Dili Port Ferry Terminal Relocation Report

1) The report provides a monthly progress update on the construction of a new ferry terminal in Dili Port, Timor-Leste. 2) As of month 8, the total actual accumulated progress was 21.82%, with material procurement at 7.1% completed and platform work at 3.62% completed. 3) Planned progress through the end of 2018 was expected to be 28.95% completed, with key milestones of jetty work at 2.84% and platform work at 5.56% completed.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
142 views6 pages

Dili Port Ferry Terminal Relocation Report

1) The report provides a monthly progress update on the construction of a new ferry terminal in Dili Port, Timor-Leste. 2) As of month 8, the total actual accumulated progress was 21.82%, with material procurement at 7.1% completed and platform work at 3.62% completed. 3) Planned progress through the end of 2018 was expected to be 28.95% completed, with key milestones of jetty work at 2.84% and platform work at 5.56% completed.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 6

URGENT RELOCATION OF FERRY TERMINAL IN DILI PORT: Monthly Report

Construction Project Schedule


Term Term 1 T
Actual
Year & Month Accum. 2017
Monthly
Progress (%) 7 8 9 10 11 12 1 2
Work Item 100 M1 M2 M3 M4 M5 M6 M7 M8
4.61%
1 Material Procurement
%
0.05% 0.00% 0.00% 4.45% 1.60%
0.22% 0.44% 0.44% 0.44% 0.44% 0.44% 0.44%
2 Preparation and Temporary Work
0.014% 0.13% 1.63% 0.15% 0.15% 0.62%
90
3 Jetty Work

0.16% 0.16% 0.16% 0.16%


3.1 Demolition of Ext.Slipway and
Revetment 0.07% 0.53% 0.03%
80
3.2 Steel Pipe Work

3.3 Super Structure Work


70 Leg
3.4 PC Beam en Term: Planed Accumulated Monthly Accomplishment (%)

3.5 Wheel Guard, Pavement Concrete


d Planed Accumulated Monthly Accomplishment (%)
60
3.6 Ancillary Work Actual Accumulated Monthly Progress (%)

4 Platform Work
50 3.62%
4.1 Steel Pile Work
50
4.1 Steel Pile Work
0.07% 1.91%
1.79%
4.2 PC Pile Work
1.11%
40
4.3 Super Structure Work

4.4 Ancillary Work


30
4.5 Movable Ramp Work

4.6 Revetment Work


0.59% 0.00%
20
4.7 Interface Work

5 Mechanical and Electrical Work


10 0.03% 0.03% 0.03% 0.03%
6 Material Transportation
0.10% 0.03%
1.28% 1.28% 1.28% 1.28% 1.28% 1.28% 1.28% 1.28%
7 Site Expenses
0.09% 0.89% 1.28% 1.28% 1.28% 1.28% 1.20% 1.30%
0 1.50% 1.72% 1.72% 1.87% 1.90% 1.90% 1.90% 11.32%
Total
0.10% 1.07% 2.98% 1.96% 1.28% 5.98% 1.86% 6.60%

Term Term 1
Term: Planed Monthly Accomplishment (%) 49.96 50.04 2.68 2.60 2.64 2.64 2.64 15.73
Term: Planed Accumulated Monthly Accomplishment (%) 49.96 100.00 2.68 5.29 7.93 10.58 13.22 28.95
Overall
Planed Monthly Accomplishment (%) 1.50 1.72 1.72 1.87 1.90 1.90 1.90 11.32
Planed Accumulated Monthly Accomplishment (%) 1.50 3.22 4.93 6.81 8.71 10.62 12.52 23.84
Actual Monthly Progress (%) 0.10 1.07 2.98 1.96 1.28 5.98 1.86 6.60
Actual Accumulated Monthly Progress (%) 0.10 1.17 4.15 6.11 7.39 13.37 15.22 21.82
Term 2 Term 3
2018 2019
3 4 5 6 7 8 9 10 11 12 1 2 3 Total Ratio

M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21
1.66% 0.54% 1.66% 14.86% 0.86% 0.70% 24.89%
0.64% 0.01% 0.35% 7.10%
2.84%
0.14% 2.84%
0.00%
0.00%
0.63%
0.63%
2.22% 2.22% 1.11% 5.56%
0.10% 0.03% 1.44% 1.57%
1.94% 1.94% 1.94% 5.82%
0.57% 0.57%
1.34% 1.34% 1.34% 1.34% 5.35%
0.00%
0.92% 0.92% 0.92% 2.76%
0.00%
0.41% 0.41% 0.41% 1.24%
0.00%
0.00%
0.00%
3.62%
0.81% 0.35% 0.17% 0.20% 3.51%
1.79% 3.57%
1.12% 1.00% 0.26% 0.04% 0.04% 3.56%
1.68% 1.68% 1.68% 1.68% 1.68% 1.68% 1.68% 11.77%
0.28% 0.63% 0.51% 1.55% 2.97%
0.16% 0.16% 0.16% 0.47%
0.00%
0.38% 0.38% 0.38% 0.38% 1.54%
0.00%
0.80% 0.80%
0.21% 0.80%
0.08% 0.08% 0.16%
0.00%
0.17% 0.34% 0.34% 0.34% 0.34% 0.17% 1.69%
0.00%
0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.39%
0.03% 0.01% 0.17%
1.28% 1.28% 1.28% 1.28% 1.28% 1.28% 1.28% 1.28% 1.28% 1.28% 1.28% 1.28% 1.28% 26.89%
1.28% 1.28% 1.09% 1.25% 1.00% 14.50%
5.32% 6.27% 6.05% 7.93% 4.87% 5.99% 4.50% 19.12% 5.66% 4.20% 2.57% 2.33% 1.36% 100.00%
4.01% 2.93% 2.25% 2.04% 5.14% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 38.20%

Term 2 Term 3
7.39 8.71 8.40 11.02 6.76 8.32 6.25 14.21 58.18 16.78 10.29 9.31 5.44
36.34 45.05 53.45 64.46 71.22 79.54 85.79 100.00 58.18 74.96 85.25 94.56 100.00

5.32 6.27 6.05 7.93 4.87 5.99 4.50 19.12 5.66 4.20 2.57 2.33 1.36
29.16 35.44 41.48 49.41 54.28 60.27 64.77 83.89 89.54 93.74 96.31 98.64 100.00
4.01 2.93 2.25 2.04 5.14
25.84 28.77 31.01 33.05 38.20