0% found this document useful (0 votes)
105 views284 pages

DPR - Jan

The daily progress report summarizes construction activities between January 30-31, 2016 for the External Chilled Water Piping Network project at Mahawi. Key activities included doubling pipe lines, excavation, pipe fitting and welding of 20 inch, 18 inch, 12 inch and 10 inch pipes. Metrics are provided on excavation, bedding, fitting, doubling, laying and backfilling progress. The report also lists planned activities for January 31, including steel fixing and deck casting at ETS-B. Temperatures were sunny with 30°C heat.

Uploaded by

Ajas Aju
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
105 views284 pages

DPR - Jan

The daily progress report summarizes construction activities between January 30-31, 2016 for the External Chilled Water Piping Network project at Mahawi. Key activities included doubling pipe lines, excavation, pipe fitting and welding of 20 inch, 18 inch, 12 inch and 10 inch pipes. Metrics are provided on excavation, bedding, fitting, doubling, laying and backfilling progress. The report also lists planned activities for January 31, including steel fixing and deck casting at ETS-B. Temperatures were sunny with 30°C heat.

Uploaded by

Ajas Aju
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 284

PROJECT TITLE: CONSTRUCTION OF BULK STORAGE TANK & FUEL SYSTEM AT SWEIHAN AIR BASE

PROJECT NO: CMW-10009-B001


DAILY PROGRESS REPORT
Date: 5-May-15 Weather: Sunny Temperature: 45ºC Working Time:
A. Manpower report as on Total Manpower:
B. Equipment report as on Total Equipment:
C. Progress Report - Executive Summary-
Sl No. Activities Done On Status
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
D. Today Planned Activities
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
F. Other Issues:
PROJECT TITLE: CONSTRUCTION OF BULK STORAGE TANK & FUEL SYSTEM AT SWEIHAN AIR BASE
PROJECT NO: CMW-10009-B001
DAILY PROGRESS REPORT
Date: 5-May-15 Weather: Sunny Temperature: 45ºC Working Time:

Contractor Sign & Stamp Client Sign & Stamp


AIR BASE

7:30am to 5:00pm

Remarks
AIR BASE

7:30am to 5:00pm

Stamp
PROJECT TITLE: CONSTRUCTION OF BULK STORAGE TANK & FUEL SYSTEM AT SWEIHAN AIR BASE
PROJECT NO: CMW-10009-B001
DAILY PROGRESS REPORT
Working Time: 7:30am to 5:00pm
Manpower Details Equipment Details Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 1 Crane 1
1 Project Manager 1 2 Excavator 2
2 Electrical Engineer (Site) 1 3 JCB 1 3
3 Mechanical Engineer (Site) 1 4 Shovel 4
4 Civil Engineer (Site) 1 5 Bob-Cat 5
5 Planning Engineer 1 6 Roller Compactor 6
6 Draftsman 1 7 Generator 1 7
7 Document Controller 1 8 Threading Machine 8
Direct Manpower 9 Welding Machine 9
8 Mech Supervisor 1 10 Water Tanker 10
9 Electrical Supervisor 1 11 Dump Truck 11
10 Pipe fitter 2 12 Trailer 12
11 Welder 1 13 Grader 13
12 Plumber 14 Pickup 1 14
13 Carpenter 15 3 Ton Pickup 1 15
14 Electrician 1 16 16
15 Helper 3 17 17
16 Machinery Driver 1 18 18
17 Driver 1 19 19
18 20 20
19 21 21
20 22 22
Total 18 Total 4
SubContractor
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Abdula Al Kulaib
1 Civil Engineer 1 1 Shovel 1 1
2 Supervisor 1 2 Ground Compactor 1 2
3 Machine Operator 2 3 Cutting Machine 1 3
4 Driver 1 4 Bending Machine 1 4
5 Carpenter 2 5 5
6 Helper 7 6 6
7 Mason 3 7 7
8 Steel Fitter 5 8 8
9 9 9
Total 22 Total 4
PROJECT TITLE: CONSTRUCTION OF BULK STORAGE TANK & FUEL SYSTEM AT SWEIHAN AIR BASE
PROJECT NO: CMW-10009-B001
DAILY PROGRESS REPORT
Working Time: 7:30am to 5:00pm
Total Manpower 40 Total Equipments 8
Contractor Sign & Stamp Client Sign & Stamp
SWEIHAN AIR BASE

Other Details
Others Qty

Total 0

Other Details
Others Qty

Total 0
SWEIHAN AIR BASE

ent Sign & Stamp


PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 31-Jan-16 Weather: Sunny Temperature: 30ºC
A. Manpower report as on 30-Jan-16 Total Manpower:
B. Equipment report as on 30-Jan-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 30-Jan-16

1 Zone - 4 pipe line doubling fit up.


2 Main Line 20 inch pipe fit up and welding.
3 Zone -3 Excavation.
4 ETS - B valve chamber Second wall steel work.
5 ETS - B and A Route pipe line fit up and welding.
6 Zone -4 Excavation is going on.
7 Inside military school excavation is going on Zone -2 and Zone - 4
8 Casting for ETS 3 Tie beam completed , Back filling in ETS 1 & 3
Activity - 20 & 18 INCH PIPE Current in mtr/no Previous in mtr/no Total in mtr/no

1 Excavation (Zone -1 and 2) 20 1843 1863


2 Bedding 20 1100 1120
3 Fit up 4 149 153
4 Doubling 5 148 153
5 Pipe Laying Fit up 3 75 78
6 Pipe Laying Welding 3 65 68
7 UPVC Sleeve Laying 200 500 700
8 Backfilling 100 500 600
Activity - 12 inch Current inmtr/no Previous in mtr/no Total inmtr/no

1 Bedding 100 300 400


2 Fit up 2 70 72
3 Doubling 2 62 64
4 Pipe Laying 300 280 580
5 First Layer Back Filling
6 Pipe Laying Fit up
7 Pipe Laying Welding

Activity - 10 inch Current in mtr/no Previous in mtr/no Total in mtr/no

1 Bedding 400 370 770


2 Fit up 2 67 69

Page 9
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 31-Jan-16 Weather: Sunny Temperature: 30ºC
3 Welding 2 35 37
4 Pipe Laying 20 620 640
5 First Layer Back Filling 100 200 300

Contractor Sign & Stamp Client Sign & Stamp

Page 10
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 31-Jan-16 Weather: Sunny Temperature: 30ºC

D. Today Planned Activities 31-Jan-16


1 ETS-B TIE BEAM Steel fixing , Deshuttering for Tie Beam ETS 3 , Shifting Shuttering to ETS B.
2 Zone - 4 pipe line doubling fit up is going on.
3 ETS - B Pipe line Doubling and welding is goin on.
4 Zone - 2 - 20 inch Pipe Doubling and Welding is going on.
5 Main Line 20 inch pipe fit up and welding is going on.- Z-2 & 1
6 20 inch main line Doubling and Welding in Zone - 2 & 1
7 Zone - 2 and 4 Excavation is going on.
8 ETS - B and A Route pipe line fit up and welding is going on.
9 Inside militry school excavation is going on - Zone -2 and Zone - 4

Activity - 14 inch Current inmtr/no Previous in mtr/no Total inmtr/no

1 Bedding 80 40 120
2 Fit up 2 45 47
3 Welding 2 42 44
4 Pipe Laying 50 100 150
5 First Layer Back Filling 50 150 200

Other Activity:
1 Pneumatic test for Zone-1 Joint No. R4 to R31 & S4 to S31 Completed
2 Pneumatic test for Zone-1 Joint No. R39 to R62 & S39 to S62 Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed
4 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S 39 to S58 Completed
5 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S4 to S31 Completed
6 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R39 to R58 Completed
7 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R4 to R31 Completed
8 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S1 to S20 Completed
9 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S21 to S31 Completed
10 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R1 to R20 Completed
11 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R21 to R31 Completed
12 2 Coat Primer + 2 coat Epoxy applied in Zone-5 S6 to S38 Completed

Page 11
Working Time: 7 am to 6:00pm
118
57

Remarks

On Progress
On Progress
On Progress Total Excavation
Completed in
On Progress Mtr
On Progress 1863
On Progress
On Progress
On Progress

Page 12
Working Time: 7 am to 6:00pm

nt Sign & Stamp

Page 13
Working Time: 7 am to 6:00pm

To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed

Page 14
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 31-Jan-16 Working Time: 7 am to 6:00p
Manpower Details Equipment Details Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1 20

10 Safety Officer 1 31 Portable Oven 5 21


11 Welder 6 32 1 22
12 Fitter 1 33 25 ton Crane 1 23
13 Sheet Fabricator 1 34 Water Tanker 1 24
14 Helper 6 25
15 Mason 1
16 Excavator & Shovel Operator 2
17 JCB Operator 1

18 BUS DRIVER 3
19 Carpenter 1
Total 32 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17

4 Site Foreman 1 12 SHOVEL 1 18


5 Fitter 0 13 25 ton Crane 0 19
6 Tak Welder 2 14 Diesel Welding machine 2
7 General Workers 6 15 Electric Welding machine 3

Page 15
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 31-Jan-16 Working Time: 7 am to 6:00p
8 BUS DRIVER 2 16 Electric oven - 50 Kg 1
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 30 Total 16
Total Manpower 80 Total Equipments 50

Contractor Sign & Stamp Client Sign & Stamp

Page 16
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 31-Jan-16 Working Time: 7 am to 6:00p

SubContractor - Richmond - J&J


Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Richmond - J&J
1 Project Engineer 1 9 Mini Bus 1
2 Document Controller 1 10 Wheel Excavator 1
3 Office Asst 0 11 Roller Compactor 1
4 Site Foreman 2 12 SHOWEL 0
5 Mason 6 13 3 ton pick up 1
6 Helper 10 14 Steel Cutting Machine 1
7 Carpenter 8 15 Steel Bending machine 1
8 BUS DRIVER 1 16 JCB 0
9 Steel Worker 8 17 2 ton roller compactor 1

10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0

Total 38 Total 7
Total Manpower Total Equipments 7

HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers Done
2 Safety barriers, safety cones and signage boards installed near to the road area Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the road Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted Done
10 Barricades provided near road area (Near Plant Area) Done

Page 17
Working Time: 7 am to 6:00pm
Other Details
Others Qty

Direct Manpower
Rigger 3

Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1

Total 16

Other Details
Others Qty

Shovel Operator
Crane Operator
Draughts man 1

BUS DRIVER 0
Site Surveyor 1

Page 18
Working Time: 7 am to 6:00pm

Total 2

ent Sign & Stamp

Page 19
Working Time: 7 am to 6:00pm

Other Details
Others Qty

Total 0

Page 20
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 30-Jan-16 Weather: Sunny Temperature: 30ºC
A. Manpower report as on 29-Jan-16 Total Manpower:
B. Equipment report as on 29-Jan-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 29-Jan-16

1 Zone - 4 pipe line doubling fit up.


2 Main Line 20 inch pipe fit up and welding.
3 Zone -3 Excavation.
4 ETS - B valve chamber Second wall steel work.
5 ETS - B and A Route pipe line fit up and welding.
6 Zone -4 Excavation is going on.
7 Inside military school excavation is going on Zone -2 and Zone - 4
8 Casting for ETS 3 Tie beam completed , Back filling in ETS 1 & 3
Activity - 20 & 18 INCH PIPE Current in mtr/no Previous in mtr/no Total in mtr/no

1 Excavation (Zone -1 and 2) 20 1823 1843


2 Bedding 20 1100 1120
3 Fit up 4 149 153
4 Doubling 5 148 153
5 Pipe Laying Fit up 3 75 78
6 Pipe Laying Welding 6 62 68
7 UPVC Sleeve Laying 100 400 500
8 Backfilling 100 400 500
Activity - 12 inch Current inmtr/no Previous in mtr/no Total inmtr/no

1 Bedding 100 300 400


2 Fit up 2 70 72
3 Doubling 2 62 64
4 Pipe Laying 300 280 580
5 First Layer Back Filling
6 Pipe Laying Fit up
7 Pipe Laying Welding

Activity - 10 inch Current in mtr/no Previous in mtr/no Total in mtr/no

1 Bedding 400 370 770


2 Fit up 2 67 69

Page 21
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 30-Jan-16 Weather: Sunny Temperature: 30ºC
3 Welding 2 35 37
4 Pipe Laying 20 620 640
5 First Layer Back Filling 200 0 200

Contractor Sign & Stamp Client Sign & Stamp

Page 22
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 30-Jan-16 Weather: Sunny Temperature: 30ºC

D. Today Planned Activities 30-Jan-16


1 ETS-B TIE BEAM Steel fixing , Deshuttering for Tie Beam ETS 3 , Shifting Shuttering to ETS B.
2 Zone - 4 pipe line doubling fit up is going on.
3 ETS - B Pipe line Doubling and welding is goin on.
4 Zone - 2 - 20 inch Pipe Doubling and Welding is going on.
5 Main Line 20 inch pipe fit up and welding is going on.- Z-2 & 1
6 20 inch main line Doubling and Welding in Zone - 2 & 1
7 Zone - 2 and 4 Excavation is going on.
8 ETS - B and A Route pipe line fit up and welding is going on.
9 Inside militry school excavation is going on - Zone -2 and Zone - 4

Activity - 14 inch Current inmtr/no Previous in mtr/no Total inmtr/no

1 Bedding 80 40 120
2 Fit up 2 45 47
3 Welding 2 42 44
4 Pipe Laying 100 100 100
5 First Layer Back Filling 150 150 150

Other Activity:
1 Pneumatic test for Zone-1 Joint No. R4 to R31 & S4 to S31 Completed
2 Pneumatic test for Zone-1 Joint No. R39 to R62 & S39 to S62 Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed
4 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S 39 to S58 Completed
5 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S4 to S31 Completed
6 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R39 to R58 Completed
7 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R4 to R31 Completed
8 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S1 to S20 Completed
9 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S21 to S31 Completed
10 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R1 to R20 Completed
11 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R21 to R31 Completed
12 2 Coat Primer + 2 coat Epoxy applied in Zone-5 S6 to S38 Completed

Page 23
Working Time: 7 am to 6:00pm
118
57

Remarks

On Progress
On Progress
On Progress Total Excavation
Completed in
On Progress Mtr
On Progress 1843
On Progress
On Progress
On Progress

Page 24
Working Time: 7 am to 6:00pm

nt Sign & Stamp

Page 25
Working Time: 7 am to 6:00pm

To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed

Page 26
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 30-Jan-16 Working Time: 7 am to 6:00p
Manpower Details Equipment Details Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1 20

10 Safety Officer 1 31 Portable Oven 5 21


11 Welder 6 32 1 22
12 Fitter 1 33 25 ton Crane 1 23
13 Sheet Fabricator 1 34 Water Tanker 1 24
14 Helper 6 25
15 Mason 1
16 Excavator & Shovel Operator 2
17 JCB Operator 1

18 BUS DRIVER 3
19 Carpenter 1
Total 32 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17

4 Site Foreman 1 12 SHOVEL 1 18


5 Fitter 0 13 25 ton Crane 0 19
6 Tak Welder 2 14 Diesel Welding machine 2
7 General Workers 6 15 Electric Welding machine 3

Page 27
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 30-Jan-16 Working Time: 7 am to 6:00p
8 BUS DRIVER 2 16 Electric oven - 50 Kg 1
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 30 Total 16
Total Manpower 80 Total Equipments 50

Contractor Sign & Stamp Client Sign & Stamp

Page 28
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 30-Jan-16 Working Time: 7 am to 6:00p

SubContractor - Richmond - J&J


Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Richmond - J&J
1 Project Engineer 1 9 Mini Bus 1
2 Document Controller 1 10 Wheel Excavator 1
3 Office Asst 0 11 Roller Compactor 1
4 Site Foreman 2 12 SHOWEL 0
5 Mason 6 13 3 ton pick up 1
6 Helper 10 14 Steel Cutting Machine 1
7 Carpenter 8 15 Steel Bending machine 1
8 BUS DRIVER 1 16 JCB 0
9 Steel Worker 8 17 2 ton roller compactor 1

10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0

Total 38 Total 7
Total Manpower Total Equipments 7

HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers Done
2 Safety barriers, safety cones and signage boards installed near to the road area Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the road Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted Done
10 Barricades provided near road area (Near Plant Area) Done

Page 29
Working Time: 7 am to 6:00pm
Other Details
Others Qty

Direct Manpower
Rigger 3

Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1

Total 16

Other Details
Others Qty

Shovel Operator
Crane Operator
Draughts man 1

BUS DRIVER 0
Site Surveyor 1

Page 30
Working Time: 7 am to 6:00pm

Total 2

ent Sign & Stamp

Page 31
Working Time: 7 am to 6:00pm

Other Details
Others Qty

Total 0

Page 32
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 28-Jan-16 Weather: Sunny Temperature: 30ºC
A. Manpower report as on 27-Jan-16 Total Manpower:
B. Equipment report as on 27-Jan-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 27-Jan-16

1 Zone - 4 pipe line doubling fit up.


2 Main Line 20 inch pipe fit up and welding.
3 Zone -3 Excavation.
4 ETS - B valve chamber Second wall steel work.
5 ETS - B and A Route pipe line fit up and welding.
6 Zone -4 Excavation is going on.
7 Inside military school excavation is going on Zone -2 and Zone - 4
8 Casting for ETS 3 Tie beam completed , Back filling in ETS 1 & 3
Activity - 20 & 18 INCH PIPE Current in mtr/no Previous in mtr/no Total in mtr/no

1 Excavation (Zone -1 and 2) 20 1823 1843


2 Bedding 20 1100 1120
3 Fit up 4 149 153
4 Doubling 5 148 153
5 Pipe Laying Fit up 3 75 78
6 Pipe Laying Welding 6 62 68
7 UPVC Sleeve Laying 100 400 500
8 Backfilling 100 400 500
Activity - 12 inch Current inmtr/no Previous in mtr/no Total inmtr/no

