Integration of Design and Construction of the Tallest Building in
Korea, Tower Palace III, Seoul, Korea
           A.K. Abdelrazaq1, W. F. Baker2, K.R. Chung3, J. Pawlikowski4, Insoo Wang 5, K.S. Yom6
                        1
                           Executive Director, Samsung Corporation, Engineering and Construction Group
                               2
                                 Partner, 4Associate, Skidmore, Owings & Merrill LLP, Chicago, USA
                                3
                                  Principal, Dong Yang Structural Engineering Co., Ltd, Seoul, Korea
                      4
                        Vice President, 5Manager, Samsung Corporation, Construction & Engineering Group
Abstract
Tower Palace III was conceived as a 93-story residential tower soaring 320 meters into Seouls skyline. However,
concerns of the local residents and authorities over the building height resulted in a 73-story tower with the same
gross floor area. The early integration of aerodynamic shaping and wind engineering considerations played a major
role in the architectural massing and design of the tower. The Contractors input in selecting the optimum
structural system resulted in a cost effective tower that served the clients needs and the tower was completed ahead
of schedule. This paper presents a brief overview of the structural system development of the tower and its direct
integration with the construction aspects, discusses the construction planning of the key structural components of
the tower, and briefly describes the monitoring program incorporated into the tower for the evaluation of time
dependent deformation.
Keywords: indirect outrigger belt-wall system, composite column instrumentation, self compacting/consolidating concrete, mat
foundation, wind engineering integration with the architectural massing.
1. Introduction
     Tower Palace III was part of Samsung Life
Insurance Togok site development plan, which is
located in the Kangnam district of Seoul, South Korea
and consisted of three phases. Phases I and II included
Tower Palace I and II development that comprised of
six high-rise residential towers varying from 42 to 66
stories. Phase III of this development, Tower Palace
III (TPIII), consisted of a 73-story single point tower
with an adjacent eight (8) story sport center, and six
(6) levels of parking below grade.
Tower Palace III site development is located in a
moderate wind climate and subject to moderate/low
seismic forces. Early planning and concept envisioned
this tower to be 320 meters high and an all-residential
building. The critical design criteria for this very tall
luxury residential tower called for controlling the
dynamic response of the tower and managing its wind
engineering aspects. During the design process, the
                                                                          Figure 1: Tower Palace Development
building evolved into three different schemes, where
each of the schemes was accepted by the client and              studies indicated that the tower massing, exterior wall
fully studied at the Boundary Layer Wind Tunnel                 treatment, and the dynamic building characteristics
Laboratory (BLWTL), See Figure 2. Force balance                 resulted in a structure that was not sensitive to
                                                                dynamic wind excitations, and the predicted building
Ahmad Abdelrazaq, Vice President / Executive Director           acceleration and torsional velocities were below the
Samsung Corporation, Engineering & Construction Group           internationally acceptable acceleration and torsional
12 flr Samsung Plaza bldg. 263Seohyun, Bundang-Gu,              velocity criteria.
Sungnam-Gu Gyonggi-Do, Korea 463-721                                 While the three schemes had the same gross floor
Tel: 82.2.2145.5190; Fax: 82.2.2145.5770,                       area and approximately the same number of apartment
E-mail, Ahmad.abdelrazaq1@samsung.com                           units, the 93-story tower was not accepted by the
654 CTBUH 2004 October 10~13, Seoul, Korea
neighbors due to its height and the potential for traffic       Structural System Design Approach
congestion in the area. The 73-story tower, scheme 3,               The structural design process of the tower was
was finally selected by the client to satisfy the               formulated based on the following goals:
concerns of the local authorities and the neighbors.
                                                                 Optimize the tower structural system for strength,
                                                                  stiffness, cost effectiveness, redundancy, and speed
                                                                  of construction.
                                                                 Manage and locate the gravity load resisting system
                                                                  so as to maximize its use in resisting the lateral
                                                                  loads while harmonizing with the architectural
                                                                  planning of a luxury residential tower.
                                                                 Incorporate the latest innovations in analysis,
                                                                  design, materials, and construction methods.
