DPR - Jan
DPR - Jan
7:30am to 5:00pm
Remarks
AIR BASE
7:30am to 5:00pm
Stamp
PROJECT TITLE: CONSTRUCTION OF BULK STORAGE TANK & FUEL SYSTEM AT SWEIHAN AIR BASE
PROJECT NO: CMW-10009-B001
DAILY PROGRESS REPORT
Working Time: 7:30am to 5:00pm
Manpower Details Equipment Details Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 1 Crane 1
1 Project Manager 1 2 Excavator 2
2 Electrical Engineer (Site) 1 3 JCB 1 3
3 Mechanical Engineer (Site) 1 4 Shovel 4
4 Civil Engineer (Site) 1 5 Bob-Cat 5
5 Planning Engineer 1 6 Roller Compactor 6
6 Draftsman 1 7 Generator 1 7
7 Document Controller 1 8 Threading Machine 8
Direct Manpower 9 Welding Machine 9
8 Mech Supervisor 1 10 Water Tanker 10
9 Electrical Supervisor 1 11 Dump Truck 11
10 Pipe fitter 2 12 Trailer 12
11 Welder 1 13 Grader 13
12 Plumber 14 Pickup 1 14
13 Carpenter 15 3 Ton Pickup 1 15
14 Electrician 1 16 16
15 Helper 3 17 17
16 Machinery Driver 1 18 18
17 Driver 1 19 19
18 20 20
19 21 21
20 22 22
Total 18 Total 4
SubContractor
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Abdula Al Kulaib
1 Civil Engineer 1 1 Shovel 1 1
2 Supervisor 1 2 Ground Compactor 1 2
3 Machine Operator 2 3 Cutting Machine 1 3
4 Driver 1 4 Bending Machine 1 4
5 Carpenter 2 5 5
6 Helper 7 6 6
7 Mason 3 7 7
8 Steel Fitter 5 8 8
9 9 9
Total 22 Total 4
PROJECT TITLE: CONSTRUCTION OF BULK STORAGE TANK & FUEL SYSTEM AT SWEIHAN AIR BASE
PROJECT NO: CMW-10009-B001
DAILY PROGRESS REPORT
Working Time: 7:30am to 5:00pm
Total Manpower 40 Total Equipments 8
Contractor Sign & Stamp Client Sign & Stamp
SWEIHAN AIR BASE
Other Details
Others Qty
Total 0
Other Details
Others Qty
Total 0
SWEIHAN AIR BASE
Page 9
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 31-Jan-16 Weather: Sunny Temperature: 30ºC
3 Welding 2 35 37
4 Pipe Laying 20 620 640
5 First Layer Back Filling 100 200 300
Page 10
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 31-Jan-16 Weather: Sunny Temperature: 30ºC
1 Bedding 80 40 120
2 Fit up 2 45 47
3 Welding 2 42 44
4 Pipe Laying 50 100 150
5 First Layer Back Filling 50 150 200
Other Activity:
1 Pneumatic test for Zone-1 Joint No. R4 to R31 & S4 to S31 Completed
2 Pneumatic test for Zone-1 Joint No. R39 to R62 & S39 to S62 Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed
4 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S 39 to S58 Completed
5 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S4 to S31 Completed
6 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R39 to R58 Completed
7 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R4 to R31 Completed
8 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S1 to S20 Completed
9 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S21 to S31 Completed
10 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R1 to R20 Completed
11 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R21 to R31 Completed
12 2 Coat Primer + 2 coat Epoxy applied in Zone-5 S6 to S38 Completed
Page 11
Working Time: 7 am to 6:00pm
118
57
Remarks
On Progress
On Progress
On Progress Total Excavation
Completed in
On Progress Mtr
On Progress 1863
On Progress
On Progress
On Progress
Page 12
Working Time: 7 am to 6:00pm
Page 13
Working Time: 7 am to 6:00pm
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
Page 14
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 31-Jan-16 Working Time: 7 am to 6:00p
Manpower Details Equipment Details Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1 20
18 BUS DRIVER 3
19 Carpenter 1
Total 32 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17
Page 15
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 31-Jan-16 Working Time: 7 am to 6:00p
8 BUS DRIVER 2 16 Electric oven - 50 Kg 1
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 30 Total 16
Total Manpower 80 Total Equipments 50
Page 16
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 31-Jan-16 Working Time: 7 am to 6:00p
10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0
Total 38 Total 7
Total Manpower Total Equipments 7
HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers Done
2 Safety barriers, safety cones and signage boards installed near to the road area Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the road Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted Done
10 Barricades provided near road area (Near Plant Area) Done
Page 17
Working Time: 7 am to 6:00pm
Other Details
Others Qty
Direct Manpower
Rigger 3
Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1
Total 16
Other Details
Others Qty
Shovel Operator
Crane Operator
Draughts man 1
BUS DRIVER 0
Site Surveyor 1
Page 18
Working Time: 7 am to 6:00pm
Total 2
Page 19
Working Time: 7 am to 6:00pm
Other Details
Others Qty
Total 0
Page 20
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 30-Jan-16 Weather: Sunny Temperature: 30ºC
A. Manpower report as on 29-Jan-16 Total Manpower:
B. Equipment report as on 29-Jan-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 29-Jan-16
Page 21
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 30-Jan-16 Weather: Sunny Temperature: 30ºC
3 Welding 2 35 37
4 Pipe Laying 20 620 640
5 First Layer Back Filling 200 0 200
Page 22
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 30-Jan-16 Weather: Sunny Temperature: 30ºC
1 Bedding 80 40 120
2 Fit up 2 45 47
3 Welding 2 42 44
4 Pipe Laying 100 100 100
5 First Layer Back Filling 150 150 150
Other Activity:
1 Pneumatic test for Zone-1 Joint No. R4 to R31 & S4 to S31 Completed
2 Pneumatic test for Zone-1 Joint No. R39 to R62 & S39 to S62 Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed
4 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S 39 to S58 Completed
5 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S4 to S31 Completed
6 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R39 to R58 Completed
7 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R4 to R31 Completed
8 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S1 to S20 Completed
9 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S21 to S31 Completed
10 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R1 to R20 Completed
11 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R21 to R31 Completed
12 2 Coat Primer + 2 coat Epoxy applied in Zone-5 S6 to S38 Completed
Page 23
Working Time: 7 am to 6:00pm
118
57
Remarks
On Progress
On Progress
On Progress Total Excavation
Completed in
On Progress Mtr
On Progress 1843
On Progress
On Progress
On Progress
Page 24
Working Time: 7 am to 6:00pm
Page 25
Working Time: 7 am to 6:00pm
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
Page 26
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 30-Jan-16 Working Time: 7 am to 6:00p
Manpower Details Equipment Details Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1 20
18 BUS DRIVER 3
19 Carpenter 1
Total 32 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17
Page 27
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 30-Jan-16 Working Time: 7 am to 6:00p
8 BUS DRIVER 2 16 Electric oven - 50 Kg 1
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 30 Total 16
Total Manpower 80 Total Equipments 50
Page 28
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 30-Jan-16 Working Time: 7 am to 6:00p
10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0
Total 38 Total 7
Total Manpower Total Equipments 7
HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers Done
2 Safety barriers, safety cones and signage boards installed near to the road area Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the road Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted Done
10 Barricades provided near road area (Near Plant Area) Done
Page 29
Working Time: 7 am to 6:00pm
Other Details
Others Qty
Direct Manpower
Rigger 3
Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1
Total 16
Other Details
Others Qty
Shovel Operator
Crane Operator
Draughts man 1
BUS DRIVER 0
Site Surveyor 1
Page 30
Working Time: 7 am to 6:00pm
Total 2
Page 31
Working Time: 7 am to 6:00pm
Other Details
Others Qty
Total 0
