12 (A) - Contract Costing: Model Wise Analysis of Past Exam Papers of Ipcc
12 (A) - Contract Costing: Model Wise Analysis of Past Exam Papers of Ipcc
M-11 M-13
N - 14
M-12
M-14
M-15
M-16
M-17
N-10
N-12
N-15
N-16
N-17
No. MODEL NAME TO TO
N-11 N-13
A contract takes longer period to complete and the result of the contract can be known only after
the completion of the contract. If the profit on such contracts is calculated only after their
completion, then wide fluctuations may be noted in the profit figures of contractors from year to
year. The profit in respect of each contract in progress is transferred to the costing profit and loss
account of the year by calculating the notional profit. The portion of notional profit to be transferred
to the costing profit and loss account depends on the stage of completion of a contract.
Contract costing is a form of specific order costing where job undertaken is relatively large and
normally takes period longer than a year to be getting completed. Contract costing is usually
adopted by the contractors engaged in the task of executing Civil Contracts. Contract costing
have the following distinct features:
1. The major part of the work in connection with each contract is ordinarily carried out at the
site of the contract.
2. The bulk of the expenses incurred by the contractor are considered as direct.
3. The indirect expenses mostly consist of office expenses of the yards, stores and works.
4. A separate account is usually maintained for each contract.
5. The number of contracts undertaken by a contractor at a time is usually few.
6. The cost unit in contract costing is the contract itself.
Profit or Loss on Incomplete Contracts:
1. If % of completion of contract is < 25% - NIL
Cash received
2. If % of completion of contract is 25% to 50% 1 3 x Notional Pr ofit x
Work certified
Cash received
3. If % of completion of contract is 50% to 90% 2 3 x Notional Pr ofit x
Work certified
4. If % of completion of contract is ≥ 90% and above – based on estimated profit
Work certified
% of completion of contract x 100
Contract Pr ice
Based on Estimated Profit: If contract is completed 90% & above then
Work Certified
1) Estimated Pr ofit x
Contract Pr ice
Combination
Situation Treatment
Current Yr Estimated
Notional Profit ETP Profit: Profit Profit should be recognised only if
Percentage of Completion.
Notional Profit Loss Profit: Loss Estimated Total Loss is Fully provided for in
the current year. Profit should not be
recognized
Loss ETP Loss: Profit Current Loss is fully provided for. Profit is not
recognised even though there may be profit
when the contract is finally completed
Loss Loss Loss: Loss Current Loss or Estimated Total Loss,
Whichever is worse, is fully provided for in the
current year.
PROBLEM 2: A contractor prepares his accounts for the year ending 31st December each
year. He commenced a contract on 1st April, 2011.
The following information relates to the contract as on 31st December, 2011:
(Rs.)
Material issued 2,51,000
Labour charges 5,65,600
Salary to Foreman 81,300
A machine costing Rs. 2,60,000 has been on the site for 146 days, its working life is estimated
at 7 years and its final scrap value at Rs. 15,000.
A supervisor, who is paid Rs. 8,000 p.m. has devoted one-half of his time to this contract.
All other expenses and administration charges amount to Rs. 1,36,500.
Material in hand at site costs Rs. 35,400 on 31st December, 2011.
The contract price is Rs. 20,00,000. On 31st December, 2011 two-third of the contract was
completed. The architect issued certificates covering 50% of the contract price, and the
contractor had been paid Rs. 7,50,000 on account.
Prepare Contract A/c and show how much profit or loss should be included in financial
accounts to 31st December, 2011.
(SM) (Ans:(notional profit = 2,13,250; amount to be transferred to P&L A/c 1,06,625)
(Solve Problem no 2 of Assignment Problems as rework)
Note:______________________________________________________________________
___________________________________________________________________________
The contract price is Rs. 10,00,000 and the estimated profit is 20%.You are required to
calculate, how much profit should have been credited to the Profit and Loss A/c by the end of
years 1, 2 and 3. (PM)(Ans.: Profit for 1st year 0; 2nd year 24,444; 3rd year 1,00,000)
Note:______________________________________________________________________
___________________________________________________________________________
IPCC_38e_Costing (Problems)_Contract Costing ___________________12A.3
Ph: 98851 25025/26 www.mastermindsindia.com
PROBLEM 4: M/s. Bansals Construction Company Ltd. took a contract for Rs. 60,00,000
expected to be completed in three years. The following particulars relating to the contract are
available:
2011 2012 2013
(Rs.) (Rs.) (Rs.)
