these floorings, the buyer assumes responsibility for any problems that might
develop after installation if the owner is advised of this fact in writing prior to installation.
                                                 28
1.   PD        Nail pops readily visible under floor covering.
     AT        None.
     CR        Contractor should correct condition and repair or replace floor covering.
2.   PD        Seams easily visible due to spacing or pattern mismatch.
     AT        Seams should not be readily visible from a standing position.          Pattern
               mismatch is unacceptable.
     CR        Contractor should make appropriate repairs or replace.
3.   PD        Floor covering becoming loose at seams, edges or bubbles in floor
               covering.
     AT        None.
     CR        Contractor should repair or replace as necessary.
4.   PD        Foreign particles under floor coverings.
     AT        None.
     CR        Contractor should repair or replace as necessary.
5.   PD        Use of materials not recommended for on-grade concrete slabs, unless
               specified by owner or plans and specifications.
     AT        Use of this material should be at contractor's risk. If hydrostatic pressure or
               moisture    causes   discoloration   or    separation,   covering   should   be
               unacceptable.
     CR        Contractor should replace with approved material.
6.   PD        Irregular cut edges along cabinets or walls.
     AT        None.
     CR        Contractor should make appropriate repairs or replace.
                                          ROOFS
     Roofs should not leak and should be installed to withstand winds accompanied by
heavy rains. The contractor should not be responsible for leaks caused by alterations, tie-
ins or penetrations caused by owner or others after completion of the roof, nor for extreme
weather conditions.
                                             29
          ROOFS - ASPHALT AND FIBERGLASS COMPOSITION (3 TAB)
1.   PD       Too much exposure.
     AT       Should be reasonably close to recommended dimensions.
     CR       Contractor should make necessary repairs.
2.   PD       Uneven, irregular or crooked shingles.
     AT       Shingles should be reasonably straight and courses even in width.
     CR       Contractor should make necessary repairs.
3.   PD       Fish mouths and/or curling.
     AT       None.
     CR       Contractor should make necessary repairs.
4.   PD       Improper nailing.
     AT       Nailing should be per approved schedule.
     CR       Contractor should make necessary repairs. Excessive nailing (more than
              six fasteners per shingle) should require shingle replacement.
5.   PD       Crooked or unsightly ridges and hips.
     AT       None.
     CR       Contractor should make necessary repairs.
6.   PD       Improper, crooked and unsightly valleys.
     AT       None.
     CR       Contractor should make necessary repairs.
7.   PD       Flashings and jacks improperly installed.
     AT       None.
     CR       Contractor should make necessary repairs.
8.   PD       Improper crickets installed by the roofing contractor.
     AT       Crickets should have a minimum slope of at least twice that of the adjacent
              roof.
     CR       Contractor should install cricket correctly & repair or replace affected
              roofing.
                                            30
9.   PD       Improper crickets (installed by other trades).
     AT        Roofer should be responsible for repairing or replacing affected roofing if
               roofer installs roof over improper crickets. Verifiable documentation that the
               potential problem was first submitted to the responsible party may relieve
               the roofer of responsibility.
     CR        Contractor should repair or replace affected roofing after cricket has been
               corrected by the responsible party.
10. PD         Vents or other penetrations located in roof valley.
     AT        Vents or other penetrations should not be located within 18" of valley
               centerline.   Verifiable documentation that the potential problem was first
               submitted to the responsible party may relieve the roofer of responsibility.
     CR        Roofer should be responsible for repairing or replacing affected roofing.
11. PD         Roof is not of a uniform color or texture due to shingle replacements.
     AT        Shingle replacements within the first two years of installation due to faulty
               materials or a workmanship deficiency should not exceed 20% of the entire
               roof area.
     CR        Contractor should remove entire roof and install a new roof.
                               ROOFS - FLAT BUILT-UP
     Failure to obtain a building official’s inspection and approval on re-roofing when
required by the governing building official may require the roof covering to be completely
removed and proper inspections made before applying the new roof.
1.   PD        Roof leaks.
     AT        None.
     CR        Contractor should determine cause and properly repair.
                                               31
2.   PD   Roof holds water.
     AT   Minor ponding (up to 1/2" deep in small areas equivalent to no more than
          1/3 of span) is acceptable providing roof is dry within 48 hours after rainfall.
          Verifiable documentation that the potential problem was first submitted to
          the responsible party may relieve the roofer of responsibility.
     CR   If drainage problem is due to improper framing problems, the roofer should
          be responsible for repairing or replacing affected roofing.
3.   PD   Excessive ponding due to build-up of roofing materials at scuppers.
     AT   Minor ponding (up to 1/2" deep in small areas equivalent to no more than
          1/3 of span) is acceptable providing roof is dry within 48 hours after rainfall.
     CR   Contractor should remove excess material and repair as necessary.
4.   PD   Bare spots on graveled roofs.
     AT   Gravel should be firmly embedded in flood coat.
     CR   Initial two pounds of gravel per square foot should be embedded in asphalt.
          Additional two pounds per square foot is for cover. Contractor should apply
          additional asphalt and embed gravel in bare spots.
5.   PD   Scuppers installed too high.
     AT   Scuppers should be installed low enough to drain roof.                 Verifiable
          documentation that the potential problem was first submitted to the
          responsible party may relieve the roofer of responsibility.
     CR   Roofer should be responsible for repairing or replacing affected roofing.
6.   PD   Improper or non-existent cants.
     AT   None.
     CR   Contractor should make necessary repairs.
7.   PD   Improper flashing and counter flashing at parapets and vertical walls.
     AT   None.
     CR   Contractor should make necessary repairs.
8.   PD   Chimneys not flashed and counter flashed.
     AT   None.
     CR   Contractor should correct by installing proper flashing.
                                         32
9.   PD   Omitted or improperly installed vent jacks.
     AT   None.
     CR   Contractor should make necessary repairs.
10. PD    Bubbles or roof-ply separations.
     AT   Minor bubbles or blisters should not be cut.
     CR   Contractor should make proper repairs as needed.        If seam separation
          occurs as a result of the blister, it should be repaired in accordance with
          manufacturer’s specifications. If condition is widespread, roof should be
          replaced.
11. PD    Gravel guard improper size and incorrectly installed.
     AT   None.
