Sample for : Pressure Vessel
TABLE OF CONTENT
1. Inspection & Test Plant (ITP)
2. Data Sheet
3. Mechanical Calculation
4. Approved GA Drawing
5. WPS & PQR
6. Welder List & Certificate
7. NDT Procedures
8. NDT Technician Certificate
9. PWHT Procedure (if any)
10. Hydrostatic Test Procedure
11. Welding Map & NDT Map
12. Fit-up & Dimensional Report Before Welding
13. Welding Traceability & NDT Clearance
14. PWHT Report (if any)
15. Final Dimensional Check after Complete Welding
16. Hydrostatic Test Record Mechanical Tools & Equipment
Calibration Report
17. Blasting & Painting Reports
18. Material Verification & Certificate
19. PMI & Hardness Test Report
20. U1 Form
21. Rubbing Name Plate
22. As Built Drawing
Sample for : Piping System
TABLE OF CONTENT
1.
2.
3.
4.
5.
P & ID and Isometric Drawing
Inspection & Test Plant (ITP)
Material Verification & Mill Test Report
Migas approved WPS/ PQR
Migas Approved Welder Certificates
6. Approved NDT Procedure
7. NDT Technician Valid Certificate
8. Passivation Procedure (if any)
9. PMI Procedure (if any)
10.
Test Package
11.
Piping Installation Report
12.
Flushing & Drying Report
13.
Hydrostatic Test Procedure
14.
NDT Clearance
15.
Line Check Report
16.
Passivation Report (if any)
17.
PMI Report (if any)
18.
Equipment Hydrostatic Test Certificates for :
- Pressure Recorder
- Pressure Gauge
- Dead Weight Tester
19.
Hydrostatic Test Report
20.
As Built Drawing
Sample for : Instrument System
TABLE OF CONTENT
1. A Complete set Drawing Scope of Work
- AFC Drawing
- P&ID
2. Inspection & Test Plant (ITP)
3. Instrument Data Sheet
4. Test Bench Report
5. Material Verification & Mill Test Report
6. Tools Calibration Report
7. Catalog/ Brochure and Instruction Manual
Sample for : Rotating Equipment
TABLE OF CONTENT
1. Data Sheet
2. WPS/ PQR
3. Design Drawing :
a. General Assembly, Plan
b. General Assembly, Elevation
4. A Complete set Drawing Scope of Work
5. Hydrostatic Test (casing)
6. Painting Report
7. Alignment Report
8. Cleaning Report
9. Rubbing Name Plate Report
10. EOM
11. FAT Report :
a. Performance Test
b. Mechanical Test
12. Complete Set Document Report
13. As Built Drawing
14. PMI
Sample for : Electrical System
TABLE OF CONTENT
1. A Complete set Drawing Scope of Work
2. Latest Revision MCC Document
3. Pulling Cable Report
4. Megger Test Report
5. Material Verification Report
6. Continuity Test Report
7. Function Test Report
8. Rubbing Name Plate
9. As Built Drawing
Sample for : Coating System
TABLE OF CONTENT
1. A Complete set Drawing Scope Work
2. Client Painting Specification
3. Painting Mgr Data Sheet
4. Material Verification
5. Performance Test Reports
6. Blasting Report
7. Painting Report
8. All Report
Sample for : PSV
TABLE OF CONTENT
1. P & ID Drawing
2. PSV Data Sheet
3. Manufactured Drawing/ Catalogue
4. Mill Certificate
5. Manufactured Inspection Test Report
6. Calibration Certificate
7. Popping Test Report
8. Test Report
9. MDR on Data Book