CONSTRUCTION
CONTRACTS DOCUEMENTS
                   BY
                LECTURER
             Maha Muhaisen
    APPLIED CIVIL ENGINEERING DEPT
CONSTRUCTION
 DOCUMENTS
            CONSTRUCTION
             DOCUMENTS
Contract documents (graphic and written) describe the proposed
construction (the ‘Work’) that results from performing services, furnishing
labor, and supplying and incorporating materials and equipment into the
construction
A.   Contract Forms
B.   Conditions of the Contract
C.   Specifications & BOQ
D.   Drawings
E.   Addenda
F.   Change Orders
      A. CONTRACT FORMS
 CONTRACT FORMS
    Acceptance Letter
    Agreement
     Performance Bond
     Payment Bond
     Certificates
     B.CONDITIONS OF CONTRACT
CONDITIONS OF CONTRACT
 Define basic rights, responsibilities, and relationships of the parties involved in
the construction project.
 2 types: General Conditions and Supplementary Conditions
GENERAL CONDITIONS
     General clauses that establish how the project is to be administered.
     Contain basic expressions of rights, duties, and limitations of the entities
    involved.
     Usually in the form of published standard documents that include principles
    common to most construction Contracts.
    SUPPLEMENTARY CONDITIONS
     Modify or supplement general conditions as need to provide for
    requirements specific to a project They are not standardized documents and
               A.1         Agreement
    The written document signed by the owner and the
    contractor that is the legal instrument binding the parties
    to the contract.
     Defines the relationship and obligations between owner
    and contractor.
   The agreement is quite brief and appears to consist
    mostly of statements of fact, whereas the general
    conditions section deals primarily with matters that
    pertain generally to be construction work and the
    persons involved.
   In other words, the agreement appears to consist of
    statements and the general conditions appear to be
    t             diti
                  Acceptance letter
   Sent to contractor before the signing the contract
   Mention to the contractor offer, and assure the commitment of the
    contractor
   The owner express his acceptance to the contractor offer as it was
    in the form of bid offer, and ask the contractor to start preparation of
    the legal and technical steps as it is stipulated in the contract.
   Signing the authorized signatory and then the contractor is invited to
    submit performance security and signing the contract.
   See example of acceptance letter
                  AGREEMENT
   The agreement should contain:
   The names of contracting parties
   A brief description of the work
   A list of contract documents, including agreement,
    general conditions, drawings, and specifications.
   The contract sum, or amount (lump-sum contract)
   The procedures for payment
   The contract time, or dates for start and completion
   The signatures of contracting parties and witnesses
   International construction documents are also often
    based on industry-prepared standard forms.
          AGREEMENT FORM
   A number of organizations prepare recommended
    standard general conditions and associated forms. Such
    as:
      ENAA (Engineering Advancement Association of
       Japan)
      FIDIC (International Federation of Consulting
       Engineers)
      ICE (Institute of Civil Engineers, United Kingdom)
      JCT (Joint Contracts Tribunal)
 SEE ATTACHED            WORD FILE FOR
    EXAMPLES
       A.2 .Bonds / Guarantees FORMS
1-        PERFORMANCE BOND / security
The Contractor, upon receiving the Letter of Acceptance, shall obtain and provide to the
     Employer before signing the Contract, the Performance Guarantee in the value of
     ten percent of the Contract Sum, as a guarantee of the proper execution of the
     Works in accordance with the Contract. This guarantee shall be issued by a
     licensed bank or financial institution acceptable to the Employer. The guarantee
     shall be prepared in the form included in part B of these conditions. The obtaining
     of such guarantee shall in all respects be at the expense of the Contractor.The
     Performance Security shall be provided to the Employer no later than the date
     specified in the Letter of Acceptance and shall be issued in an amount specified in
     the PCC (particular conditions of contract), by a bank or surety acceptable to the
     Employer, and denominated in the types and proportions of the currencies in which
     the Contract Price is payable.