     CR   Contractors should make necessary repairs.
12. PD    Roof coating alligatored.
     AT   Some minor alligatoring is normal.       Emulsified asphalt used in proper
          quantities should not alligator excessively.
     CR   Contractor should recoat to correct problems, pursuant to manufacturer's
          specifications.
13. PD    Seams lifting or curling.
     AT   None.
     CR   Contractor should properly mop down and flood coat.
14. PD    Roof not installed per specifications.
     AT   None - Roof must be proper type and proper number of plies.
     CR   Contractor should repair or replace as necessary.
15. PD    Roofing material applied over debris on roof deck.
     AT   None.
     CR   Contractors should make necessary repairs.
                                        33
6.   PD        Improper crickets installed by the roofing contractor.
     AT        Crickets should have a minimum slope of at least twice that of the adjacent
               roof.
     CR        Contractor should install cricket correctly and repair or replace affected
               roofing.
17. PD         Improper crickets (installed by other trades).
     AT        Roofer should be responsible for repairing or replacing affected roofing if the
               contractor installs roof over improper crickets. Verifiable documentation that
               the potential problem was first submitted to the responsible party may
               relieve the roofer of responsibility.
     CR        Contractor should repair or replace affected roofing after cricket has been
               corrected by the responsible party.
                                      ROOFS - FOAM
     Failure to obtain a building official's inspection and approval on re-roofing may require
the roof covering to be completely removed and proper inspections made before applying
the new roof. For the purposes of these standards, “nominal inch” will be defined as “at
least 1 inch” with occasional 7/8” measurements acceptable.
1.   PD        Bubbles in foam coating (separation from deck).
     AT        None.
     CR        Contractor should make necessary repairs.
2.   PD        Humps in foam.
     AT        None.
     CR        Contractor should make necessary repairs.
3.   PD        Ripples in foam.
     AT        Excessive waves or ripples are unacceptable.
     CR        Contractor should make necessary repairs.
                                               34
4.   PD   Coating too thin or incomplete.
     AT   Coating should be proper thickness and have no voids.
     CR   Contractor should recoat as necessary.
5.   PD   Overspray on areas of building or equipment.
     AT   None.
     CR   Contractor should remove overspray and clean affected areas.
6.   PD   Repairs with asphaltic materials.
     AT   None – Unapproved materials should not be used on foam.
     CR   Contractor should remove and repair with foam or approved materials.
7.   PD   Scuppers or drains plugged by foam.
     AT   None.
     CR   Contractor should make necessary repairs.
8.   PD   Debris on roof.
     AT   None.
     CR   Contractor should remove debris from roof and recoat foam if necessary.
9.   PD   Ponding.
     AT   Minor ponding (up to 1/2" deep in small areas equivalent to no more than
          1/3 of span) is acceptable providing roof is dry within 48 hours after rainfall.
          Verifiable documentation that the potential problem was first submitted to
          the responsible party may relieve the roofer of responsibility.
     CR   Contractor should make necessary repairs to insure proper drainage.
10. PD    Improper crickets (installed by other trades).
     AT   Roofer will be responsible if the roofer installs roof over improper crickets.
          Verifiable documentation that the potential problem was first submitted to
          the responsible party may relieve the roofer of responsibility.
     CR   Contractor should install cricket correctly and repair or replace roofing.
                                        35
          ROOFS - LIGHTWEIGHT AGGREGATE CONCRETE
1.   PD   Roof leaks.
     AT   None.
     CR   Contractor should determine cause and make necessary repairs.
2.   PD   Improper underlayment.
     AT   Since the underlayment is really the waterproof barrier, it should be of the
          specified material and properly installed.
     CR   Contractor should remove roof and replace.
3.   PD   Excessive cracking or chipping.
     AT   None.
     CR   Contractor should remove and replace affected area.
4.   PD   Excessively cracked, chipped, irregular and unsightly edges.
     AT   None.
     CR   Contractor should repair or replace as necessary.
5.   PD   Unsightly, irregular or chipped rises.
     AT   Forms should not be moved too soon. Edges at rise should be uniform and
          smooth.
     CR   Contractor should make necessary repairs.
6.   PD   Color variation.
     AT   Color between batches should be reasonably close.
     CR   Contractor should remove and replace affected areas.
7.   PD   Overspray on building, chimneys or equipment.
     AT   None.
     CR   Contractor should make necessary repairs.
                                        36
8.   PD   Improper crickets (installed by other trades).
     AT   Roofer will be responsible if the roofer installs roof over improper crickets.
          Verifiable documentation that the potential problem was first submitted to
          the responsible party may relieve the roofer of responsibility.
     CR   Contractor should install cricket correctly and repair or replace.
                                    ROOFS - TILE
1.   PD   Roof leaks.
     AT   None.
     CR   Contractor should determine cause of leak and make necessary repairs.
2.   PD   Loose or falling tiles.
     AT   None.
     CR   Contractor should make necessary repairs.
3.   PD   Ridge - hip and rake tiles loose or missing.
     AT   None.
     CR   Contractor should make necessary repairs.
4.   PD   Wood nailers visible under hip or ridge tiles per manufacturer's
          specifications.
     AT   None.
     CR   Contractor should remove tiles and make necessary repairs.
5.   PD   Chipped and broken tiles.
     AT   Chips larger than a quarter or excessive in number are unacceptable.
          Broken and cracked tiles are unacceptable.
     CR   Contractor should replace affected tiles. Roofing contractor should not be
          responsible for damage caused by others.
6.   PD   Irregular, uneven and unsightly valleys.
     AT   Valleys should be reasonably straight and aesthetically acceptable.
     CR   Contractor should make necessary repairs.
                                         37
7.   PD   Unsightly and/or off color mortar.
     AT   Mortar should be neat and reasonably uniform in color.
     CR   Contractor should make necessary repairs.
8.   PD   Improper exposure.
     AT   Exposure should not exceed limits recommended by manufacturer.
     CR   Contractor should make necessary repairs.
9.   PD   Vents not flashed or improperly flashed.
     AT   Unapproved, missing or improperly installed roof jacks are unacceptable.
     CR   Contractor should make necessary repairs.
10. PD    Improper or inadequate flashing.
     AT   Flashings should be installed according to manufacturer's recommendations
          and should be an approved type.
