0% found this document useful (0 votes)
2K views6 pages

CT Sizing Calculation For 132kV System: GHATAIL 132/33Kv, 2X80/120MVA NEW AIS Sub-Station

This document summarizes the calculation of current transformer sizing parameters for a 132kV substation project in Bangladesh. It includes the system details like voltage level, fault current, time constant, and relay requirements. Calculations are provided to verify that the selected CT knee point voltage and rated burdens can adequately meet the minimum requirements for connected relays and meters at each feeder bay. The conclusions indicate that the selected CT parameters are sufficient based on the design criteria and calculations outlined in the document.

Uploaded by

arafin
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
2K views6 pages

CT Sizing Calculation For 132kV System: GHATAIL 132/33Kv, 2X80/120MVA NEW AIS Sub-Station

This document summarizes the calculation of current transformer sizing parameters for a 132kV substation project in Bangladesh. It includes the system details like voltage level, fault current, time constant, and relay requirements. Calculations are provided to verify that the selected CT knee point voltage and rated burdens can adequately meet the minimum requirements for connected relays and meters at each feeder bay. The conclusions indicate that the selected CT parameters are sufficient based on the design criteria and calculations outlined in the document.

Uploaded by

arafin
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 6

CT Sizing Calculation for 132kV System: GHATAIL 132/33Kv,

2X80/120MVA NEW AIS Sub-Station

1. Overview:
The purpose of this document is to verify the sizing of the Current Transformer (CT) in terms of
knee point voltage and rated burden of relay and meter.

2. Notes for Calculation:


Design inputs such as

1) Instead of specific relays, the generic ANSI codes for relays are used with their
usual burdens as per the reference document of ABB.
2) Technical specification and drawing in contract document.
3) CT requirements and burden by related relays and meters

Design Criteria:

Knee point voltage: Apart from rated short time rating of the system, to arrive at the minimum
knee point voltage, value for time constant or X/R ratio and steady state through fault current
values need to be determined.

Considering the rated capacity of the bus bars of 132kV, the fault level considered is 40kA.

The time constant (τ) for 132kV system is calculated on the basis of the DC breaking capacity of
the breaker. The breaker is capable of breaking DC current of 40% of the symmetrical capacity
(40kA) of the breaker. The breaker breaking time is 60ms.

SL System Particulars Notation Value Unit


1 Nominal System Voltage V 132 kV
2 Nominal Frequency f 50 Hz
3 Rated Short Circuit Current of Station Iscc 40 kA
4 CB DC Current breaking capacity %DC 40 %
5 CB breaking time T 60 ms

1 | Page
Time Constant of the system is given by the following formula:

𝑇
𝜏 =
√2
𝑙𝑛( %𝐷𝐶 )
100
Where

T = Circuit Breaker Breaking time in ms = 60 ms

%DC = DC Current breaking capacity (%) = 40%

With given system data for 132kV we get


60
𝜏= =47.511ms
√2
𝑙𝑛( 40 )
100

𝑋
And the X/R ratio is given by, 𝑅
=2 × 𝜋 × ƒ × 𝜏

𝑋
𝑅
= 2 × 𝜋 × 50 × 47.511 × 10−3

𝑋
= 14.926
𝑅

Hence all CT selections are being verified for the above X/R ratio of 14.926.

Rated burden selected for CT must be more than the sum of the relay/metering burden connected
across CT.

3. Calculations:
Calculations performed for the CT parameters are enclosed in following sections.

4. Conclusion:
Calculation results show that selected parameters for CT are adequate to meet the minimum
requirement for the connected relays at each bay. Please refer to “Results Summary”

2 | Page
132 kV Line Feeder
1.1 CT dimensioning for Metering: Applicable Core: 1

General Project Data:

Customer: PGCB
Project: DESIGN,SUPPLY,INSTAKKATION,
TESTING AND COMMISSIONING OF 132/33KV
SUBSTATIONS ON TURNKEY BASIS (PACKAGE-2.1)
Station: GHATAIL 132/33KV NEW AIS SUBSTATION.