The Performance Security shall be valid until a date 28 days from the date of issue of the
     Certificate of Completion in the case of a Bank Guarantee, and until one year from
     the date of issue of the Completion Certificate in the case of a Performance Bond.
     Advanced PAYMENT BOND
   Provide a guarantee that subcontractor, material suppliers, and
    others providing labor, material goods, and services to the project
    will be paid.
          • The Employer shall make advance payment to the Contractor
            of the amounts stated in the PCC by the date stated in the
            PCC, against provision by the Contractor of an Unconditional
            Bank Guarantee in a form and by a bank acceptable to the
            Employer in amounts and currencies equal to the advance
            payment. The Guarantee shall remain effective until the
            advance payment has been repaid, but the amount of the
            Guarantee shall be progressively reduced by the amounts
            repaid by the Contractor. Interest shall not be charged on the
            advance payment.
      • The Contractor is to use the advance payment only to pay for
        Equipment, Plant, Materials, and mobilization expenses
        required specifically for execution of the Contract. The
        Contractor shall demonstrate that advance payment has
        been used in this way by supplying copies of invoices or
        other documents to the Project Manager.
   The advance payment shall be repaid by deducting
    proportionate amounts from payments otherwise due to the
    Contractor, following the schedule of completed percentages of
    the Works on a payment basis. No account shall be taken of the
    advance payment or its repayment in assessing valuations of
    work done, Variations, price adjustments, Compensation Events,
    Bonuses, or Liquidated Damages.
          Defect liability Security
 After primary taking over, 5% guarantee is
  submitted to employer for defect liability,
  valid for 365 days or as stipulated in PCC.
           INSURANCE Certificates
   Insurance for Works and Contractor’s Equipment,
   Insurance against Injury to Persons and Damage to
    Property ,
   Insurance for Contractor’s Personnel
        Lecture (6), (7), (8)
 Conditions   of the contract
 General Conditions of contract
 Theconditions are intended to govern and
 regulate the obligation of formal contract.
 Although  the headings and topics included
 within different sets of GCC vary, there is a
 certain similarity of subject matter
                  Contents of GCC
   Definitions
   Contract documents
   Rights and responsibilities of owner
   Duties and authorities of engineer
   Rights and responsibilities of contractor
   Sub-contractor, Separate contractors
   Time
   Payments and completions
   Changes in the work
   Protection of persons and property
   Insurance and bond
   Disputes
   Termination of contract
   Miscellaneous provisions
            FIDIC , AN INTRODUCTION
   Founded in 1913
   Expanded in 1945 to include 40 national associations
   Published first Conditions of Contract in 1957
   In 2004 has 64 member associations
   Headquarters in Switzerland
   Web Site : www.fidic.org
        FIDIC , AN INTRODUCTION
 Pre  1957 – no internationally recognised
  contract conditions
 First “red book” based on UK ICE
  conditions
 FIDIC has international committees to
  improve contracts
   Contract Documents 1999
 Conditions  of Contract for Construction
  (Red Book)
 Conditions of Contract for Plant & Design
  Build (Yellow Book)
 Conditions of Contract for EPC Turnkey
  Projects (Silver Book)
 Short Form of Contracts (Green Book)
     FIDIC Document Usage
      Conditions of Contract for
            Construction
 Works designed by Employer or Engineer
 Contractor Constructs in accordance with
  designs provided
 May include some design elements
         FIDIC Document Usage
Conditions of Contract for, Plant & Design
                 Build
 Electrical
           & Mechanical Plant
 May include building and engineering
 Design & Execution of works
 Contractor designs and constructs in
  accordance with Employer’s Requirements
 Engineer Administers
     FIDIC Document Usage
          Short Form of Contract
 Small capital value projects
 Simple content
 Contractor constructs to Employer’s
  designs
 No “Particular Conditions”
 No “Impartial” Engineer
Typical sequence of Principal
  Events during Contracts
     Typical sequence of Payment Events
     envisaged in Clause 14(contract price
                and payment)
              14.3 Contractor           14.6 Employer              14.7 Employer
              submits                   gives Contractor           makes the
              Statement to the          notice of amount           payment to the
              Employer                  considered due             Contractor
                                      <56d
Each of the
monthly (or
otherwise)
interim                 <28d
payments
The final       Employer verifies the draft final statement, Contractor
payment                          submits information
                                                                                               <42d
              14.11 Contractor submits                                    14.11 Contractor            14.7 employer
              draft final statement to the                                submits Final Statement     makes payment
              Employer                                                    and the 14.12 discharge
 Typical sequence of Dispute
Events envisaged in Clause 20
  DAB: the persons so named in the contract or other persons
  appointed under sub-clause (appointment of the dispute
  adjudication board)