     CR   Contractor should make necessary repairs.
11. PD    Improperly installed nailing strips.
     AT   None -Nailing strips should be installed per manufacturer's
          recommendations.
     CR   Contractor should make necessary repairs.
12. PD    Inadequate underlayment.
     AT   None.
     CR   Contractor should make necessary repairs.
13. PD    Improper crickets (installed by other trades).
     AT   Roofer will be responsible if the roofer installs roof over improper crickets.
          Verifiable documentation that the potential problem was first submitted to
          the responsible party may relieve the roofer of responsibility.
     CR   Contractor should install cricket correctly and repair or replace roofing.
14. PD    Tile droops at eaves.
     AT   None.
     CR   Contractor should install proper spacer at eaves.
                                         38
15. PD    Crooked vertical and horizontal lines.
     AT   Vertical and horizontal lines should be reasonably straight unless varied
          deliberately for effect.
     CR   Contractor should make necessary repairs.
               ROOFS - WOOD SHINGLES AND SHAKES
1.   PD   Type and grade not per plans and specifications.
     AT   None.
     CR   Contractor should make necessary repairs.
2.   PD   Improper exposure, edge lap or spacing.
     AT   Should be reasonably close to recommended dimensions.
     CR   Contractor should make necessary repairs.
3.   PD   Edges line up in adjacent courses.
     AT   Edges should not line up within three courses.
     CR   Contractor should make necessary repairs.
4.   PD   Improper placement of felt strips when required.
     AT   Felt should not be visible through spacing.
     CR   Contractor should make necessary repairs.
5.   PD   Improper nailing.
     AT   Nails should be weather resistant and properly sized for material used.
     CR   Contractor should make necessary repairs.
6.   PD   Improper flashings and valleys.
     AT   Flashings and valleys should be the size and type specified or required by
          code.
     CR   Contractor should make necessary repairs.
7.   PD   Loose or uneven ridge and hip shingles.
     AT   Ridges and hips should be straight, uniform and secured.
     CR   Contractor should make necessary repairs.
                                        39
8.   PD   Roof jacks improper.
     AT   Roof jacks should be designed for wood shingles or shakes.
     CR   Contractor should replace jacks if necessary.
9.   PD   Starter shingles not used.
     AT   None.
     CR   Contractor should make necessary repairs.
10. PD    Improper crickets (installed by other trades).
     AT   Roofer will be responsible if the roofer installs roof over improper crickets.
          Verifiable documentation that the potential problem was first submitted to
          the responsible party may relieve the roofer of responsibility.
     CR   Contractor should install crickets correctly and repair or replace roofing.
                          SEPTIC TANK SYSTEMS
1.   PD   Septic system fails to operate properly.
     AT   Septic system should be built according to regulating Health Department.
     CR   Contractor should make necessary repairs.
2.   PD   Improper depth or improper backfill over leach field.
     AT   Should be as designed. Surface water should not stand over leach field.
     CR   Contractor should make necessary repairs.
3.   PD   Pipe leaking.
     AT   None.
     CR   Contractor should make necessary repairs.
4.   PD   Cleanout improper size or height.
     AT   Cleanout should be sized to allow pumping with standard equipment.
     CR   Contractor should make necessary repairs.
5.   PD   Cover on tank or cesspool collapsed.
     AT   None - Unless caused by others not under the contractor’s control.
     CR   Contractor should make necessary repairs.
                                        40
6.   PD        System installed too close to structure.
     AT        None.
     CR        Contractor should place system as required by regulating agency.
                                   SIDING (EXTERIOR)
     Due to varying moisture conditions throughout Arizona, wood products will expand
and contract. This is normal and beyond the contractor's control.
1.   PD        Uneven building siding.
     AT        Siding should be straight and flat within 3/8" in 10'.
     CR        Contractor should make necessary repairs.
2.   PD        Siding delaminating.
     AT        None.
     CR        Contractor should make necessary repairs.
3.   PD        Joints in siding not directly over stud.
     AT        Siding should match stud layout so that both sheets of siding are supported
               by stud.
     CR        Contractor should make necessary repairs.
4.   PD        Improper or inadequate nailing on siding.
     AT        Siding should be nailed according to manufacturer's specifications or as
               required by code.
     CR        Contractor should make necessary repairs.
5.   PD        Siding not properly caulked.
     AT        None - Siding should be properly caulked as required by manufacturer or
               code.
     CR        Contractor should make necessary repairs.
                                              41
                                  SITE WORK
1.   PD   Settling of ground around foundations, filled areas and trenches.
     AT   Excessively settled areas are unacceptable. Evaluation must be made on a
          case-by-case basis.     The contractor should not be required to correct
          conditions caused by owner or landscapers not under the control of the
          contractor.
     CR   The contractor should upon notification of this condition, fill and compact the
          affected area taking care to maintain the proper slope and drainage.
2.   PD   Excessive settlement or cracking of floors, slabs, walks, drives or stems due
          to improper compaction of the subsurface and/or improper compaction of
          trenches.
     AT   None.
     CR   Contractor should make necessary repairs.
3.   PD   Excessive cracking due to expansive soils.
     AT   None. Soil conditions are known or should be known to the contractor prior
          to construction. The technology is available and a state of the art exists to
          avoid problems arising from expansive soil.
     CR   Contractor should make necessary repairs.
4.   PD   Improper drainage of site.
     AT   None - Grades should be established to insure proper drainage away from
          the structure. No standing water should remain in the yard more than 48
          hours after a rain, unless requirements specify retention of storm water in
          yard. If a sump pump is included in the contract, all water should drain to
          the sump.
     CR   The contractor should correct deviations from the established grades, but is
          not responsible for conditions caused by others not under the contractor’s
          control.
                                        42
                           SOLAR HOT WATER SYSTEMS
     Solar hot water systems or heating and cooling systems should be installed to I.M.P.S.
Manufacturer's Installation Manual.
1.   PD        Solar system does not operate properly.
     AT        None.
     CR        Contractor should repair or replace components, parts or panels in
               accordance with manufacturer's warranties and/or guarantees if less than
               one year.   Installer should be responsible for damage due to improper
               installation of solar systems for two years including interior damage caused
               by leaks.