Feeder: RPCL-1/2(LINE BAY-01)

General System and Substation Data:

Nominal Voltage: 132KV

Nominal Frequency: 50HZ

Power System Time Constant: 47.511ms

Rated Short Circuit current of the station: 40KA

Data of Line CT according to IEC Norm:

<For CT Ratio 2000/1A>

Accuracy Class: 0.2

Rated Burden: 10 VA

Rated Primary Current Ipn: 2000 A

Rated Secondary Current Isn: 1A

Internal Burden RCT at 75oC: 10 Ω

Instrument Security Factor FS: 5

<For CT Ratio 1000/1A>

Accuracy Class: 0.2

Rated Burden: 5 VA

Rated Primary Current Ipn: 1000 A

Rated Secondary Current Isn: 1A


3 | Page
Internal Burden RCT at 75oC: 5Ω

Instrument Security Factor FS: 5

ENERGY METER DATA:

Manufacturer: CEWE

Type: Prometer 100

Rated relay current, Ir : 1A

Relay burden SR (Per phase): 0.7mVA

Permissive Overload for 1sec IPO : 50

Calculation of Cable Burden:

Distance Iwire 170 m


Cable cross section αwire 4.0 mm2
Special resistivity(Cu) ρwire .02171 Ωmm2/m at 750C
Effective wire length kwire 1

𝐼𝑤𝑖𝑟𝑒 𝑥 𝜌𝑤𝑖𝑟𝑒 𝑥 𝑘𝑤𝑖𝑟𝑒


Rwire=
𝛼𝑤𝑖𝑟𝑒

Calculated Cable Burden Rwire 0.922675 Ω


With 20% margin RI 1.10721 Ω

CT requirements for metering:

Requirement 1:

The current transformer for metering must have an effective instrument security factor FS’ that is
smaller than the value of the equations below

(𝑅𝑐𝑡 + 𝑅𝑁 )
𝐹𝑆 ′ = 𝐹𝑆 × 𝑆 ≤ 𝐼𝑝𝑜 (Requirement 1)
𝑅𝑐𝑡 +𝑅𝑙 + 2𝑅
𝐼𝑟

Requirement 2:

The ratio of actual burden to rated burden should be the value of equations below:
𝑆
(𝑅𝑐𝑡 +𝑅𝑙 + 2𝑅 )
𝐼𝑟 )
25% ≤ (𝑅𝑐𝑡 + 𝑅𝑁 )
≤ 100% (Requirement 2)
4 | Page
Where,

FS: Instrument Security Factor

RCT: Internal CT burden at 75oC [Ω]


𝑉𝐴
RN: Rated CT burden ( 𝐼2 )[Ω]
𝑛

Rl: Secondary wire burden [Ω]

SR: Rated instrument Burden[VA]

Ir: Rated Secondary Current of Relay [A]

Ipo: Rated instrument minimum permissive overload

<For CT ratio 2000/1>

FS: Instrument Security Factor = 5

RCT: Internal CT burden at 75oC [Ω] = 10 Ω

RN: Rated CT burden = 10 Ω

RL: Secondary wire burden = 1.10721 Ω

SR: Rated instrument burden = 0.0021 Ω

Ir: Rated Secondary Current of Relay [A] = 1A

Ipo: Rated instrument minimum permissive overload = 50

Requirement 1:

10 + 10
𝐹𝑆 ′ = 5 ×
10 + 1.107212 + 0.0021

𝐹𝑆 ′ = 9 ≤ 50

Which fulfills requirement 1.

10+1.1072+0.0021
Requirement 2: Ratio =
10+10

= 55.55%

Therefore, Ratio=55.55% and fulfills requirement 2

5 | Page
<For CT ratio 1000/1>

FS: Instrument Security Factor = 5

RCT: Internal CT burden at 75oC [Ω] = 5 Ω

RN: Rated CT burden = 5 Ω

RL: Secondary wire burden = 1.107212 Ω

SR: Rated instrument burden = 0.0021 Ω

Ir: Rated Secondary Current of Relay [A] = 1A

Ipo: Rated instrument minimum permissive overload = 50

Requirement 1:

5+5
𝐹𝑆 ′ = 5 ×
5 + 1.107212 + 0.0021

𝐹𝑆 ′ = 8.1842 ≤ 50

Which fulfills requirement 1.

5+1.10721+0.0021
Requirement 2: Ratio =
5+10

= 61.0931%

Therefore, Ratio=61.0931% and fulfills requirement 2

SO, CT IS CORRECTLY DIMENSIONED.

6 | Page

You might also like