   FIDIC conditions of contract
1 GENERAL PROVISIONS
2 THE EMPLOYER .
3 THE ENGINEER
4 THE CONTRACTOR
5 NOMINATED SUBCONTRACTORS
6 STAFF AND LABOUR
7 PLANT, MATERIALS AND WORKMANSHIP
8 COMMENCEMENT, DELAYS AND SUSPENSION
9 TESTS ON COMPLETION
10 EMPLOYER’S TAKING OVER .
11 DEFECTS LIABILITY
12 MEASUREMENT AND EVALUATION
  FIDIC conditions of contract
           (cont’d)
13 VARIATIONS AND ADJUSTMENTS
14 CONTRACT PRICE AND PAYMENT
15 TERMINATION BY EMPLOYER
16 SUSPENSION AND TERMINATION BY CONTRACTOR
17 RISK AND RESPONSIBILITY
18 INSURANCE
19 FORCE MAJEURE
20 CLAIMS, DISPUTES AND ARBITRATION
    FIDIC conditions of contract
1 GENERAL PROVISIONS
1.1 Definitions
1.2 Interpretation
1.3 Communications
1.4 Law and Language
1.5 Priority of Documents
1.6 Contract Agreement
1.7 Assignment
1.8 Care and Supply of Documents
1.9 Delayed Drawings or Instructions
1.10 Employer’s Use of Contractor’s Documents
1.11 Contractor’s Use of Employer’s Documents
1.12 Confidential Details
1.13 Compliance with Laws
1 14 J i t d S        l Li bilit
    FIDIC conditions of contract cont’d
2 THE EMPLOYER .
2.1 Right of Access to the Site
2.2 Permits, Licenses or Approvals
2.3 Employer’s Personnel
2.4 Employer’s Financial Arrangements
2.5 Employer’s Claims
3 THE ENGINEER
3.1 Engineer’s Duties and Authority
3.2 Delegation by the Engineer
3.3 Instructions of the Engineer
3.4 Replacement of the Engineer
3.5 Determinations
    FIDIC conditions of contract cont’d
4 THE CONTRACTOR
4.1 Contractor’s General Obligations
4.2 Performance Security
4.3 Contractor’s Representative
4.4 Subcontractors
4.5 Assignment of Benefit of Subcontract
4.6 Co-operation
4.7 Setting Out
4.8 Safety Procedures
4.9 Quality Assurance
4.10 Site Data
4.11 Sufficiency of the Accepted Contract Amount
4.12 Unforeseeable Physical Conditions
4.13 Rights of Way and Facilities
4.14 Avoidance of Interference
4.15 Access Route
4.16 Transport of Goods
4.17 Contractor’s Equipment
4.18 Protection of the Environment
4.19 Electricity, Water and Gas
4.20 Employer’s Equipment and Free-Issue Material
4.21 Progress Reports
4.22 Security of the Site
4.23 Contractor’s Operations on Site
4.24 Fossils
5 NOMINATED SUBCONTRACTORS
5.1 Definition of “nominated Subcontractor”
5.2 Objection to Nomination
5.3 Payments to nominated Subcontractors
5.4 Evidence of Payments
6 STAFF AND LABOUR
6.1 Engagement of Staff and Labour
6.2 Rates of Wages and Conditions of Labour
6.3 Persons in the Service of Employer
6.4 Labour Laws
6.5 Working Hours
6.6 Facilities for Staff and Labour
6.7 Health and Safety
6.8 Contractor’s Superintendence
6.9 Contractor’s Personnel
6.10 Records of Contractor’s Personnel and Equipment
6.11 Disorderly Conduct
6.12 Foreign Personnel
6.13 Supply of Foodstuffs
6.14 Supply of Water
6.15 Measures against Insect and Pest Nuisance
6.16 Alcoholic Liquor or Drugs
6.17 Arms and Ammunition
6.18 Festival and Religious Customs
6.19 Funeral Arrangements
6.20 Prohibition of Forced or Compulsory Labor
6.21 Prohibition of Harmful Child Labour
6.22 Employment Records of Workers
7 PLANT, MATERIALS AND WORKMANSHIP
7.1 Manner of Execution
7.2 Samples
7.3 Inspection
7.4 Testing
7.5 Rejection
7.6 Remedial Work
7.7 Ownership of Plant and Materials
7.8 Royalties