                SPRINKLERS, BUBBLERS AND DRIP SYSTEMS
     Buyer assumes responsibility of sprinkler heads, bubbler heads and distribution tubing
of drip systems after 90 days unless improper workmanship by the contractor can be
shown.
1.   PD        System does not function.
     AT        None.
     CR        Contractor should determine cause and make necessary repairs.
2.   PD        System does not cover area.
     AT        Heads should be placed to cover area intended with water pressure and
               volume available.
     CR        Contractor should make necessary repairs.
3.   PD        Trenches visible over piping, improperly filled or compacted.
     AT        None.
     CR        Contractor should make necessary repairs.
                                             43
4.   PD   Heads not working properly.
     AT   Defective sprinkler heads are unacceptable. Heads damaged by mower or
          vandals are not responsibility of contractor.
     CR   Contractor should make necessary repairs.
5.   PD   Bubblers not functioning properly.
     AT   None.
     CR   Contractor should adjust one time and instruct owner how to clean and
          adjust heads.
6.   PD   Clock not operating properly or defective.
     AT   None.
     CR   Contractor should make necessary repairs. Determine cause and correct
          condition. Replace clock if defective and within warranty.
7.   PD   Heads too low or too high.
     AT   Heads should clear top of grass when mowed and retract to clear
          lawnmower.
     CR   Contractor should adjust height of heads one time after grass is established
          if necessary.
8.   PD   Stolenized lawns not smooth with low spots and areas between stolens.
     AT   None.
     CR   Contractor should make necessary repairs.
9.   PD   Boxes or covers not installed at solenoid valves.
     AT   Valves should be installed in proper box with covers when required by
          manufacturer’s specifications or code.
     CR   Contractor should make necessary repairs.
10. PD    Operating instructions not provided.
     AT   None.
     CR   Contractor should provide owner with operating instructions.
                                        44
                                         STUCCO
     Stucco products should be mixed and installed to specifications.
1.   PD        Cracks in stucco.
     AT        Hairline cracks, if excessive, or cracks that exceed 1/16" are unacceptable.
     CR        Contractor should determine cause of crack and make necessary repairs.
2.   PD        Stucco falling or chipping around window or door frames.
     AT        None.
     CR        Contractor should determine cause and make necessary repairs.
3.   PD        Stucco too thin. Wire lath visible.
     AT        None.
     CR        Contractor should make necessary repairs.
4.   PD        Voids in stucco at beams, columns, etc.
     AT        None.
     CR        Contractor should make necessary repairs.
5.   PD        Stud locations visible on stucco wall.
     AT        None.
     CR        Contractor should make necessary repairs.
6.   PD        Weep screeds missing on frame walls or not properly installed.
     AT        None.
     CR        Contractor should make necessary repairs.
                                             45
                                   SWIMMING POOLS
     Swimming pool construction and design should meet or exceed the suggested
minimum standards for swimming pools of the National Spa and Pool Institute, applicable
building code requirements, as well as these standards. Spa construction and design is
incorporated in these standards.
     The construction site should be examined by the contractor and the consumer should
be made aware of any conditions, which could result in future problems.
                              SWIMMING POOLS - COPING
1.   PD        Coping cracks or becomes loose.
     AT        None.
     CR        Contractor should make necessary repairs.
2.   PD        Cracks appear in grout or grout becomes loose.
     AT        None - Checks in grouting of coping joints are commonly due to normal
               shrinkage conditions and as such are normal maintenance responsibilities
               of the owner.
     CR        Contractor should within the first 12 months repair loose grouting or cracks
               in grouting.
3.   PD        Crack in cantilever nose and cap tile grout under white cap at control joint.
     AT        This is a normal condition.
     CR        None.
                    SWIMMING POOLS - DECKS - CONCRETE
1.   PD        Standing water.
     AT        At the time of substantial completion all deck work should be sloped to drain
               to the exterior edge and/or to deck drains. Puddles 2' in diameter or more
               and/or over 1/8" in depth 20 minutes after the addition of water to the decks
               are unacceptable.
     CR        Contractor should make necessary repairs.
                                             46
2.   PD   Cracks.
     AT   Shrinkage and minor movement cracks occur in concrete deck work without
          adversely affecting its serviceability.   Maximum allowable horizontal or
          vertical displacement should not exceed 1/16" except at designed joints
          where horizontal and vertical displacement of up to 1/8" in 5' are acceptable.
     CR   Contractor may relieve the excess vertical separation at designed joints by
          grinding down the high side up to 1/8" and may fill the excess horizontal
          separation.   Decks cracked in other locations in excess of the standard
          should be replaced matching the deck as closely as possible. Repositioning
          of slabs to correct the excess movement may also be done.
3.   PD   Irregular appearance and/or finish.
     AT   All concrete deck work should be equivalent to any sample or display of that
          finish displayed to owner. In the absence of a display sample, owner and
          contractor should rely upon the standards of quality found in similar work in
          the area.
     CR   Contractor should provide at least the consistency of workmanship called for
          in the standard. Colors should match as closely as reasonably possible.
              SWIMMING POOLS – DECKS - EQUIPMENT
1.   PD   Deck equipment such as slides, diving boards, ladders; etc., installed with
          the pool/spa are either loose, not level or plumb.
     AT   None - Deck equipment supplied and installed as part of the work should be
          securely anchored, mechanically firm as a unit and installed in a true, level
          and aligned fashion.
     CR   Contractor should make the necessary changes and/or corrections to
          installation of the equipment to comply with the standards.
                                        47
                  SWIMMING POOLS - DECKS - WOOD
1.   PD   Finished product does not match plans.
     AT   A scale drawing of top and side of deck in relationship to pool/spa and
          structure, should be supplied to owner prior to start. The decking should
          match within reason the scale drawing.
     CR   Contractor should make necessary repairs.
2.   PD   Decking sags, has excessive springiness or motion when in use or
          otherwise provides an unstable structure.
     AT   At time of substantial completion, decking should be firm and stable in
          normal use.
     CR   Contractor should make necessary repairs.
3.   PD   Loose or rusty nails, splintered or split boards, excessive loose knotholes.
     AT   During a period of thirty days following substantial completion, the deck
          should not exhibit any of the above deficiencies.
     CR   Contractor should make necessary repairs.