Materials 6,75,000 10,50,000 9,00,000
Wages 6,20,000 9,00,000 7,50,000
Cartage 30,000 90,000 75,000
Other expenses 30,000 75,000 24,000
Cumulative work certified 13,50,000 45,00,000 60,00,000
Cumulative work uncertified 15,000 75,000 —
Plant costing Rs. 3,00,000 was bought at the commencement of the contract. Depreciation
was to be charged at 25% per annum, on the written down value method. The contractee
pays75% of the value of work certified as and when certified, and makes the final payment on
completion of the contract.
You are required to make a contract account and contractee account as they would appear in
each of the three years. Also show how the work-in-progress and other items should appear in
the balance sheet.
(SM)(Ans:(2011-loss transferred to costing p&l A/c-65,000; 2012-notional profit-10,38,750; 2013- profit
transferred to costing P & L A/c-1,53,187)
(Solve Problem no 3 of Assignment Problems as rework)
Note:______________________________________________________________________
___________________________________________________________________________
Note:______________________________________________________________________
___________________________________________________________________________
Additional Information:
a) A plant was purchased for the contract at Rs. 8,00,000 on 01-12-2013.
b) Depreciation @ 15% per annum is to be charged.
c) Material which cost Rs.1,30,000 was destroyed by fire.
Prepare:
i) Contract Account for the year ended 31st March, 2014 and computes the profit to be taken
to the Profit & Loss Account.
ii) Account of Contractee.
iii) Profit & Loss Account showing the relevant items.
iv) Balance Sheet showing the relevant items. (PM)(MAY-14,8M)(Ans:(i)880 (ii)10,120 (iii)750)
(Solve Problem no 5 of Assignment Problems as rework)
Note:______________________________________________________________________
___________________________________________________________________________
PROBLEM 11: From the following particulars compute a conservative estimate of profit by 4
methods on a contract which has 80 percent complete:
(Rs.)
Total expenditure to date 8,50,000
Estimate further expenditure to complete the contract 1,70,000
Contract Price 15,30,000
Work Certified 10,00,000
Work not certified 85,000
Cash received 8,16,000
(PM) (N12 - 8M) (Ans.: amount to be transferred to P&L A/c- 1,25,333)
Note:______________________________________________________________________
___________________________________________________________________________
The contract price is Rs.11 corers and the received on account till 31st March was Rs.6 Crores.
A technical estimate of the contract indicates the following degree of completion of work:
Fabrication: Direct Material - 70%, Direct Labour and Overheads 60%. Erection - 40%. You
are required to estimate the profit that could be taken to Profit and Loss Account against this
partly completed contract as at 31st March.
(PM)(Ans.: Alternative-I-Rs. 86.36 lakhs; Alternative-II-92.48lakhs)
Note:______________________________________________________________________
___________________________________________________________________________
IPCC_38e_Costing (Problems)_Contract Costing ___________________12A.7
Ph: 98851 25025/26 www.mastermindsindia.com
Required:
i) Determine the profit/loss in respect of each contract for the year ended 31st March, 2012.
ii) State the profit/loss to be carried to Profit & Loss A/c for the year ended 31st March, 2012.
(SM)(Ans.:(i) 5.20, 4.28, (1.27), (0.06); (ii)1.91, 1.80, (1.27), (0.06))
(Solve Problem no 13 of Assignment Problems as rework)
Note:______________________________________________________________________
___________________________________________________________________________
ASSIGNMENT PROBLEMS
Life of plant purchased is 5 years and scrap value is nil. Prepare the contract account for the
year ended 30th September, 1989. Show the amount of profit which you consider might be
fairly taken on the contract and how you have calculated it. (Ans.: Profit & Loss a/c 19,200)
PROBLEM 3: Mr. Bhagwandas undertook a contact for Rs. 15,00,000 on an arrangement that
80% of the value of the work done as certified by the architect of the contract should be paid
immediately and that the remaining 20% be retained until the contract was completed. In
2005-'06-'07 amounts expended were:
Particulars 2005 2006 2007
Materials 1,80,000 2,20,000 1,26,000
Wages 1,70,000 2,30,000 1,70,000
Carriage 6,000 23,000 ---
Cartage 1,000 2,000 6,000
Sundry Exp. 3,000 4,000 3,000
Other information:
2005: Work certified for Rs.3,75,000 & 80% cash received.
2006: 3/4th of contract was certified and 80% of cash received. Uncertified work -20,000.
2007: on 30th June, the work completed.
Shown how the contract account and also contractee's account would appear each of these
years in the books of the contractor assuming that the balance due to him was paid on
completion of the contract.