8 COMMENCEMENT, DELAYS AND SUSPENSION
8.1 Commencement of Works
8.2 Time for Completion
8.3 Programme
8.4 Extension of Time for Completion
8.5 Delays Caused by Authorities
8.6 Rate of Progress
8.7 Delay Damages
8.8 Suspension of Work
8.9 Consequences of Suspension
8.10 Payment for Plant and Materials in Event of Suspension
8.11 Prolonged Suspension
8.12 Resumption of Work
9 TESTS ON COMPLETION
9.1 Contractor’s Obligations
9.2 Delayed Tests
9.3 Retesting
9.4 Failure to Pass Tests on Completion
10 EMPLOYER’S TAKING OVER
10.1 Taking Over of the Works and Sections
10.2 Taking Over of Parts of the Works
10.3 Interference with Tests on Completion
10.4 Surfaces Requiring Reinstatement
11 DEFECTS LIABILITY
11.1 Completion of Outstanding Work and Remedying Defects
11.2 Cost of Remedying Defects
11.3 Extension of Defects Notification Period
11.4 Failure to Remedy Defects
11.5 Removal of Defective Work
11.6 Further Tests
11.7 Right of Access
11.8 Contractor to Search
11.9 Performance Certificate
11.10 Unfulfilled Obligations
11.11 Clearance of Site
   12 MEASUREMENT AND EVALUATION .
   12.1 Works to be Measured
   12.2 Method of Measurement
   12.3 Evaluation
   12.4 Omissions
   13 VARIATIONS AND ADJUSTMENTS
   13.1 Right to Vary
   13.2 Value Engineering
   13.3 Variation Procedure
   13.4 Payment in Applicable Currencies
   13.5 Provisional Sums
   13.6 Daywork
   13.7 Adjustments for Changes in Legislation
   13.8 Adjustments for Changes in Cost
14 CONTRACT PRICE AND PAYMENT
14.1 The Contract Price
14.2 Advance Payment
14.3 Application for Interim Payment Certificates
14.4 Schedule of Payments
14.5 Plant and Materials intended for the Works
14.6 Issue of Interim Payment Certificates
14.7 Payment
14.8 Delayed Payment
14.9 Payment of Retention Money
14.10 Statement at Completion
14.11 Application for Final Payment Certificate
14.12 Discharge
14.13 Issue of Final Payment Certificate
14.14 Cessation of Employer’s Liability
14.15 Currencies of Payment
15 TERMINATION BY EMPLOYER
15.1 Notice to Correct
15.2 Termination by Employer
15.3 Valuation at Date of Termination
15.4 Payment after Termination
15.5 Employer’s Entitlement to Termination for Convenience
15.6 Corrupt or Fraudulent Practices
16 SUSPENSION AND TERMINATION BY CONTRACTOR
16.1 Contractor’s Entitlement to Suspend Work
16.2 Termination by Contractor
16.3 Cessation of Work and Removal of Contractor’s Equipment
16.4 Payment on Termination
17 RISK AND RESPONSIBILITY
17.1 Indemnities
17.2 Contractor’s Care of the Works
17.3 Employer’s Risks
17.4 Consequences of Employer’s Risks
17.5 Intellectual and Industrial Property Rights
17.6 Limitation of Liability
17.7 Use of Employer’s Accommodation/Facilities
18 INSURANCE
18.1 General Requirements for Insurances
18.2 Insurance for Works and Contractor’s Equipment
18.3 Insurance against Injury to Persons and Damage to Property
18.4 Insurance for Contractor’s Personnel
19 FORCE MAJEURE
19.1 Definition of Force Majeure
19.2 Notice of Force Majeure
19.3 Duty to Minimize Delay
19.4 Consequences of Force Majeure
19.5 Force Majeure Affecting Subcontractor
19.6 Optional Termination, Payment and Release
19.7 Release from Performance
20 CLAIMS, DISPUTES AND ARBITRATION
20.1 Contractor’s Claims