                    SWIMMING POOLS - ELECTRICAL
          POTENTIALLY HAZARDOUS SITUATIONS SHOULD
                     BE CORRECTED IMMEDIATELY.
1.   PD   Electrical boxes, conduits, disconnects or equipment not level or plumb.
     AT   None.
     CR   Contractor should make necessary repairs.
2.   PD   Erratic performance.
     AT   None - All electrical circuits, controls, etc., should be installed to meet the
          requirements of the N.E.C. and local electrical codes.
     CR   Contractor should make necessary repairs.
                                        48
       SWIMMING POOLS - INTERIOR FINISH - FIBERGLASS/ACRYLIC
1.   PD         Finish has hairline cracking, checking or blistering.
     AT         None.
     CR         Contractor should make necessary repairs.
 SWIMMING POOLS - INTERIOR FINISH - FIBERGLASS/ACRYLIC/PAINTED
1.   PD         Black spots, bubbles, surface separation or imperfections.
     AT         None.
     CR         Contractor should make necessary repairs.
                 SWIMMING POOLS - INTERIOR FINISH - PLASTER
     Colored plaster: It is the nature of colored plaster to accentuate characteristics
normally found in white pool plaster. Mottling can be more pronounced, the plaster may
exhibit pigment stains, streaks, fade out or get gradually lighter and the color shade may
not be exactly as anticipated.
     It is recommended the contractor advise the pool owner of these characteristics prior
to finalizing the contract.
1.   PD         Cracks, tears that allow water passage out of the pool/spa.
     AT         None - The structure along with the interior lining should form a single
                waterproof unit.
     CR         Contractor should make necessary repairs.
2.   PD         Hairline checks and crazing or cracks in plaster.
     AT         Owner should provide the water and allow the pool to be filled upon
                completion of plaster finish. Hairline checks and crazing that may appear in
                plaster are normal. Plaster cracks that appear within the first 12 months of
                substantial completion are unacceptable.
     CR         Contractor should make necessary repairs.
                                              49
3.   PD   Rust stains.
     AT   There should be no rust stains in plaster finish occurring from reinforcing
          steel, tie wires or other contractor-installed components.
     CR   Contractor should remove rust stains and remedy reason for occurrence
          matching the repair area with rest of surface as close as possible.
          Contractor is not responsible for rust stains caused by objects placed in pool
          by others.
4.   PD   Rough plaster and highlighting.
     AT   Contractor should provide an acceptable plaster finish before substantial
          completion.     At the time of the substantial completion inspection, owner
          should    advise   contractor     of   any   unacceptable   plaster   roughness,
          irregularities or highlighting.
     CR   Contractor should provide an acceptable plaster finish before substantial
          completion.     After substantial completion the contractor should not be
          responsible for plaster roughness caused by mineral deposits on pool
          surface and stains and/or roughness caused by pool water chemicals.
5.   PD   Trowel burns.
     AT   None.
     CR   Contractor should one time within the first ninety- (90) days following
          substantial completion remove all trowel burn discoloration.
6.   PD   Excessive shading or mottling.
     AT   At the time of substantial completion, owner should notify contractor of any
          excessive shading or mottling of the plaster finish.          Minor shading or
          mottling of the plaster finish is acceptable. (NOTE: Colored plaster finishes
          may have an even more pronounced degree of shading or mottling because
          of factors inherent in colored finishes.       Normal variations in pool water
          chemistry and ultraviolet action will cause some discoloration or shading of
          the plaster finish after completion and is considered normal. Calcium or
          alkali may precipitate out of pool water onto the plaster surface causing
          discoloration or roughness.)
     CR   Contractor should make necessary repairs.
                                            50
7.   PD    Spot etching at or prior to substantial completion.
     AT    The owner should notify the contractor of any spot etching at substantial
           completion. Contractor should provide an acceptable plaster finish prior to
           substantial completion.
     CR    After substantial completion, contractor should not be responsible for spot
           etching caused by water chemistry.
8.   PD    Calcium or whiteness on colored plaster or that has settled in checks or
           crazing cracks.
     AT    This is a normal occurrence. It is noticeable on colored plaster because of
           the color contrast. Contractor should provide an acceptable plaster finish at
           substantial completion.
     CR    After substantial completion, the contractor should not be responsible for
           plaster discoloration or stains on pool surfaces caused by water chemistry.
          SWIMMING POOLS - INTERIOR FINISH - VINYL LINER
1.   PD    Liner comes loose from fastening around top of pool.
     AT    None.
     CR    Contractor should make necessary repairs.
2.   PD    Wrinkles or folds of material.
     AT    At the time of substantial completion of the pool, the liner should be as
           wrinkle free as possible and should have no folds.
     CR    Contractor should reset liner to eliminate excessive wrinkles and folds at
           substantial completion.
3.   PD    Tears or cuts in vinyl liner.
     AT    At the time of substantial completion, the interior lining should form a single
           waterproof unit.        The interior lining should be designed to provide for
           patching (sealing) of the vinyl liner with similar vinyl material and adhesive.
     CR    Contractor should make necessary repairs and contractor should carry out
           all liner warranties.
                                            51
                   SWIMMING POOLS - MECHANICAL
1.   PD   Mechanical and/or electrical equipment supplied and installed does not
          perform correctly.
     AT   All equipment supplied should be covered by a manufacturer's warranty
          delivered to owner prior to or at the time of substantial completion of the
          work.
     CR   During the first 30 days following substantial completion of the work
          contractor should carry out all manufacturer’s equipment warranties at the
          site of the installation. Thereafter, any manufacturer's warranties should be
          carried out at contractor’s place of business.
2.   PD   Water, gas and waste lines do not function properly or are not installed in
          accordance with established trade practices or codes.
     AT   None - Water, gas and waste lines should be of adequate size and installed
          in accordance with established trade practices and applicable building
          codes.
     CR   Contractor should make necessary repairs.
3.   PD   Mechanical equipment not level or plumb.
     AT   All mechanical equipment supplied and installed by contractor should be
          done so that the completed appearance of the system(s) and piping are
          level and plumb whenever possible.
     CR   Contractor should make necessary repairs.
4.   PD   Water leaks from equipment or piping.
     AT   All mechanical equipment and related components and piping should be air
          and water tight in the range of 1.5 times the normal operating pressure.
     CR   Contractor should make necessary repairs.