Page 32
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 28-Jan-16 Weather: Sunny Temperature: 30ºC
A. Manpower report as on 27-Jan-16 Total Manpower:
B. Equipment report as on 27-Jan-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 27-Jan-16
Page 33
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 28-Jan-16 Weather: Sunny Temperature: 30ºC
3 Welding 2 35 37
4 Pipe Laying 20 620 640
5 First Layer Back Filling 200 0 200
Page 34
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 28-Jan-16 Weather: Sunny Temperature: 30ºC
1 Bedding 50 40 50
2 Fit up 2 45 47
3 Welding 2 42 44
4 Pipe Laying 100 100 100
5 First Layer Back Filling 150 150 150
Other Activity:
1 Pneumatic test for Zone-1 Joint No. R4 to R31 & S4 to S31 Completed
2 Pneumatic test for Zone-1 Joint No. R39 to R62 & S39 to S62 Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed
4 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S 39 to S58 Completed
5 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S4 to S31 Completed
6 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R39 to R58 Completed
7 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R4 to R31 Completed
8 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S1 to S20 Completed
9 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S21 to S31 Completed
10 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R1 to R20 Completed
11 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R21 to R31 Completed
12 2 Coat Primer + 2 coat Epoxy applied in Zone-5 S6 to S38 Completed
Page 35
Working Time: 7 am to 6:00pm
118
57
Remarks
On Progress
On Progress
On Progress Total Excavation
Completed in
On Progress Mtr
On Progress 1843
On Progress
On Progress
On Progress
Page 36
Working Time: 7 am to 6:00pm
Page 37
Working Time: 7 am to 6:00pm
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
Page 38
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 28-Jan-16 Working Time: 7 am to 6:00p
Manpower Details Equipment Details Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1 20
18 BUS DRIVER 3
19 Carpenter 1
Total 32 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17
Page 39
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 28-Jan-16 Working Time: 7 am to 6:00p
8 BUS DRIVER 2 16 Electric oven - 50 Kg 1
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 30 Total 16
Total Manpower 80 Total Equipments 50
Page 40
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 28-Jan-16 Working Time: 7 am to 6:00p
10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0
Total 38 Total 7
Total Manpower Total Equipments 7
HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers Done
2 Safety barriers, safety cones and signage boards installed near to the road area Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the road Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted Done
10 Barricades provided near road area (Near Plant Area) Done
Page 41
Working Time: 7 am to 6:00pm
Other Details
Others Qty
Direct Manpower
Rigger 3
Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1
Total 16
Other Details
Others Qty
Shovel Operator
Crane Operator
Draughts man 1
BUS DRIVER 0
Site Surveyor 1
Page 42
Working Time: 7 am to 6:00pm
Total 2
Page 43
Working Time: 7 am to 6:00pm
Other Details
Others Qty
Total 0
Page 44
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 27-Jan-16 Weather: Sunny Temperature: 30ºC
A. Manpower report as on 26-Jan-16 Total Manpower:
B. Equipment report as on 26-Jan-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 26-Jan-16
Page 45
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 27-Jan-16 Weather: Sunny Temperature: 30ºC
3 Welding 2 35 37
4 Pipe Laying 20 620 640
5 First Layer Back Filling 200 0 200
Page 46
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 27-Jan-16 Weather: Sunny Temperature: 30ºC
1 Bedding 50 40 50
2 Fit up 2 45 47
3 Welding 2 42 44
4 Pipe Laying
5 First Layer Back Filling
Other Activity:
1 Pneumatic test for Zone-1 Joint No. R4 to R31 & S4 to S31 Completed
2 Pneumatic test for Zone-1 Joint No. R39 to R62 & S39 to S62 Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed
4 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S 39 to S58 Completed
5 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S4 to S31 Completed
6 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R39 to R58 Completed
7 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R4 to R31 Completed
8 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S1 to S20 Completed
9 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S21 to S31 Completed
10 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R1 to R20 Completed
11 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R21 to R31 Completed
12 2 Coat Primer + 2 coat Epoxy applied in Zone-5 S6 to S38 Completed
Page 47
Working Time: 7 am to 6:00pm
118
57
Remarks
On Progress
On Progress
On Progress Total Excavation
Completed in
On Progress Mtr
On Progress 1823
On Progress
On Progress
On Progress
Page 48
Working Time: 7 am to 6:00pm
Page 49
Working Time: 7 am to 6:00pm
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
Page 50
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 27-Jan-16 Working Time: 7 am to 6:00p
Manpower Details Equipment Details Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1 20
18 BUS DRIVER 3
19 Carpenter 1
Total 32 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17
Page 51
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 27-Jan-16 Working Time: 7 am to 6:00p
8 BUS DRIVER 2 16 Electric oven - 50 Kg 1
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 30 Total 16
Total Manpower 80 Total Equipments 50
Page 52
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 27-Jan-16 Working Time: 7 am to 6:00p
10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0
Total 38 Total 7
Total Manpower Total Equipments 7
HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers Done
2 Safety barriers, safety cones and signage boards installed near to the road area Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the road Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted Done
10 Barricades provided near road area (Near Plant Area) Done
Page 53
Working Time: 7 am to 6:00pm
Other Details
Others Qty
Direct Manpower
Rigger 3
Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1
Total 16
Other Details
Others Qty
Shovel Operator
Crane Operator
Draughts man 1
BUS DRIVER 0
Site Surveyor 1
Page 54
Working Time: 7 am to 6:00pm
Total 2
Page 55
Working Time: 7 am to 6:00pm
Other Details
Others Qty
Total 0
Page 56
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 26-Jan-16 Weather: Sunny Temperature: 30ºC
A. Manpower report as on 25-Jan-16 Total Manpower:
B. Equipment report as on 25-Jan-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 25-Jan-16
Page 57
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 26-Jan-16 Weather: Sunny Temperature: 30ºC
3 Welding 2 35 37
4 Pipe Laying 20 620 640
5 First Layer Back Filling 200 0 200
Page 58
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 26-Jan-16 Weather: Sunny Temperature: 30ºC
1 Bedding 50 40 50
2 Fit up 2 45 47
3 Welding 2 42 44
4 Pipe Laying
5 First Layer Back Filling
Other Activity:
1 Pneumatic test for Zone-1 Joint No. R4 to R31 & S4 to S31 Completed
2 Pneumatic test for Zone-1 Joint No. R39 to R62 & S39 to S62 Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed
4 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S 39 to S58 Completed
5 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S4 to S31 Completed
6 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R39 to R58 Completed
7 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R4 to R31 Completed
8 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S1 to S20 Completed
9 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S21 to S31 Completed
10 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R1 to R20 Completed
11 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R21 to R31 Completed