(Ans.: 2005: P & L A/c – 4000, 2006: P & L A/c – 161067, 2005: P & L A/c – 1,90,933 )
PROBLEM 5: Dream house (P) Ltd. is engaged in building two residential housing projects in
the city. Particulars related to two housing projects are as below:
HP-1 (Rs.) HP-2 (Rs.)
Work in Progress on 1st April 2013 7,80,000 2,80,000
Materials Purchased 6,20,000 8,10,000
Land purchased near to the site to open an office - 12,00,000
Brokerage and registration fee paid on the above - 60,000
purchase
Wages paid 85,000 62,000
Wages outstanding as on 31st March, 2014 12,000 8,400
Donation paid to local clubs 5,000 2,500
Plant hire charges paid for three years effecting 72,000 57,000
from 1st April 2013
Value of materials at site as on 31st March, 2014 47,000 52,000
Contract price of the projects 48,00,000 36,00,000
Value of work certified 20,50,000 16,10,000
Work not certified 1,90,000 1,40,000
A concrete mixture machine was bought on 1st April 2013 for Rs. 8,20,000 and used for 180
days in HP-1 and for 100 days in HP-2. Depreciation is provided @ 15% p.a.( this machine
can be used for any other projects)
As per the contract agreement contractee shall retain 20% of work certified as retention money.
Prepare contract account for the two housing projects showing the profit or loss on each
project for the year ended 31st March, 2014.
(PM, RTP - M15)(Ans: amount to be transferred to P&L A/c 1,86,758; 1,56,374)
PROBLEM 7: Hut-to-Palace Ltd. undertook a contract in last year. In the agreement between
the Hut-to-Palace Ltd. and the contractee, there is a clause stating that Hut-to-Palace Ltd. will
receive total cost plus 40% as contract consideration. The following are the details of the
contract as on 31st March, 2014:
(Rs.)
Total expenditure to date 17,64,525
Estimated further expenditure to complete the contract 8,38,645
Value of work certified 21,07,500
Cost of work not certified 3,11,075
Progress payment received from the contractee 14,75,250
From the above information calculate the
a) Conservative estimate of profit for the management of Hut-to-Palace Ltd.
b) What would be the estimated profit from the contract if management of Hut-to- Palace Ltd
has come to know that the contractee has liquidity crunch and it is not able to pay further
payments. (RTP - M14) (Ans.: a) 3,05,223, b) (2,89,275))
PROBLEM 8: PQR Construction Ltd. commenced a contract on April 1, 2009. The total
contract was for Rs.27,12,500. It was decided to estimate the total profit and to take to the
credit of P/L A/c the proportion of estimated profit on cash basis which work completed bear to
the total contract. Actual expenditure in 2009-10 and estimated expenditure in 2010-11 are
given below:
2009 – 10 2010 – 11
Particulars
Actual (Rs.) Estimated (Rs.)
Material issued 4,56,000 8,14,000
Labour : Paid 3,05,000 3,80,000
: Outstanding at end 24,000 37,500
Plant purchased 2,25,000 -
Expenses : Paid 1,00,000 1,75,000
: Outstanding at the end - 25,000
: Prepaid at the end 22,500 -
Plant returned to stores (a historical stores) 75,000 1,50,000 (on Dec
31 2010)
Material at site 30,000 75,000
Work-in-Progress certified 12,75,000 Full
Work-in-progress uncertified 40,000 -----
Cash received 10,00,000 Full
The plant is subject to annual depreciation @ 20% of WDV cost. The contract is likely to be
completed on December 31, 2010.
Required:
i) Prepare the Contract A/c for the year 2009-10.
ii) Estimate the profit on the contract for the year 2009-10 on prudent basis which has to be
credited to P/L A/c (PM, N10 – 8M)(Ans.:(i)notional profit-4,37,500(ii)1,59,263)
IPCC_38e_Costing (Problems)_Contract Costing ___________________12A.14
No.1 for CA/CWA & MEC/CEC MASTER MINDS
PROBLEM 9: MNP Construction Ltd. commenced a contract on April 1, 2010. The total
contract was for Rs. 17,50,000. It was decided to estimate the total profit and to take to the
credit of Costing P/L A/c the proportion of estimated profit on cash basis which work
completed bore to the total contract. Actual expenditure in 2010-11 and estimated expenditure
in 2011-2012 are given below:
Particulars 2010-11 2012-13
(actual) (Rs.) (estimated) (Rs.)