                                        52
5.   PD   Water pipes or equipment have no freeze protection.
     AT   Contractor should provide freeze protection for pipes and equipment.
          A. In mild freezing climates contractor should construct the system so that
             by circulating the water all components and pipes are protected.
          B. In moderately severe climates the piping should be placed below the
             frost line and the equipment placed in a heated area.
          C. As an alternate for severe climates all piping and equipment subject to
             freezing should be capable of being conveniently drained.
          Contractor should instruct owner of the method of freeze protection
          designed into system. The owner should insure said method is properly
          carried out during freezing weather.
     CR   Contractor should make necessary repairs.
6.   PD   Clogged suction line.
     AT   Suction lines to the recirculating pump should not be stepped down in size
          on the way to the pump except at equipment connection. Openings from
          the suction line into the pool/spa should be covered by suitable grates,
          screens, etc., to keep large objects from entering.
     CR   Contractor should make necessary repairs.
7.   PD   Pump will not prime.
     AT   Pool/spa pumps should not require an owner to do more than fill certain
          components with an open garden hose, seal such openings, operate the
          necessary valves and turn the system on.
     CR   Contractor should design and install a system to accomplish the standard.
8.   PD   Mechanical components damaged by system vacuum.
     AT   Mechanical components should be installed in such a way that a normally
          created vacuum in system will not cause damage to any of the mechanical
          equipment.
     CR   Contractor should make necessary repairs.
                                        53
9.   PD   Difficulty in servicing mechanical and electrical components.
     AT   Pool/spa mechanical and electrical components should be installed in a
          manner that allows normal access for ease of servicing.
     CR   Contractor should make necessary repairs.
                     SWIMMING POOLS - SITE WORK
1.   PD   Settling of ground around the improvement, utility trenches or other filled
          areas.
     AT   Settling should not interfere with water drainage away from the
          improvements.
     CR   Contractor should fill excessively settled areas one time during the 12-
          month period following substantial completion unless there is a continuing
          problem due to poor workmanship. The owner should be responsible for
          any grass; shrubs or other landscaping affected by placement of such fill.
2.   PD   Standing water.
     AT   At time of substantial completion the necessary grades and swales should
          have been established to insure proper drainage away from the
          improvements. Site drainage is limited to the immediate grades and swales
          affecting the improvements. No standing or ponding of water should remain
          in this immediate area after a rain, except swales, which may drain other
          areas after a rain.
     CR   The contractor should establish the proper grades, elevations and swales
          and the owner should maintain such grades and swales after substantial
          completion.
3.   PD   Site cleaning, leveling, trench backfilling not satisfactory.
     AT   All construction debris should be removed. Site contours should be graded
          so that they may be mowed with normal equipment, rocks and boulders
          removed and/or covered with suitable topsoil (or if impractical, so
          designated in the pre-construction plans.
     CR   Contractor should provide a one-time site clean up and grading prior to
          substantial completion.
                                         54
4.   PD       Irregular contours in site and/or drainage passages.
     AT       Site drainage should, if carried on the surface of the ground, be carried in
              swales of cross sectional contours easily mowed with normal equipment.
     CR       Contractor should correct as necessary.
                      SWIMMING POOLS - SOLAR HEATERS
     Plumbing lines in solar pool heaters should not have mineral build up with normal
water and contractor is not liable for mineral build up due to water conditions and/or
chemical imbalance.
1.   PD       System does not perform properly.
     AT       Solar equipment should be covered by a written manufacturer or
              contractor’s performance warranty delivered to owner prior to or at
              substantial completion of the work.
     CR       Contractor should make necessary repairs.
2.   PD       Equipment not properly secured, level or plumb.
     AT       Collectors, pipes, conduits, etc., should be secured and adequately braced.
              Piping and collectors should be level and plumb wherever possible.
     CR       Contractor should make necessary repairs.
3.   PD       Solar collectors and/or system have no freeze protection.
     AT       The collectors and related piping system should be designed and installed
              so as to provide freeze protection.
              A.   In mild freezing climates contractor should design the system so that
                   by circulating the water all components and pipes are protected.
              B.   In moderately severe climates, the piping should be placed below the
                   frost line and the equipment placed in a heated area.
              C.   As an alternate for severe climates all piping and equipment subject to
                   freezing should be capable of being conveniently drained.
     CR       Contractor should instruct owner of the method of freeze protection
              designed into system and should repair/replace freeze damage caused by
              an improperly installed system.
                                            55
           SWIMMING POOLS - SOLAR HEATERS - MECHANICAL
1.   PD      Solar pool heating collectors or plumbing damaged by freezing during a
             power failure.
     AT      Solar pool heating systems should be equipped with a fail-safe diversion
             valve allowing collectors to drain. Valve should return to an open position
             during a power failure or equipment malfunction.
     CR      Contractor should make necessary repairs.
          SWIMMING POOLS - SOLAR HEATERS - ON THE BUILDING
1.   PD      Roof leaks due to improper penetration and/or sealant.
     AT      None - Protection against water penetration around solar components or tie
             down penetrations should be in accordance with local building codes.
             Properly tested roof sealant should be used per collector manufacturer's
             recommendation, so as not to interfere with the integrity of the existing
             waterproof membrane.
     CR      Contractor should make necessary repairs.
2.   PD      Roof leaks where supply and return piping penetrate eaves.
     AT      None – Holes made for pipes to penetrate eaves should be protected by
             roof jacks (flashing material), so as not to interfere with the integrity of
             waterproof characteristics of the roof membrane.
     CR      Contractor should make necessary repairs.
3.   PD      Roof under solar collectors showing signs of deterioration (rot).
     AT      None - All solar pool heaters should be installed in such a way as to not
             encourage premature roof deterioration.
     CR      Contractor should make necessary repairs.
                                           56
                     SWIMMING POOLS - STRUCTURE
1.   PD   Will not hold water.
     AT   None – Shotcrete or gunite shrinks, as there is a drying out of the original
          moisture content. Shrinkage cracks occur because the surface of the gunite
          dries out faster than the underlying layers. These cracks are not structural
          cracks; they penetrate only the surface area (per ASTM C-42-61
          specifications). Proper care and curing can keep this problem minimal. To
          minimize the shrinkage cracks the gunite must be kept moist. Gunite is
          porous and has the ability to absorb a large volume of water, much like a
          sponge. The gunite should be saturated with water until it is no longer
          absorbed. This process should be repeated every two hours during the day
          for five days after installation. The structure along with the interior lining
          should form a single waterproof unit.