1 Bedding 100 300 400


2 Fit up 2 70 72
3 Doubling 2 62 64
4 Pipe Laying 300 280 580
5 First Layer Back Filling
6 Pipe Laying Fit up
7 Pipe Laying Welding

Activity - 10 inch Current in mtr/no Previous in mtr/no Total in mtr/no

1 Bedding 400 370 770


2 Fit up 2 67 69

Page 33
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 28-Jan-16 Weather: Sunny Temperature: 30ºC
3 Welding 2 35 37
4 Pipe Laying 20 620 640
5 First Layer Back Filling 200 0 200

Contractor Sign & Stamp Client Sign & Stamp

Page 34
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 28-Jan-16 Weather: Sunny Temperature: 30ºC

D. Today Planned Activities 28-Jan-16


1 ETS-B TIE BEAM Steel fixing , Deshuttering for Tie Beam ETS 3 , Shifting Shuttering to ETS B.
2 Zone - 4 pipe line doubling fit up is going on.
3 ETS - B Pipe line Doubling and welding is goin on.
4 Zone - 2 - 20 inch Pipe Doubling and Welding is going on.
5 Main Line 20 inch pipe fit up and welding is going on.- Z-2 & 1
6 20 inch main line Doubling and Welding in Zone - 2 & 1
7 Zone - 2 and 4 Excavation is going on.
8 ETS - B and A Route pipe line fit up and welding is going on.
9 Inside militry school excavation is going on - Zone -2 and Zone - 4

Activity - 14 inch Current inmtr/no Previous in mtr/no Total inmtr/no

1 Bedding 50 40 50
2 Fit up 2 45 47
3 Welding 2 42 44
4 Pipe Laying 100 100 100
5 First Layer Back Filling 150 150 150

Other Activity:
1 Pneumatic test for Zone-1 Joint No. R4 to R31 & S4 to S31 Completed
2 Pneumatic test for Zone-1 Joint No. R39 to R62 & S39 to S62 Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed
4 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S 39 to S58 Completed
5 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S4 to S31 Completed
6 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R39 to R58 Completed
7 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R4 to R31 Completed
8 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S1 to S20 Completed
9 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S21 to S31 Completed
10 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R1 to R20 Completed
11 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R21 to R31 Completed
12 2 Coat Primer + 2 coat Epoxy applied in Zone-5 S6 to S38 Completed

Page 35
Working Time: 7 am to 6:00pm
118
57

Remarks

On Progress
On Progress
On Progress Total Excavation
Completed in
On Progress Mtr
On Progress 1843
On Progress
On Progress
On Progress

Page 36
Working Time: 7 am to 6:00pm

nt Sign & Stamp

Page 37
Working Time: 7 am to 6:00pm

To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed

Page 38
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 28-Jan-16 Working Time: 7 am to 6:00p
Manpower Details Equipment Details Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1 20

10 Safety Officer 1 31 Portable Oven 5 21


11 Welder 6 32 1 22
12 Fitter 1 33 25 ton Crane 1 23
13 Sheet Fabricator 1 34 Water Tanker 1 24
14 Helper 6 25
15 Mason 1
16 Excavator & Shovel Operator 2
17 JCB Operator 1

18 BUS DRIVER 3
19 Carpenter 1
Total 32 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17

4 Site Foreman 1 12 SHOVEL 1 18


5 Fitter 0 13 25 ton Crane 0 19
6 Tak Welder 2 14 Diesel Welding machine 2
7 General Workers 6 15 Electric Welding machine 3

Page 39
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 28-Jan-16 Working Time: 7 am to 6:00p
8 BUS DRIVER 2 16 Electric oven - 50 Kg 1
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 30 Total 16
Total Manpower 80 Total Equipments 50

Contractor Sign & Stamp Client Sign & Stamp

Page 40
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 28-Jan-16 Working Time: 7 am to 6:00p

SubContractor - Richmond - J&J


Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Richmond - J&J
1 Project Engineer 1 9 Mini Bus 1
2 Document Controller 1 10 Wheel Excavator 1
3 Office Asst 0 11 Roller Compactor 1
4 Site Foreman 2 12 SHOWEL 0
5 Mason 6 13 3 ton pick up 1
6 Helper 10 14 Steel Cutting Machine 1
7 Carpenter 8 15 Steel Bending machine 1
8 BUS DRIVER 1 16 JCB 0
9 Steel Worker 8 17 2 ton roller compactor 1

10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0

Total 38 Total 7
Total Manpower Total Equipments 7

HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers Done
2 Safety barriers, safety cones and signage boards installed near to the road area Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the road Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted Done
10 Barricades provided near road area (Near Plant Area) Done

Page 41
Working Time: 7 am to 6:00pm
Other Details
Others Qty

Direct Manpower
Rigger 3

Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1

Total 16

Other Details
Others Qty

Shovel Operator
Crane Operator
Draughts man 1

BUS DRIVER 0
Site Surveyor 1

Page 42
Working Time: 7 am to 6:00pm

Total 2

ent Sign & Stamp

Page 43
Working Time: 7 am to 6:00pm

Other Details
Others Qty

Total 0

Page 44
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 27-Jan-16 Weather: Sunny Temperature: 30ºC
A. Manpower report as on 26-Jan-16 Total Manpower:
B. Equipment report as on 26-Jan-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 26-Jan-16

1 Zone - 4 pipe line doubling fit up.


2 Main Line 20 inch pipe fit up and welding.
3 Zone -3 Excavation.
4 ETS - B valve chamber Second wall steel work.
5 ETS - B and A Route pipe line fit up and welding.
6 Zone -4 Excavation is going on.
7 Inside military school excavation is going on Zone -2 and Zone - 4
8 Casting for ETS 3 Tie beam completed , Back filling in ETS 1 & 3
Activity - 20 & 18 INCH PIPE Current in mtr/no Previous in mtr/no Total in mtr/no

1 Excavation (Zone -1 and 2) 20 1803 1823


2 Bedding 20 1080 1100
3 Fit up 4 149 153
4 Doubling 5 148 153
5 Pipe Laying Fit up 3 75 78
6 Pipe Laying Welding 6 62 68
7 UPVC Sleeve Laying 100 400 500
8 Backfilling 100 400 500
Activity - 12 inch Current inmtr/no Previous in mtr/no Total inmtr/no

1 Bedding 100 300 400


2 Fit up 2 70 72
3 Doubling 2 62 64
4 Pipe Laying 280 240 520
5 First Layer Back Filling
6 Pipe Laying Fit up
7 Pipe Laying Welding

Activity - 10 inch Current in mtr/no Previous in mtr/no Total in mtr/no

1 Bedding 400 370 770


2 Fit up 2 67 69

Page 45
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 27-Jan-16 Weather: Sunny Temperature: 30ºC
3 Welding 2 35 37
4 Pipe Laying 20 620 640
5 First Layer Back Filling 200 0 200

Contractor Sign & Stamp Client Sign & Stamp

Page 46
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 27-Jan-16 Weather: Sunny Temperature: 30ºC

D. Today Planned Activities 27-Jan-16


1 ETS-B TIE BEAM Steel fixing , Deshuttering for Tie Beam ETS 3 , Shifting Shuttering to ETS B.
2 Zone - 4 pipe line doubling fit up is going on.
3 ETS - B Pipe line Doubling and welding is goin on.
4 Zone - 2 - 20 inch Pipe Doubling and Welding is going on.
5 Main Line 20 inch pipe fit up and welding is going on.- Z-2 & 1
6 20 inch main line Doubling and Welding in Zone - 2 & 1
7 Zone - 2 and 4 Excavation is going on.
8 ETS - B and A Route pipe line fit up and welding is going on.
9 Inside militry school excavation is going on - Zone -2 and Zone - 4

Activity - 14 inch Current inmtr/no Previous in mtr/no Total inmtr/no

1 Bedding 50 40 50
2 Fit up 2 45 47
3 Welding 2 42 44
4 Pipe Laying
5 First Layer Back Filling

Other Activity:
1 Pneumatic test for Zone-1 Joint No. R4 to R31 & S4 to S31 Completed
2 Pneumatic test for Zone-1 Joint No. R39 to R62 & S39 to S62 Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed
4 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S 39 to S58 Completed
5 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S4 to S31 Completed
6 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R39 to R58 Completed
7 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R4 to R31 Completed
8 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S1 to S20 Completed
9 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S21 to S31 Completed
10 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R1 to R20 Completed
11 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R21 to R31 Completed
12 2 Coat Primer + 2 coat Epoxy applied in Zone-5 S6 to S38 Completed

Page 47
Working Time: 7 am to 6:00pm
118
57

Remarks

On Progress
On Progress
On Progress Total Excavation
Completed in
On Progress Mtr
On Progress 1823
On Progress
On Progress
On Progress

Page 48
Working Time: 7 am to 6:00pm

nt Sign & Stamp

Page 49
Working Time: 7 am to 6:00pm

To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed

Page 50
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 27-Jan-16 Working Time: 7 am to 6:00p
Manpower Details Equipment Details Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1 20

10 Safety Officer 1 31 Portable Oven 5 21


11 Welder 6 32 1 22
12 Fitter 1 33 25 ton Crane 1 23
13 Sheet Fabricator 1 34 Water Tanker 1 24
14 Helper 6 25
15 Mason 1
16 Excavator & Shovel Operator 2
17 JCB Operator 1

18 BUS DRIVER 3
19 Carpenter 1
Total 32 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17

4 Site Foreman 1 12 SHOVEL 1 18


5 Fitter 0 13 25 ton Crane 0 19
6 Tak Welder 2 14 Diesel Welding machine 2
7 General Workers 6 15 Electric Welding machine 3

Page 51
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 27-Jan-16 Working Time: 7 am to 6:00p
8 BUS DRIVER 2 16 Electric oven - 50 Kg 1
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 30 Total 16
Total Manpower 80 Total Equipments 50

Contractor Sign & Stamp Client Sign & Stamp

Page 52
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 27-Jan-16 Working Time: 7 am to 6:00p

SubContractor - Richmond - J&J


Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Richmond - J&J
1 Project Engineer 1 9 Mini Bus 1
2 Document Controller 1 10 Wheel Excavator 1
3 Office Asst 0 11 Roller Compactor 1
4 Site Foreman 2 12 SHOWEL 0
5 Mason 6 13 3 ton pick up 1
6 Helper 10 14 Steel Cutting Machine 1
7 Carpenter 8 15 Steel Bending machine 1
8 BUS DRIVER 1 16 JCB 0
9 Steel Worker 8 17 2 ton roller compactor 1

10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0

Total 38 Total 7
Total Manpower Total Equipments 7

HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers Done
2 Safety barriers, safety cones and signage boards installed near to the road area Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the road Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted Done
10 Barricades provided near road area (Near Plant Area) Done

Page 53
Working Time: 7 am to 6:00pm
Other Details
Others Qty

Direct Manpower
Rigger 3

Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1

Total 16

Other Details
Others Qty

Shovel Operator
Crane Operator
Draughts man 1

BUS DRIVER 0
Site Surveyor 1

Page 54
Working Time: 7 am to 6:00pm

Total 2

ent Sign & Stamp

Page 55
Working Time: 7 am to 6:00pm

Other Details
Others Qty

Total 0

Page 56
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 26-Jan-16 Weather: Sunny Temperature: 30ºC
A. Manpower report as on 25-Jan-16 Total Manpower:
B. Equipment report as on 25-Jan-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 25-Jan-16

1 Zone - 4 pipe line doubling fit up.


2 Main Line 20 inch pipe fit up and welding.
3 Zone -3 Excavation.
4 ETS - B valve chamber Second wall steel work.
5 ETS - B and A Route pipe line fit up and welding.
6 Zone -4 Excavation is going on.
7 Inside military school excavation is going on Zone -2 and Zone - 4
8 Casting for ETS 3 Tie beam completed , Back filling in ETS 1 & 3
Activity - 20 & 18 INCH PIPE Current in mtr/no Previous in mtr/no Total in mtr/no

1 Excavation (Zone -1 and 2) 20 1803 1823


2 Bedding 20 1080 1100
3 Fit up 4 149 153
4 Doubling 5 148 153
5 Pipe Laying Fit up 3 75 78
6 Pipe Laying Welding 6 62 68
7 UPVC Sleeve Laying 100 400 500
8 Backfilling 100 400 500
Activity - 12 inch Current inmtr/no Previous in mtr/no Total inmtr/no

1 Bedding 100 300 400


2 Fit up 2 68 70
3 Doubling 2 60 62
4 Pipe Laying 260 240 500
5 First Layer Back Filling
6 Pipe Laying Fit up
7 Pipe Laying Welding

Activity - 10 inch Current in mtr/no Previous in mtr/no Total in mtr/no

1 Bedding 400 370 770


2 Fit up 2 67 69

Page 57
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 26-Jan-16 Weather: Sunny Temperature: 30ºC
3 Welding 2 35 37
4 Pipe Laying 20 620 640
5 First Layer Back Filling 200 0 200

Contractor Sign & Stamp Client Sign & Stamp

Page 58
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 26-Jan-16 Weather: Sunny Temperature: 30ºC

D. Today Planned Activities 26-Jan-16


1 ETS-B TIE BEAM Steel fixing , Deshuttering for Tie Beam ETS 3 , Shifting Shuttering to ETS B.
2 Zone - 4 pipe line doubling fit up is going on.
3 ETS - B Pipe line Doubling and welding is goin on.
4 Zone - 2 - 20 inch Pipe Doubling and Welding is going on.
5 Main Line 20 inch pipe fit up and welding is going on.- Z-2 & 1
6 20 inch main line Doubling and Welding in Zone - 2 & 1
7 Zone - 2 and 4 Excavation is going on.
8 ETS - B and A Route pipe line fit up and welding is going on.
9 Inside militry school excavation is going on - Zone -2 and Zone - 4

Activity - 14 inch Current inmtr/no Previous in mtr/no Total inmtr/no

1 Bedding 50 40 50
2 Fit up 2 45 47
3 Welding 2 42 44
4 Pipe Laying
5 First Layer Back Filling

Other Activity:
1 Pneumatic test for Zone-1 Joint No. R4 to R31 & S4 to S31 Completed
2 Pneumatic test for Zone-1 Joint No. R39 to R62 & S39 to S62 Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed
4 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S 39 to S58 Completed
5 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S4 to S31 Completed
6 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R39 to R58 Completed
7 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R4 to R31 Completed
8 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S1 to S20 Completed
9 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S21 to S31 Completed
10 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R1 to R20 Completed
11 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R21 to R31 Completed
12 2 Coat Primer + 2 coat Epoxy applied in Zone-5 S6 to S38 Completed

Page 59
Working Time: 7 am to 6:00pm
118
57

Remarks

On Progress
On Progress
On Progress Total Excavation
Completed in
On Progress Mtr
On Progress 1823
On Progress
On Progress
On Progress

Page 60
Working Time: 7 am to 6:00pm

nt Sign & Stamp

Page 61
Working Time: 7 am to 6:00pm

To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed

Page 62
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 26-Jan-16 Working Time: 7 am to 6:00p
Manpower Details Equipment Details Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1 20

10 Safety Officer 1 31 Portable Oven 5 21


11 Welder 6 32 1 22
12 Fitter 1 33 25 ton Crane 1 23
13 Sheet Fabricator 1 34 Water Tanker 1 24
14 Helper 6 25
15 Mason 1
16 Excavator & Shovel Operator 2
17 JCB Operator 1

18 BUS DRIVER 3
19 Carpenter 1
Total 32 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17

4 Site Foreman 1 12 SHOVEL 1 18


5 Fitter 0 13 25 ton Crane 0 19
6 Tak Welder 2 14 Diesel Welding machine 2
7 General Workers 6 15 Electric Welding machine 3

Page 63
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 26-Jan-16 Working Time: 7 am to 6:00p
8 BUS DRIVER 2 16 Electric oven - 50 Kg 1
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 30 Total 16
Total Manpower 80 Total Equipments 50

Contractor Sign & Stamp Client Sign & Stamp

Page 64
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 26-Jan-16 Working Time: 7 am to 6:00p

SubContractor - Richmond - J&J


Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Richmond - J&J
1 Project Engineer 1 9 Mini Bus 1
2 Document Controller 1 10 Wheel Excavator 1
3 Office Asst 0 11 Roller Compactor 1
4 Site Foreman 2 12 SHOWEL 0
5 Mason 6 13 3 ton pick up 1
6 Helper 10 14 Steel Cutting Machine 1
7 Carpenter 8 15 Steel Bending machine 1
8 BUS DRIVER 1 16 JCB 0
9 Steel Worker 8 17 2 ton roller compactor 1

10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0

Total 38 Total 7
Total Manpower Total Equipments 7

HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers Done
2 Safety barriers, safety cones and signage boards installed near to the road area Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the road Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted Done
10 Barricades provided near road area (Near Plant Area) Done

Page 65
Working Time: 7 am to 6:00pm
Other Details
Others Qty

Direct Manpower
Rigger 3

Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1

Total 16

Other Details
Others Qty

Shovel Operator
Crane Operator
Draughts man 1

BUS DRIVER 0
Site Surveyor 1

Page 66
Working Time: 7 am to 6:00pm

Total 2

ent Sign & Stamp

Page 67
Working Time: 7 am to 6:00pm

Other Details
Others Qty

Total 0

Page 68
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 25-Jan-16 Weather: Sunny Temperature: 30ºC
A. Manpower report as on 24-Jan-16 Total Manpower:
B. Equipment report as on 24-Jan-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 24-Jan-16

1 Zone - 4 pipe line doubling fit up.


2 Main Line 20 inch pipe fit up and welding.
3 Zone -3 Excavation.
4 ETS - B valve chamber Second wall steel work.
5 ETS - B and A Route pipe line fit up and welding.
6 Zone -4 Excavation is going on.
7 Inside military school excavation is going on Zone -2 and Zone - 4
8 Casting for ETS 3 Tie beam completed , Back filling in ETS 1 & 3
Activity - 20 & 18 INCH PIPE Current in mtr/no Previous in mtr/no Total in mtr/no

