Architect's Construction Progress Certification

1) The architect certifies the percentage of completion for buildings/wings in a real estate project registered with MahaRERA. 2) The certificate provides tables with details of percentage work done for individual tasks like excavation, basement, slabs for each building/wing. 3) It also includes a table listing common development works for the entire registered phase and percentage completed for items like roads, drainage, landscaping, and more.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
890 views4 pages

Architect's Construction Progress Certification

1) The architect certifies the percentage of completion for buildings/wings in a real estate project registered with MahaRERA. 2) The certificate provides tables with details of percentage work done for individual tasks like excavation, basement, slabs for each building/wing. 3) It also includes a table listing common development works for the entire registered phase and percentage completed for items like roads, drainage, landscaping, and more.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

FORM 1 [see Regulation 3]

ARCHITECT'S CERTIFICATE

(To be submitted at the time of Registration of Ongoing Project and for


withdrawal of Money from Designated Account)

Date :
To
The ________________ (Name & Address of Promoter),

Subject : Certificate of Percentage of Completion of Construction Work of


___________ No. of Building(s)/______ Wing(s) of the ______ Phase of the Project
[MahaRERA Registration Number] situated on the Plot bearing C.N. No/CTS
No./Survey no./ Final Plot no _________ demarcated by its boundaries (latitude and
longitude of the end points) ______to the North____to the South _____to
the East _____to the West of Division __________ village _____________ taluka
________________ District ___________ PIN_________admeasuring ________sq.mts.
area being developed by

Sir,

I/ We________________ have undertaken assignment as Architect /Licensed Surveyor of


Certifying Percentage of Completion of Construction Work of the
___________Building(s)/________Wing(s) of the _____Phase of the Project, situated on the
plot bearing C.N. No/CTS No./Survey no./ Final Plot no ______________ of Division
__________ village _____________ taluka _____________________ District _______________
PIN____________admeasuring __________sq.mts. area being develo
Name]

1. Following technical professionals are appointed by Owner / Promoter :-


(i) M/s/Shri/Smt __________________________as L.S. / Architect ;
(ii) M/s /Shri / Smt ________________________ as Structural Consultant
(iii) M/s /Shri / Smt ________________________ as MEP Consultant
(iv) M/s /Shri / Smt ________________________as Site Supervisor
Based on Site Inspection, with respect to each of the Building/Wing of the aforesaid
Real Estate Project , I certify that as on the date of this certificate, the Percentage of
Work done for each of the building/Wing of the Real Estate Project as registered vide
number ________________ under MahaRERA is as per table A herein below. The
percentage of the work executed with respect to each of the activity of the entire phase
is detailed in Table B.

Table A

Building /Wing Number_____(to be prepared separately for each Building /Wing of


the Project)

Sr. No Tasks /Activity Percentage


of work done

1 Excavation
2 _________ number of Basement(s) and Plinth
3 _________ number of Podiums

4 Stilt Floor
5 __________number of Slabs of Super Structure
6 Internal walls, Internal Plaster,
Floorings within Flats/Premises,
Doors and Windows to each of the Flat/Premises

12
7 Sanitary Fittings within the Flat/Premises,
Electrical Fittings within the Flat/Premises
8 Staircases, Lifts Wells and Lobbies at each
Floor level connecting Staircases and Lifts,
Overhead and Underground Water Tanks

9 The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of
the Building/Wing,
10 Installation of lifts, water pumps, Fire Fighting Fittings
and Equipment as per CFO NOC, Electrical fittings to
Common Areas, electro, mechanical equipment,
Compliance to conditions of environment /CRZ NOC,
Finishing to entrance lobby/s, plinth protection,
paving of areas appurtenant to Building/Wing,
Compound Wall and all other requirements as may be
required to Obtain Occupation /Completion Certificate

TABLE-B

Internal & External Development Works in Respect of the entire Registered Phase

S.No Common areas Proposed Percentage of Details


and Facilities, (Yes/No) Work done
Amenities
1. Internal Roads &
Foothpaths
2. Water Supply
3. Sewarage
(chamber, lines,
Septic Tank ,
STP)
4. Storm Water
Drains
5. Landscaping &
Tree Planting
6. Street Lighting
7. Community
Buildings
8. Treatment and
disposal of
sewage and
sullage water

13
9. Solid Waste
management &
Disposal
10. Water
conservation,
Rain water
harvesting
11. Energy
management
12. Fire protection
and fire safety
requirements
13. Electrical meter
room, sub-station,
receiving station
14. Others ( Option to
Add more)

Yours Faithfully

Signature & Name (IN BLOCK LETTERS) of L.S/ Architect