Materials issued 3,00,000 5,50,000
Labour : Paid 2,00,000 2,50,000
Outstanding at end 20,000 30,000
Plant purchased 1,50,000 —
Expenses : Paid 75,000 1,50,000
: Prepaid at end 15,000 —
Plant returns to store (historical cost) 50,000 1,00,000
(on Dec. 31, 2011)
Material at site 20,000 50,000
Work certified 8,00,000 Full
Work uncertified 25,000 —
Cash received 6,00,000 Full
The plant is subject to annual depreciation @ 25% of WDV Cost. The contract is likely to be
completed on Dec. 31, 2011. Prepare the Contract A/c. Determine the profit on the contract for
the year 2010-2011 on prudent basis, which has to be credited to Costing P/L A/c.
(SM)(Ans.: Amount to be transferred to p & l A/c – 66,322)
PROBLEM 10: A loan Construction Company Ltd. commenced its business of construction on
1-1-2006. The trial balance as on 31-12-2006 showed the following balances:
Particulars Dr. Cr.
Paid-up Share capital 1,00,000
Cash received on a/c of contract
(80% of work certified) 1,20,000
Land and Building 30,000
Machinery at cost (75% at site) 40,000
Bank 4,000
Materials issued to site 40,000
Direct Labour 55,000
Expenses at site 2,000
Lorries and Vehicles 30,000
Furniture 1,000
Office Equipment 10,000
Postage and Telegrams 500
Office Expenses 2,000
Rate and Taxes 3,000
Fuel and Power 2,500
2,20,000 2,20,000
The contract Price is Rs. 3,00,000 and work certified is Rs.1,50,000. the work completed since
certification is estimated at Rs. 1,000(at cost). Machinery costing Rs. 2,000 was returned to
stores at the end of the year. Stock of material at site on 31-12-2006 was of the value of
Rs.5,000. Wages outstanding were Rs. 200. Depreciation on Machinery at 10%. You are
required to calculate the profit from the contract and show how the work-in-progress will appear in
the balance sheet as on 31-12-2006. (M - 14) (Ans.: Profit & Loss a/c 28,427, Reserves 24,873)
PROBLEM 11: Modern Constructions Ltd obtained a contract No.B-37 for Rs.40 Lakhs. The
following balances and information relates to the contract for the year just ended.
At the beginning At the end of the
Particulars
of the year Rs. year Rs.
Work-in-Progress: Work Certificate 9,40,000 30,00,000
Work Uncertified 11,200 32,000
Materials at site 8,000 20,000
Accrued Wages 5,000 3,000
PROBLEM 12: PVK Constructions commenced a contract on 1st April, 2014.total contract
value was Rs.100 lakhs. The contract is expected to be completed by 31st December 2016.
Actual expenditure during the period 1st April, 2014 to 31st December 2015 and estimated
expenditure for the period 1st April, 2014 to 31st December 2016 are as follows:
Actual(Rs.) Estimated(Rs.)
1st April, 2014 to 1st April, 2015 to 31st
31st March 2015 December 2016
Material issued 15,30,000 21,00,000
Direct wages paid 10,12,500 12,25,000
Direct wages outstanding 80,000 1,15,000
Plant purchased 7,50,000 -
Expenses paid 3,25,000 5,40,000
Prepaid expenses 68,000 -
Site office expenses 3,00,000 -
Part of the material procured for the contract was un suitable and was sold for
Rs.2,40,000(cost being Rs.2,55,000)and a part of plant was scrapped and disposed of for
Rs.80,000.the value of plant at site on 31st March ,2015 was Rs.2,50,000 and the value of
material at site was Rs.73,000.cash received on account to date was Rs.36,00,000.
Representing 80% of the work certified was valued at Rs.5,40,000
Estimated further expenditure for completion of contract is as follows:
a) An additional amount of Rs.4,62,000 would have to be spent on the plant and the residual
value of the plant on the completion of the contract would be Rs.67,500.
b) Site office expenses would be the same amount per month as charged in the previous year.
c) An amount of Rs.1,57,500 would have to be incurred towards consultancy charges.
REQUIRED:
Prepare Contract Account And Calculate Estimated Total Profit On This Contract.
(N15 - 8M)(Ans.: notional profit – 17,68,500; costing p & L A/c – 4,11,967 and estimated profit – 13,60,000)
IPCC_38e_Costing (Problems)_Contract Costing ___________________12A.16
No.1 for CA/CWA & MEC/CEC MASTER MINDS
PROBLEM 13: ABC LLP, contractors and civil engineers, are building a new wing to a school.
The quoted fixed price for the contract is Rs. 30,00,000. Work commenced on 1st January
2014 and is expected to be completed on schedule by 30 June 2015.
Data relating to the contract at the year ended 31st March 2015 is as follows.
Amount (Rs.)