1 Excavation (Zone -1 and 2) 20 1783 1803


2 Bedding 20 1080 1100
3 Fit up 4 149 153
4 Doubling 5 148 153
5 Pipe Laying Fit up 3 75 78
6 Pipe Laying Welding 6 62 68
7 UPVC Sleeve Laying 100 400 500
8 Backfilling 100 400 500
Activity - 12 inch Current inmtr/no Previous in mtr/no Total inmtr/no

1 Bedding 100 300 400


2 Fit up 2 68 70
3 Doubling 2 60 62
4 Pipe Laying 260 240 500
5 First Layer Back Filling
6 Pipe Laying Fit up
7 Pipe Laying Welding

Activity - 10 inch Current in mtr/no Previous in mtr/no Total in mtr/no

1 Bedding 400 370 770


2 Fit up 2 67 69

Page 69
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 25-Jan-16 Weather: Sunny Temperature: 30ºC
3 Welding 2 35 37
4 Pipe Laying 20 620 640
5 First Layer Back Filling 200 0 200

Contractor Sign & Stamp Client Sign & Stamp

Page 70
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 25-Jan-16 Weather: Sunny Temperature: 30ºC

D. Today Planned Activities 25-Jan-16


1 ETS-B TIE BEAM Steel fixing , Deshuttering for Tie Beam ETS 3 , Shifting Shuttering to ETS B.
2 Zone - 4 pipe line doubling fit up is going on.
3 ETS - B Pipe line Doubling and welding is goin on.
4 Zone - 2 - 20 inch Pipe Doubling and Welding is going on.
5 Main Line 20 inch pipe fit up and welding is going on.- Z-2 & 1
6 20 inch main line Doubling and Welding in Zone - 2 & 1
7 Zone - 2 and 4 Excavation is going on.
8 ETS - B and A Route pipe line fit up and welding is going on.
9 Inside militry school excavation is going on - Zone -2 and Zone - 4

Activity - 14 inch Current inmtr/no Previous in mtr/no Total inmtr/no

1 Bedding 50 40 50
2 Fit up 2 45 47
3 Welding 2 42 44
4 Pipe Laying
5 First Layer Back Filling

Other Activity:
1 Pneumatic test for Zone-1 Joint No. R4 to R31 & S4 to S31 Completed
2 Pneumatic test for Zone-1 Joint No. R39 to R62 & S39 to S62 Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed
4 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S 39 to S58 Completed
5 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S4 to S31 Completed
6 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R39 to R58 Completed
7 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R4 to R31 Completed
8 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S1 to S20 Completed
9 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S21 to S31 Completed
10 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R1 to R20 Completed
11 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R21 to R31 Completed
12 2 Coat Primer + 2 coat Epoxy applied in Zone-5 S6 to S38 Completed

Page 71
Working Time: 7 am to 6:00pm
118
57

Remarks

On Progress
On Progress
On Progress Total Excavation
Completed in
On Progress Mtr
On Progress 1803
On Progress
On Progress
On Progress

Page 72
Working Time: 7 am to 6:00pm

nt Sign & Stamp

Page 73
Working Time: 7 am to 6:00pm

To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed

Page 74
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 25-Jan-16 Working Time: 7 am to 6:00p
Manpower Details Equipment Details Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1 20

10 Safety Officer 1 31 Portable Oven 5 21


11 Welder 6 32 1 22
12 Fitter 1 33 25 ton Crane 1 23
13 Sheet Fabricator 1 34 Water Tanker 1 24
14 Helper 6 25
15 Mason 1
16 Excavator & Shovel Operator 2
17 JCB Operator 1

18 BUS DRIVER 3
19 Carpenter 1
Total 32 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17

4 Site Foreman 1 12 SHOVEL 1 18


5 Fitter 0 13 25 ton Crane 0 19
6 Tak Welder 2 14 Diesel Welding machine 2
7 General Workers 6 15 Electric Welding machine 3

Page 75
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 25-Jan-16 Working Time: 7 am to 6:00p
8 BUS DRIVER 2 16 Electric oven - 50 Kg 1
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 30 Total 16
Total Manpower 80 Total Equipments 50

Contractor Sign & Stamp Client Sign & Stamp

Page 76
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 25-Jan-16 Working Time: 7 am to 6:00p

SubContractor - Richmond - J&J


Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Richmond - J&J
1 Project Engineer 1 9 Mini Bus 1
2 Document Controller 1 10 Wheel Excavator 1
3 Office Asst 0 11 Roller Compactor 1
4 Site Foreman 2 12 SHOWEL 0
5 Mason 6 13 3 ton pick up 1
6 Helper 10 14 Steel Cutting Machine 1
7 Carpenter 8 15 Steel Bending machine 1
8 BUS DRIVER 1 16 JCB 0
9 Steel Worker 8 17 2 ton roller compactor 1

10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0

Total 38 Total 7
Total Manpower Total Equipments 7

HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers Done
2 Safety barriers, safety cones and signage boards installed near to the road area Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the road Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted Done
10 Barricades provided near road area (Near Plant Area) Done

Page 77
Working Time: 7 am to 6:00pm
Other Details
Others Qty

Direct Manpower
Rigger 3

Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1

Total 16

Other Details
Others Qty

Shovel Operator
Crane Operator
Draughts man 1

BUS DRIVER 0
Site Surveyor 1

Page 78
Working Time: 7 am to 6:00pm

Total 2

ent Sign & Stamp

Page 79
Working Time: 7 am to 6:00pm

Other Details
Others Qty

Total 0

Page 80
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 24-Jan-16 Weather: Sunny Temperature: 30ºC
A. Manpower report as on 23-Jan-16 Total Manpower:
B. Equipment report as on 23-Jan-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 23-Jan-16

1 Zone - 4 pipe line doubling fit up.


2 Main Line 20 inch pipe fit up and welding.
3 Zone -3 Excavation.
4 ETS - B valve chamber Second wall steel work.
5 ETS - B and A Route pipe line fit up and welding.
6 Zone -4 Excavation is going on.
7 Inside military school excavation is going on Zone -2 and Zone - 4
8 Casting for ETS 3 Tie beam completed , Back filling in ETS 1 & 3
Activity - 20 & 18 INCH PIPE Current in mtr/no Previous in mtr/no Total in mtr/no

1 Excavation (Zone -1 and 2) 10 1783 1793


2 Bedding 20 1080 1100
3 Fit up 4 149 153
4 Doubling 5 148 153
5 Pipe Laying Fit up 3 72 75
6 Pipe Laying Welding 6 62 68
7 UPVC Sleeve Laying
Activity - 12 inch Current inmtr/no Previous in mtr/no Total inmtr/no

1 Bedding 100 300 400


2 Fit up 2 68 70
3 Doubling 2 60 62
4 Pipe Laying 260 240 500
5 First Layer Back Filling
6 Pipe Laying Fit up
7 Pipe Laying Welding

Activity - 10 inch Current in mtr/no Previous in mtr/no Total in mtr/no

1 Bedding 400 370 770


2 Fit up 2 67 69
3 Welding 2 35 37

Page 81
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 24-Jan-16 Weather: Sunny Temperature: 30ºC
4 Pipe Laying 20 620 640
5 First Layer Back Filling 200 0 200

Contractor Sign & Stamp Client Sign & Stamp

D. Today Planned Activities 24-Jan-16


1 ETS-B TIE BEAM Steel fixing , Deshuttering for Tie Beam ETS 3 , Shifting Shuttering to ETS B.
2 Zone - 4 pipe line doubling fit up is going on.
3 ETS - B Pipe line Doubling and welding is goin on.
4 Zone - 2 - 20 inch Pipe Doubling and Welding is going on.
5 Main Line 20 inch pipe fit up and welding is going on.- Z-2 & 1
6 20 inch main line Doubling and Welding in Zone - 2 & 1
7 Zone - 2 and 4 Excavation is going on.
8 ETS - B and A Route pipe line fit up and welding is going on.
9 Inside militry school excavation is going on - Zone -2 and Zone - 4

Activity - 14 inch Current inmtr/no Previous in mtr/no Total inmtr/no

1 Bedding 50 40 50
2 Fit up 2 43 45
3 Welding 3 40 43
4 Pipe Laying
5 First Layer Back Filling

Other Activity:

Page 82
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 24-Jan-16 Weather: Sunny Temperature: 30ºC
1 Pneumatic test for Zone-1 Joint No. R4 to R31 & S4 to S31 Completed
2 Pneumatic test for Zone-1 Joint No. R39 to R62 & S39 to S62 Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed
4 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S 39 to S58 Completed
5 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S4 to S31 Completed
6 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R39 to R58 Completed
7 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R4 to R31 Completed
8 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S1 to S20 Completed
9 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S21 to S31 Completed
10 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R1 to R20 Completed
11 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R21 to R31 Completed
12 2 Coat Primer + 2 coat Epoxy applied in Zone-5 S6 to S38 Completed

Page 83
Working Time: 7 am to 6:00pm
118
57

Remarks

On Progress
On Progress
On Progress Total Excavation
Completed in
On Progress Mtr
On Progress 1793
On Progress
On Progress
On Progress

Page 84
Working Time: 7 am to 6:00pm

nt Sign & Stamp

To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed

Page 85
Working Time: 7 am to 6:00pm

Page 86
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 24-Jan-16 Working Time: 7 am to 6:00p
Manpower Details Equipment Details Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1 20

10 Safety Officer 1 31 Portable Oven 5 21


11 Welder 6 32 1 22
12 Fitter 1 33 25 ton Crane 1 23
13 Sheet Fabricator 1 34 Water Tanker 1 24
14 Helper 6 25
15 Mason 1
16 Excavator & Shovel Operator 2
17 JCB Operator 1

18 BUS DRIVER 3
19 Carpenter 1
Total 32 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17

4 Site Foreman 1 12 SHOVEL 1 18


5 Fitter 0 13 25 ton Crane 0 19
6 Tak Welder 2 14 Diesel Welding machine 2
7 General Workers 6 15 Electric Welding machine 3
8 BUS DRIVER 2 16 Electric oven - 50 Kg 1

Page 87
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 24-Jan-16 Working Time: 7 am to 6:00p
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 30 Total 16
Total Manpower 80 Total Equipments 50

Contractor Sign & Stamp Client Sign & Stamp

SubContractor - Richmond - J&J


Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Richmond - J&J
1 Project Engineer 1 9 Mini Bus 1
2 Document Controller 1 10 Wheel Excavator 1
3 Office Asst 0 11 Roller Compactor 1
4 Site Foreman 2 12 SHOWEL 0
5 Mason 6 13 3 ton pick up 1
6 Helper 10 14 Steel Cutting Machine 1
7 Carpenter 8 15 Steel Bending machine 1
8 BUS DRIVER 1 16 JCB 0
9 Steel Worker 8 17 2 ton roller compactor 1

10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0

Total 38 Total 7
Total Manpower Total Equipments 7

Page 88
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 24-Jan-16 Working Time: 7 am to 6:00p
HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers Done
2 Safety barriers, safety cones and signage boards installed near to the road area Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the road Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted Done
10 Barricades provided near road area (Near Plant Area) Done

Page 89
Working Time: 7 am to 6:00pm
Other Details
Others Qty

Direct Manpower
Rigger 3

Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1

Total 16

Other Details
Others Qty

Shovel Operator
Crane Operator
Draughts man 1

BUS DRIVER 0
Site Surveyor 1

Page 90
Working Time: 7 am to 6:00pm

Total 2

ent Sign & Stamp

Other Details
Others Qty

Total 0

Page 91
Working Time: 7 am to 6:00pm

Page 92
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 23-Jan-16 Weather: Sunny Temperature: 30ºC
A. Manpower report as on 22-Jan-16 Total Manpower:
B. Equipment report as on 22-Jan-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 22-Jan-16

1 Zone - 4 pipe line doubling fit up.


2 Main Line 20 inch pipe fit up and welding.
3 Zone -3 Excavation.
4 ETS - B valve chamber Second wall steel work.
5 ETS - B and A Route pipe line fit up and welding.
6 Zone -4 Excavation is going on.
7 Inside military school excavation is going on Zone -2 and Zone - 4
8 Casting for ETS 3 Tie beam completed , Back filling in ETS 1 & 3
Activity - 20 & 18 INCH PIPE Current in mtr/no Previous in mtr/no Total in mtr/no

1 Excavation (Zone -1 and 2) 10 1783 1793


2 Bedding 20 1080 1100
3 Fit up 4 149 153
4 Doubling 5 148 153
5 Pipe Laying Fit up 3 69 75
6 Pipe Laying Welding 3 62 65
7 UPVC Sleeve Laying
Activity - 12 inch Current inmtr/no Previous in mtr/no Total inmtr/no

1 Bedding 100 300 400


2 Fit up 2 68 70
3 Doubling 2 60 62
4 Pipe Laying 260 240 500
5 First Layer Back Filling
6 Pipe Laying Fit up
7 Pipe Laying Welding

Activity - 10 inch Current in mtr/no Previous in mtr/no Total in mtr/no

1 Bedding 400 370 770


2 Fit up 2 67 69
3 Welding 2 35 37

Page 93
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 23-Jan-16 Weather: Sunny Temperature: 30ºC
4 Pipe Laying 20 620 640
5 First Layer Back Filling 200 0 200

Contractor Sign & Stamp Client Sign & Stamp

D. Today Planned Activities 23-Jan-16


1 ETS-B TIE BEAM Steel fixing , Deshuttering for Tie Beam ETS 3 , Shifting Shuttering to ETS B.
2 Zone - 4 pipe line doubling fit up is going on.
3 ETS - B Pipe line Doubling and welding is goin on.
4 Zone - 2 - 20 inch Pipe Doubling and Welding is going on.
5 Main Line 20 inch pipe fit up and welding is going on.- Z-2 & 1
6 20 inch main line Doubling and Welding in Zone - 2 & 1
7 Zone - 2 and 4 Excavation is going on.
8 ETS - B and A Route pipe line fit up and welding is going on.
9 Inside militry school excavation is going on - Zone -2 and Zone - 4

Activity - 14 inch Current inmtr/no Previous in mtr/no Total inmtr/no

1 Bedding 50 40 50
2 Fit up 2 41 43
3 Welding 3 37 40
4 Pipe Laying
5 First Layer Back Filling

Other Activity:

Page 94
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 23-Jan-16 Weather: Sunny Temperature: 30ºC
1 Pneumatic test for Zone-1 Joint No. R4 to R31 & S4 to S31 Completed
2 Pneumatic test for Zone-1 Joint No. R39 to R62 & S39 to S62 Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed

Page 95
Working Time: 7 am to 6:00pm
118
57

Remarks

On Progress
On Progress
On Progress Total Excavation
Completed in
On Progress Mtr
On Progress 1793
On Progress
On Progress
On Progress

Page 96
Working Time: 7 am to 6:00pm

nt Sign & Stamp

To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed

Page 97
Working Time: 7 am to 6:00pm

Page 98
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 23-Jan-16 Working Time: 7 am to 6:00p
Manpower Details Equipment Details Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1 20

10 Safety Officer 1 31 Portable Oven 5 21


11 Welder 6 32 1 22
12 Fitter 1 33 25 ton Crane 1 23
13 Sheet Fabricator 1 34 Water Tanker 1 24
14 Helper 6 25
15 Mason 1
16 Excavator & Shovel Operator 2
17 JCB Operator 1

18 BUS DRIVER 3
19 Carpenter 1
Total 32 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17

4 Site Foreman 1 12 SHOVEL 1 18


5 Fitter 0 13 25 ton Crane 0 19
6 Tak Welder 2 14 Diesel Welding machine 2
7 General Workers 6 15 Electric Welding machine 3
8 BUS DRIVER 2 16 Electric oven - 50 Kg 1

Page 99
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 23-Jan-16 Working Time: 7 am to 6:00p
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 30 Total 16
Total Manpower 80 Total Equipments 50

Contractor Sign & Stamp Client Sign & Stamp

SubContractor - Richmond - J&J


Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Richmond - J&J
1 Project Engineer 1 9 Mini Bus 1
2 Document Controller 1 10 Wheel Excavator 1
3 Office Asst 0 11 Roller Compactor 1
4 Site Foreman 2 12 SHOWEL 0
5 Mason 6 13 3 ton pick up 1
6 Helper 10 14 Steel Cutting Machine 1
7 Carpenter 8 15 Steel Bending machine 1
8 BUS DRIVER 1 16 JCB 0
9 Steel Worker 8 17 2 ton roller compactor 1

10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0

Total 38 Total 7
Total Manpower Total Equipments 7

Page 100
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 23-Jan-16 Working Time: 7 am to 6:00p
HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers Done
2 Safety barriers, safety cones and signage boards installed near to the road area Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the road Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted Done
10 Barricades provided near road area (Near Plant Area) Done

Page 101
Working Time: 7 am to 6:00pm
Other Details
Others Qty

Direct Manpower
Rigger 3

Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1

Total 16

Other Details
Others Qty

Shovel Operator
Crane Operator
Draughts man 1

BUS DRIVER 0
Site Surveyor 1

Page 102
Working Time: 7 am to 6:00pm

Total 2

ent Sign & Stamp

Other Details
Others Qty

Total 0

Page 103
Working Time: 7 am to 6:00pm

Page 104
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 21-Jan-16 Weather: Sunny Temperature: 30ºC
A. Manpower report as on 20-Jan-16 Total Manpower:
B. Equipment report as on 20-Jan-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 20-Jan-16