20.2 Appointment of the Dispute Board
20.3 Failure to Agree on the Composition of the Dispute Board
20.4 Obtaining Dispute Board’s Decision
20.5 Amicable Settlement
20.6 Arbitration
20.7 Failure to Comply with Dispute Board’s Decision
20.8 Expiry of Dispute Board’s Appointment
                     1.1 Definitions
 1.1.1. Contract : include contract agreement, letter of acceptance,
  letter of tender, specifications, drawings, schedules, tender,
  appendix to tender, bill of quantities.
 1.1.2 parties and persons : party, employer, contractor, engineer,
  contractor representative, employers' personnel, contractors
  personnel, sub- contractor, DAB (dispute adjudication board), Fidic.
 1.1.3 Dates , tests, periods and completion include base date,
  commencement date, time of completion, test on completion, taking
  over certificate, defects notification period, performance certificate,
  day
 1.1.4 money and payement: acceted contract amount, contract
  price, cost, final , interim payement certificate, currency, provisional
  sum, retension money,
        General conditions
 The following are main items that include
 in the general conditions for the tender ( or
 the construction contract.
                      1 : definitions
   The main definitions that are included in and repeated in the articles
    of general conditions, are:
   Employer : "Employer" The party named in the Contract as the
    "FIRST PARTY" who will enter into contract with the Contractor for
    the execution of the Works covered by the Contract, or any other
    party authorized by the Employer to exercise the powers and
    obligations of the First Party, provided that the Contractor will be
    informed accordingly in writing .
   Contractor : "Contractor" - The person, company or joint venture
    named as Second Party in the Contract whose Tender has been
    accepted by the Employer and with whom the Employer has entered
    into Contract, and includes the Contractors personal agents and his
    legal successors
   Engineer" - The Consulting office, or Engineering office or Engineer
    or any other technical body appointed from time to time by the
    Employer to exercise in whole or in part the powers of the Engineer
    in accordance with the Conditions of the Contract provided that the
    Contractor shall be accordingly notified in writing.
               Article 1 : definitions
   "Engineers Representative" - Any resident engineer, or clerk of
    works appointed by the Engineer from time to time
   "Contract" - The documents constituting these Conditions (Parts I
    and II), the Specification, the Drawings, the Bill of Quantities, the
    Tender, the Letter of Acceptance, the Contract Agreement, and
    such further documents as may be expressly incorporated in the
    Letter of Acceptance or Contract Agreement (if completed).
   "Contract Sum" - The sum stated in the Letter of Acceptance as
    payable to the Contractor for the execution and completion of the
    Works and the remedying of any defects therein in accordance with
    the provisions of the Contract, subject to such additions thereto or
    deductions therefrom as may be made under the provisions of the
    Contract.