12 2 Coat Primer + 2 coat Epoxy applied in Zone-5 S6 to S38 Completed
Page 59
Working Time: 7 am to 6:00pm
118
57
Remarks
On Progress
On Progress
On Progress Total Excavation
Completed in
On Progress Mtr
On Progress 1823
On Progress
On Progress
On Progress
Page 60
Working Time: 7 am to 6:00pm
Page 61
Working Time: 7 am to 6:00pm
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
Page 62
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 26-Jan-16 Working Time: 7 am to 6:00p
Manpower Details Equipment Details Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1 20
18 BUS DRIVER 3
19 Carpenter 1
Total 32 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17
Page 63
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 26-Jan-16 Working Time: 7 am to 6:00p
8 BUS DRIVER 2 16 Electric oven - 50 Kg 1
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 30 Total 16
Total Manpower 80 Total Equipments 50
Page 64
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 26-Jan-16 Working Time: 7 am to 6:00p
10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0
Total 38 Total 7
Total Manpower Total Equipments 7
HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers Done
2 Safety barriers, safety cones and signage boards installed near to the road area Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the road Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted Done
10 Barricades provided near road area (Near Plant Area) Done
Page 65
Working Time: 7 am to 6:00pm
Other Details
Others Qty
Direct Manpower
Rigger 3
Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1
Total 16
Other Details
Others Qty
Shovel Operator
Crane Operator
Draughts man 1
BUS DRIVER 0
Site Surveyor 1
Page 66
Working Time: 7 am to 6:00pm
Total 2
Page 67
Working Time: 7 am to 6:00pm
Other Details
Others Qty
Total 0
Page 68
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 25-Jan-16 Weather: Sunny Temperature: 30ºC
A. Manpower report as on 24-Jan-16 Total Manpower:
B. Equipment report as on 24-Jan-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 24-Jan-16
Page 69
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 25-Jan-16 Weather: Sunny Temperature: 30ºC
3 Welding 2 35 37
4 Pipe Laying 20 620 640
5 First Layer Back Filling 200 0 200
Page 70
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 25-Jan-16 Weather: Sunny Temperature: 30ºC
1 Bedding 50 40 50
2 Fit up 2 45 47
3 Welding 2 42 44
4 Pipe Laying
5 First Layer Back Filling
Other Activity:
1 Pneumatic test for Zone-1 Joint No. R4 to R31 & S4 to S31 Completed
2 Pneumatic test for Zone-1 Joint No. R39 to R62 & S39 to S62 Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed
4 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S 39 to S58 Completed
5 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S4 to S31 Completed
6 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R39 to R58 Completed
7 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R4 to R31 Completed
8 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S1 to S20 Completed
9 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S21 to S31 Completed
10 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R1 to R20 Completed
11 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R21 to R31 Completed
12 2 Coat Primer + 2 coat Epoxy applied in Zone-5 S6 to S38 Completed
Page 71
Working Time: 7 am to 6:00pm
118
57
Remarks
On Progress
On Progress
On Progress Total Excavation
Completed in
On Progress Mtr
On Progress 1803
On Progress
On Progress
On Progress
Page 72
Working Time: 7 am to 6:00pm
Page 73
Working Time: 7 am to 6:00pm
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
Page 74
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 25-Jan-16 Working Time: 7 am to 6:00p
Manpower Details Equipment Details Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1 20
18 BUS DRIVER 3
19 Carpenter 1
Total 32 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17
Page 75
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 25-Jan-16 Working Time: 7 am to 6:00p
8 BUS DRIVER 2 16 Electric oven - 50 Kg 1
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 30 Total 16
Total Manpower 80 Total Equipments 50
Page 76
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 25-Jan-16 Working Time: 7 am to 6:00p
10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0
Total 38 Total 7
Total Manpower Total Equipments 7
HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers Done
2 Safety barriers, safety cones and signage boards installed near to the road area Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the road Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted Done
10 Barricades provided near road area (Near Plant Area) Done
Page 77
Working Time: 7 am to 6:00pm
Other Details
Others Qty
Direct Manpower
Rigger 3
Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1
Total 16
Other Details
Others Qty
Shovel Operator
Crane Operator
Draughts man 1
BUS DRIVER 0
Site Surveyor 1
Page 78
Working Time: 7 am to 6:00pm
Total 2
Page 79
Working Time: 7 am to 6:00pm
Other Details
Others Qty
Total 0
Page 80
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 24-Jan-16 Weather: Sunny Temperature: 30ºC
A. Manpower report as on 23-Jan-16 Total Manpower:
B. Equipment report as on 23-Jan-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 23-Jan-16
Page 81
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 24-Jan-16 Weather: Sunny Temperature: 30ºC
4 Pipe Laying 20 620 640
5 First Layer Back Filling 200 0 200
1 Bedding 50 40 50
2 Fit up 2 43 45
3 Welding 3 40 43
4 Pipe Laying
5 First Layer Back Filling
Other Activity:
Page 82
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 24-Jan-16 Weather: Sunny Temperature: 30ºC
1 Pneumatic test for Zone-1 Joint No. R4 to R31 & S4 to S31 Completed
2 Pneumatic test for Zone-1 Joint No. R39 to R62 & S39 to S62 Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed
4 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S 39 to S58 Completed
5 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S4 to S31 Completed
6 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R39 to R58 Completed
7 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R4 to R31 Completed
8 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S1 to S20 Completed
9 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S21 to S31 Completed
10 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R1 to R20 Completed
11 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R21 to R31 Completed
12 2 Coat Primer + 2 coat Epoxy applied in Zone-5 S6 to S38 Completed
Page 83
Working Time: 7 am to 6:00pm
118
57
Remarks
On Progress
On Progress
On Progress Total Excavation
Completed in
On Progress Mtr
On Progress 1793
On Progress
On Progress
On Progress
Page 84
Working Time: 7 am to 6:00pm
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
Page 85
Working Time: 7 am to 6:00pm
Page 86
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 24-Jan-16 Working Time: 7 am to 6:00p
Manpower Details Equipment Details Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1 20
18 BUS DRIVER 3
19 Carpenter 1
Total 32 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17
Page 87
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 24-Jan-16 Working Time: 7 am to 6:00p
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 30 Total 16
Total Manpower 80 Total Equipments 50
10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0
Total 38 Total 7
Total Manpower Total Equipments 7
Page 88
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 24-Jan-16 Working Time: 7 am to 6:00p
HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers Done
2 Safety barriers, safety cones and signage boards installed near to the road area Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the road Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted Done
10 Barricades provided near road area (Near Plant Area) Done
Page 89
Working Time: 7 am to 6:00pm
Other Details
Others Qty
Direct Manpower
Rigger 3
Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1
Total 16
Other Details
Others Qty
Shovel Operator
Crane Operator
Draughts man 1
BUS DRIVER 0
Site Surveyor 1
Page 90
Working Time: 7 am to 6:00pm
Total 2
Other Details
Others Qty
Total 0
Page 91
Working Time: 7 am to 6:00pm
Page 92
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 23-Jan-16 Weather: Sunny Temperature: 30ºC
A. Manpower report as on 22-Jan-16 Total Manpower:
B. Equipment report as on 22-Jan-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 22-Jan-16
Page 93
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 23-Jan-16 Weather: Sunny Temperature: 30ºC
4 Pipe Laying 20 620 640
5 First Layer Back Filling 200 0 200
1 Bedding 50 40 50
2 Fit up 2 41 43
3 Welding 3 37 40
4 Pipe Laying
5 First Layer Back Filling
Other Activity:
Page 94
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 23-Jan-16 Weather: Sunny Temperature: 30ºC
1 Pneumatic test for Zone-1 Joint No. R4 to R31 & S4 to S31 Completed
2 Pneumatic test for Zone-1 Joint No. R39 to R62 & S39 to S62 Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed
Page 95
Working Time: 7 am to 6:00pm
118
57
Remarks
On Progress
On Progress
On Progress Total Excavation
Completed in
On Progress Mtr
On Progress 1793
On Progress
On Progress
On Progress
Page 96
Working Time: 7 am to 6:00pm
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
Page 97
Working Time: 7 am to 6:00pm
Page 98
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 23-Jan-16 Working Time: 7 am to 6:00p
Manpower Details Equipment Details Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1 20
18 BUS DRIVER 3
19 Carpenter 1
Total 32 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17
Page 99
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 23-Jan-16 Working Time: 7 am to 6:00p
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 30 Total 16
Total Manpower 80 Total Equipments 50
10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0
Total 38 Total 7
Total Manpower Total Equipments 7
Page 100
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 23-Jan-16 Working Time: 7 am to 6:00p
HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers Done
2 Safety barriers, safety cones and signage boards installed near to the road area Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the road Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted Done
10 Barricades provided near road area (Near Plant Area) Done
Page 101
Working Time: 7 am to 6:00pm
Other Details
Others Qty
Direct Manpower
Rigger 3
Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1
Total 16
Other Details
Others Qty
Shovel Operator
Crane Operator
Draughts man 1
BUS DRIVER 0
Site Surveyor 1
Page 102
Working Time: 7 am to 6:00pm
Total 2
Other Details
Others Qty
Total 0
Page 103
Working Time: 7 am to 6:00pm
Page 104
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 21-Jan-16 Weather: Sunny Temperature: 30ºC
A. Manpower report as on 20-Jan-16 Total Manpower:
B. Equipment report as on 20-Jan-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 20-Jan-16
Page 105
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 21-Jan-16 Weather: Sunny Temperature: 30ºC
4 Pipe Laying 20 620 640
5 First Layer Back Filling 200 0 200
1 Bedding 40 20 40
2 Fit up 2 41 43
3 Welding 3 34 37
4 Pipe Laying
5 First Layer Back Filling
Other Activity:
Page 106
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 21-Jan-16 Weather: Sunny Temperature: 30ºC
1 Pneumatic test for Zone-1 Joint No. R4 to R31 & S4 to S31 Completed
2 Pneumatic test for Zone-1 Joint No. R39 to R62 & S39 to S62 Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed
Page 107
Working Time: 7 am to 6:00pm
118
57
Remarks
On Progress
On Progress
On Progress Total Excavation
Completed in
On Progress Mtr
On Progress 1793
On Progress
On Progress
On Progress
Page 108
Working Time: 7 am to 6:00pm
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
Page 109
Working Time: 7 am to 6:00pm
Page 110
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 21-Jan-16 Working Time: 7 am to 6:00p
Manpower Details Equipment Details Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1 20
18 BUS DRIVER 3
19 Carpenter 1
Total 32 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17
Page 111
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 21-Jan-16 Working Time: 7 am to 6:00p
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 30 Total 16
Total Manpower 80 Total Equipments 50
10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0
Total 38 Total 7
Total Manpower Total Equipments 7
Page 112
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 21-Jan-16 Working Time: 7 am to 6:00p
HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers Done
2 Safety barriers, safety cones and signage boards installed near to the road area Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the road Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted Done
10 Barricades provided near road area (Near Plant Area) Done
Page 113
Working Time: 7 am to 6:00pm
Other Details
Others Qty
Direct Manpower
Rigger 3
Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1
Total 16
Other Details
Others Qty
Shovel Operator
Crane Operator
Draughts man 1
BUS DRIVER 0
Site Surveyor 1
Page 114
Working Time: 7 am to 6:00pm
Total 2
Other Details
Others Qty
Total 0
Page 115
Working Time: 7 am to 6:00pm
Page 116
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 20-Jan-16 Weather: Sunny Temperature: 30ºC
A. Manpower report as on 19-Jan-16 Total Manpower:
B. Equipment report as on 19-Jan-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 19-Jan-16
Page 117
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 20-Jan-16 Weather: Sunny Temperature: 30ºC
4 Pipe Laying 20 620 640
5 First Layer Back Filling 180 0 180
1 Bedding 40 20 40
2 Fit up 2 41 43
3 Welding 3 34 37
4 Pipe Laying
5 First Layer Back Filling
Other Activity:
Page 118
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 20-Jan-16 Weather: Sunny Temperature: 30ºC
1 Pneumatic test for Zone-1 Joint No. R4 to R31 & S4 to S31 Completed
2 Pneumatic test for Zone-1 Joint No. R39 to R62 & S39 to S62 Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed
Page 119
Working Time: 7 am to 6:00pm
119
57
Remarks
On Progress
On Progress
On Progress Total Excavation
Completed in
On Progress Mtr
On Progress 1793
On Progress
On Progress
On Progress
Page 120
Working Time: 7 am to 6:00pm
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
Page 121
Working Time: 7 am to 6:00pm
Page 122
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 20-Jan-16 Working Time: 7 am to 6:00p
Manpower Details Equipment Details Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1 20
18 BUS DRIVER 3
19 Carpenter 1
Total 33 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17
Page 123
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 20-Jan-16 Working Time: 7 am to 6:00p
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 30 Total 16
Total Manpower 81 Total Equipments 50
10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0
Total 38 Total 7
Total Manpower Total Equipments 7
Page 124
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 20-Jan-16 Working Time: 7 am to 6:00p
HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers Done
2 Safety barriers, safety cones and signage boards installed near to the road area Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the road Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted Done
10 Barricades provided near road area (Near Plant Area) Done
Page 125
Working Time: 7 am to 6:00pm
Other Details
Others Qty
Direct Manpower
Rigger 3
Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1
Total 16
Other Details
Others Qty
Shovel Operator
Crane Operator
Draughts man 1
BUS DRIVER 0
Site Surveyor 1
Page 126
Working Time: 7 am to 6:00pm
Total 2
Other Details
Others Qty
Total 0
Page 127
Working Time: 7 am to 6:00pm
Page 128
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 19-Jan-16 Weather: Sunny Temperature: 30ºC
A. Manpower report as on 18-Jan-16 Total Manpower:
B. Equipment report as on 18-Jan-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 18-Jan-16
Page 129
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 19-Jan-16 Weather: Sunny Temperature: 30ºC
4 Pipe Laying 20 620 640
5 First Layer Back Filling 180 0 180
1 Bedding 40 20 40
2 Fit up 2 41 43
3 Welding 3 34 37
4 Pipe Laying
5 First Layer Back Filling
Other Activity:
Page 130
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 19-Jan-16 Weather: Sunny Temperature: 30ºC
1 Pneumatic test for Zone-1 Joint No. R4 to R31 & S4 to S31 Completed
2 Pneumatic test for Zone-1 Joint No. R39 to R62 & S39 to S62 Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed
Page 131
Working Time: 7 am to 6:00pm
119
57
Remarks
On Progress
On Progress
On Progress Total Excavation
Completed in
On Progress Mtr
On Progress 1793
On Progress
On Progress
On Progress
Page 132
Working Time: 7 am to 6:00pm
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
Page 133
Working Time: 7 am to 6:00pm
Page 134
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 19-Jan-16 Working Time: 7 am to 6:00p
Manpower Details Equipment Details Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1 20
18 BUS DRIVER 3
19 Carpenter 1
Total 33 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17
Page 135
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 19-Jan-16 Working Time: 7 am to 6:00p
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 30 Total 16
Total Manpower 81 Total Equipments 50
10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0
Total 38 Total 7
Total Manpower Total Equipments 7
Page 136
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 19-Jan-16 Working Time: 7 am to 6:00p
HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers Done
2 Safety barriers, safety cones and signage boards installed near to the road area Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the road Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted Done
10 Barricades provided near road area (Near Plant Area) Done
Page 137
Working Time: 7 am to 6:00pm
Other Details
Others Qty
Direct Manpower
Rigger 3
Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1
Total 16
Other Details
Others Qty
Shovel Operator
Crane Operator
Draughts man 1
BUS DRIVER 0
Site Surveyor 1
Page 138
Working Time: 7 am to 6:00pm
Total 2
Other Details
Others Qty
Total 0
Page 139
Working Time: 7 am to 6:00pm
Page 140
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 17-Jan-16 Weather: Sunny Temperature: 30ºC
A. Manpower report as on 16-Jan-16 Total Manpower:
B. Equipment report as on 16-Jan-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 16-Jan-16
Page 141
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 17-Jan-16 Weather: Sunny Temperature: 30ºC
4 Pipe Laying 20 600 620
5 First Layer Back Filling 170 0 170
1 Bedding 20 20 20
2 Fit up 2 39 41
3 Welding 3 34 37
4 Pipe Laying
5 First Layer Back Filling
Other Activity:
Page 142
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 17-Jan-16 Weather: Sunny Temperature: 30ºC
1 Pneumatic test for Zone-1 Joint No. R4 to R31 & S4 to S31 Completed
2 Pneumatic test for Zone-1 Joint No. R39 to R62 & S39 to S62 Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed
Page 143
Working Time: 7 am to 6:00pm
118
57
Remarks
On Progress
On Progress
On Progress Total Excavation
Completed in
On Progress Mtr
On Progress 1783
On Progress
On Progress
On Progress
Page 144
Working Time: 7 am to 6:00pm
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
Page 145
Working Time: 7 am to 6:00pm
Page 146
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 17-Jan-16 Working Time: 7 am to 6:00p
Manpower Details Equipment Details Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1 20
18 BUS DRIVER 3
19 Carpenter 1
Total 33 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17
Page 147
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 17-Jan-16 Working Time: 7 am to 6:00p
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 29 Total 16
Total Manpower 80 Total Equipments 50
10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0
Total 38 Total 7
Total Manpower Total Equipments 7
Page 148
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 17-Jan-16 Working Time: 7 am to 6:00p
HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers Done
2 Safety barriers, safety cones and signage boards installed near to the road area Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the road Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted Done
10 Barricades provided near road area (Near Plant Area) Done
Page 149
Working Time: 7 am to 6:00pm
Other Details
Others Qty
Direct Manpower
Rigger 3
Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1
Total 16
Other Details
Others Qty
Shovel Operator
Crane Operator
Draughts man 1
BUS DRIVER 0
Site Surveyor 1
Page 150
Working Time: 7 am to 6:00pm
Total 2
Other Details
Others Qty
Total 0
Page 151
Working Time: 7 am to 6:00pm
Page 152
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 16-Jan-16 Weather: Sunny Temperature: 30ºC
A. Manpower report as on 15-Jan-16 Total Manpower:
B. Equipment report as on 15-Jan-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 15-Jan-16
Page 153
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 16-Jan-16 Weather: Sunny Temperature: 30ºC
4 Pipe Laying 20 600 620
5 First Layer Back Filling 170 0 170
1 Bedding 20 20 20
2 Fit up 2 39 41
3 Welding 3 34 37
4 Pipe Laying
5 First Layer Back Filling
Other Activity:
Page 154
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 16-Jan-16 Weather: Sunny Temperature: 30ºC
1 Pneumatic test for Zone-1 Joint No. R4 to R31 & S4 to S31 Completed
2 Pneumatic test for Zone-1 Joint No. R39 to R62 & S39 to S62 Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed
Page 155
Working Time: 7 am to 6:00pm
117
57
Remarks
On Progress
On Progress
On Progress Total Excavation
Completed in
On Progress Mtr
On Progress 1783
On Progress
On Progress
On Progress
Page 156
Working Time: 7 am to 6:00pm
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
Page 157
Working Time: 7 am to 6:00pm
Page 158
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 16-Jan-16 Working Time: 7 am to 6:00p
Manpower Details Equipment Details Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1 20
18 BUS DRIVER 3
19 Carpenter 1
Total 33 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17
Page 159
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 16-Jan-16 Working Time: 7 am to 6:00p
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 29 Total 16
Total Manpower 80 Total Equipments 50
10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0
Total 37 Total 7
Total Manpower Total Equipments 7
Page 160
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 16-Jan-16 Working Time: 7 am to 6:00p
HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers Done
2 Safety barriers, safety cones and signage boards installed near to the road area Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the road Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted Done
10 Barricades provided near road area (Near Plant Area) Done
Page 161
Working Time: 7 am to 6:00pm
Other Details
Others Qty
Direct Manpower
Rigger 3
Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1
Total 16
Other Details
Others Qty
Shovel Operator
Crane Operator
Draughts man 1
BUS DRIVER 0
Site Surveyor 1
Page 162
Working Time: 7 am to 6:00pm
Total 2
Other Details
Others Qty
Total 0
Page 163
Working Time: 7 am to 6:00pm
Page 164
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 14-Jan-16 Weather: Sunny Temperature: 30ºC
A. Manpower report as on 13-Jan-16 Total Manpower:
B. Equipment report as on 13-Jan-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 13-Jan-16
Page 165
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 14-Jan-16 Weather: Sunny Temperature: 30ºC