                                                                 Limit the building drift, acceleration, and torsional
                                                                  velocity to within the international accepted design
                                                                  criteria.
                                                                 Control the relative displacement between the
                                                                  vertical members, especially for composite
                                                                  buildings.
                                                                 Control the dynamic response of the tower under
                                                                  wind loading by tuning the structural characteristics
                                                                  of the building to improve its dynamic behavior and
 a) 93-Story (320m)   b) 77-Story (270m)   c) 73-Story (264m)
                                                                  to prevent lock-in vibration due to the vortex
     Scheme 1             Scheme 2              Scheme 3
                                                                  shedding. Favorable dynamic behavior of the
     Figure 2: Tower Palace III Massing Studies                   tower was achieved by:
     This paper presents an overview of the                        a) Varying the building shape along the height
development of the towers structural system and its                  while continuing, without interruption, the
direct integration with the architectural massing and                 building gravity and lateral load resisting
construction planning for the key structural                          system;
components of the tower. In addition, this paper                   b) reducing the floor plan along the buildings
briefly discusses the instrumentation of the tower to                 upper zone; and
evaluate the long term behavior of the composite                   c) creating irregularities along the buildings
columns and the reinforced concrete core wall. The                    exterior surfaces, thus reducing the local
strain measurements at the composite columns and the                  cladding pressures as well as the overall
core wall correlated well with the predicted strains.                 wind loads on the building structure.
2. Structural System Design Approach                            Wind Engineering
                                                                     Wind loads considered in the analysis of the tower
                                                                structure were developed using the code defined load
                                                                criteria as well as the results from the wind tunnel
                                                                testing program, which is based on historical
                                                                climatological data. The wind tunnel testing program,
                                                                conducted at the Boundary Layer Wind Tunnel
                                                                Laboratory (BLWTL) included 1) site proximity wind
                                                                analysis model, 2) force balance tests, see Figure 3,
                                                                conducted for all schemes, 3) cladding and pressure
                                                                integration test, and 4) pedestrian wind studies.
                                                                    The climatological study performed for the project
                                                                was determined for a 100 year return period with a
                                                                mean-hourly gradient wind speed of 41 m/s. This
                                                                resulted in a wind pressure of 2.5kN/m2. Strength
                                                                design of the tower was based on both the code-
                                                                prescribed wind loads with exposure A and the wind
 93 Story Tower       77 story Tower       73 story Tower       tunnel developed 100-year return period. Wind tunnel
                                                                recommendation included combining the wind loads in
         Figure 3: Wind Tunnel Test Models
                                                                           CTBUH 2004 October 10~13, Seoul, Korea   655
the orthogonal direction and torsional moments                  A 3-dimensional finite elements analysis model,
simultaneously. 1.5% and 2% damping were assumed            using FLAC 3D, was utilized to model the entire rock
for serviceability and strength design respectively.        mass/foundation mat in order to better estimate the
                                                            foundation settlement and behavior. See figure 4.
Seismic Considerations
                                                                 Two FLAC3D foundation analysis models were
     TPIII is located in an area with low seismic
                                                            performed to evaluate the impact of the faults on the
activity and the building is essentially founded on rock
                                                            settlement analysis. Comparison of the analysis results
foundation with locally fractured and weak layers of
                                                            between the two models indicated that the overall
rocks. The seismic behavior and response of the tower
                                                            building settlement was increased by approximately
was evaluated using the modal response spectrum
                                                            23% due to the presence of the faults.
analysis method. Response spectrum curves and
loading conditions required by the Korean Building
                                                                 Because of the variation of the rock quality, the
Law were utilized as a base for the seismic loading
                                                            presence of faults, and the shape of the
conditions. Since the building is very tall and flexible,
                                                            building/structure, it was prudent to utilize a mat
the tower was controlled by wind design rather than
                                                            foundation system under the tower footprint in order to
seismic design except at the top of the building, where
                                                            minimize the differential settlement, reduce the impact
the whip lash effects generated forces that are slightly
                                                            of the differential settlement on the superstructure
higher than the wind forces. The overall building drift
                                                            member design, and to bridge over the local weak rock
and interstory drift met the Korean and UBC 97
                                                            layers and pockets. Based on the 3DFLAC settlement
building code requirements.
