100% found this document useful (1 vote)
608 views2 pages

09 Failure Inspection Report

The inspection report summarizes a failure of a rig water cooling system motor that occurred on February 21, 2017 at location BB-25. The bearing was found to be damaged, likely due to long operating hours. It was concluded that the motor could no longer function properly. The report recommends replacing the pump due to its long lifespan and previous repairs to seals.

Uploaded by

Fuad
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
608 views2 pages

09 Failure Inspection Report

The inspection report summarizes a failure of a rig water cooling system motor that occurred on February 21, 2017 at location BB-25. The bearing was found to be damaged, likely due to long operating hours. It was concluded that the motor could no longer function properly. The report recommends replacing the pump due to its long lifespan and previous repairs to seals.

Uploaded by

Fuad
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

2 of 1 Page

ENGINEERING &
NUS-QP-OP-
.Doc. No MAINTENANCEPROCEDURE
MNT/09
01 Rev
MAINTENANCE PROCEDURE
01/08/2016 Date

Failure Inspection Report


Date: 2/21/2017 Rig No.: S_04

Location: BB-25 Inspected Unit: Rig water cooling


system motor
S/ No.: Operating HRS:

Failure Description:
Rig water cooling system motor stopped working .

InspectionFindings:

Bearing is damaged

Probable and Root Cause (s) for the Failure:

Long time working hours

Conclusion:
The motor cant work

Comments and Recommend


it was already fixed and had a total repair for seals due to
that and the long life it had THE PUMP NEEDS TO BE
CHANGE

Inspected by: Signature:


Abubakr abdelbagi Abubakr abdelbagi
2 of 2 Page
ENGINEERING &
NUS-QP-OP-
.Doc. No MAINTENANCEPROCEDURE
MNT/09
01 Rev
MAINTENANCE PROCEDURE
01/08/2016 Date

**Use Additional Page (s) for Demonstrative Photos,


Sketches, Drawings or Others.

You might also like