Gammon India Ltd. C/o Bhavnagar Energy Company Limited 2X250 MW Lignite Based TPP at Padva, Bhavnagar Daily Progress Report

The daily progress report summarizes the work completed on various tasks for a lignite-based thermal power plant project in Bhavnagar, India. It reports that staircase erection is 90% complete, handrail fixation has reached 8310 meters out of 8550 meters, and lighting work like HPSV lamp fixation is ongoing. The manpower details indicate that a total of 10 workers were on site that day, including 5 mechanical workers, 0 civil workers, and 5 electrical workers engaged on various activities of the project.

Uploaded by

saravan1891
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
79 views1 page

Gammon India Ltd. C/o Bhavnagar Energy Company Limited 2X250 MW Lignite Based TPP at Padva, Bhavnagar Daily Progress Report

The daily progress report summarizes the work completed on various tasks for a lignite-based thermal power plant project in Bhavnagar, India. It reports that staircase erection is 90% complete, handrail fixation has reached 8310 meters out of 8550 meters, and lighting work like HPSV lamp fixation is ongoing. The manpower details indicate that a total of 10 workers were on site that day, including 5 mechanical workers, 0 civil workers, and 5 electrical workers engaged on various activities of the project.

Uploaded by

saravan1891
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 1

GAMMON INDIA LTD.

C/o Bhavnagar Energy Company Limited


2x250 MW LIGNITE BASED TPP AT PADVA, BHAVNAGAR
Daily Progress Report
Progress Date: 2/21/2017 Reporting Date: 2/22/2017
Fot the mnt Feb'17
Manpower Report

Upto Previous
Sr. No. Work Description Scope (Approx.) UOM Month Total Cumm. Remarks Remarks
Today Previous Total Cumm. (31-01-17)
Sr.No. Designation

1 Staircase Erection 90 MT 0 2.500 2.500 87.500 90.000 Completed STAFF

2 Handrail Fixation 8550 Rms 0 1850.000 1850.000 6460.000 8310.000 Welding work is in progress. 1 1
Site Incharge/Project Manager

3 Grade Slab Ouside 25 Cum 0 0.000 0.000 17.500 17.500 2 1


Engineers

4 Chimney shell paint out side 13000 Sqm 0 0.000 0.000 13000.000 13000.000 2 0

QA/QC Engineer

5 AWL Fixation 20 Nos 0 0.000 0.000 20.000 20.000 3 2


Adm./Accountant

Staircase Lighting work is in


6 HPSV Lamp Fiaxtion. 116 Nos 0 26.000 26.000 8.000 34.000 4 1
progress. Store Keeper

7 Lightening Arrester 8 Nos 0 0.000 0.000 0.000 0.000 5 Safety 0

Earthing Pit Work is in progress


8 Drain Water Pipe Laying 210 Mts 0 0.000 0.000 210.000 210.000 6 Forman 2

Others 2
7
TOTAL 9

MANPOWER AT SITE (DAY SHIFT)

Mech

1 Supervisor 1

2 Fitter 0

3 rolling operator 0

4 Welder 1

5 Gas Cutter 0

6 Grinder 1

7 Helper 1

8 Rigger 1

9 T. Welder 0

SUB TOTAL 5

Civil

12 Skilled 0
13 Semi Skilled 0
SUB TOTAL 0
electrical

12 Skilled 4

13 Semi Skilled 1

SUB TOTAL 5

Grand Total 10