                                                            analysis model, Dames & Moore provided the soil
                                                            stiffness that was utilized as a basis for soil-structure
                                                            analysis model of the tower.
  Figure 4: FLAC3D- Foundation Analysis model
                    (Courtesy of Dames & Moore)             Figure 5: Soil Structure Interaction Analysis Model
Foundation System Considerations
     The tower superstructure is founded on a 3500              The mat foundation analysis indicated that the
mm high performance reinforced concrete mat over            maximum anticipated settlement under the tower
lean concrete slab over prepared rock. The rock             would be approximately 15mm. The building survey
quality and mechanical characteristics varied over the      indicated that the actual foundation settlement was
site in general and in particular at the footprint of the   smaller than anticipated.
tower due to the presence of ancient faults and shear
zones.       These faults/shear zones started at            Differential Axial Shortening Considerations
approximately 7 meters north of the foundation mat to           While optimizing the lateral load resisting system
approximately 150 meters below the south edge of the        of the tower, minimizing the differential shortening,
foundation mat. The presence of these fault caused          between the composite columns and the core wall, was
concerns about the behavior of the foundation system.       one of the critical issues considered during the
The geotechnical engineering work, performed by             development of the structural system of the tower.
Dames and Moore, San Francisco, CA, USA, indicated
that these faults are inactive.
656 CTBUH 2004 October 10~13, Seoul, Korea
                                            55 Belt Wall
                                            Exterior
                                            Columns
                                                             Exterior                                R/C Core
                                                             Columns                                 Wall System
                                            16 Belt Wall
                                                             Interior                                Composite
                                                             Columns                                 Floor Framing
                                            Core Wall
                                            Mat
                                            Foundation
            a) Structural System Diagram                                          b) Floor Framing Plan
                      Figure 5: Structural System Diagram & Typical Floor Framing Plan
3. Structural System Description                           components, which included the belt wall and the floor
                                                           slabs.
Floor Framing System
     Several Floor framing system were considered for      The core wall system
the tower, including a flat plate system and composite         While the exterior flanges of the core wall vary in
steel framing.     However, because of the client          thickness from 550 mm at the bottom to 400 mm at the
marketing requirements, a composite floor framing          top, the interior core wall web thicknesses were
system was selected. The composite floor framing           maintained at 300mm throughout the building height.
system consisted of a 150mm composite metal deck           In a typical level, the core wall vertical wall
slab spanning 3 to 4 meters between 400mm deep hot         components are rigidly connected by a series of
rolled composite steel beams, see Figure 5. The            750mm deep composite or reinforced concrete link
400mm beam depth was selected to allow for MEP             beams. The link beam widths typically match the
openings so that the ceiling sandwich is minimized.        adjacent core wall thicknesses.
The composite structural steel beams were arranged to
reduce the number of embedded plates into the core
wall and were fireproofed with cementitious material
to achieve the applicable fire rating.
Lateral Load Resisting System
    The lateral load resisting system of the tower
provided resistance to wind and seismic forces and
consisted of a high performance, reinforced concrete
core wall system, from the foundation to the roof that
was linked to the exterior composite columns by an
indirect outrigger belt wall system at the mechanical
levels (16 to 17, and 55 to 56). The interaction of the
core wall system and the exterior columns was
provided through deformation compatibility, resulting
in significant forces in the belt wall system                           Figure 6: Composite Link Beam Details
                                                                        CTBUH 2004 October 10~13, Seoul, Korea   657
      Figure 7: Belt wall system load flow diagram between the core wall and the exterior belt wall system
     Due to the link beam depth limitations, a             core walls throughout the building life, and during the
composite structural steel beam was introduced at the      construction period.