1 Zone - 4 pipe line doubling fit up.


2 Main Line 20 inch pipe fit up and welding.
3 Zone -3 Excavation.
4 ETS - B valve chamber Second wall steel work.
5 ETS - B and A Route pipe line fit up and welding.
6 Zone -4 Excavation is going on.
7 Inside military school excavation is going on Zone -2 and Zone - 4
8 Casting for ETS 3 Tie beam completed , Back filling in ETS 1 & 3
Activity - 20 & 18 INCH PIPE Current in mtr/no Previous in mtr/no Total in mtr/no

1 Excavation (Zone -1 and 2) 10 1783 1793


2 Bedding 50 1080 1080
3 Fit up 4 149 153
4 Doubling 5 148 153
5 Pipe Laying Fit up 3 72 69
6 Pipe Laying Welding 3 59 62
7 UPVC Sleeve Laying
Activity - 12 inch Current inmtr/no Previous in mtr/no Total inmtr/no

1 Bedding 100 300 400


2 Fit up 2 68 70
3 Doubling 2 60 62
4 Pipe Laying 260 240 500
5 First Layer Back Filling
6 Pipe Laying Fit up
7 Pipe Laying Welding

Activity - 10 inch Current in mtr/no Previous in mtr/no Total in mtr/no

1 Bedding 400 370 770


2 Fit up 2 67 69
3 Welding 2 35 37

Page 105
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 21-Jan-16 Weather: Sunny Temperature: 30ºC
4 Pipe Laying 20 620 640
5 First Layer Back Filling 200 0 200

Contractor Sign & Stamp Client Sign & Stamp

D. Today Planned Activities 21-Jan-16


1 ETS-B TIE BEAM Steel fixing , Deshuttering for Tie Beam ETS 3 , Shifting Shuttering to ETS B.
2 Zone - 4 pipe line doubling fit up is going on.
3 ETS - B Pipe line Doubling and welding is goin on.
4 Zone - 2 - 20 inch Pipe Doubling and Welding is going on.
5 Main Line 20 inch pipe fit up and welding is going on.- Z-2 & 1
6 20 inch main line Doubling and Welding in Zone - 2 & 1
7 Zone - 2 and 4 Excavation is going on.
8 ETS - B and A Route pipe line fit up and welding is going on.
9 Inside militry school excavation is going on - Zone -2 and Zone - 4

Activity - 14 inch Current inmtr/no Previous in mtr/no Total inmtr/no

1 Bedding 40 20 40
2 Fit up 2 41 43
3 Welding 3 34 37
4 Pipe Laying
5 First Layer Back Filling

Other Activity:

Page 106
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 21-Jan-16 Weather: Sunny Temperature: 30ºC
1 Pneumatic test for Zone-1 Joint No. R4 to R31 & S4 to S31 Completed
2 Pneumatic test for Zone-1 Joint No. R39 to R62 & S39 to S62 Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed

Page 107
Working Time: 7 am to 6:00pm
118
57

Remarks

On Progress
On Progress
On Progress Total Excavation
Completed in
On Progress Mtr
On Progress 1793
On Progress
On Progress
On Progress

Page 108
Working Time: 7 am to 6:00pm

nt Sign & Stamp

To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed

Page 109
Working Time: 7 am to 6:00pm

Page 110
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 21-Jan-16 Working Time: 7 am to 6:00p
Manpower Details Equipment Details Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1 20

10 Safety Officer 1 31 Portable Oven 5 21


11 Welder 6 32 1 22
12 Fitter 1 33 25 ton Crane 1 23
13 Sheet Fabricator 1 34 Water Tanker 1 24
14 Helper 6 25
15 Mason 1
16 Excavator & Shovel Operator 2
17 JCB Operator 1

18 BUS DRIVER 3
19 Carpenter 1
Total 32 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17

4 Site Foreman 1 12 SHOVEL 1 18


5 Fitter 0 13 25 ton Crane 0 19
6 Tak Welder 2 14 Diesel Welding machine 2
7 General Workers 6 15 Electric Welding machine 3
8 BUS DRIVER 2 16 Electric oven - 50 Kg 1

Page 111
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 21-Jan-16 Working Time: 7 am to 6:00p
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 30 Total 16
Total Manpower 80 Total Equipments 50

Contractor Sign & Stamp Client Sign & Stamp

SubContractor - Richmond - J&J


Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Richmond - J&J
1 Project Engineer 1 9 Mini Bus 1
2 Document Controller 1 10 Wheel Excavator 1
3 Office Asst 0 11 Roller Compactor 1
4 Site Foreman 2 12 SHOWEL 0
5 Mason 6 13 3 ton pick up 1
6 Helper 10 14 Steel Cutting Machine 1
7 Carpenter 8 15 Steel Bending machine 1
8 BUS DRIVER 1 16 JCB 0
9 Steel Worker 8 17 2 ton roller compactor 1

10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0

Total 38 Total 7
Total Manpower Total Equipments 7

Page 112
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 21-Jan-16 Working Time: 7 am to 6:00p
HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers Done
2 Safety barriers, safety cones and signage boards installed near to the road area Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the road Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted Done
10 Barricades provided near road area (Near Plant Area) Done

Page 113
Working Time: 7 am to 6:00pm
Other Details
Others Qty

Direct Manpower
Rigger 3

Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1

Total 16

Other Details
Others Qty

Shovel Operator
Crane Operator
Draughts man 1

BUS DRIVER 0
Site Surveyor 1

Page 114
Working Time: 7 am to 6:00pm

Total 2

ent Sign & Stamp

Other Details
Others Qty

Total 0

Page 115
Working Time: 7 am to 6:00pm

Page 116
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 20-Jan-16 Weather: Sunny Temperature: 30ºC
A. Manpower report as on 19-Jan-16 Total Manpower:
B. Equipment report as on 19-Jan-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 19-Jan-16

1 Zone - 4 pipe line doubling fit up.


2 Main Line 20 inch pipe fit up and welding.
3 Zone -3 Excavation.
4 ETS - B valve chamber Second wall steel work.
5 ETS - B and A Route pipe line fit up and welding.
6 Zone -4 Excavation is going on.
7 Inside military school excavation is going on Zone -2 and Zone - 4
8 Casting for ETS 3 Tie beam completed , Back filling in ETS 1 & 3
Activity - 20 & 18 INCH PIPE Current in mtr/no Previous in mtr/no Total in mtr/no

1 Excavation (Zone -1 and 2) 10 1783 1793


2 Bedding 50 1080 1080
3 Fit up 4 149 153
4 Doubling 5 148 153
5 Pipe Laying Fit up 3 72 69
6 Pipe Laying Welding 3 59 62
7 UPVC Sleeve Laying
Activity - 12 inch Current inmtr/no Previous in mtr/no Total inmtr/no

1 Bedding 100 300 400


2 Fit up 2 68 70
3 Doubling 2 60 62
4 Pipe Laying 240 220 460
5 First Layer Back Filling
6 Pipe Laying Fit up
7 Pipe Laying Welding

Activity - 10 inch Current in mtr/no Previous in mtr/no Total in mtr/no

1 Bedding 400 370 770


2 Fit up 2 65 67
3 Welding 2 63 65

Page 117
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 20-Jan-16 Weather: Sunny Temperature: 30ºC
4 Pipe Laying 20 620 640
5 First Layer Back Filling 180 0 180

Contractor Sign & Stamp Client Sign & Stamp

D. Today Planned Activities 20-Jan-16


1 ETS-B TIE BEAM Steel fixing , Deshuttering for Tie Beam ETS 3 , Shifting Shuttering to ETS B.
2 Zone - 4 pipe line doubling fit up is going on.
3 ETS - B Pipe line Doubling and welding is goin on.
4 Zone - 2 - 20 inch Pipe Doubling and Welding is going on.
5 Main Line 20 inch pipe fit up and welding is going on.- Z-2 & 1
6 20 inch main line Doubling and Welding in Zone - 2 & 1
7 Zone - 2 and 4 Excavation is going on.
8 ETS - B and A Route pipe line fit up and welding is going on.
9 Inside militry school excavation is going on - Zone -2 and Zone - 4

Activity - 14 inch Current inmtr/no Previous in mtr/no Total inmtr/no

1 Bedding 40 20 40
2 Fit up 2 41 43
3 Welding 3 34 37
4 Pipe Laying
5 First Layer Back Filling

Other Activity:

Page 118
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 20-Jan-16 Weather: Sunny Temperature: 30ºC
1 Pneumatic test for Zone-1 Joint No. R4 to R31 & S4 to S31 Completed
2 Pneumatic test for Zone-1 Joint No. R39 to R62 & S39 to S62 Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed

Page 119
Working Time: 7 am to 6:00pm
119
57

Remarks

On Progress
On Progress
On Progress Total Excavation
Completed in
On Progress Mtr
On Progress 1793
On Progress
On Progress
On Progress

Page 120
Working Time: 7 am to 6:00pm

nt Sign & Stamp

To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed

Page 121
Working Time: 7 am to 6:00pm

Page 122
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 20-Jan-16 Working Time: 7 am to 6:00p
Manpower Details Equipment Details Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1 20

10 Safety Officer 1 31 Portable Oven 5 21


11 Welder 6 32 1 22
12 Fitter 1 33 25 ton Crane 1 23
13 Sheet Fabricator 1 34 Water Tanker 1 24
14 Helper 7 25
15 Mason 1
16 Excavator & Shovel Operator 2
17 JCB Operator 1

18 BUS DRIVER 3
19 Carpenter 1
Total 33 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17

4 Site Foreman 1 12 SHOVEL 1 18


5 Fitter 0 13 25 ton Crane 0 19
6 Tak Welder 2 14 Diesel Welding machine 2
7 General Workers 6 15 Electric Welding machine 3
8 BUS DRIVER 2 16 Electric oven - 50 Kg 1

Page 123
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 20-Jan-16 Working Time: 7 am to 6:00p
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 30 Total 16
Total Manpower 81 Total Equipments 50

Contractor Sign & Stamp Client Sign & Stamp

SubContractor - Richmond - J&J


Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Richmond - J&J
1 Project Engineer 1 9 Mini Bus 1
2 Document Controller 1 10 Wheel Excavator 1
3 Office Asst 0 11 Roller Compactor 1
4 Site Foreman 2 12 SHOWEL 0
5 Mason 6 13 3 ton pick up 1
6 Helper 10 14 Steel Cutting Machine 1
7 Carpenter 8 15 Steel Bending machine 1
8 BUS DRIVER 1 16 JCB 0
9 Steel Worker 8 17 2 ton roller compactor 1

10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0

Total 38 Total 7
Total Manpower Total Equipments 7

Page 124
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 20-Jan-16 Working Time: 7 am to 6:00p
HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers Done
2 Safety barriers, safety cones and signage boards installed near to the road area Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the road Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted Done
10 Barricades provided near road area (Near Plant Area) Done

Page 125
Working Time: 7 am to 6:00pm
Other Details
Others Qty

Direct Manpower
Rigger 3

Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1

Total 16

Other Details
Others Qty

Shovel Operator
Crane Operator
Draughts man 1

BUS DRIVER 0
Site Surveyor 1

Page 126
Working Time: 7 am to 6:00pm

Total 2

ent Sign & Stamp

Other Details
Others Qty

Total 0

Page 127
Working Time: 7 am to 6:00pm

Page 128
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 19-Jan-16 Weather: Sunny Temperature: 30ºC
A. Manpower report as on 18-Jan-16 Total Manpower:
B. Equipment report as on 18-Jan-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 18-Jan-16

1 Zone - 4 pipe line doubling fit up.


2 Main Line 20 inch pipe fit up and welding.
3 Zone -2 Excavation.
4 ETS - B valve chamber Second wall steel work.
5 ETS - B and A Route pipe line fit up and welding.
6 Zone -4 Excavation is going on.
7 Inside military school excavation is going on Zone -2 and Zone - 4
8 Casting for ETS 3 Tie beam completled , Back filling in ETS 1 & 3
Activity - 20 & 18 INCH PIPE Current in mtr/no Previous in mtr/no Total in mtr/no

1 Excavation (Zone -1 and 2) 10 1783 1793


2 Bedding 50 1080 1080
3 Fit up 4 149 153
4 Doubling 5 148 153
5 Pipe Laying Fit up 3 72 69
6 Pipe Laying Welding 3 59 62
7 UPVC Sleeve Laying
Activity - 12 inch Current inmtr/no Previous in mtr/no Total inmtr/no

1 Bedding 100 300 400


2 Fit up 2 68 70
3 Doubling 2 60 62
4 Pipe Laying 240 220 460
5 First Layer Back Filling
6 Pipe Laying Fit up
7 Pipe Laying Welding

Activity - 10 inch Current in mtr/no Previous in mtr/no Total in mtr/no

1 Bedding 400 370 770


2 Fit up 2 65 67
3 Welding 2 63 65

Page 129
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 19-Jan-16 Weather: Sunny Temperature: 30ºC
4 Pipe Laying 20 620 640
5 First Layer Back Filling 180 0 180

Contractor Sign & Stamp Client Sign & Stamp

D. Today Planned Activities 19-Jan-16


1 ETS-B TIE BEAM Steel fixing , Deshuttering for Tie Beam ETS 3 , Shifting Shuttering to ETS B.
2 Zone - 4 pipe line doubling fit up is going on.
3 ETS - B Pipe line Doubling and welding is goin on.
4 Zone - 2 - 20 inch Pipe Doubling and Welding is going on.
5 Main Line 20 inch pipe fit up and welding is going on.- Z-2 & 1
6 20 inch main line Doubling and Welding in Zone - 2 & 1
7 Zone - 2 and 4 Excavation is going on.
8 ETS - B and A Route pipe line fit up and welding is going on.
9 Inside militry school excavation is going on - Zone -2 and Zone - 4

Activity - 14 inch Current inmtr/no Previous in mtr/no Total inmtr/no

1 Bedding 40 20 40
2 Fit up 2 41 43
3 Welding 3 34 37
4 Pipe Laying
5 First Layer Back Filling

Other Activity:

Page 130
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 19-Jan-16 Weather: Sunny Temperature: 30ºC
1 Pneumatic test for Zone-1 Joint No. R4 to R31 & S4 to S31 Completed
2 Pneumatic test for Zone-1 Joint No. R39 to R62 & S39 to S62 Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed

Page 131
Working Time: 7 am to 6:00pm
119
57

Remarks

On Progress
On Progress
On Progress Total Excavation
Completed in
On Progress Mtr
On Progress 1793
On Progress
On Progress
On Progress

Page 132
Working Time: 7 am to 6:00pm

nt Sign & Stamp

To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed

Page 133
Working Time: 7 am to 6:00pm

Page 134
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 19-Jan-16 Working Time: 7 am to 6:00p
Manpower Details Equipment Details Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1 20

10 Safety Officer 1 31 Portable Oven 5 21


11 Welder 6 32 1 22
12 Fitter 1 33 25 ton Crane 1 23
13 Sheet Fabricator 1 34 Water Tanker 1 24
14 Helper 7 25
15 Mason 1
16 Excavator & Shovel Operator 2
17 JCB Operator 1

18 BUS DRIVER 3
19 Carpenter 1
Total 33 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17

4 Site Foreman 1 12 SHOVEL 1 18


5 Fitter 0 13 25 ton Crane 0 19
6 Tak Welder 2 14 Diesel Welding machine 2
7 General Workers 6 15 Electric Welding machine 3
8 BUS DRIVER 2 16 Electric oven - 50 Kg 1

Page 135
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 19-Jan-16 Working Time: 7 am to 6:00p
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 30 Total 16
Total Manpower 81 Total Equipments 50

Contractor Sign & Stamp Client Sign & Stamp

SubContractor - Richmond - J&J


Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Richmond - J&J
1 Project Engineer 1 9 Mini Bus 1
2 Document Controller 1 10 Wheel Excavator 1
3 Office Asst 0 11 Roller Compactor 1
4 Site Foreman 2 12 SHOWEL 0
5 Mason 6 13 3 ton pick up 1
6 Helper 10 14 Steel Cutting Machine 1
7 Carpenter 8 15 Steel Bending machine 1
8 BUS DRIVER 1 16 JCB 0
9 Steel Worker 8 17 2 ton roller compactor 1

10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0

Total 38 Total 7
Total Manpower Total Equipments 7

Page 136
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 19-Jan-16 Working Time: 7 am to 6:00p
HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers Done
2 Safety barriers, safety cones and signage boards installed near to the road area Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the road Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted Done
10 Barricades provided near road area (Near Plant Area) Done

Page 137
Working Time: 7 am to 6:00pm
Other Details
Others Qty

Direct Manpower
Rigger 3

Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1

Total 16

Other Details
Others Qty

Shovel Operator
Crane Operator
Draughts man 1

BUS DRIVER 0
Site Surveyor 1

Page 138
Working Time: 7 am to 6:00pm

Total 2

ent Sign & Stamp

Other Details
Others Qty

Total 0

Page 139
Working Time: 7 am to 6:00pm

Page 140
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 17-Jan-16 Weather: Sunny Temperature: 30ºC
A. Manpower report as on 16-Jan-16 Total Manpower:
B. Equipment report as on 16-Jan-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 16-Jan-16

1 Zone - 4 pipe line doubling fit up.


2 Main Line 20 inch pipe fit up and welding.
3 Zone -2 Excavation.
4 ETS - B valve chamber Second wall steel work.
5 ETS - B and A Route pipe line fit up and welding.
6 Zone -4 Excavation is going on.
7 Inside military school excavation is going on Zone -2 and Zone - 4
8 Casting for ETS 3 Tie beam completled , Back filling in ETS 1 & 3
Activity - 20 & 18 INCH PIPE Current in mtr/no Previous in mtr/no Total in mtr/no

1 Excavation (Zone -1 and 2) 10 1773 1783


2 Bedding 100 1030 1030
3 Fit up 4 149 153
4 Doubling 5 148 153
5 Pipe Laying Fit up 3 72 69
6 Pipe Laying Welding 3 59 62
7 UPVC Sleeve Laying
Activity - 12 inch Current inmtr/no Previous in mtr/no Total inmtr/no

