GAMMON INDIA LTD.
C/o Bhavnagar Energy Company Limited
2x250 MW LIGNITE BASED TPP AT PADVA, BHAVNAGAR
Daily Progress Report
Progress Date: 2/21/2017 Reporting Date: 2/22/2017
Fot the mnt Feb'17
Manpower Report
Upto Previous
Sr. No. Work Description Scope (Approx.) UOM Month Total Cumm. Remarks Remarks
Today Previous Total Cumm. (31-01-17)
Sr.No. Designation
1 Staircase Erection 90 MT 0 2.500 2.500 87.500 90.000 Completed STAFF
2 Handrail Fixation 8550 Rms 0 1850.000 1850.000 6460.000 8310.000 Welding work is in progress. 1 1
Site Incharge/Project Manager
3 Grade Slab Ouside 25 Cum 0 0.000 0.000 17.500 17.500 2 1
Engineers
4 Chimney shell paint out side 13000 Sqm 0 0.000 0.000 13000.000 13000.000 2 0
QA/QC Engineer
5 AWL Fixation 20 Nos 0 0.000 0.000 20.000 20.000 3 2
Adm./Accountant
Staircase Lighting work is in
6 HPSV Lamp Fiaxtion. 116 Nos 0 26.000 26.000 8.000 34.000 4 1
progress. Store Keeper
7 Lightening Arrester 8 Nos 0 0.000 0.000 0.000 0.000 5 Safety 0
Earthing Pit Work is in progress
8 Drain Water Pipe Laying 210 Mts 0 0.000 0.000 210.000 210.000 6 Forman 2
Others 2
7
TOTAL 9
MANPOWER AT SITE (DAY SHIFT)
Mech
1 Supervisor 1
2 Fitter 0
3 rolling operator 0
4 Welder 1
5 Gas Cutter 0
6 Grinder 1
7 Helper 1
8 Rigger 1
9 T. Welder 0
SUB TOTAL 5
Civil
12 Skilled 0
13 Semi Skilled 0
SUB TOTAL 0
electrical
12 Skilled 4
13 Semi Skilled 1
SUB TOTAL 5
Grand Total 10
NOTE: