Report Accompanying The Estimate For Improvements To Dandu - Mustipally Road From Km. 15/6 To 19/8 in Mahabubnagar District

The document is a report accompanying an estimate of 144 lakh for improvements to the Dandu-Mustipally road from km 15.6 to 19.8 in Mahabubnagar district. The road is an important district road connecting highways and providing access to villages and markets. The current road section has a non-bituminous surface making it inconvenient for traffic. The estimate includes provisions for embankments, granular sub-base, wet mix macadam, bituminous concrete surface, and a culvert to improve the traffic-worthiness of the road.

Uploaded by

Happy Hour
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
76 views1 page

Report Accompanying The Estimate For Improvements To Dandu - Mustipally Road From Km. 15/6 To 19/8 in Mahabubnagar District

The document is a report accompanying an estimate of 144 lakh for improvements to the Dandu-Mustipally road from km 15.6 to 19.8 in Mahabubnagar district. The road is an important district road connecting highways and providing access to villages and markets. The current road section has a non-bituminous surface making it inconvenient for traffic. The estimate includes provisions for embankments, granular sub-base, wet mix macadam, bituminous concrete surface, and a culvert to improve the traffic-worthiness of the road.

Uploaded by

Happy Hour
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 1

Report accompanying the estimate for Improvements to Dandu - Mustipally road

from Km. 15/6 to 19/8 in Mahabubnagar district.

Amount of Estimate: 144.00 Lakh

The Dandu - Mustipally road is an important an important major district road,


connecting state high way SH 18 such as Mahabubnagar – Raichur road and PJP Dam
road to Gadwal. This road leads to number of interior villages. It is an important road
useful for all categories of people and the road is useful for farmers to transfer agriculture
products to Makthal, Gadwal and Atmakur market yard.
The road from Km. 0/0 to 15/6 is already improved under RIDF and other
Schemes, and Km. 15/6 to 19/8 is non BT surface very inconvenient to the vehicular
traffic. Further the road passing in between wet fields on either sides, Hence the
provision of borrowed earth have been provided with a lead of minimum 8 Km.
Hence the estimate is prepared with the following provisions to make the road
traffic worthy condition.

1. Forming embankment with borrowed useful earth


2. Construction of Granular sub-base by providing HBG material confirming to
Grading - III in appropriate reaches and village portions 150 mm thick.
3. Providing Wet Mix macadam 225 mm thick
4. Providing 25mm thick MSS by hot mix.
5. Providing 1 No. s of CD works II vent of 800 mm dia HP culvert.
6. L.S. provision such as VAT, Q.C. Price escalation and unforeseen works etc.

The estimate is prepared based on the current SSR of 2008-09 with


MORT&H specifications.
An early sanction to the estimate is solicited.