1 Bedding 100 300 400


2 Fit up 2 68 70
3 Doubling 2 60 62
4 Pipe Laying 240 220 460
5 First Layer Back Filling
6 Pipe Laying Fit up
7 Pipe Laying Welding

Activity - 10 inch Current in mtr/no Previous in mtr/no Total in mtr/no

1 Bedding 400 370 770


2 Fit up 2 65 67
3 Welding 2 63 65

Page 141
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 17-Jan-16 Weather: Sunny Temperature: 30ºC
4 Pipe Laying 20 600 620
5 First Layer Back Filling 170 0 170

Contractor Sign & Stamp Client Sign & Stamp

D. Today Planned Activities 17-Jan-16


1 ETS-B TIE BEAM Steel fixing , Deshuttering for Tie Beam ETS 3 , Shifting Shuttering to ETS B.
2 Zone - 4 pipe line doubling fit up is going on.
3 ETS - B Pipe line Doubling and welding is goin on.
4 Zone - 2 - 20 inch Pipe Doubling and Welding is going on.
5 Main Line 20 inch pipe fit up and welding is going on.- Z-2 & 1
6 20 inch main line Doubling and Welding in Zone - 2 & 1
7 Zone - 2 and 4 Excavation is going on.
8 ETS - B and A Route pipe line fit up and welding is going on.
9 Inside militry school excavation is going on - Zone -2 and Zone - 4

Activity - 14 inch Current inmtr/no Previous in mtr/no Total inmtr/no

1 Bedding 20 20 20
2 Fit up 2 39 41
3 Welding 3 34 37
4 Pipe Laying
5 First Layer Back Filling

Other Activity:

Page 142
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 17-Jan-16 Weather: Sunny Temperature: 30ºC
1 Pneumatic test for Zone-1 Joint No. R4 to R31 & S4 to S31 Completed
2 Pneumatic test for Zone-1 Joint No. R39 to R62 & S39 to S62 Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed

Page 143
Working Time: 7 am to 6:00pm
118
57

Remarks

On Progress
On Progress
On Progress Total Excavation
Completed in
On Progress Mtr
On Progress 1783
On Progress
On Progress
On Progress

Page 144
Working Time: 7 am to 6:00pm

nt Sign & Stamp

To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed

Page 145
Working Time: 7 am to 6:00pm

Page 146
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 17-Jan-16 Working Time: 7 am to 6:00p
Manpower Details Equipment Details Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1 20

10 Safety Officer 1 31 Portable Oven 5 21


11 Welder 6 32 1 22
12 Fitter 1 33 25 ton Crane 1 23
13 Sheet Fabricator 1 34 Water Tanker 1 24
14 Helper 7 25
15 Mason 1
16 Excavator & Shovel Operator 2
17 JCB Operator 1

18 BUS DRIVER 3
19 Carpenter 1
Total 33 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17

4 Site Foreman 1 12 SHOVEL 1 18


5 Fitter 0 13 25 ton Crane 0 19
6 Tak Welder 2 14 Diesel Welding machine 2
7 General Workers 5 15 Electric Welding machine 3
8 BUS DRIVER 2 16 Electric oven - 50 Kg 1

Page 147
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 17-Jan-16 Working Time: 7 am to 6:00p
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 29 Total 16
Total Manpower 80 Total Equipments 50

Contractor Sign & Stamp Client Sign & Stamp

SubContractor - Richmond - J&J


Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Richmond - J&J
1 Project Engineer 1 9 Mini Bus 1
2 Document Controller 1 10 Wheel Excavator 1
3 Office Asst 0 11 Roller Compactor 1
4 Site Foreman 2 12 SHOWEL 0
5 Mason 6 13 3 ton pick up 1
6 Helper 10 14 Steel Cutting Machine 1
7 Carpenter 8 15 Steel Bending machine 1
8 BUS DRIVER 1 16 JCB 0
9 Steel Worker 8 17 2 ton roller compactor 1

10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0

Total 38 Total 7
Total Manpower Total Equipments 7

Page 148
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 17-Jan-16 Working Time: 7 am to 6:00p
HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers Done
2 Safety barriers, safety cones and signage boards installed near to the road area Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the road Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted Done
10 Barricades provided near road area (Near Plant Area) Done

Page 149
Working Time: 7 am to 6:00pm
Other Details
Others Qty

Direct Manpower
Rigger 3

Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1

Total 16

Other Details
Others Qty

Shovel Operator
Crane Operator
Draughts man 1

BUS DRIVER 0
Site Surveyor 1

Page 150
Working Time: 7 am to 6:00pm

Total 2

ent Sign & Stamp

Other Details
Others Qty

Total 0

Page 151
Working Time: 7 am to 6:00pm

Page 152
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 16-Jan-16 Weather: Sunny Temperature: 30ºC
A. Manpower report as on 15-Jan-16 Total Manpower:
B. Equipment report as on 15-Jan-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 15-Jan-16

1 Zone - 4 pipe line doubling fit up.


2 Main Line 20 inch pipe fit up and welding.
3 Zone -2 Excavation.
4 ETS - B valve chamber Second wall steel work.
5 ETS - B and A Route pipe line fit up and welding.
6 Zone -4 Excavation is going on.
7 Inside military school excavation is going on Zone -2 and Zone - 4
8 Casting for ETS 3 Tie beam completled , Back filling in ETS 1 & 3
Activity - 20 & 18 INCH PIPE Current in mtr/no Previous in mtr/no Total in mtr/no

1 Excavation (Zone -1 and 2) 10 1773 1783


2 Bedding 100 1030 1030
3 Fit up 4 149 153
4 Doubling 5 148 153
5 Pipe Laying Fit up 3 72 69
6 Pipe Laying Welding 3 59 62
7 UPVC Sleeve Laying
Activity - 12 inch Current inmtr/no Previous in mtr/no Total inmtr/no

1 Bedding 100 300 400


2 Fit up 2 68 70
3 Doubling 2 60 62
4 Pipe Laying 240 220 460
5 First Layer Back Filling
6 Pipe Laying Fit up
7 Pipe Laying Welding

Activity - 10 inch Current in mtr/no Previous in mtr/no Total in mtr/no

1 Bedding 400 370 770


2 Fit up 2 65 67
3 Welding 2 63 65

Page 153
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 16-Jan-16 Weather: Sunny Temperature: 30ºC
4 Pipe Laying 20 600 620
5 First Layer Back Filling 170 0 170

Contractor Sign & Stamp Client Sign & Stamp

D. Today Planned Activities 16-Jan-16


1 ETS-B TIE BEAM Steel fixing , Deshuttering for Tie Beam ETS 3 , Shifting Shuttering to ETS B.
2 Zone - 4 pipe line doubling fit up is going on.
3 ETS - B Pipe line Doubling and welding is goin on.
4 Zone - 2 - 20 inch Pipe Doubling and Welding is going on.
5 Main Line 20 inch pipe fit up and welding is going on.- Z-2 & 1
6 20 inch main line Doubling and Welding in Zone - 2 & 1
7 Zone - 2 and 4 Excavation is going on.
8 ETS - B and A Route pipe line fit up and welding is going on.
9 Inside militry school excavation is going on - Zone -2 and Zone - 4

Activity - 14 inch Current inmtr/no Previous in mtr/no Total inmtr/no

1 Bedding 20 20 20
2 Fit up 2 39 41
3 Welding 3 34 37
4 Pipe Laying
5 First Layer Back Filling

Other Activity:

Page 154
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 16-Jan-16 Weather: Sunny Temperature: 30ºC
1 Pneumatic test for Zone-1 Joint No. R4 to R31 & S4 to S31 Completed
2 Pneumatic test for Zone-1 Joint No. R39 to R62 & S39 to S62 Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed

Page 155
Working Time: 7 am to 6:00pm
117
57

Remarks

On Progress
On Progress
On Progress Total Excavation
Completed in
On Progress Mtr
On Progress 1783
On Progress
On Progress
On Progress

Page 156
Working Time: 7 am to 6:00pm

nt Sign & Stamp

To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed

Page 157
Working Time: 7 am to 6:00pm

Page 158
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 16-Jan-16 Working Time: 7 am to 6:00p
Manpower Details Equipment Details Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1 20

10 Safety Officer 1 31 Portable Oven 5 21


11 Welder 6 32 1 22
12 Fitter 1 33 25 ton Crane 1 23
13 Sheet Fabricator 1 34 Water Tanker 1 24
14 Helper 7 25
15 Mason 1
16 Excavator & Shovel Operator 2
17 JCB Operator 1

18 BUS DRIVER 3
19 Carpenter 1
Total 33 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17

4 Site Foreman 1 12 SHOVEL 1 18


5 Fitter 0 13 25 ton Crane 0 19
6 Tak Welder 2 14 Diesel Welding machine 2
7 General Workers 5 15 Electric Welding machine 3
8 BUS DRIVER 2 16 Electric oven - 50 Kg 1

Page 159
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 16-Jan-16 Working Time: 7 am to 6:00p
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 29 Total 16
Total Manpower 80 Total Equipments 50

Contractor Sign & Stamp Client Sign & Stamp

SubContractor - Richmond - J&J


Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Richmond - J&J
1 Project Engineer 1 9 Mini Bus 1
2 Document Controller 1 10 Wheel Excavator 1
3 Office Asst 0 11 Roller Compactor 1
4 Site Foreman 2 12 SHOWEL 0
5 Mason 6 13 3 ton pick up 1
6 Helper 9 14 Steel Cutting Machine 1
7 Carpenter 8 15 Steel Bending machine 1
8 BUS DRIVER 1 16 JCB 0
9 Steel Worker 8 17 2 ton roller compactor 1

10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0

Total 37 Total 7
Total Manpower Total Equipments 7

Page 160
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 16-Jan-16 Working Time: 7 am to 6:00p
HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers Done
2 Safety barriers, safety cones and signage boards installed near to the road area Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the road Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted Done
10 Barricades provided near road area (Near Plant Area) Done

Page 161
Working Time: 7 am to 6:00pm
Other Details
Others Qty

Direct Manpower
Rigger 3

Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1

Total 16

Other Details
Others Qty

Shovel Operator
Crane Operator
Draughts man 1

BUS DRIVER 0
Site Surveyor 1

Page 162
Working Time: 7 am to 6:00pm

Total 2

ent Sign & Stamp

Other Details
Others Qty

Total 0

Page 163
Working Time: 7 am to 6:00pm

Page 164
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 14-Jan-16 Weather: Sunny Temperature: 30ºC
A. Manpower report as on 13-Jan-16 Total Manpower:
B. Equipment report as on 13-Jan-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 13-Jan-16

1 Zone - 4 pipe line doubling fit up.


2 Main Line 20 inch pipe fit up and welding.
3 Zone -2 Excavation.
4 ETS - B valve chamber Second wall steel work.
5 ETS - B and A Route pipe line fit up and welding.
6 Zone -4 Excavation is going on.
7 Inside military school excavation is going on Zone -2 and Zone - 4
8 Casting for ETS 3 Tie beam completled , Back filling in ETS 1 & 3
Activity - 20 & 18 INCH PIPE Current in mtr/no Previous in mtr/no Total in mtr/no

1 Excavation (Zone -1 and 2) 10 1773 1783


2 Bedding 100 1030 1030
3 Fit up 4 149 153
4 Doubling 5 148 153
5 Pipe Laying Fit up 3 72 69
6 Pipe Laying Welding 3 59 62
7 UPVC Sleeve Laying
Activity - 12 inch Current inmtr/no Previous in mtr/no Total inmtr/no

1 Bedding 100 300 400


2 Fit up 2 68 70
3 Doubling 2 60 62
4 Pipe Laying 220 140 360
5 First Layer Back Filling
6 Pipe Laying Fit up
7 Pipe Laying Welding

Activity - 10 inch Current in mtr/no Previous in mtr/no Total in mtr/no

1 Bedding 400 370 770


2 Fit up 2 63 65
3 Welding 2 61 63

Page 165
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 14-Jan-16 Weather: Sunny Temperature: 30ºC
4 Pipe Laying 0 600 600
5 First Layer Back Filling 170 0 170

Contractor Sign & Stamp Client Sign & Stamp

D. Today Planned Activities 14-Jan-16


1 ETS-B TIE BEAM Steel fixing , Deshuttering for Tie Beam ETS 3 , Shifting Shuttering to ETS B.
2 Zone - 4 pipe line doubling fit up is going on.
3 ETS - B Pipe line Doubling and welding is goin on.
4 Zone - 2 - 20 inch Pipe Doubling and Welding is going on.
5 Main Line 20 inch pipe fit up and welding is going on.- Z-2 & 1
6 20 inch main line Doubling and Welding in Zone - 2 & 1
7 Zone - 2 and 4 Excavation is going on.
8 ETS - B and A Route pipe line fit up and welding is going on.
9 Inside militry school excavation is going on - Zone -2 and Zone - 4

Activity - 14 inch Current inmtr/no Previous in mtr/no Total inmtr/no

1 Bedding
2 Fit up 2 39 41
3 Welding 3 34 37
4 Pipe Laying
5 First Layer Back Filling

Other Activity:

Page 166
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 14-Jan-16 Weather: Sunny Temperature: 30ºC
1 Pneumatic test for Zone-1 Joint No. R4 to R31 & S4 to S31 Completed
2 Pneumatic test for Zone-1 Joint No. R39 to R62 & S39 to S62 Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed

Page 167
Working Time: 7 am to 6:00pm
117
57

Remarks

On Progress
On Progress
On Progress Total Excavation
Completed in
On Progress Mtr
On Progress 1783
On Progress
On Progress
On Progress

Page 168
Working Time: 7 am to 6:00pm

nt Sign & Stamp

To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed

Page 169
Working Time: 7 am to 6:00pm

Page 170
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 14-Jan-16 Working Time: 7 am to 6:00p
Manpower Details Equipment Details Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1 20

10 Safety Officer 1 31 Portable Oven 5 21


11 Welder 6 32 1 22
12 Fitter 1 33 25 ton Crane 1 23
13 Sheet Fabricator 1 34 Water Tanker 1 24
14 Helper 7 25
15 Mason 1
16 Excavator & Shovel Operator 2
17 JCB Operator 1

18 BUS DRIVER 3
19 Carpenter 1
Total 33 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17

4 Site Foreman 1 12 SHOVEL 1 18


5 Fitter 0 13 25 ton Crane 0 19
6 Tak Welder 2 14 Diesel Welding machine 2
7 General Workers 5 15 Electric Welding machine 3
8 BUS DRIVER 2 16 Electric oven - 50 Kg 1

Page 171
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 14-Jan-16 Working Time: 7 am to 6:00p
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 29 Total 16
Total Manpower 80 Total Equipments 50

Contractor Sign & Stamp Client Sign & Stamp

SubContractor - Richmond - J&J


Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Richmond - J&J
1 Project Engineer 1 9 Mini Bus 1
2 Document Controller 1 10 Wheel Excavator 1
3 Office Asst 0 11 Roller Compactor 1
4 Site Foreman 2 12 SHOWEL 0
5 Mason 6 13 3 ton pick up 1
6 Helper 9 14 Steel Cutting Machine 1
7 Carpenter 8 15 Steel Bending machine 1
8 BUS DRIVER 1 16 JCB 0
9 Steel Worker 8 17 2 ton roller compactor 1

10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0

Total 37 Total 7
Total Manpower Total Equipments 7

Page 172
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 14-Jan-16 Working Time: 7 am to 6:00p
HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers Done
2 Safety barriers, safety cones and signage boards installed near to the road area Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the road Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted Done
10 Barricades provided near road area (Near Plant Area) Done

Page 173
Working Time: 7 am to 6:00pm
Other Details
Others Qty

Direct Manpower
Rigger 3

Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1

Total 16

Other Details
Others Qty

Shovel Operator
Crane Operator
Draughts man 1

BUS DRIVER 0
Site Surveyor 1

Page 174
Working Time: 7 am to 6:00pm

Total 2

ent Sign & Stamp

Other Details
Others Qty

Total 0

Page 175
Working Time: 7 am to 6:00pm

Page 176
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 13-Jan-16 Weather: Sunny Temperature: 30ºC
A. Manpower report as on 12-Jan-16 Total Manpower:
B. Equipment report as on 12-Jan-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 12-Jan-16

1 Zone - 4 pipe line doubling fit up.


2 Main Line 20 inch pipe fit up and welding.
3 Zone -2 Excavation.
4 ETS - B valve chamber Second wall steel work.
5 ETS - B and A Route pipe line fit up and welding.
6 Zone -4 Excavation is going on.
7 Inside military school excavation is going on Zone -2 and Zone - 4
8 Casting for ETS 3 Tie beam completled , Back filling in ETS 1 & 3
Activity - 20 & 18 INCH PIPE Current in mtr/no Previous in mtr/no Total in mtr/no

1 Excavation (Zone -1 and 2) 10 1773 1783


2 Bedding 100 1030 1030
3 Fit up 4 145 149
4 Doubling 5 143 148
5 Pipe Laying Fit up 3 69 69
6 Pipe Laying Welding 3 59 62
7 UPVC Sleeve Laying
Activity - 12 inch Current inmtr/no Previous in mtr/no Total inmtr/no

1 Bedding 100 300 400


2 Fit up 2 68 70
3 Doubling 2 58 60
4 Pipe Laying 220 140 360
5 First Layer Back Filling
6 Pipe Laying Fit up
7 Pipe Laying Welding

Activity - 10 inch Current in mtr/no Previous in mtr/no Total in mtr/no

1 Bedding 400 370 770


2 Fit up 3 61 64
3 Welding 2 61 63

Page 177
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 13-Jan-16 Weather: Sunny Temperature: 30ºC
4 Pipe Laying 0 600 600
5 First Layer Back Filling 170 0 170