     CR   Contractor should make necessary repairs.
2.   PD   Structure is cracked, torn or otherwise separated.
     AT   None - The structure should not crack, tear or separate and should be
          designed to withstand all normally anticipated loads or stresses.
     CR   Contractor should make necessary repairs.
3.   PD   Pool/spa is unlevel.
     AT   At the time of substantial completion of the work, the pool/spa should be
          within +/- (plus or minus) 1/4" (1/2" of level - from high to low) when
          measured at the waterline tile. In the absence of such tile or when a vinyl
          lined interior is used or the unit is a one-piece fiberglass pool, water level
          should be +/- 1/2" (1" of level from high to low) when measured at the
          uppermost surface of the structure.
     CR   Contractor should make necessary repairs.
4.   PD   Exterior and/or interior contours of irregular shape and/or profile.
     AT   All designs should be in accordance with the applicable NSPI standards and
          all workmanship should be within the construction tolerances allowed
          therein.
     CR   Contractor should make necessary repairs.
                                        57
5.   PD   Pool shell or liner floats when pool water is removed.
     AT   Pools are designed to remain relatively full of water. At time of substantial
          completion, written instructions covering this, as well as how to drain the
          pool should be furnished with instructions on who to contact should
          additional information or help be desired.
     CR   Contractor should make necessary repairs.
                           SWIMMING POOLS - TILE
1.   PD   Ceramic tile cracks or becomes loose.
     AT   None.
     CR   Contractor should make necessary repairs.
2.   PD   Cracks appear in grout or grout becomes loose.
     AT   Checks in grouting are normal shrinkage conditions and should be
          maintenance responsibilities of the owner.
     CR   Contractor should repair loose grouting or cracks in grouting one time within
          the first 12 months.
3.   PD   Tile out of level.
     AT   Tile should be level within a tolerance of + or – 1/4" from level at time of
          substantial completion.
     CR   Contractor should make necessary repairs.
                  SWIMMING POOLS - WATER QUALITY
1.   PD   Water is not clear because circulation and filtration equipment provided do
          not meet the design requirements specified in the NSPI design standards.
     AT   None - Complete written operating instructions should be provided owner
          along with verbal instructions.
     CR   Contractor should evaluate owner's water quality problem, provide
          instructions covering equipment furnished and provide up to one hour verbal
          assistance including time spent on owner water samples and make
          necessary repairs.
                                        58
2.   PD         Poor surface skimming or circulation.
     AT         Inlets, skimmers, main drains, etc., should be provided and installed in
                accordance with the appropriate NSPI design standard. Written operating
                instructions should be provided owner.
     CR         Contractor should make necessary repairs.
                                             TILE
                  CERAMIC AND NATURAL STONE FLOOR TILE
     When an inadequate or defective substrate is present prior to installation of tile, the
general contractor and/or the owner should be notified in writing by the tile contractor that a
specific surface area is unacceptable for installation.
1.   PD         Cracked tile.
     AT         None.
     CR         Contractor should make necessary repairs.
2.   PD         Loose tile.
     AT         None.
     CR         Contractor should make necessary repairs.
3.   PD         Hollow sounding tile.
     AT         Acceptable if not extensive and tile is solidly bonded to floor membrane.
     CR         Contractor should make necessary repairs.
4.   PD         Crooked, out of line tile.
     AT         Tile surface should be straight and reasonably flat, allowing for individual
                characteristics of the tile. Nominal centerline of all joints should be straight
                and even width, with due allowances for hand-molded or rustic tiles.
     CR         Contractor should make necessary repairs.
                                              59
5.   PD   Uneven tile. (Lippage)
     AT   Inherent characteristics of the tile dictate the method of installation.      All
          unusual characteristics of the tile should be explained to the owner or the
          owner’s agent prior to installation.
     CR   Contractor should make necessary repairs.
6.   PD   Uneven Natural Stone Tile (Lippage)
     AT   Lippage of all manufactured Natural Stone Tiles are to be no greater than
          1/32" between individual tiles
     CR   Contractor should make necessary repairs.
7.   PD   Grout discoloration.
     AT   Some grout discoloration is inherent in all Portland cement based products.
          Discoloration may occur due to jobsite conditions, individual characteristics
          of ceramic tile, variances in the rate of hydration, etc.
          Excessive grout discoloration is unacceptable. Contractor is not responsible
          for discoloration after the first year nor for discoloration caused by the use of
          waxes, sealers, cleaning solutions, etc., not applied or recommended by the
          contractor or manufacturer.
     CR   Contractor should make necessary repairs during the first year.
8.   PD   Missing or irregular grout.
     AT   None.
     CR   Contractor should make necessary repairs.
9.   PD   Cracks of more than 1/16” at joints with other dissimilar materials such as
          bath tubs.
     AT   None.
     CR   Contractor should correct one time within the first year.
                                           60
                  TILE - CERAMIC AND NATURAL STONE WALL TILE
     When an inadequate or defective substrate is present prior to installation of tile, the
general contractor and/or the owner should be notified in writing by the tile contractor that a
specific surface area is unacceptable for installation. Verifiable documentation that the
potential problem was first submitted to the responsible party may relieve the installer of
responsibility.
1.   PD           Ceramic tile cracks or becomes loose.
     AT           None.
     CR           Contractor should make necessary repairs.
2.   PD           Missing or irregular grout.
     AT           None.
     CR           Contractor should make necessary repairs.
3.   PD           Cracks of 1/16” or more at joints or with other dissimilar materials such as
                  bath tubs.
     AT           None.
     CR           Contractor should correct one time within first year.
4.   PD           Crooked, improperly cut or unevenly set tile.
     AT           None.
     CR           Contractor should make necessary repairs.
5.   PD           Shower floors and tubs do not slope to drain.
     AT           None.
     CR           Contractor should make necessary repairs.
6.   PD           Showers leaking through pan.
     AT           None.
     CR           Contractor should make necessary repairs.
                                                61
7.   PD           Improper or omitted trim parts.
     AT           None.
