Activities Summary: - End of February

The document provides status updates for plumbing works at three buildings in February and March. In February, Building 2 had the most progress with 40% of below ground piping works completed. For the first week of March, the plan was to reach 60% completion for most piping activities in all buildings. By the end of the first week, Building 2 had 80% of below ground piping works done. The plan for the second week of March was to reach 100% completion for piping works in all buildings. No updates were provided for achievements in the second week.

Uploaded by

Neal Johnson
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
30 views3 pages

Activities Summary: - End of February

The document provides status updates for plumbing works at three buildings in February and March. In February, Building 2 had the most progress with 40% of below ground piping works completed. For the first week of March, the plan was to reach 60% completion for most piping activities in all buildings. By the end of the first week, Building 2 had 80% of below ground piping works done. The plan for the second week of March was to reach 100% completion for piping works in all buildings. No updates were provided for achievements in the second week.

Uploaded by

Neal Johnson
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 3

Activities Summary

-----End of February

PLUMBING WORKS:- (as on 28.02.2017)

Building Building Building


S. No Activity Description
No.1 No.2 No.3
1 BELOW GROUND PIPING WORKS 10% 40% %20
2 BLOCKWALL CHASING & MARKING 0% 4% %1

3 HIGHER LEVEL DRAINAGE PIPE WORKS 0% 2% 2%

4 CONCEALED DRAINAGE PIPE WORKS 0% 4% %0

5 H/L WATER SUPPLY PIPE WORKS 0% 0% %0


CONCEALED WATER SUPPLY
6 0% 4% %0
PIPEWORKS
7 SANITARYWARES FIXING 0% 4% %0

8 PUMPROOM & WATER TANK AREA S.N %2 S.N


9 ROOF @WORKS 0% 0% %0

*N.S----No Service
MARCH (1st Week)
Activities Planned for the Week (01.03.17 to 08.03.17)
Building Building Building
S. No Activity Description
No.1 No.2 No.3
1 BELOW GROUND PIPING WORKS %60 60% 60%
2 BLOCKWALL CHASING & MARKING 10% 10% %10
3 HIGHER LEVEL DRAINAGE PIPE WORKS 10% 10% 10%
4 CONCEALED DRAINAGE PIPE WORKS 10% 10% %10
5 H/L WATER SUPPLY PIPE WORKS 10% 10% %10
6 CONCEALED WATER SUPPLY PIPEWORKS 10% 10% %10
7 SANITARYWARES FIXING 0% 4% %0
8 PUMPROOM & WATER TANK AREA N.S %10 N.S
9 ROOF @WORKS 0% 0% %0

PLUMBING WORKS:- (as on 08.03.2017)


Building Building Building
S. No Activity Description
No.1 No.2 No.3
1 BELOW GROUND PIPING WORKS %30 80% 70%
2 BLOCKWALL CHASING & MARKING 2% 6% %4
3 HIGHER LEVEL DRAINAGE PIPE WORKS 4% 10% 10%
4 CONCEALED DRAINAGE PIPE WORKS 2% 6% %4
5 H/L WATER SUPPLY PIPE WORKS 0% 4% %0
6 CONCEALED WATER SUPPLY PIPEWORKS 0% 4% %0
7 SANITARYWARES FIXING 0% 4% %0
8 PUMPROOM & WATER TANK AREA N.S %2 N.S
9 ROOF @WORKS 0% 0% %0

`
MARCH (2ND Week)

Activities Planned for the Week (09.03.17 to 16.03.17)


S. Building Building Building
Activity Description
No No.1 No.2 No.3
1 BELOW GROUND PIPING WORKS %100 100% 100%
2 BLOCKWALL CHASING & MARKING 20% 20% %20
3 HIGHER LEVEL DRAINAGE PIPE WORKS 20% 20% %20
4 CONCEALED DRAINAGE PIPE WORKS 20% 20% %20
5 H/L WATER SUPPLY PIPE WORKS 20% 20% %20
6 CONCEALED WATER SUPPLY PIPEWORKS 20% 20% %20
7 SANITARYWARES FIXING 0% 4% %0
8 PUMPROOM & WATER TANK AREA N.S %10 N.S
9 ROOF @WORKS 0% 0% %0
`
MARCH (2ND Week)

Activities Achieved for the Week (09.03.17 to 16.03.17)

S. Building Building Building


Activity Description
No No.1 No.2 No.3
1 BELOW GROUND PIPING WORKS
2 BLOCKWALL CHASING & MARKING
3 HIGHER LEVEL DRAINAGE PIPE WORKS
4 CONCEALED DRAINAGE PIPE WORKS
5 H/L WATER SUPPLY PIPE WORKS
6 CONCEALED WATER SUPPLY PIPEWORKS
7 SANITARYWARES FIXING
8 PUMPROOM & WATER TANK AREA
9 ROOF @WORKS