Contractor Sign & Stamp Client Sign & Stamp

D. Today Planned Activities 13-Jan-16


1 ETS-B TIE BEAM Steel fixing , Deshuttering for Tie Beam ETS 3 , Shifting Shuttering to ETS B.
2 Zone - 4 pipe line doubling fit up is going on.
3 ETS - B Pipe line Doubling and welding is goin on.
4 Zone - 2 - 20 inch Pipe Doubling and Welding is going on.
5 Main Line 20 inch pipe fit up and welding is going on.- Z-2 & 1
6 20 inch main line Doubling and Welding in Zone - 2 & 1
7 Zone - 2 and 4 Excavation is going on.
8 ETS - B and A Route pipe line fit up and welding is going on.
9 Inside militry school excavation is going on - Zone -2 and Zone - 4

Activity - 14 inch Current inmtr/no Previous in mtr/no Total inmtr/no

1 Bedding
2 Fit up 2 37 39
3 Welding 2 31 33
4 Pipe Laying
5 First Layer Back Filling

Other Activity:

Page 178
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 13-Jan-16 Weather: Sunny Temperature: 30ºC
1 Pneumatic test for Zone-1 Joint No. R4 to R31 & S4 to S31 Completed
2 Pneumatic test for Zone-1 Joint No. R39 to R62 & S39 to S62 Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed

Page 179
Working Time: 7 am to 6:00pm
117
57

Remarks

On Progress
On Progress
On Progress Total Excavation
Completed in
On Progress Mtr
On Progress 1783
On Progress
On Progress
On Progress

Page 180
Working Time: 7 am to 6:00pm

nt Sign & Stamp

To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed

Page 181
Working Time: 7 am to 6:00pm

Page 182
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 13-Jan-16 Working Time: 7 am to 6:00p
Manpower Details Equipment Details Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1 20

10 Safety Officer 1 31 Portable Oven 5 21


11 Welder 6 32 1 22
12 Fitter 1 33 25 ton Crane 1 23
13 Sheet Fabricator 1 34 Water Tanker 1 24
14 Helper 7 25
15 Mason 1
16 Excavator & Shovel Operator 2
17 JCB Operator 1

18 BUS DRIVER 3
19 Carpenter 1
Total 33 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17

4 Site Foreman 1 12 SHOVEL 1 18


5 Fitter 0 13 25 ton Crane 0 19
6 Tak Welder 2 14 Diesel Welding machine 2
7 General Workers 5 15 Electric Welding machine 3
8 BUS DRIVER 2 16 Electric oven - 50 Kg 1

Page 183
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 13-Jan-16 Working Time: 7 am to 6:00p
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 29 Total 16
Total Manpower 80 Total Equipments 50

Contractor Sign & Stamp Client Sign & Stamp

SubContractor - Richmond - J&J


Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Richmond - J&J
1 Project Engineer 1 9 Mini Bus 1
2 Document Controller 1 10 Wheel Excavator 1
3 Office Asst 0 11 Roller Compactor 1
4 Site Foreman 2 12 SHOWEL 0
5 Mason 6 13 3 ton pick up 1
6 Helper 9 14 Steel Cutting Machine 1
7 Carpenter 8 15 Steel Bending machine 1
8 BUS DRIVER 1 16 JCB 0
9 Steel Worker 8 17 2 ton roller compactor 1

10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0

Total 37 Total 7
Total Manpower Total Equipments 7

Page 184
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 13-Jan-16 Working Time: 7 am to 6:00p
HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers Done
2 Safety barriers, safety cones and signage boards installed near to the road area Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the road Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted Done
10 Barricades provided near road area (Near Plant Area) Done

Page 185
Working Time: 7 am to 6:00pm
Other Details
Others Qty

Direct Manpower
Rigger 3

Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1

Total 16

Other Details
Others Qty

Shovel Operator
Crane Operator
Draughts man 1

BUS DRIVER 0
Site Surveyor 1

Page 186
Working Time: 7 am to 6:00pm

Total 2

ent Sign & Stamp

Other Details
Others Qty

Total 0

Page 187
Working Time: 7 am to 6:00pm

Page 188
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 12-Jan-16 Weather: Sunny Temperature: 30ºC
A. Manpower report as on 11-Jan-16 Total Manpower:
B. Equipment report as on 11-Jan-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 11-Jan-16

1 Zone - 4 pipe line doubling fit up.


2 Main Line 20 inch pipe fit up and welding.
3 Zone -2 Excavation.
4 ETS - B valve chamber Second wall steel work.
5 ETS - B and A Route pipe line fit up and welding.
6 Zone -4 Excavation is going on.
7 Inside military school excavation is going on Zone -2 and Zone - 4
8 Casting for ETS 3 Tie beam completled , Back filling in ETS 1 & 3
Activity - 20 & 18 INCH PIPE Current in mtr/no Previous in mtr/no Total in mtr/no

1 Excavation (Zone -1 and 2) 10 1773 1783


2 Bedding 100 1030 1030
3 Fit up 4 145 149
4 Doubling 5 143 148
5 Pipe Laying Fit up 3 69 69
6 Pipe Laying Welding 3 59 62
7 UPVC Sleeve Laying
Activity - 12 inch Current inmtr/no Previous in mtr/no Total inmtr/no

1 Bedding 100 300 400


2 Fit up 2 68 70
3 Doubling 2 58 60
4 Pipe Laying 220 140 360
5 First Layer Back Filling
6 Pipe Laying Fit up
7 Pipe Laying Welding

Activity - 10 inch Current in mtr/no Previous in mtr/no Total in mtr/no

1 Bedding 400 370 770


2 Fit up 3 61 64
3 Welding 2 61 63

Page 189
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 12-Jan-16 Weather: Sunny Temperature: 30ºC
4 Pipe Laying 0 600 600
5 First Layer Back Filling 170 0 170

Contractor Sign & Stamp Client Sign & Stamp

D. Today Planned Activities 12-Jan-16


1 ETS-B TIE BEAM Steel fixing , Deshuttering for Tie Beam ETS 3 , Shifting Shuttering to ETS B.
2 Zone - 4 pipe line doubling fit up is going on.
3 ETS - B Pipe line Doubling and welding is goin on.
4 Zone - 2 - 20 inch Pipe Doubling and Welding is going on.
5 Main Line 20 inch pipe fit up and welding is going on.- Z-2 & 1
6 20 inch main line Doubling and Welding in Zone - 2 & 1
7 Zone - 2 and 4 Excavation is going on.
8 ETS - B and A Route pipe line fit up and welding is going on.
9 Inside militry school excavation is going on - Zone -2 and Zone - 4

Activity - 14 inch Current inmtr/no Previous in mtr/no Total inmtr/no

1 Bedding
2 Fit up 2 37 39
3 Welding 2 31 33
4 Pipe Laying
5 First Layer Back Filling

Other Activity:

Page 190
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 12-Jan-16 Weather: Sunny Temperature: 30ºC
1 Pneumatic test for Zone-1 Joint No. R4 to R31 & S4 to S31 Completed
2 Pneumatic test for Zone-1 Joint No. R39 to R62 & S39 to S62 Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed

Page 191
Working Time: 7 am to 6:00pm
117
57

Remarks

On Progress
On Progress
On Progress Total Excavation
Completed in
On Progress Mtr
On Progress 1783
On Progress
On Progress
On Progress

Page 192
Working Time: 7 am to 6:00pm

nt Sign & Stamp

To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed

Page 193
Working Time: 7 am to 6:00pm

Page 194
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 12-Jan-16 Working Time: 7 am to 6:00p
Manpower Details Equipment Details Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1 20

10 Safety Officer 1 31 Portable Oven 5 21


11 Welder 6 32 1 22
12 Fitter 1 33 25 ton Crane 1 23
13 Sheet Fabricator 1 34 Water Tanker 1 24
14 Helper 7 25
15 Mason 1
16 Excavator & Shovel Operator 2
17 JCB Operator 1

18 BUS DRIVER 3
19 Carpenter 1
Total 33 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17

4 Site Foreman 1 12 SHOVEL 1 18


5 Fitter 0 13 25 ton Crane 0 19
6 Tak Welder 2 14 Diesel Welding machine 2
7 General Workers 5 15 Electric Welding machine 3
8 BUS DRIVER 2 16 Electric oven - 50 Kg 1

Page 195
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 12-Jan-16 Working Time: 7 am to 6:00p
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 29 Total 16
Total Manpower 80 Total Equipments 50

Contractor Sign & Stamp Client Sign & Stamp

SubContractor - Richmond - J&J


Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Richmond - J&J
1 Project Engineer 1 9 Mini Bus 1
2 Document Controller 1 10 Wheel Excavator 1
3 Office Asst 0 11 Roller Compactor 1
4 Site Foreman 2 12 SHOWEL 0
5 Mason 6 13 3 ton pick up 1
6 Helper 9 14 Steel Cutting Machine 1
7 Carpenter 8 15 Steel Bending machine 1
8 BUS DRIVER 1 16 JCB 0
9 Steel Worker 8 17 2 ton roller compactor 1

10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0

Total 37 Total 7
Total Manpower Total Equipments 7

Page 196
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 12-Jan-16 Working Time: 7 am to 6:00p
HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers Done
2 Safety barriers, safety cones and signage boards installed near to the road area Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the road Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted Done
10 Barricades provided near road area (Near Plant Area) Done

Page 197
Working Time: 7 am to 6:00pm
Other Details
Others Qty

Direct Manpower
Rigger 3

Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1

Total 16

Other Details
Others Qty

Shovel Operator
Crane Operator
Draughts man 1

BUS DRIVER 0
Site Surveyor 1

Page 198
Working Time: 7 am to 6:00pm

Total 2

ent Sign & Stamp

Other Details
Others Qty

Total 0

Page 199
Working Time: 7 am to 6:00pm

Page 200
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 11-Jan-16 Weather: Sunny Temperature: 30ºC
A. Manpower report as on 10-Jan-16 Total Manpower:
B. Equipment report as on 10-Jan-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 10-Jan-16

1 Zone - 4 pipe line doubling fit up.


2 Main Line 20 inch pipe fit up and welding.
3 Zone -2 Excavation.
4 ETS - B valve chamber Second wall steel work.
5 ETS - B and A Route pipe line fit up and welding.
6 Zone -4 Excavation is going on.
7 Inside military school excavation is going on Zone -2 and Zone - 4
8 Casting for ETS 3 Tie beam completled , Back filling in ETS 1 & 3
Activity - 20 & 18 INCH PIPE Current in mtr/no Previous in mtr/no Total in mtr/no

1 Excavation (Zone -1 and 2) 10 1763 1773


2 Bedding 100 1030 1030
3 Fit up 4 145 149
4 Doubling 5 143 148
5 Pipe Laying Fit up 3 69 69
6 Pipe Laying Welding 3 59 62
7 UPVC Sleeve Laying
Activity - 12 inch Current inmtr/no Previous in mtr/no Total inmtr/no

1 Bedding 100 300 400


2 Fit up 2 68 70
3 Doubling 2 58 60
4 Pipe Laying 220 140 360
5 First Layer Back Filling
6 Pipe Laying Fit up
7 Pipe Laying Welding

Activity - 10 inch Current in mtr/no Previous in mtr/no Total in mtr/no

1 Bedding 400 370 770


2 Fit up 3 61 64
3 Welding 2 61 63

Page 201
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 11-Jan-16 Weather: Sunny Temperature: 30ºC
4 Pipe Laying 0 600 600
5 First Layer Back Filling 170 0 170

Contractor Sign & Stamp Client Sign & Stamp

D. Today Planned Activities 11-Jan-16


1 ETS-B TIE BEAM Steel fixing , Deshuttering for Tie Beam ETS 3 , Shifting Shuttering to ETS B.
2 Zone - 4 pipe line doubling fit up is going on.
3 ETS - B Pipe line Doubling and welding is goin on.
4 Zone - 2 - 20 inch Pipe Doubling and Welding is going on.
5 Main Line 20 inch pipe fit up and welding is going on.- Z-2 & 1
6 20 inch main line Doubling and Welding in Zone - 2 & 1
7 Zone - 2 and 4 Excavation is going on.
8 ETS - B and A Route pipe line fit up and welding is going on.
9 Inside militry school excavation is going on - Zone -2 and Zone - 4

Activity - 14 inch Current inmtr/no Previous in mtr/no Total inmtr/no

1 Bedding
2 Fit up 2 37 39
3 Welding 2 31 33
4 Pipe Laying
5 First Layer Back Filling

Page 202
Working Time: 7 am to 6:00pm
113
57

Remarks

On Progress
On Progress
On Progress Total Excavation
Completed in
On Progress Mtr
On Progress 1773
On Progress
On Progress
On Progress

Page 203
Working Time: 7 am to 6:00pm

nt Sign & Stamp

To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed

Page 204
Working Time: 7 am to 6:00pm

Page 205
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 11-Jan-16 Working Time: 7 am to 6:00p
Manpower Details Equipment Details Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1 20

10 Safety Officer 1 31 Portable Oven 5 21


11 Welder 6 32 1 22
12 Fitter 1 33 25 ton Crane 1 23
13 Sheet Fabricator 1 34 Water Tanker 1 24
14 Helper 7 25
15 Mason 1
16 Excavator & Shovel Operator 2
17 JCB Operator 1

18 BUS DRIVER 3
19 Carpenter 1
Total 33 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17

4 Site Foreman 1 12 SHOVEL 1 18


5 Fitter 0 13 25 ton Crane 0 19
6 Tak Welder 2 14 Diesel Welding machine 2
7 General Workers 5 15 Electric Welding machine 3
8 BUS DRIVER 2 16 Electric oven - 50 Kg 1

Page 206
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 11-Jan-16 Working Time: 7 am to 6:00p
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 29 Total 16
Total Manpower 80 Total Equipments 50

Contractor Sign & Stamp Client Sign & Stamp

SubContractor - Richmond - J&J


Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Richmond - J&J
1 Project Engineer 1 9 Mini Bus 1
2 Document Controller 1 10 Wheel Excavator 1
3 Office Asst 0 11 Roller Compactor 1
4 Site Foreman 2 12 SHOWEL 0
5 Mason 6 13 3 ton pick up 1
6 Helper 9 14 Steel Cutting Machine 1
7 Carpenter 8 15 Steel Bending machine 1
8 BUS DRIVER 1 16 JCB 0
9 Steel Worker 8 17 2 ton roller compactor 1

10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0

Total 37 Total 7
Total Manpower Total Equipments 7

Page 207
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 11-Jan-16 Working Time: 7 am to 6:00p
HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers Done
2 Safety barriers, safety cones and signage boards installed near to the road area Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the road Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted Done
10 Barricades provided near road area (Near Plant Area) Done

Page 208
Working Time: 7 am to 6:00pm
Other Details
Others Qty

Direct Manpower
Rigger 3

Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1

Total 16

Other Details
Others Qty

Shovel Operator
Crane Operator
Draughts man 1

BUS DRIVER 0
Site Surveyor 1

Page 209
Working Time: 7 am to 6:00pm

Total 2

ent Sign & Stamp

Other Details
Others Qty

Total 0

Page 210
Working Time: 7 am to 6:00pm

Page 211
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 10-Jan-16 Weather: Sunny Temperature: 30ºC
A. Manpower report as on 9-Jan-16 Total Manpower:
B. Equipment report as on 9-Jan-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 9-Jan-16

1 Zone - 4 pipe line doubling fit up.


2 Main Line 20 inch pipe fit up and welding.
3 Zone -2 Excavation.
4 ETS - B valve chamber Second wall steel work.
5 ETS - B and A Route pipe line fit up and welding.
6 Zone -4 Excavation is going on.
7 Inside military school excavation is going on Zone -2 and Zone - 4
8 Casting for ETS 3 Tie beam completled , Back filling in ETS 1 & 3
Activity - 20 & 18 INCH PIPE Current in mtr/no Previous in mtr/no Total in mtr/no

1 Excavation (Zone -1 and 2) 10 1763 1773


2 Bedding 100 1030 1030
3 Fit up 2 141 143
4 Doubling 3 138 141
5 Pipe Laying Fit up 3 66 69
6 Pipe Laying Welding 2 56 58
7 UPVC Sleeve Laying
Activity - 12 inch Current inmtr/no Previous in mtr/no Total inmtr/no

1 Bedding 100 300 400


2 Fit up 2 68 70
3 Doubling 2 58 60
4 Pipe Laying 220 140 360
5 First Layer Back Filling
6 Pipe Laying Fit up
7 Pipe Laying Welding

Activity - 10 inch Current in mtr/no Previous in mtr/no Total in mtr/no

1 Bedding 400 370 770


2 Fit up 3 61 64
3 Welding 2 61 63

Page 212
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 10-Jan-16 Weather: Sunny Temperature: 30ºC
4 Pipe Laying 0 600 600
5 First Layer Back Filling 170 0 170

Contractor Sign & Stamp Client Sign & Stamp

D. Today Planned Activities 10-Jan-16


1 ETS-B TIE BEAM Steel fixing , Deshuttering for Tie Beam ETS 3 , Shifting Shuttering to ETS B.
2 Zone - 4 pipe line doubling fit up is going on.
3 ETS - B Pipe line Doubling and welding is goin on.
4 Zone - 2 - 20 inch Pipe Doubling and Welding is going on.
5 Main Line 20 inch pipe fit up and welding is going on.- Z-2 & 1
6 20 inch main line Doubling and Welding in Zone - 2 & 1
7 Zone - 2 and 4 Excavation is going on.
8 ETS - B and A Route pipe line fit up and welding is going on.
9 Inside militry school excavation is going on - Zone -2 and Zone - 4

Activity - 14 inch Current inmtr/no Previous in mtr/no Total inmtr/no

1 Bedding
2 Fit up 3 35 38
3 Welding 4 29 33
4 Pipe Laying
5 First Layer Back Filling

Page 213
Working Time: 7 am to 6:00pm
113
57

Remarks

On Progress
On Progress
On Progress Total Excavation
Completed in
On Progress Mtr
On Progress 1773
On Progress
On Progress
On Progress