locations where large shear and bending moment
forces existed. See Figure 6. The composite link           The indirect outrigger belt wall system
beam consisted of a built-up wide flanged structural           The indirect outrigger belt wall system is
steel beam or a single structural steel plate that were    essentially similar to an outrigger wall system;
embedded in the concrete section. The structural steel     however, the mechanism of force resolution between
web section, where required, was designed to resist the    the core wall and the belt wall system is indirect,
majority of the shear forces and the composite section     through the floor slabs rather than the direct wall
was utilized in resisting the bending moments. Since       connection. The indirect outrigger belt wall system
the composite link beam section provides significant       consists of an exterior reinforced concrete perimeter
shear ductility, the bending moment forces in the link     wall that rigidly connects the exterior composite
beams can be limited. Thus the maximum forces that         columns and the very stiff floor slabs.
the core wall system can attract in a seismic event can
                                                                The indirect outrigger belt walls for TPIII were
be managed, and the overall building behavior can be
                                                           located at the mechanical levels (16 and 55) and
controlled without significant damage even in severe
                                                           consisted of an 800mm wide by 8 meter high wall
seismic event.
                                                           perimeter wall and a 300mm thick floor slabs, at the
                                                           top and the bottom of the perimeter walls. While the
The exterior columns
                                                           high perimeter belt wall bending and shear stiffness
     The exterior columns of the tower are typically
                                                           connected the exterior composite columns rigidly, the
steel reinforced concrete columns (SRCC) that vary
                                                           floor slab high in-plane bending and shear stiffness
from 1350mm Diameter at subgrade levels, to a
                                                           forced deformation compatibility and shear force
maximum of 1000x1000 from levels 4 to 56, to
                                                           redistribution between the core wall and the exterior
900x900 from level 57 to 65, to 800x800 from the 66
                                                           belt wall frame system.
level to the roof. In order to minimize the column size,
concrete filled (CFT) with high strength concrete was           Since the perimeter belt walls reduced the relative
considered for the exterior and interior columns at the    displacements between floors, the lateral system
conceptual design stage. However, SRC columns were         rotations at the belt wall levels were significantly
adopted instead, in order to minimize the differential     reduced, and thus reducing the building lateral
relative movement, due to immediate and long term          displacement significantly. The restraining effects of
deformations, between the exterior columns and the         the exterior columns against the belt wall rotation
                                                           resulted in axial loads in the exterior columns. These
658 CTBUH 2004 October 10~13, Seoul, Korea
axial forces were counter balanced by force couples          saving in casting time by placing the mat in a
into the belt wall system, which were then counter            single pour and within 12-hours;
balanced by force couples into the slabs that are finally    reduction of labor force;
resisted by the interior core wall system.                   consistent concrete quality and uniformity,
    The advantages of the indirect outrigger belt wall        especially in areas with high rebar congestion.
system over a more conventional direct outrigger wall        Increasing the concrete bond to rebar due to the
system can be summarized as follows:                          elimination of bleeding under rebar;
                                                             reduction of concrete bleeding;
 Placement of the belt wall system at the perimeter         eliminating the vibration noise.
  did not restrict the mechanical floor space and
  allowed for freedom in placing the mechanical
  equipment in the plant space, thus reducing the
  amount of coordination work required between
  trades.
 The Construction of the belt wall system was not
  in the construction schedule critical path;
 The belt system did not have a direct link between
  the core wall and the exterior columns, and
  therefore eliminated one of the most difficult
  technical problems encountered in the design and
  detailing of the direct outrigger wall systems,
  which is the potential of generating large forces
  due to the differential movement between the core
  wall and the exterior columns; and                                                                   Figure 8: Casting the foundation mat
 The extensive detailing and construction sequence
  work required for the direct outrigger wall system             A cooling pipe system was suggested by the
  is significantly reduced.                                 contractor to control the heat of hydration for the
                                                            massive mat concrete pour and to reduce the curing
4. Construction Planning                                    time. The curing time was reduced from 45 days to 15
                                                            days and the maximum temperature at the center of the
     Samsung Construction was involved with the             mat was reduced from 93oC to 82oC. The maximum
design team from the early design stage in evaluating       differential temperature between any two points within
all building systems (structural, architectural, building   the mat was less than 20 oC.