4 Pipe Laying 0 600 600
5 First Layer Back Filling 170 0 170
1 Bedding
2 Fit up 2 39 41
3 Welding 3 34 37
4 Pipe Laying
5 First Layer Back Filling
Other Activity:
Page 166
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 14-Jan-16 Weather: Sunny Temperature: 30ºC
1 Pneumatic test for Zone-1 Joint No. R4 to R31 & S4 to S31 Completed
2 Pneumatic test for Zone-1 Joint No. R39 to R62 & S39 to S62 Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed
Page 167
Working Time: 7 am to 6:00pm
117
57
Remarks
On Progress
On Progress
On Progress Total Excavation
Completed in
On Progress Mtr
On Progress 1783
On Progress
On Progress
On Progress
Page 168
Working Time: 7 am to 6:00pm
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
Page 169
Working Time: 7 am to 6:00pm
Page 170
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 14-Jan-16 Working Time: 7 am to 6:00p
Manpower Details Equipment Details Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1 20
18 BUS DRIVER 3
19 Carpenter 1
Total 33 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17
Page 171
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 14-Jan-16 Working Time: 7 am to 6:00p
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 29 Total 16
Total Manpower 80 Total Equipments 50
10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0
Total 37 Total 7
Total Manpower Total Equipments 7
Page 172
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 14-Jan-16 Working Time: 7 am to 6:00p
HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers Done
2 Safety barriers, safety cones and signage boards installed near to the road area Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the road Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted Done
10 Barricades provided near road area (Near Plant Area) Done
Page 173
Working Time: 7 am to 6:00pm
Other Details
Others Qty
Direct Manpower
Rigger 3
Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1
Total 16
Other Details
Others Qty
Shovel Operator
Crane Operator
Draughts man 1
BUS DRIVER 0
Site Surveyor 1
Page 174
Working Time: 7 am to 6:00pm
Total 2
Other Details
Others Qty
Total 0
Page 175
Working Time: 7 am to 6:00pm
Page 176
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 13-Jan-16 Weather: Sunny Temperature: 30ºC
A. Manpower report as on 12-Jan-16 Total Manpower:
B. Equipment report as on 12-Jan-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 12-Jan-16
Page 177
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 13-Jan-16 Weather: Sunny Temperature: 30ºC
4 Pipe Laying 0 600 600
5 First Layer Back Filling 170 0 170
1 Bedding
2 Fit up 2 37 39
3 Welding 2 31 33
4 Pipe Laying
5 First Layer Back Filling
Other Activity:
Page 178
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 13-Jan-16 Weather: Sunny Temperature: 30ºC
1 Pneumatic test for Zone-1 Joint No. R4 to R31 & S4 to S31 Completed
2 Pneumatic test for Zone-1 Joint No. R39 to R62 & S39 to S62 Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed
Page 179
Working Time: 7 am to 6:00pm
117
57
Remarks
On Progress
On Progress
On Progress Total Excavation
Completed in
On Progress Mtr
On Progress 1783
On Progress
On Progress
On Progress
Page 180
Working Time: 7 am to 6:00pm
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
Page 181
Working Time: 7 am to 6:00pm
Page 182
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 13-Jan-16 Working Time: 7 am to 6:00p
Manpower Details Equipment Details Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1 20
18 BUS DRIVER 3
19 Carpenter 1
Total 33 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17
Page 183
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 13-Jan-16 Working Time: 7 am to 6:00p
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 29 Total 16
Total Manpower 80 Total Equipments 50
10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0
Total 37 Total 7
Total Manpower Total Equipments 7
Page 184
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 13-Jan-16 Working Time: 7 am to 6:00p
HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers Done
2 Safety barriers, safety cones and signage boards installed near to the road area Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the road Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted Done
10 Barricades provided near road area (Near Plant Area) Done
Page 185
Working Time: 7 am to 6:00pm
Other Details
Others Qty
Direct Manpower
Rigger 3
Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1
Total 16
Other Details
Others Qty
Shovel Operator
Crane Operator
Draughts man 1
BUS DRIVER 0
Site Surveyor 1
Page 186
Working Time: 7 am to 6:00pm
Total 2
Other Details
Others Qty
Total 0
Page 187
Working Time: 7 am to 6:00pm
Page 188
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 12-Jan-16 Weather: Sunny Temperature: 30ºC
A. Manpower report as on 11-Jan-16 Total Manpower:
B. Equipment report as on 11-Jan-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 11-Jan-16
Page 189
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 12-Jan-16 Weather: Sunny Temperature: 30ºC
4 Pipe Laying 0 600 600
5 First Layer Back Filling 170 0 170
1 Bedding
2 Fit up 2 37 39
3 Welding 2 31 33
4 Pipe Laying
5 First Layer Back Filling
Other Activity:
Page 190
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 12-Jan-16 Weather: Sunny Temperature: 30ºC
1 Pneumatic test for Zone-1 Joint No. R4 to R31 & S4 to S31 Completed
2 Pneumatic test for Zone-1 Joint No. R39 to R62 & S39 to S62 Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed
Page 191
Working Time: 7 am to 6:00pm
117
57
Remarks
On Progress
On Progress
On Progress Total Excavation
Completed in
On Progress Mtr
On Progress 1783
On Progress
On Progress
On Progress
Page 192
Working Time: 7 am to 6:00pm
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
Page 193
Working Time: 7 am to 6:00pm
Page 194
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 12-Jan-16 Working Time: 7 am to 6:00p
Manpower Details Equipment Details Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1 20
18 BUS DRIVER 3
19 Carpenter 1
Total 33 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17
Page 195
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 12-Jan-16 Working Time: 7 am to 6:00p
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 29 Total 16
Total Manpower 80 Total Equipments 50
10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0
Total 37 Total 7
Total Manpower Total Equipments 7
Page 196
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 12-Jan-16 Working Time: 7 am to 6:00p
HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers Done
2 Safety barriers, safety cones and signage boards installed near to the road area Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the road Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted Done
10 Barricades provided near road area (Near Plant Area) Done
Page 197
Working Time: 7 am to 6:00pm
Other Details
Others Qty
Direct Manpower
Rigger 3
Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1
Total 16
Other Details
Others Qty
Shovel Operator
Crane Operator
Draughts man 1
BUS DRIVER 0
Site Surveyor 1
Page 198
Working Time: 7 am to 6:00pm
Total 2
Other Details
Others Qty
Total 0
Page 199
Working Time: 7 am to 6:00pm
Page 200
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 11-Jan-16 Weather: Sunny Temperature: 30ºC
A. Manpower report as on 10-Jan-16 Total Manpower:
B. Equipment report as on 10-Jan-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 10-Jan-16
Page 201
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 11-Jan-16 Weather: Sunny Temperature: 30ºC
4 Pipe Laying 0 600 600
5 First Layer Back Filling 170 0 170
1 Bedding
2 Fit up 2 37 39
3 Welding 2 31 33
4 Pipe Laying
5 First Layer Back Filling
Page 202
Working Time: 7 am to 6:00pm
113
57
Remarks
On Progress
On Progress
On Progress Total Excavation
Completed in
On Progress Mtr
On Progress 1773
On Progress
On Progress
On Progress
Page 203