   Equipment is the Contractor’s machinery and vehicles brought
    temporarily to the Site to construct the Works.
    "Site" - The land and other places provided by the Employer or
    designated as such where the Works are to be executed, and any
    other places specifically designated in the Contract as forming part
    of the Site.
   approval (written approval)
   time (calendar / working days)
       2. Engineer's Duties and
              Authority
   a) The Engineer shall carry out the duties specified in the
    Contract .
   b) The Engineer shall exercise the authority specified in or
    necessarily to be implied from the Contract .
         Provided, that the Engineer shall obtain the specific approval of
    the Employer, in compliance with the terms of his appointment, and
    after submitting his recommendations to the Employer in writing, in
    the following matters :
   (i) "issuing variation orders";
   (ii) "deciding on the extension of Time for Completion and applying
    the Liquidated Damages Clause";
   (iii) "approving the appointment of Subcontractors";
   (iv) "notifying the Contractor on suspension of Works";(and any
    other matters as may be set out in Part II of these conditions).
   (c) Except as expressly stated in the Contract, the Engineer shall
    have no authority to relieve the Contractor of any of his obligations
    under the Contract
 Engineer's Representative
    The Engineer's Representative shall be
  appointed by and be responsible to the
  Engineer and shall carry out such duties of
  watching and supervising the execution
  and workmanship of the Works and to test
  and examine any materials to be used or
  workshop employed in connection with the
  Works. He shall exercise such authority as
  may be delegated to him by the Engineer
   Engineer's Authority to Delegate
        The Engineer may from time to time delegate to the
    Engineer's Representative any of the duties and authorities
    vested in the Engineer and he may at any time revoke such
    delegation. Any such delegation or revocation shall be in
    writing and shall not take effect until a copy thereof has
    been delivered to the Employer and the Contractor .
        Any communication given by the Engineer's
    Representative to the Contractor in accordance with such
    delegation shall have the same effect as though it had been
    given by the Engineer
        Provided that :
   (a) any failure of the Engineer's Representative to
    disapprove any work, materials or Plant shall not prejudice
    the authority of the Engineer to disapprove such work,
    material or Plant and to give instructions for the rectification
    thereof;
   (b) if the Contractor questions any communication of the
    Engineers Representative, he may refer the matter to the
    Engineer who shall confirm, reverse or vary the contents of
    such communication .
              3. Contractor’s General
                    Obligations
   The Contractor shall design (to the extent specified in the
    Contract), execute and complete the Works in accordance with
    the Contract and with the Engineer’s instructions, and shall
    remedy any defects in the Works.
   The Contractor shall provide the Plant and Contractor’s
    Documents specified in the Contract, and all Contractor’s
    Personnel, Goods, consumables and other things and services,
    whether of a temporary or permanent nature, required in and
    for this design, execution, completion and remedying of defects.
   The Contractor shall be responsible for the adequacy, stability
    and safety of all Site operations and of all methods of
    construction. Except to the extent specified in the Contract, the
    Contractor (i) shall be responsible for all Contractor’s
    Documents, Temporary Works, and such design of each item of
    Plant and Materials as is required for the item to be in
    accordance with the Contract, and (ii) shall not otherwise be
    responsible for the design or specification of the Permanent
    Works.
            Contractor’s General
                Obligations
   The Contractor shall, whenever required by the
    Engineer, submit details of the arrangements and
    methods which the Contractor proposes to adopt for the
    execution of the Works. No significant alteration to these
    arrangements and methods shall be made without this
    having previously been notified to the Engineer.
   If the Contract specifies that the Contractor shall design
    any part of the Permanent Works, then unless otherwise
    stated in the Particular Conditions:
   (a) the Contractor shall submit to the Engineer the
    Contractor’s Documents for this part in accordance with
    the procedures specified in the Contract;
   (b) these Contractor’s Documents shall be in accordance
    with the Specification and Drawings, shall be written in
    the language for communications