services, etc.). Alternate systems and details were
discussed and incorporated in the construction
documents. In addition, the General Contractor issued                                     90
                                                                                                                                        Hydration Analysis
                                                                                                                                                                                          A
                                                                                                                                                                                          B
a detailed construction and design schedule that was                                      80                     B
                                                                                                                                   C
                                                                                                                                                                                          C
utilized by the design team as a base for providing the                                   70
                                                            Temperature ( C)
necessary documents on time so that the General                                           60                             A
Contractor could proceed early in the construction                                        50
                                                                                                                                    o                                                                                                                                                           
                                                                                                                ambient+20 C
planning and work. The core and shell of the 73 story                                     40
tower and the six (6) subgrade levels were completed                                      30
                                                                                                                ambient
in approximately 18 months. The entire project was                                        20
completed in 28 months, including the residential fit-                                    10
                                                                                               0   1        2        3       4      5         6    7      8        9    10     11    12   13    14    15
out space and finishing work. A 3-day cycle was                                                                                               Time (days)
utilized for the tower superstructure and all subsequent                                1 00
                                                                                                                                                                       Actual Temperature
construction activities.                                                                 90
                                                                                         80
                                                                                                                                                  C enter
                                                                                         70
                                                                      Tem perture ()
Mat Foundation Construction                                                              60                     T op              0. 5m from top
     The tower is founded on 3500mm thick, 40Mpa                                         50
reinforced concrete mat. The mat foundation system                                       40
                                                                                         30
                                                                                                                         a m b ient
required significant planning effort while preparing for                                 20
the 8000 cubic meter pour of high performance                                            10
                                                                                                   20H           52H                    96H             139H       163H 177H                   240H
concrete. See Figure 8. The General Contractor used                                       0
                                                                                               0       24        48          72          96       12 0      14 4       16 8    192    216      2 40
self-compacting self-consolidating concrete (SCC) for                                                                                             T im e (h)
the mat foundation. The advantages of using SCC                                                Figure 9: Hydration analysis and measurement
included:
                                                                                                         CTBUH 2004 October 10~13, Seoul, Korea                                                 659
     The cooling pipe system consisted of 25mm
stainless steel coils that were spaced vertically at
750mm on center, and horizontally at approximately
1500mm on center, at 128 locations. , The water flow
rate in the cooling pipe system was limited 18
liters/min. The cooling pipes were connected to a
central cooling tower, located at the job site, which
was used to temper the water. The water entered the
cooling pipe system at 34oC, existed at 47oC.
Comparison between the predicted and the actual
temperature of the mat, due to heat generated by the                                                  Steel Erection
hydration process, confirmed that the predicted heat of        Tier N
                                                                                                      Plumbing
                                                                                                      Bolting,
hydration analysis results were consistent with the                                                   W ldi
actual temperature of the mat. Thus testifying to the
already established analysis procedures utilized for                                                  Decking
predicting the heat of hydration of mass concrete.              N-1                                   Stopper
                                                                                                      Stud Bolt
Core Wall Construction
    Figures 10 and 12 depict the construction                                                         MEP work
sequence of the tower and shows that the reinforced             N-2                                   Reinforcing
                                                                                                      Conc casting
concrete core wall is constructed at four (4) floors
ahead of the structural steel framing. The core wall
and the structural steel construction is followed by the        N-3
                                                                                                      Curtain wall
                                                                                                      Fire proofing
composite deck placement, the floor slab concrete
pouring, the MEP system installation, and finally the
exterior cladding system installation. The central core
wall construction utilized a climbing formwork system             Figure 10: Tower Construction Sequence
designed and provided by Doka (DOKA SKE 100).
                                                            shrinkage effects, because of the restraining effects of
Structural Steel Erection and Floor Framing                 the core wall and the exterior belt wall system.