Working Time: 7 am to 6:00pm
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
Page 204
Working Time: 7 am to 6:00pm
Page 205
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 11-Jan-16 Working Time: 7 am to 6:00p
Manpower Details Equipment Details Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1 20
18 BUS DRIVER 3
19 Carpenter 1
Total 33 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17
Page 206
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 11-Jan-16 Working Time: 7 am to 6:00p
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 29 Total 16
Total Manpower 80 Total Equipments 50
10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0
Total 37 Total 7
Total Manpower Total Equipments 7
Page 207
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 11-Jan-16 Working Time: 7 am to 6:00p
HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers Done
2 Safety barriers, safety cones and signage boards installed near to the road area Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the road Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted Done
10 Barricades provided near road area (Near Plant Area) Done
Page 208
Working Time: 7 am to 6:00pm
Other Details
Others Qty
Direct Manpower
Rigger 3
Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1
Total 16
Other Details
Others Qty
Shovel Operator
Crane Operator
Draughts man 1
BUS DRIVER 0
Site Surveyor 1
Page 209
Working Time: 7 am to 6:00pm
Total 2
Other Details
Others Qty
Total 0
Page 210
Working Time: 7 am to 6:00pm
Page 211
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 10-Jan-16 Weather: Sunny Temperature: 30ºC
A. Manpower report as on 9-Jan-16 Total Manpower:
B. Equipment report as on 9-Jan-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 9-Jan-16
Page 212
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 10-Jan-16 Weather: Sunny Temperature: 30ºC
4 Pipe Laying 0 600 600
5 First Layer Back Filling 170 0 170
1 Bedding
2 Fit up 3 35 38
3 Welding 4 29 33
4 Pipe Laying
5 First Layer Back Filling
Page 213
Working Time: 7 am to 6:00pm
113
57
Remarks
On Progress
On Progress
On Progress Total Excavation
Completed in
On Progress Mtr
On Progress 1773
On Progress
On Progress
On Progress
Page 214
Working Time: 7 am to 6:00pm
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
Page 215
Working Time: 7 am to 6:00pm
Page 216
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 10-Jan-16 Working Time: 7 am to 6:00p
Manpower Details Equipment Details Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1 20
18 BUS DRIVER 3
19 Carpenter 1
Total 33 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17
Page 217
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 10-Jan-16 Working Time: 7 am to 6:00p
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 29 Total 16
Total Manpower 80 Total Equipments 50
10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0
Total 37 Total 7
Total Manpower Total Equipments 7
Page 218
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 10-Jan-16 Working Time: 7 am to 6:00p
HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers Done
2 Safety barriers, safety cones and signage boards installed near to the road area Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the road Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted Done
10 Barricades provided near road area (Near Plant Area) Done
Page 219
Working Time: 7 am to 6:00pm
Other Details
Others Qty
Direct Manpower
Rigger 3
Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1
Total 16
Other Details
Others Qty
Shovel Operator
Crane Operator
Draughts man 1
BUS DRIVER 0
Site Surveyor 1
Page 220
Working Time: 7 am to 6:00pm
Total 2
Other Details
Others Qty
Total 0
Page 221
Working Time: 7 am to 6:00pm
Page 222
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 9-Jan-16 Weather: Sunny Temperature: 30ºC
A. Manpower report as on 8-Jan-16 Total Manpower:
B. Equipment report as on 8-Jan-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 8-Jan-16
Page 223
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 9-Jan-16 Weather: Sunny Temperature: 30ºC
4 Pipe Laying 0 600 600
5 First Layer Back Filling 170 0 170
1 Bedding
2 Fit up 2 35 37
3 Welding 4 29 33
4 Pipe Laying
5 First Layer Back Filling
Page 224
Working Time: 7 am to 6:00pm
113
57
Remarks
On Progress
On Progress
On Progress Total Excavation
Completed in
On Progress Mtr
On Progress 1763
On Progress
On Progress
On Progress
Page 225
Working Time: 7 am to 6:00pm
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
Page 226
Working Time: 7 am to 6:00pm
Page 227
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 9-Jan-16 Working Time: 7 am to 6:00p
Manpower Details Equipment Details Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1 20
18 BUS DRIVER 3
19 Carpenter 1
Total 33 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17
Page 228
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 9-Jan-16 Working Time: 7 am to 6:00p
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 29 Total 16
Total Manpower 80 Total Equipments 50
10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0
Total 37 Total 7
Total Manpower Total Equipments 7
Page 229
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 9-Jan-16 Working Time: 7 am to 6:00p
HSE Issues:
F. HSE Issues:
1 orange mesh installed at ETS 1 locations Done
2 Safety barriers, safety cones and signage boards installed near to the road area Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the road Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted Done
10 Barricades provided near road area (Near Plant Area) Done
Page 230
Working Time: 7 am to 6:00pm
Other Details
Others Qty
Direct Manpower
Rigger 3
Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1
Total 16
Other Details
Others Qty
Shovel Operator
Crane Operator
Draughts man 1
BUS DRIVER 0
Site Surveyor 1
Page 231
Working Time: 7 am to 6:00pm
Total 2
Other Details
Others Qty
Total 0
Page 232
Working Time: 7 am to 6:00pm
Page 233
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 7-Jan-16 Weather: Sunny Temperature: 30ºC
A. Manpower report as on 6-Jan-16 Total Manpower:
B. Equipment report as on 6-Jan-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 6-Jan-16
Page 234
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 7-Jan-16 Weather: Sunny Temperature: 30ºC
4 Pipe Laying 0 600 600
5 First Layer Back Filling 170 0 170
1 Bedding
2 Fit up 2 33 35
3 Welding 2 25 27
4 Pipe Laying
5 First Layer Back Filling
Page 235
Working Time: 7 am to 6:00pm
113
57
Remarks
On Progress
On Progress
On Progress Total Excavation
Completed in
On Progress Mtr
On Progress 1753
On Progress
On Progress
On Progress
Page 236
Working Time: 7 am to 6:00pm
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
Page 237
Working Time: 7 am to 6:00pm
Page 238
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 7-Jan-16 Working Time: 7 am to 6:00p
Manpower Details Equipment Details Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1 20
18 BUS DRIVER 3
19 Carpenter 1
Total 33 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17
Page 239
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 7-Jan-16 Working Time: 7 am to 6:00p
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 29 Total 16
Total Manpower 80 Total Equipments 50
10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0
Total 37 Total 7
Total Manpower Total Equipments 7
Page 240
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 7-Jan-16 Working Time: 7 am to 6:00p
HSE Issues:
F. HSE Issues:
1 orange mesh installed at ETS 1 locations Done
2 Safety barriers, safety cones and signage boards installed near to the road area Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the road Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted Done
10 Barricades provided near road area (Near Plant Area) Done
Page 241
Working Time: 7 am to 6:00pm
Other Details
Others Qty
Direct Manpower
Rigger 3
Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1
Total 16