     CR           Contractor should make necessary repairs.
8.   PD           Uneven tiles.
     AT           Inherent characteristics of the tile dictate the method of installation of the
                  tile. All unusual characteristics of the tile regarding joint width and lippage
                  should be explained to the owner or the owner’s agent prior to installation.
     CR           Contractor should make necessary repairs.
9.   PD           Uneven Natural Stone Tile (Lippage)
     AT           Lippage of all manufactured Natural Stone Tiles are to be no greater than
                  1/32” between individual tiles
     CR           Contractor should make necessary repairs.
10. PD            Grout discoloration.
     AT           Some discoloration is inherent in all Portland cement based products.
                  Discoloration may occur due to job-site conditions, individual characteristics
                  of ceramic tile, variances in the rate of hydration, etc.
                  Excessive discoloration is unacceptable. Contractor is not responsible for
                  discoloration after the first year nor for discoloration caused by the use of
                  waxes, sealers, cleaning solutions, etc., not applied or recommended by the
                  contractor or manufacturer.
     CR           Contractor should make necessary repairs within the first year.
             TILE - SALTILLO TILE AND UNGLAZED CLAY PAVERS
     When an inadequate or defective substrate is present prior to installation of tile, the
general contractor and/or the owner should be notified in writing by the tile contractor that a
specific surface area is unacceptable for installation. Verifiable documentation that the
potential problem was first submitted to the responsible party may relieve the installer of
responsibility.
     Irregularities in color, size and shape are normal inherent characteristics of Saltillo tile.
                                                   62
1.   PD   Cracked tile.
     AT   None.
     CR   Contractor should make necessary repairs.
2.   PD   Loose tile.
     AT   None.
     CR   Contractor should make necessary repairs.
3.   PD   Hollow sounding tile.
     AT   Acceptable if not extensive and tile is solidly bonded to floor or slip-sheet.
     CR   Contractor should make necessary repairs.
4.   PD   Crooked, out of line tile.
     AT   Tile surface should be straight and reasonably flat, allowing for individual
          characteristics of the tile. Nominal centerline of all joints should be straight
          and even width, with due allowances for hand-molded or rustic tiles.
     CR   Contractor should make necessary repairs.
5.   PD   Uneven tiles.
     AT   Lippage of more than 3/16” is unacceptable. Inherent characteristics of the
          tile dictate the method of installation of the tile. All unusual characteristics of
          the tile should be explained to the owner or the owner’s agent prior to
          installation.
     CR   Contractor should make necessary repairs.
                            Lippage of more than
                            3/16” is unacceptable
                                         63
6.   PD   Limepops and cavities.
     AT   Limepops and cavities may be appropriately repaired if less than 1” in
          diameter, with no more than one repair per tile. Repaired tiles should not be
          excessive in number.
     CR   Contractor should repair limepops or cavities.
7.   PD   Grout discoloration.
     AT   Some discoloration is inherent in all Portland cement based products.
          Discoloration may occur due to jobsite conditions, individual characteristics
          of ceramic tile, variances in the rate of hydration, etc.    Excessive grout
          discoloration is unacceptable. Contractor is not responsible for discoloration
          after the first year nor for discoloration caused by the use of waxes, sealers,
          cleaning solutions, etc., not applied or recommended by the contractor or
          manufacturer.
     CR   Contractor should make necessary repairs during the first year.
8.   PD   Missing or irregular grout.
     AT   None. Grout should be flush to the top edge of the adjacent tile.
     CR   Contractor should make necessary repairs.
                                        Exposed vertical face
                                        of tile is unacceptable
9.   PD   Cracks of more than 1/16” at joints with dissimilar materials such as bath
          tubs.
     AT   None.
     CR   Contractor should correct one time within the first year.
                                          64
                            VENTS, LOUVERS AND TURBINES
1.   PD        Leaks at vents, louvers or turbines other than wind-driven rain.
     AT        None.
     CR        Contractor should make necessary repairs.
2.   PD        Turbines not vertical.
     AT        None.
     CR        Contractor should install jacks with proper pitch for roof upon which
               installed.
3.   PD        Vents in overhang not screened.
     AT        None.
     CR        Contractor should make necessary repairs.
                             WALLS, CURBS, FENCES, ETC.
1.   PD        Walls, curbs, fences, etc., do not perform the function for which they were
               designed.
     AT        Walls, curbs, fences, etc., should be designed and built in accordance with
               established practices and applicable building codes in the area.
     CR        Contractor should make necessary repairs.
                   WATERPROOFING AND VAPOR BARRIERS
     Waterproofing and vapor barrier requirements vary according to area. Check with the
local building official about specific requirements and methods approved in that area.
1.   PD        Leaks in foundation or basement walls.
     AT        None.
     CR        Contractor should determine cause of leaks and make necessary repairs.
                                             65
2.   PD   Leaks in conversation pit, or other areas designated to be constructed
          below floor level.
     AT   None.
     CR   Contractor should determine if leak is in foundation wall or chimney and
          make necessary repairs.
3.   PD   Leaks in gable end walls.
     AT   None.
     CR   Contractor should make necessary repairs.
4.   PD   Leaks through slump block walls.
     AT   None.
     CR   Contractor should make necessary repairs.
                  WEATHER STRIP AND THRESHOLDS
1.   PD   Drafts around doors and windows.
     AT   Some infiltration of moisture and dust is normally noticeable around doors
          and windows, especially during high winds and heavy rain.            Excessive
          infiltration resulting from open cracks, poorly fitted doors and windows or
          poorly fitted weather stripping is unacceptable.
     CR   The contractor should adjust or correct open cracks, poorly fitted doors or
          windows or poorly fitted weather stripping.        If necessary, the contractor
          should adjust or replace the weather stripping or threshold one time during
          the first year of occupancy.
2.   PD   Threshold leaks water.
     AT   None.
     CR   Contractor should make necessary repairs.
3.   PD   Weather strips missing or damaged on windows.
     AT   None.
     CR   Contractor should make necessary repairs.
                                         66
4.   PD   Excessive gap between doors at T astragal on double doors.
     AT   None.
     CR   Contractor should make necessary repairs.
5.   PD   Weather strip missing at T astragal.
     AT   None.
     CR   Contractor should make necessary repairs.
                                       67