     The structural steel erection of the tower was
divided into 3 wings. In order to reduce the structural     Major Equipment
steel erection time and to improve the construction             Three (3) self climbing cranes, supported directly
cycle, all the steel columns were erected as four story     by the core wall, were utilized for the tower
tiers, and the five (5) different balcony framing around    construction.     Two concrete pumps (one for
the perimeter of the building were prefabricated and        emergency) were available at the site and were used
erected as single units. This erection sequence reduced     for concrete placement. All concrete was pumped
the number of pieces handled at the site. Each tier         from the ground level to approximately 264m above
consisted of four (4) floors and all the structural steel   the ground.
in these floors were erected in 12 days, thus resulting
in 3-day cycle. The concrete slab, at a typical floor,
                                                            5. Axial Shortening of the Tower
was divided into 3 equal pours, one for each wing.
Belt Wall Construction                                          One of the key issues considered during the
     Because of the complex behavior of the belt wall       development of the structural system of the tower was
system, the size of the concrete pour, and the geometry     the differential shortening between the core wall and
of the tower, the project called for special detailing,     the exterior/interior composite columns during
construction sequence, and construction planning            construction and after significant completion time of
effort. Discussion between the General Contractor and       the project. The complex behavior of the composite
the design team resulted in eliminating the belt wall       columns called for special considerations in
construction sequence from the construction schedule        calculating the elastic and long term deformation for
critical path. Construction sequence analysis of the        the core wall and the exterior columns. The axial
tower was performed and its impact on the building          shortening of the building was done using the state of
design was incorporated into the design process.            the art ACI 209 committee draft report for predicting
While the belt wall system was cast in two separate         the creep, shrinkage and temperature effects of
pours, the floor slabs were cast in three different pours   reinforced concrete structures. This draft report is
at each floor in order to eliminate the potential for       based the Gardner-Lockman GL2000 Model, which is
axial load cracking in the slabs, resulting from            based on RILEM base of test data.
660 CTBUH 2004 October 10~13, Seoul, Korea
    The predicted composite columns and core wall              At TPIII, several high frequency strain gages were
axial shortening by the new analysis program were         installed at several SRC columns and at two locations
compared to the actual in-situ strain measurements at     in the core wall at several floors. These strain gages
TPIII, and was found to correlate well, thus testifying   were connected to a single data logger from which the
to the accuracy of the new analysis models and            information has been down loaded automatically for
approach in predicting the time dependent deformation     processing by the researchers and the design team.
for axially loaded members. See Figures 11 for
                                                              In addition to the in-situ elastic and inelastic time
comparison of the predicted strain to the actual
                                                          dependent deformation monitoring programs, a
measured strain.
                                                          monitoring program has been installed to monitor the
                                                          building dynamic response to dynamic excitations,
                                                          especially as it relates to wind effects. It is anticipated
                                                          that the instrumentation programs will be expanded
                                                          and integrated into a single system that could
                                                          essentially provides a health monitoring program to the
                                                          building structure, which could finally be integrated
                                                          with the permanent intelligent building system.
     Figure 11: Measured vs. predicted strains at a
                typical Interior composite column
   Figure 12: Measured vs. predicted strain at
         reinforced concrete core wall
     A compensation program was developed to make
up for the overall building shortening and the              Figure 12: In progress construction of the tower
differential shortening between the columns and the          showing the construction methods of the tower.
core wall. The building shortening was calculated to
be between 270mm to 300mm for the core wall and           6. Conclusion
the exterior columns respectively. However, the
maximum differential shortening, at level 60, between         This paper provided a brief overview of some of
the columns and the core wall was estimated to be         the issues considered in developing the structural
40mm, at the completion of the building, and 20mm         systems and construction planning of Tower Palace III,
after 20 years. Therefore, the column elevations were     the tallest building in Korea.       The monitoring
adjusted during construction for 20mm so the relative     programs incorporated into the design of the tower are
movement between the core wall and the columns            very unique, could provide invaluable information and
would be limited to a maximum of 20mm. The actual         reference to the engineering community, and should be
measured differential shortening between the core wall    considered as part of the intelligent building
and the exterior columns have been found to be less       system of important building in the world. Tower
than the predicted shortening.                            Palace III is a landmark tower for the city of Seoul.
                                                                      CTBUH 2004 October 10~13, Seoul, Korea      661