This was an ask mainly dealing with special events that run for a day (eg. WeDigBio, Douglass Days, etc).
There has been an ask to get an hourly sense of classification counts for these program events that span a day or 2.
Project team is aware that there is a data retention policy on HourlyProjectClassificationCounts that will only hold hourly data counts up to 3 days. This is OK, but will need to be documented.
Dev Estimate:
2 days (1 day code, 1 day review, test, and deploy)
cc @lcjohnso