LABOUR ESTIMATE FOR VARIOUS ITEMS OF WORKS
SN
.
ITEM DESCRIPTION
QUANTITY
LABOUR ( 8 hours per day)
1.
Concrete in Foundation.
10 m3
Head Mason 1/4, Mason 2, Labour
20
2.
R.C.C. M - 15 grade.
10 m3
Head Mason 1/2, Mason 3, Labour
23
Note: For each additional storey, the strength should be increased by 6 nos. for
volume of 10 cu.m to lift the materials.
3.
Supplying, fitting, fixing
and removing shuttering &
staging.
7 m2
Carpenter 1, Labour 2
4.
Reinforcement for R.C.C.
work including cutting,
bending and placing in
position.
100 kg.
Bar binder (Black- smith/fitter) 1,
Labour 1
5.
Damp proof course.
100 m2
Head Mason 1/2, Mason 5, Labour 6
6.
First class brickwork in 1:6
in super structure.
10 m3
Head Mason 1/2, Mason 9, Labour
18, Bhisti 2
7.
Brick on edge flooring with 100 m2
cement Mortar (1:3).
Head Mason 1/2, Mason 10, Labour
14, Bhisti 1
8.
Ironite flooring (40mm
thk).
100 m2
Head Mason 1, Mason 24, Labour
27, Labour for Scrubbing 3
9.
C.G.I sheeting on roof
10 m2
Carpenter 1, Fitter (Blacksmith)
1/2, Labour 2
10. C.I. rain water pipe fixing.
9m
Mason 1/2, Labour 2.5
11. 12mm thk cement plaster
on brickwork in 1:6.
100 m2
Head Mason 1, Mason 10, Labour
14, Bhisti 1
12. Ruled pointing (1:3).
100 m2
Head mason 1/2, Mason 10, Labour
9, Bhisti 1
13. White washing primer coat
and 2 finished coats to
new plaster.
100 m2
Painter 1/2, Labour 2
14. Dry Distemper
100 m2
Painter 8.5, Labour 5.5
15. Plastic Emulsion paint on
new work.
100 m2
Painter 5.5, Labour (Helper) 5.5
16. Primer coat on wood
work/ steel work.
100 m2
Painter 2.5, Labour (Helper) 2.5
17. Panting two coats over
priming coat for new wood
work/steel work.
100 m2
Painter 5.5, Labour (Helper) 5.5
18. Demolishing cement
concrete (1:2:4/1:3:6)
including lead upto 50m.
10 m3
Labour 23
19. Demolishing R.C.C. work
including lead upto 50m.
10 m3
Labour 33.5
20. Demolishing Brickwork in
cement mortar including
stacking of serviceable
material and disposal of
unserviceable materials
within a lead of 50m.
10 m3
Labour 19.5
21. Removing mortar and
cleaning bricks and
stacking cleaned bricks.
10 m3
Mason 6, Labour 25
22. Dismantling doors &
windows including
framing, stacking of
material.
1 no.
Mason 1, Labour 0.20
23. Supplying and fixing
12mn/15mm dia G.I. pipe
with G.I. fittings and M.S.
clamps including cutting
holes in walls and making
good the same
100 r.m.
Fitter 7, Labour (Beldar) 6
24. Supplying, fitting and
laying 25mm G.I pipes
with G.I. fittings including
trenching and refilling of
external work
100 r.m.
Fitter 1, Labour 8
25. Laying, fitting and fixing
100 mm dia G.I. pipes
including testing of joint,
trench cutting for pipe
laying upto a depth of 90
cm. and refilling, dressing
etc.
20 r.m.
Fitter 1.5, Labour 13
26. Supplying, laying, joining
100 dia stoneware pipes
with cement mortar 1:1
(excluding earthwork
etc.).
15 r.m..
Mason 1, Labour 2
27. Wash Basin with C.I.
brackets, brass taps, brass
plug with brass chain,
waste pipe Including
cutting walls and making
good the same.
1 no.
Plumber 1, Mason 1/2, Labour 1
28. Sink.
1 no.
Plumber 1/2, Mason 1/2, Labour 1
29. 9" thick brick flat soling
filled with local sand.
10 m2
Labour 1
30. Earth work for roads
including cutting, loading,
unloading, carrying &
dressing.
10 m2
Labour 4
31. Stone soling for roads
including packing with
smaller stones manually.
10 m3
Labour 7
32. Stone soling for roads
including packing with
smaller stones With steam
roller.
20 m3
Labour 7
33. Surface
dressing/Bituminous
carpeting on roads
100 m2
Labour (for one layer) 10, Labour
(for two layers) 15