Other Details
Others Qty
Shovel Operator
Crane Operator
Draughts man 1
BUS DRIVER 0
Site Surveyor 1
Page 242
Working Time: 7 am to 6:00pm
Total 2
Other Details
Others Qty
Total 0
Page 243
Working Time: 7 am to 6:00pm
Page 244
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 7-Jan-16 Weather: Sunny Temperature: 30ºC
A. Manpower report as on 6-Jan-16 Total Manpower:
B. Equipment report as on 6-Jan-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 6-Jan-16
Page 245
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 7-Jan-16 Weather: Sunny Temperature: 30ºC
4 Pipe Laying 0 600 600
5 First Layer Back Filling 170 0 170
1 Bedding
2 Fit up 2 33 35
3 Welding 2 25 27
4 Pipe Laying
5 First Layer Back Filling
Page 246
Working Time: 7 am to 6:00pm
113
57
Remarks
On Progress
On Progress
On Progress Total Excavation
Completed in
On Progress Mtr
On Progress 1753
On Progress
On Progress
On Progress
Page 247
Working Time: 7 am to 6:00pm
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
Page 248
Working Time: 7 am to 6:00pm
Page 249
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 7-Jan-16 Working Time: 7 am to 6:00p
Manpower Details Equipment Details Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1 20
18 BUS DRIVER 3
19 Carpenter 1
Total 33 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17
Page 250
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 7-Jan-16 Working Time: 7 am to 6:00p
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 29 Total 16
Total Manpower 80 Total Equipments 50
10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0
Total 37 Total 7
Total Manpower Total Equipments 7
Page 251
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 7-Jan-16 Working Time: 7 am to 6:00p
HSE Issues:
F. HSE Issues:
1 orange mesh installed at ETS 1 locations Done
2 Safety barriers, safety cones and signage boards installed near to the road area Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the road Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted Done
10 Barricades provided near road area (Near Plant Area) Done
Page 252
Working Time: 7 am to 6:00pm
Other Details
Others Qty
Direct Manpower
Rigger 3
Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1
Total 16
Other Details
Others Qty
Shovel Operator
Crane Operator
Draughts man 1
BUS DRIVER 0
Site Surveyor 1
Page 253
Working Time: 7 am to 6:00pm
Total 2
Other Details
Others Qty
Total 0
Page 254
Working Time: 7 am to 6:00pm
Page 255
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 5-Jan-16 Weather: Sunny Temperature: 30ºC
A. Manpower report as on 4-Jan-16 Total Manpower:
B. Equipment report as on 4-Jan-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 4-Jan-16
Page 256
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 5-Jan-16 Weather: Sunny Temperature: 30ºC
4 Pipe Laying 0 600 600
5 First Layer Back Filling 170 0 170
1 Bedding
2 Fit up 2 33 35
3 Welding 2 25 27
4 Pipe Laying
5 First Layer Back Filling
Page 257
Working Time: 7 am to 6:00pm
113
57
Remarks
On Progress
On Progress
On Progress Total Excavation
Completed in
On Progress Mtr
On Progress 1733
On Progress
On Progress
On Progress
Page 258
Working Time: 7 am to 6:00pm
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
Page 259
Working Time: 7 am to 6:00pm
Page 260
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 5-Jan-16 Working Time: 7 am to 6:00p
Manpower Details Equipment Details Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1 20
18 BUS DRIVER 3
19 Carpenter 1
Total 33 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17
Page 261
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 5-Jan-16 Working Time: 7 am to 6:00p
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 29 Total 16
Total Manpower 80 Total Equipments 50
10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0
Total 37 Total 7
Total Manpower Total Equipments 7
Page 262
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 5-Jan-16 Working Time: 7 am to 6:00p
HSE Issues:
F. HSE Issues:
1 orange mesh installed at ETS 1 locations Done
2 Safety barriers, safety cones and signage boards installed near to the road area Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the road Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted Done
10 Barricades provided near road area (Near Plant Area) Done
Page 263
Working Time: 7 am to 6:00pm
Other Details
Others Qty
Direct Manpower
Rigger 3
Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1
Total 16
Other Details
Others Qty
Shovel Operator
Crane Operator
Draughts man 1
BUS DRIVER 0
Site Surveyor 1
Page 264
Working Time: 7 am to 6:00pm
Total 2
Other Details
Others Qty
Total 0
Page 265
Working Time: 7 am to 6:00pm
Page 266
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 4-Jan-16 Weather: Sunny Temperature: 30ºC Working Time:
Total
Activity - 14 inch Current inmtr/no
Previous in mtr/no
inmtr/no
1 Bedding
2 Fit up 2 33 35
3 Welding 2 25 27
4 Pipe Laying
5 First Layer Back Filling
AWI
7 am to 6:00pm
Remarks
Total
Excavation
Completed
in Mtr
1723
& Stamp
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 4-Jan-16 Working Time: 7 am to
18 BUS DRIVER 3
19 Carpenter 1
Total 33 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other D
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17
10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0
Total 37 Total 7
Total Manpower Total Equipments 7
HSE Issues:
F. HSE Issues:
1 orange mesh installed at ETS 1 locations Done
2 Safety barriers, safety cones and signage boards installed near to the road area Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the road Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signages were poste Done
10 Barricades provided near road area (Near Plant Area) Done
Working Time: 7 am to 6:00pm
Other Details
Others Qty
Direct Manpower
Rigger 3
Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1
Total 16
Other Details
Others Qty
Shovel Operator
Crane Operator
Draughts man 1
BUS DRIVER 0
Site Surveyor 1
Total 2
Total 0
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 3-Jan-16 Weather: Sunny Temperature: 30ºC Working Time:7 am to 6:00pm
Total in
Activity - 10 inch Current inPrevious
mtr/no in mtr/no
mtr/no
D. Today Planned
ETS-B TIE BEAMActivities
Steel fixing , Deshuttering for Tie3-Jan-16
Beam ETS 3 ,
1 Shifting Shuttering to ETS B. To Be Progressed
2 Zone - 4 pipe line doubling fit up is going on. To Be Progressed
3 ETS - B Pipe line Doubling and welding is goin on. To Be Progressed
4 Zone - 2 - 20 inch Pipe Doubling and Welding is going on. To Be Progressed
5 Main Line 20 inch pipe fit up and welding is going on.- Z-2 & 1 To Be Progressed
6 20 inch main line Doubling and Welding in Zone - 2 & 1 To Be Progressed
7 Zone - 2 and 4 Excavation is going on. To Be Progressed
8 ETS - B and A Route pipe line fit up and welding is going on. To Be Progressed
9 Inside militry school excavation is going on - Zone -2 and Zone -To Be Progressed
Total
Activity - 14 inch Current inmtr/no
Previous in mtr/no
inmtr/no
1 Bedding
2 Fit up 2 33 35
3 Welding 2 25 27
4 Pipe Laying
5 First Layer Back Filling
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 3-Jan-16 Working Time: 7 am to 6:00pm
18 BUS DRIVER 3
19 Carpenter 1
Total 33 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17
10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Op 0
Total 37 Total 7
Total Manpower Total Equipments 7
HSE Issues:
F. HSE Issues:
1 orange mesh installed at ETS 1 locations Done
2 Safety barriers, safety cones and signage boards installed near to the road Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the r Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signa Done
10 Barricades provided near road area (Near Plant Area) Done
AHAWI
Other Details
Others Qty
Direct Manpower
Rigger 3
Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1
Total 16
C
Other Details
Others Qty
Shovel Operator
Crane Operator
Draughts man 1
BUS DRIVER 0
Site Surveyor 1
Total 2
Other Details
Others Qty
Total 0