Page 214
Working Time: 7 am to 6:00pm

nt Sign & Stamp

To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed

Page 215
Working Time: 7 am to 6:00pm

Page 216
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 10-Jan-16 Working Time: 7 am to 6:00p
Manpower Details Equipment Details Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1 20

10 Safety Officer 1 31 Portable Oven 5 21


11 Welder 6 32 1 22
12 Fitter 1 33 25 ton Crane 1 23
13 Sheet Fabricator 1 34 Water Tanker 1 24
14 Helper 7 25
15 Mason 1
16 Excavator & Shovel Operator 2
17 JCB Operator 1

18 BUS DRIVER 3
19 Carpenter 1
Total 33 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17

4 Site Foreman 1 12 SHOVEL 1 18


5 Fitter 0 13 25 ton Crane 0 19
6 Tak Welder 2 14 Diesel Welding machine 2
7 General Workers 5 15 Electric Welding machine 3
8 BUS DRIVER 2 16 Electric oven - 50 Kg 1

Page 217
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 10-Jan-16 Working Time: 7 am to 6:00p
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 29 Total 16
Total Manpower 80 Total Equipments 50

Contractor Sign & Stamp Client Sign & Stamp

SubContractor - Richmond - J&J


Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Richmond - J&J
1 Project Engineer 1 9 Mini Bus 1
2 Document Controller 1 10 Wheel Excavator 1
3 Office Asst 0 11 Roller Compactor 1
4 Site Foreman 2 12 SHOWEL 0
5 Mason 6 13 3 ton pick up 1
6 Helper 9 14 Steel Cutting Machine 1
7 Carpenter 8 15 Steel Bending machine 1
8 BUS DRIVER 1 16 JCB 0
9 Steel Worker 8 17 2 ton roller compactor 1

10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0

Total 37 Total 7
Total Manpower Total Equipments 7

Page 218
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 10-Jan-16 Working Time: 7 am to 6:00p
HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers Done
2 Safety barriers, safety cones and signage boards installed near to the road area Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the road Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted Done
10 Barricades provided near road area (Near Plant Area) Done

Page 219
Working Time: 7 am to 6:00pm
Other Details
Others Qty

Direct Manpower
Rigger 3

Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1

Total 16

Other Details
Others Qty

Shovel Operator
Crane Operator
Draughts man 1

BUS DRIVER 0
Site Surveyor 1

Page 220
Working Time: 7 am to 6:00pm

Total 2

ent Sign & Stamp

Other Details
Others Qty

Total 0

Page 221
Working Time: 7 am to 6:00pm

Page 222
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 9-Jan-16 Weather: Sunny Temperature: 30ºC
A. Manpower report as on 8-Jan-16 Total Manpower:
B. Equipment report as on 8-Jan-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 8-Jan-16

1 Zone - 4 pipe line doubling fit up.


2 Main Line 20 inch pipe fit up and welding.
3 Zone -2 Excavation.
4 ETS - B valve chamber Second wall steel work.
5 ETS - B and A Route pipe line fit up and welding.
6 Zone -4 Excavation is going on.
7 Inside military school excavation is going on Zone -2 and Zone - 4
8 Casting for ETS 3 Tie beam completled , Back filling in ETS 1 & 3
Activity - 20 & 18 INCH PIPE Current in mtr/no Previous in mtr/no Total in mtr/no

1 Excavation (Zone -1 and 2) 10 1753 1763


2 Bedding 100 1030 1030
3 Fit up 2 139 141
4 Doubling 3 136 139
5 Pipe Laying Fit up 2 64 66
6 Pipe Laying Welding 2 54 56
7 UPVC Sleeve Laying
Activity - 12 inch Current inmtr/no Previous in mtr/no Total inmtr/no

1 Bedding 100 300 400


2 Fit up 2 68 70
3 Doubling 2 58 60
4 Pipe Laying 220 140 360
5 First Layer Back Filling
6 Pipe Laying Fit up
7 Pipe Laying Welding

Activity - 10 inch Current in mtr/no Previous in mtr/no Total in mtr/no

1 Bedding 400 370 770


2 Fit up 3 61 64
3 Welding 2 61 63

Page 223
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 9-Jan-16 Weather: Sunny Temperature: 30ºC
4 Pipe Laying 0 600 600
5 First Layer Back Filling 170 0 170

Contractor Sign & Stamp Client Sign & Stamp

D. Today Planned Activities 9-Jan-16


1 ETS-B TIE BEAM Steel fixing , Deshuttering for Tie Beam ETS 3 , Shifting Shuttering to ETS B.
2 Zone - 4 pipe line doubling fit up is going on.
3 ETS - B Pipe line Doubling and welding is goin on.
4 Zone - 2 - 20 inch Pipe Doubling and Welding is going on.
5 Main Line 20 inch pipe fit up and welding is going on.- Z-2 & 1
6 20 inch main line Doubling and Welding in Zone - 2 & 1
7 Zone - 2 and 4 Excavation is going on.
8 ETS - B and A Route pipe line fit up and welding is going on.
9 Inside militry school excavation is going on - Zone -2 and Zone - 4

Activity - 14 inch Current inmtr/no Previous in mtr/no Total inmtr/no

1 Bedding
2 Fit up 2 35 37
3 Welding 4 29 33
4 Pipe Laying
5 First Layer Back Filling

Page 224
Working Time: 7 am to 6:00pm
113
57

Remarks

On Progress
On Progress
On Progress Total Excavation
Completed in
On Progress Mtr
On Progress 1763
On Progress
On Progress
On Progress

Page 225
Working Time: 7 am to 6:00pm

nt Sign & Stamp

To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed

Page 226
Working Time: 7 am to 6:00pm

Page 227
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 9-Jan-16 Working Time: 7 am to 6:00p
Manpower Details Equipment Details Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1 20

10 Safety Officer 1 31 Portable Oven 5 21


11 Welder 6 32 1 22
12 Fitter 1 33 25 ton Crane 1 23
13 Sheet Fabricator 1 34 Water Tanker 1 24
14 Helper 7 25
15 Mason 1
16 Excavator & Shovel Operator 2
17 JCB Operator 1

18 BUS DRIVER 3
19 Carpenter 1
Total 33 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17

4 Site Foreman 1 12 SHOVEL 1 18


5 Fitter 0 13 25 ton Crane 0 19
6 Tak Welder 2 14 Diesel Welding machine 2
7 General Workers 5 15 Electric Welding machine 3
8 BUS DRIVER 2 16 Electric oven - 50 Kg 1

Page 228
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 9-Jan-16 Working Time: 7 am to 6:00p
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 29 Total 16
Total Manpower 80 Total Equipments 50

Contractor Sign & Stamp Client Sign & Stamp

SubContractor - Richmond - J&J


Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Richmond - J&J
1 Project Engineer 1 9 Mini Bus 1
2 Document Controller 1 10 Wheel Excavator 1
3 Office Asst 0 11 Roller Compactor 1
4 Site Foreman 2 12 SHOWEL 0
5 Mason 6 13 3 ton pick up 1
6 Helper 9 14 Steel Cutting Machine 1
7 Carpenter 8 15 Steel Bending machine 1
8 BUS DRIVER 1 16 JCB 0
9 Steel Worker 8 17 2 ton roller compactor 1

10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0

Total 37 Total 7
Total Manpower Total Equipments 7

Page 229
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 9-Jan-16 Working Time: 7 am to 6:00p
HSE Issues:
F. HSE Issues:
1 orange mesh installed at ETS 1 locations Done
2 Safety barriers, safety cones and signage boards installed near to the road area Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the road Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted Done
10 Barricades provided near road area (Near Plant Area) Done

Page 230
Working Time: 7 am to 6:00pm
Other Details
Others Qty

Direct Manpower
Rigger 3

Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1

Total 16

Other Details
Others Qty

Shovel Operator
Crane Operator
Draughts man 1

BUS DRIVER 0
Site Surveyor 1

Page 231
Working Time: 7 am to 6:00pm

Total 2

ent Sign & Stamp

Other Details
Others Qty

Total 0

Page 232
Working Time: 7 am to 6:00pm

Page 233
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 7-Jan-16 Weather: Sunny Temperature: 30ºC
A. Manpower report as on 6-Jan-16 Total Manpower:
B. Equipment report as on 6-Jan-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 6-Jan-16

1 Zone - 4 pipe line doubling fit up.


2 Main Line 20 inch pipe fit up and welding.
3 Zone -2 Excavation.
4 ETS - B valve chamber Second wall steel work.
5 ETS - B and A Route pipe line fit up and welding.
6 Zone -4 Excavation is going on.
7 Inside military school excavation is going on Zone -2 and Zone - 4
8 Casting for ETS 3 Tie beam completled , Back filling in ETS 1 & 3
Activity - 20 & 18 INCH PIPE Current in mtr/no Previous in mtr/no Total in mtr/no

1 Excavation (Zone -1 and 2) 10 1743 1753


2 Bedding 100 1030 1030
3 Fit up 2 139 141
4 Doubling 3 136 139
5 Pipe Laying Fit up 2 64 66
6 Pipe Laying Welding 2 54 56
7 UPVC Sleeve Laying
Activity - 12 inch Current inmtr/no Previous in mtr/no Total inmtr/no

1 Bedding 100 300 400


2 Fit up 2 68 70
3 Doubling 2 58 60
4 Pipe Laying 220 140 360
5 First Layer Back Filling
6 Pipe Laying Fit up
7 Pipe Laying Welding

Activity - 10 inch Current in mtr/no Previous in mtr/no Total in mtr/no

1 Bedding 400 370 770


2 Fit up 3 61 64
3 Welding 2 61 63

Page 234
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 7-Jan-16 Weather: Sunny Temperature: 30ºC
4 Pipe Laying 0 600 600
5 First Layer Back Filling 170 0 170

Contractor Sign & Stamp Client Sign & Stamp

D. Today Planned Activities 7-Jan-16


1 ETS-B TIE BEAM Steel fixing , Deshuttering for Tie Beam ETS 3 , Shifting Shuttering to ETS B.
2 Zone - 4 pipe line doubling fit up is going on.
3 ETS - B Pipe line Doubling and welding is goin on.
4 Zone - 2 - 20 inch Pipe Doubling and Welding is going on.
5 Main Line 20 inch pipe fit up and welding is going on.- Z-2 & 1
6 20 inch main line Doubling and Welding in Zone - 2 & 1
7 Zone - 2 and 4 Excavation is going on.
8 ETS - B and A Route pipe line fit up and welding is going on.
9 Inside militry school excavation is going on - Zone -2 and Zone - 4

Activity - 14 inch Current inmtr/no Previous in mtr/no Total inmtr/no

1 Bedding
2 Fit up 2 33 35
3 Welding 2 25 27
4 Pipe Laying
5 First Layer Back Filling

Page 235
Working Time: 7 am to 6:00pm
113
57

Remarks

On Progress
On Progress
On Progress Total Excavation
Completed in
On Progress Mtr
On Progress 1753
On Progress
On Progress
On Progress

Page 236
Working Time: 7 am to 6:00pm

nt Sign & Stamp

To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed

Page 237
Working Time: 7 am to 6:00pm

Page 238
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 7-Jan-16 Working Time: 7 am to 6:00p
Manpower Details Equipment Details Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1 20

10 Safety Officer 1 31 Portable Oven 5 21


11 Welder 6 32 1 22
12 Fitter 1 33 25 ton Crane 1 23
13 Sheet Fabricator 1 34 Water Tanker 1 24
14 Helper 7 25
15 Mason 1
16 Excavator & Shovel Operator 2
17 JCB Operator 1

18 BUS DRIVER 3
19 Carpenter 1
Total 33 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17

4 Site Foreman 1 12 SHOVEL 1 18


5 Fitter 0 13 25 ton Crane 0 19
6 Tak Welder 2 14 Diesel Welding machine 2
7 General Workers 5 15 Electric Welding machine 3
8 BUS DRIVER 2 16 Electric oven - 50 Kg 1

Page 239
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 7-Jan-16 Working Time: 7 am to 6:00p
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 29 Total 16
Total Manpower 80 Total Equipments 50

Contractor Sign & Stamp Client Sign & Stamp

SubContractor - Richmond - J&J


Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Richmond - J&J
1 Project Engineer 1 9 Mini Bus 1
2 Document Controller 1 10 Wheel Excavator 1
3 Office Asst 0 11 Roller Compactor 1
4 Site Foreman 2 12 SHOWEL 0
5 Mason 6 13 3 ton pick up 1
6 Helper 9 14 Steel Cutting Machine 1
7 Carpenter 8 15 Steel Bending machine 1
8 BUS DRIVER 1 16 JCB 0
9 Steel Worker 8 17 2 ton roller compactor 1

10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0

Total 37 Total 7
Total Manpower Total Equipments 7

Page 240
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 7-Jan-16 Working Time: 7 am to 6:00p
HSE Issues:
F. HSE Issues:
1 orange mesh installed at ETS 1 locations Done
2 Safety barriers, safety cones and signage boards installed near to the road area Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the road Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted Done
10 Barricades provided near road area (Near Plant Area) Done

Page 241
Working Time: 7 am to 6:00pm
Other Details
Others Qty

Direct Manpower
Rigger 3

Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1

Total 16

Other Details
Others Qty

Shovel Operator
Crane Operator
Draughts man 1

BUS DRIVER 0
Site Surveyor 1

Page 242
Working Time: 7 am to 6:00pm

Total 2

ent Sign & Stamp

Other Details
Others Qty

Total 0

Page 243
Working Time: 7 am to 6:00pm

Page 244
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 7-Jan-16 Weather: Sunny Temperature: 30ºC
A. Manpower report as on 6-Jan-16 Total Manpower:
B. Equipment report as on 6-Jan-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 6-Jan-16

1 Zone - 4 pipe line doubling fit up.


2 Main Line 20 inch pipe fit up and welding.
3 Zone -2 Excavation.
4 ETS - B valve chamber Second wall steel work.
5 ETS - B and A Route pipe line fit up and welding.
6 Zone -4 Excavation is going on.
7 Inside military school excavation is going on Zone -2 and Zone - 4
8 Casting for ETS 3 Tie beam completled , Back filling in ETS 1 & 3
Activity - 20 & 18 INCH PIPE Current in mtr/no Previous in mtr/no Total in mtr/no

1 Excavation (Zone -1 and 2) 10 1743 1753


2 Bedding 100 1030 1030
3 Fit up 2 139 141
4 Doubling 3 136 139
5 Pipe Laying Fit up 2 64 66
6 Pipe Laying Welding 2 54 56
7 UPVC Sleeve Laying
Activity - 12 inch Current inmtr/no Previous in mtr/no Total inmtr/no

1 Bedding 100 300 400


2 Fit up 2 68 70
3 Doubling 2 58 60
4 Pipe Laying 220 140 360
5 First Layer Back Filling
6 Pipe Laying Fit up
7 Pipe Laying Welding

Activity - 10 inch Current in mtr/no Previous in mtr/no Total in mtr/no

1 Bedding 400 370 770


2 Fit up 3 61 64
3 Welding 2 61 63

Page 245
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 7-Jan-16 Weather: Sunny Temperature: 30ºC
4 Pipe Laying 0 600 600
5 First Layer Back Filling 170 0 170

Contractor Sign & Stamp Client Sign & Stamp

D. Today Planned Activities 7-Jan-16


1 ETS-B TIE BEAM Steel fixing , Deshuttering for Tie Beam ETS 3 , Shifting Shuttering to ETS B.
2 Zone - 4 pipe line doubling fit up is going on.
3 ETS - B Pipe line Doubling and welding is goin on.
4 Zone - 2 - 20 inch Pipe Doubling and Welding is going on.
5 Main Line 20 inch pipe fit up and welding is going on.- Z-2 & 1
6 20 inch main line Doubling and Welding in Zone - 2 & 1
7 Zone - 2 and 4 Excavation is going on.
8 ETS - B and A Route pipe line fit up and welding is going on.
9 Inside militry school excavation is going on - Zone -2 and Zone - 4

Activity - 14 inch Current inmtr/no Previous in mtr/no Total inmtr/no

1 Bedding
2 Fit up 2 33 35
3 Welding 2 25 27
4 Pipe Laying
5 First Layer Back Filling

Page 246
Working Time: 7 am to 6:00pm
113
57

Remarks

On Progress
On Progress
On Progress Total Excavation
Completed in
On Progress Mtr
On Progress 1753
On Progress
On Progress
On Progress

Page 247
Working Time: 7 am to 6:00pm

nt Sign & Stamp

To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed

Page 248
Working Time: 7 am to 6:00pm

Page 249
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 7-Jan-16 Working Time: 7 am to 6:00p
Manpower Details Equipment Details Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1 20

10 Safety Officer 1 31 Portable Oven 5 21


11 Welder 6 32 1 22
12 Fitter 1 33 25 ton Crane 1 23
13 Sheet Fabricator 1 34 Water Tanker 1 24
14 Helper 7 25
15 Mason 1
16 Excavator & Shovel Operator 2
17 JCB Operator 1

18 BUS DRIVER 3
19 Carpenter 1
Total 33 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17

4 Site Foreman 1 12 SHOVEL 1 18


5 Fitter 0 13 25 ton Crane 0 19
6 Tak Welder 2 14 Diesel Welding machine 2
7 General Workers 5 15 Electric Welding machine 3
8 BUS DRIVER 2 16 Electric oven - 50 Kg 1

Page 250
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 7-Jan-16 Working Time: 7 am to 6:00p
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 29 Total 16
Total Manpower 80 Total Equipments 50

Contractor Sign & Stamp Client Sign & Stamp

SubContractor - Richmond - J&J


Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Richmond - J&J
1 Project Engineer 1 9 Mini Bus 1
2 Document Controller 1 10 Wheel Excavator 1
3 Office Asst 0 11 Roller Compactor 1
4 Site Foreman 2 12 SHOWEL 0
5 Mason 6 13 3 ton pick up 1
6 Helper 9 14 Steel Cutting Machine 1
7 Carpenter 8 15 Steel Bending machine 1
8 BUS DRIVER 1 16 JCB 0
9 Steel Worker 8 17 2 ton roller compactor 1