Plant sent to site at commencement of contract 2,40,000
Hire of plant and equipment 77,000
Materials sent to site 6,62,000
Materials returned from site 47,000
Direct wages paid 9,60,000
Wage related costs 1,32,000
Direct expenses incurred 34,000
Supervisory staff salaries - Direct 90,000
- Indirect 20,000
Regional office expenses apportioned to contract 50,000
Head office expenses apportioned to contract 30,000
Surveyor’s fees 27,000
Progress payments received from school 18,00,000
Additional information:
1. Plant is to be depreciated at the rate of 25 % per annum following straight line method,
with no residual value.
2. Unused materials on site at 31st March are estimated at Rs. 50,000.
3. Wages owed to direct workers total Rs. 40,000
4. No profit in respect of this contract was included in the year ended 31st March 2014.
5. Budgeted profit on the contract is Rs. 8,00,000
6. While the contract is expected to be completed by the scheduled date without
encountering difficulties, it is obvious to the management that the budgeted profit will not
be realised. However, to calculated the attributable profit to date you are to assume that
further costs to completion will be Rs. 3,00,000.
7. Value of work certified by the surveyor is Rs. 24,00,000.
8. The surveyor has not certified the work costing Rs. 1,80,000
You are required to prepare the account for the school contract for the fifteen months ended
31st March 2015, and calculate the attributable profit to date.
(MTP - N15)(Ans.: Amount to be transferred to p&l A/c – 2,40,000)
PROBLEM 14: Giant Construction Ltd. has been constructing a flyover for 15 months and is
under progress. The following information relating to the work on the contract has been
prepared for the period ended 31st March, 2014.
Amount (Rs.)
Contract price 65,00,000
Value of work certified at the end of the year 57,20,000
Cost of work not yet certified at the end of the year 1,20,000
Opening balances:
Cost of work completed 8,00,000
Materials on site 80,000
Costs incurred during the year:
Material delivered to site 15,90,000
Wages 14,95,000
Hire of plant 2,86,000
Other expenses 2,30,000
Closing balance: Material on site 40,000
IPCC_38e_Costing (Problems)_Contract Costing ___________________12A.17
Ph: 98851 25025/26 www.mastermindsindia.com
As soon as materials are delivered to the site, they are charged to the contract account. A
record is kept on actual use basis, periodically a stock verification is made and any
discrepancy between book stock and physical stock is transferred to a general contract
material discrepancy account. The stock verification at the yearend revealed a stock shortage
of Rs. 15,000.
In addition to the direct charges listed above, general overheads are charged to contracts at
5% of the value of work certified. General overheads of Rs. 35,000 had been absorbed into
the cost of work completed at the beginning of the year.
It has been estimated that further costs to complete the contract will be Rs. 5,72,000. This
estimate includes the cost of materials on site at the end of the year (31.3.2014) and also a
provision for rectification.
Required:
i) Determine profitability of the above contract and recommend how much profit should be
taken for the year just ended. (Provide a detailed schedule of costs).
ii) State how your recommendation in (i) would be affected if the contract price was Rs. 80,00,000
(rather than Rs. 65,00,000) and if no estimate has been made of costs to completion.
(MTP - N15)(Ans.: i) amount to be transferred to P & L A/c – 8,59,584; ii)amount to be transferred to P & L
A/c – 6,04,267)
PROBLEM 15: Deluxe Limited undertook a contract for Rs. 5,00,000 on 1st July 1986. On
30th June 1987, when the accounts were closed, the following details about the contract were
gathered:
Particulars Amount Particulars Amount
Materials purchased 1,00,000 Wages accrued 30.6.1987 5,000
Waged paid 45,000 Work certified 2,00,000
General Expenses 10,000 Cash received 1,50,000
Plant purchased 50,000 Work Uncertified 15,000
Materials on hand 30.6.87 25,000 Depreciation of Plant 5,000
The above contract contained an escalation clause which reads as following: "In the event of
price of materials and rates of wages increase by more than 5% the contract price will be
increased accordingly by 25% of the rise in the cost of materials and wages beyond 5% in
each case". It was found that since the date of signing the agreement the prices of materials
and wage rates increased by 25%. The value of the work certified does not take into account
the effect of the above clause. Prepare the contract account. Workings should form part of the
answer. (Ans.: Notional Profit 80,000)
ABC ANALYSIS
A category B category C category
Classroom problems 1, 2, 5, 6, 8, 9, 10, 3, 4, 7, 12, 15, 17 -
11, 13, 14, 16, 18
Assignment problems 1, 2, 4, 7, 9, 11, 12, 3, 5, 8, 13, 14 6,10
15, 16
Copyrights Reserved
To MASTER MINDS, Guntur
THE END