10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0

Total 37 Total 7
Total Manpower Total Equipments 7

Page 251
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 7-Jan-16 Working Time: 7 am to 6:00p
HSE Issues:
F. HSE Issues:
1 orange mesh installed at ETS 1 locations Done
2 Safety barriers, safety cones and signage boards installed near to the road area Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the road Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted Done
10 Barricades provided near road area (Near Plant Area) Done

Page 252
Working Time: 7 am to 6:00pm
Other Details
Others Qty

Direct Manpower
Rigger 3

Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1

Total 16

Other Details
Others Qty

Shovel Operator
Crane Operator
Draughts man 1

BUS DRIVER 0
Site Surveyor 1

Page 253
Working Time: 7 am to 6:00pm

Total 2

ent Sign & Stamp

Other Details
Others Qty

Total 0

Page 254
Working Time: 7 am to 6:00pm

Page 255
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 5-Jan-16 Weather: Sunny Temperature: 30ºC
A. Manpower report as on 4-Jan-16 Total Manpower:
B. Equipment report as on 4-Jan-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 4-Jan-16

1 Zone - 4 pipe line doubling fit up.


2 Main Line 20 inch pipe fit up and welding.
3 Zone -2 Excavation.
4 ETS - B valve chamber Second wall steel work.
5 ETS - B and A Route pipe line fit up and welding.
6 Zone -4 Excavation is going on.
7 Inside military school excavation is going on Zone -2 and Zone - 4
8 Casting for ETS 3 Tie beam completled , Back filling in ETS 1 & 3
Activity - 20 & 18 INCH PIPE Current in mtr/no Previous in mtr/no Total in mtr/no

1 Excavation (Zone -1 and 2) 10 1723 1733


2 Bedding 100 960 1030
3 Fit up 4 135 139
4 Doubling 4 130 134
5 Pipe Laying Fit up 0 60 60
6 Pipe Laying Welding 0 52 52
7 UPVC Sleeve Laying
Activity - 12 inch Current inmtr/no Previous in mtr/no Total inmtr/no

1 Bedding 100 300 400


2 Fit up 2 68 70
3 Doubling 2 58 60
4 Pipe Laying 220 140 360
5 First Layer Back Filling
6 Pipe Laying Fit up
7 Pipe Laying Welding

Activity - 10 inch Current in mtr/no Previous in mtr/no Total in mtr/no

1 Bedding 370 370 740


2 Fit up 2 59 61
3 Welding 3 61 64

Page 256
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 5-Jan-16 Weather: Sunny Temperature: 30ºC
4 Pipe Laying 0 600 600
5 First Layer Back Filling 170 0 170

Contractor Sign & Stamp Client Sign & Stamp

D. Today Planned Activities 5-Jan-16


1 ETS-B TIE BEAM Steel fixing , Deshuttering for Tie Beam ETS 3 , Shifting Shuttering to ETS B.
2 Zone - 4 pipe line doubling fit up is going on.
3 ETS - B Pipe line Doubling and welding is goin on.
4 Zone - 2 - 20 inch Pipe Doubling and Welding is going on.
5 Main Line 20 inch pipe fit up and welding is going on.- Z-2 & 1
6 20 inch main line Doubling and Welding in Zone - 2 & 1
7 Zone - 2 and 4 Excavation is going on.
8 ETS - B and A Route pipe line fit up and welding is going on.
9 Inside militry school excavation is going on - Zone -2 and Zone - 4

Activity - 14 inch Current inmtr/no Previous in mtr/no Total inmtr/no

1 Bedding
2 Fit up 2 33 35
3 Welding 2 25 27
4 Pipe Laying
5 First Layer Back Filling

Page 257
Working Time: 7 am to 6:00pm
113
57

Remarks

On Progress
On Progress
On Progress Total Excavation
Completed in
On Progress Mtr
On Progress 1733
On Progress
On Progress
On Progress

Page 258
Working Time: 7 am to 6:00pm

nt Sign & Stamp

To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed

Page 259
Working Time: 7 am to 6:00pm

Page 260
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 5-Jan-16 Working Time: 7 am to 6:00p
Manpower Details Equipment Details Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1 20

10 Safety Officer 1 31 Portable Oven 5 21


11 Welder 6 32 1 22
12 Fitter 1 33 25 ton Crane 1 23
13 Sheet Fabricator 1 34 Water Tanker 1 24
14 Helper 7 25
15 Mason 1
16 Excavator & Shovel Operator 2
17 JCB Operator 1

18 BUS DRIVER 3
19 Carpenter 1
Total 33 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17

4 Site Foreman 1 12 SHOVEL 1 18


5 Fitter 0 13 25 ton Crane 0 19
6 Tak Welder 2 14 Diesel Welding machine 2
7 General Workers 5 15 Electric Welding machine 3
8 BUS DRIVER 2 16 Electric oven - 50 Kg 1

Page 261
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 5-Jan-16 Working Time: 7 am to 6:00p
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 29 Total 16
Total Manpower 80 Total Equipments 50

Contractor Sign & Stamp Client Sign & Stamp

SubContractor - Richmond - J&J


Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Richmond - J&J
1 Project Engineer 1 9 Mini Bus 1
2 Document Controller 1 10 Wheel Excavator 1
3 Office Asst 0 11 Roller Compactor 1
4 Site Foreman 2 12 SHOWEL 0
5 Mason 6 13 3 ton pick up 1
6 Helper 9 14 Steel Cutting Machine 1
7 Carpenter 8 15 Steel Bending machine 1
8 BUS DRIVER 1 16 JCB 0
9 Steel Worker 8 17 2 ton roller compactor 1

10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0

Total 37 Total 7
Total Manpower Total Equipments 7

Page 262
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 5-Jan-16 Working Time: 7 am to 6:00p
HSE Issues:
F. HSE Issues:
1 orange mesh installed at ETS 1 locations Done
2 Safety barriers, safety cones and signage boards installed near to the road area Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the road Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted Done
10 Barricades provided near road area (Near Plant Area) Done

Page 263
Working Time: 7 am to 6:00pm
Other Details
Others Qty

Direct Manpower
Rigger 3

Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1

Total 16

Other Details
Others Qty

Shovel Operator
Crane Operator
Draughts man 1

BUS DRIVER 0
Site Surveyor 1

Page 264
Working Time: 7 am to 6:00pm

Total 2

ent Sign & Stamp

Other Details
Others Qty

Total 0

Page 265
Working Time: 7 am to 6:00pm

Page 266
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 4-Jan-16 Weather: Sunny Temperature: 30ºC Working Time:

A. Manpower report as on 3-Jan-16 Total Manpower: 113


B. Equipment report as on 3-Jan-16 Total Equipment: 57
C. Progress Report - Executive Summary
Sl No. Activities Done On 3-Jan-16

1 Zone - 4 pipe line doubling fit up. On Progress


2 Main Line 20 inch pipe fit up and welding. On Progress
3 Zone -2 Excavation. On Progress
4 ETS - B valve chamber Second wall steel work. On Progress
5 ETS - B and A Route pipe line fit up and welding. On Progress
6 Zone -4 Excavation is going on. On Progress
7 Inside military school excavation is going on Zone -2 and Zone - 4 On Progress
8 Casting for ETS 3 Tie beam completled , Back filling in ETS 1 & 3 On Progress
Activity - 20 & 18 INCH PIPE Current in Previous in Total in
mtr/no mtr/no mtr/no
1 Excavation (Zone -1 and 2) 10 1713 1723
2 Bedding 100 960 1030
3 Fit up 4 135 139
4 Doubling 4 130 134
5 Pipe Laying Fit up 0 60 60
6 Pipe Laying Welding 0 52 52
7 UPVC Sleeve Laying
Current in Previous in Total in
Activity - 12 inch mtr/no mtr/no mtr/no

1 Bedding 100 300 400


2 Fit up 2 68 70
3 Doubling 2 58 60
4 Pipe Laying 220 140 360
5 First Layer Back Filling
6 Pipe Laying Fit up
7 Pipe Laying Welding

Current in Previous in Total in


Activity - 10 inch mtr/no mtr/no mtr/no

1 Bedding 370 370 740


2 Fit up 2 59 61
3 Welding 3 61 64
4 Pipe Laying 0 600 600
5 First Layer Back Filling 170 0 170

Contractor Sign & Stamp Client Sign & Stamp


D. Today Planned
ETS-B TIE BEAMActivities 4-Jan-16
Steel fixing , Deshuttering for Tie Beam ETS 3 ,
1 Shifting Shuttering to ETS B. To Be Progressed
2 Zone - 4 pipe line doubling fit up is going on. To Be Progressed
3 ETS - B Pipe line Doubling and welding is goin on. To Be Progressed
4 Zone - 2 - 20 inch Pipe Doubling and Welding is going on. To Be Progressed
5 Main Line 20 inch pipe fit up and welding is going on.- Z-2 & 1 To Be Progressed
6 20 inch main line Doubling and Welding in Zone - 2 & 1 To Be Progressed
7 Zone - 2 and 4 Excavation is going on. To Be Progressed
8 ETS - B and A Route pipe line fit up and welding is going on. To Be Progressed
9 Inside militry school excavation is going on - Zone -2 and Zone - 4 To Be Progressed

Total
Activity - 14 inch Current inmtr/no
Previous in mtr/no
inmtr/no

1 Bedding
2 Fit up 2 33 35
3 Welding 2 25 27
4 Pipe Laying
5 First Layer Back Filling
AWI

7 am to 6:00pm

Remarks

Total
Excavation
Completed
in Mtr
1723
& Stamp
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 4-Jan-16 Working Time: 7 am to

Manpower Details Equipment Details Other D


Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1 20

10 Safety Officer 1 31 Portable Oven 5 21


11 Welder 6 32 1 22
12 Fitter 1 33 25 ton Crane 1 23
13 Sheet Fabricator 1 34 Water Tanker 1 24
14 Helper 7 25
15 Mason 1
16 Excavator & Shovel Operator 2
17 JCB Operator 1

18 BUS DRIVER 3
19 Carpenter 1
Total 33 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other D
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17

4 Site Foreman 1 12 SHOVEL 1 18


5 Fitter 1 13 25 ton Crane 0 19
6 Tak Welder 2 14 Diesel Welding machine 2
7 General Workers 5 15 Electric Welding machine 3
8 BUS DRIVER 2 16 Electric oven - 50 Kg 1
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 30 Total 16
Total Manpower 81 Total Equipments 50
Contractor Sign & Stamp Client Sign & Stamp
SubContractor - Richmond - J&J
Manpower Details Equipment Detail Other D
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Richmond - J&J
1 Project Engineer 1 9 Mini Bus 1
2 Document Controller 1 10 Wheel Excavator 1
3 Office Asst 0 11 Roller Compactor 1
4 Site Foreman 2 12 SHOWEL 0
5 Mason 6 13 3 ton pick up 1
6 Helper 9 14 Steel Cutting Machine 1
7 Carpenter 8 15 Steel Bending machine 1
8 BUS DRIVER 1 16 JCB 0
9 Steel Worker 8 17 2 ton roller compactor 1

10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0

Total 37 Total 7
Total Manpower Total Equipments 7

HSE Issues:
F. HSE Issues:
1 orange mesh installed at ETS 1 locations Done
2 Safety barriers, safety cones and signage boards installed near to the road area Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the road Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signages were poste Done
10 Barricades provided near road area (Near Plant Area) Done
Working Time: 7 am to 6:00pm

Other Details
Others Qty

Direct Manpower
Rigger 3

Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1

Total 16

Other Details
Others Qty

Shovel Operator
Crane Operator
Draughts man 1

BUS DRIVER 0
Site Surveyor 1
Total 2

ient Sign & Stamp


Other Details
Others Qty

Total 0
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 3-Jan-16 Weather: Sunny Temperature: 30ºC Working Time:7 am to 6:00pm

A. Manpower report as on 2-Jan-16 Total Manpower: 113


B. Equipment report as on 2-Jan-16 Total Equipment: 57
C. Progress Report - Executive Summary
Sl No. Activities Done On 2-Jan-16 Remarks

1 Zone - 4 pipe line doubling fit up. On Progress


2 Main Line 20 inch pipe fit up and welding. On Progress Total
3 Zone -2 Excavation. On Progress Excavation
4 ETS - B valve chamber Second wall steel work. On Progress Completed
in Mtr
5 ETS - B and A Route pipe line fit up and welding. On Progress 1718
6 Zone -4 Excavation is going on. On Progress
7 Inside military school excavation is going on Zone -2 and Zone - On Progress
8 Casting for ETS 3 Tie beam completled , Back filling in ETS 1 & 3 On Progress
Total in
Activity - 20 & 18 INCH PIPECurrent inPrevious
mtr/no in mtr/no mtr/no
1 Excavation (Zone -1 and 2) 15 1703 1718
2 Bedding 0 860 930
3 Fit up 4 131 135
4 Doubling 4 126 130
5 Pipe Laying Fit up 0 58 60
6 Pipe Laying Welding 0 52 52
7 UPVC Sleeve Laying
Total
Activity - 12 inch Current inmtr/no
Previous in mtr/no
inmtr/no

1 Bedding 100 200 300


2 Fit up 2 68 70
3 Doubling 2 54 56
4 Pipe Laying 220 140 360
5 First Layer Back Filling
6 Pipe Laying Fit up
7 Pipe Laying Welding

Total in
Activity - 10 inch Current inPrevious
mtr/no in mtr/no
mtr/no

1 Bedding 370 370 740


2 Fit up 2 59 61
3 Welding 3 61 64
4 Pipe Laying 0 600 600
5 First Layer Back Filling 170 0 170

Contractor Sign & Stamp Client Sign & Stamp

D. Today Planned
ETS-B TIE BEAMActivities
Steel fixing , Deshuttering for Tie3-Jan-16
Beam ETS 3 ,
1 Shifting Shuttering to ETS B. To Be Progressed
2 Zone - 4 pipe line doubling fit up is going on. To Be Progressed
3 ETS - B Pipe line Doubling and welding is goin on. To Be Progressed
4 Zone - 2 - 20 inch Pipe Doubling and Welding is going on. To Be Progressed
5 Main Line 20 inch pipe fit up and welding is going on.- Z-2 & 1 To Be Progressed
6 20 inch main line Doubling and Welding in Zone - 2 & 1 To Be Progressed
7 Zone - 2 and 4 Excavation is going on. To Be Progressed
8 ETS - B and A Route pipe line fit up and welding is going on. To Be Progressed
9 Inside militry school excavation is going on - Zone -2 and Zone -To Be Progressed

Total
Activity - 14 inch Current inmtr/no
Previous in mtr/no
inmtr/no

1 Bedding
2 Fit up 2 33 35
3 Welding 2 25 27
4 Pipe Laying
5 First Layer Back Filling
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 3-Jan-16 Working Time: 7 am to 6:00pm

Manpower Details Equipment Details Other Details


Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Superviso 1 30 Electric oven - 50 Kg 1 20

10 Safety Officer 1 31 Portable Oven 5 21


11 Welder 6 32 1 22
12 Fitter 1 33 25 ton Crane 1 23
13 Sheet Fabricator 1 34 Water Tanker 1 24
14 Helper 7 25
15 Mason 1
16 Excavator & Shovel Op 2
17 JCB Operator 1

18 BUS DRIVER 3
19 Carpenter 1
Total 33 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1 15
2 Site Engineer 1 10 Wheel Excavator 1 16
3 Safety Officer 1 11 Roller Compactor 1 17

4 Site Foreman 1 12 SHOVEL 1 18


5 Fitter 0 13 25 ton Crane 0 19
6 Tak Welder 2 14 Diesel Welding machine 2
7 General Workers 5 15 Electric Welding machine 3
8 BUS DRIVER 2 16 Electric oven - 50 Kg 1
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 29 Total 16
Total Manpower 80 Total Equipments 50
Contractor Sign & Stamp Client Sign & Stamp

SubContractor - Richmond - J&J


Manpower Details Equipment Detail Other Details
Sl No. Designation Qty Sl No. Equipments Qty Sl No.
Richmond - J&J
1 Project Engineer 1 9 Mini Bus 1
2 Document Controller 1 10 Wheel Excavator 1
3 Office Asst 0 11 Roller Compactor 1
4 Site Foreman 2 12 SHOWEL 0
5 Mason 6 13 3 ton pick up 1
6 Helper 9 14 Steel Cutting Machine 1
7 Carpenter 8 15 Steel Bending machine 1
8 BUS DRIVER 1 16 JCB 0
9 Steel Worker 8 17 2 ton roller compactor 1

10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Op 0

Total 37 Total 7
Total Manpower Total Equipments 7

HSE Issues:
F. HSE Issues:
1 orange mesh installed at ETS 1 locations Done
2 Safety barriers, safety cones and signage boards installed near to the road Done
3 Pipes at ETS A near fance barricaded with warning Taypes Done
4 Provided signages board near road area Done
5 Provided mesh along with the crush barriers and safety cones beside the r Done
6 pipes are covered with tarpolin Done
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh Done
8 Excavation at ETS-2 are barricaded with orange Mesh Done
9 Installed Crush Barriers with water beside the road side area Safety Signa Done
10 Barricades provided near road area (Near Plant Area) Done
AHAWI

Working Time: 7 am to 6:00pm

Other Details
Others Qty

Direct Manpower
Rigger 3

Pipe Fabricator 5
Multi Skill Helper 5
Electrican 1
Crane Operator 1
Tanker Driver 1

Total 16
C
Other Details
Others Qty

Shovel Operator
Crane Operator
Draughts man 1

BUS DRIVER 0
Site Surveyor 1
Total 2

Client Sign & Stamp

Other Details
Others Qty

Total 0

You might also like