0% found this document useful (0 votes)
198 views5 pages

1.2 - CT (Metering) - Core-2 - Line

The document discusses the sizing of current transformers (CTs) for metering on a 132 kV line feeder for a substation project in Bangladesh. It provides technical specifications of the line, substation, meters and CTs. It then calculates the cable burden and ensures the selected CTs with ratios of 2000/1A and 1000/1A meet two requirements - having an effective instrument security factor below the rated overload and having an actual to rated burden ratio between 25-100%. The CTs are found to meet both requirements and are considered correctly dimensioned for the metering purpose.

Uploaded by

arafin
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
198 views5 pages

1.2 - CT (Metering) - Core-2 - Line

The document discusses the sizing of current transformers (CTs) for metering on a 132 kV line feeder for a substation project in Bangladesh. It provides technical specifications of the line, substation, meters and CTs. It then calculates the cable burden and ensures the selected CTs with ratios of 2000/1A and 1000/1A meet two requirements - having an effective instrument security factor below the rated overload and having an actual to rated burden ratio between 25-100%. The CTs are found to meet both requirements and are considered correctly dimensioned for the metering purpose.

Uploaded by

arafin
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 5

132 kV Line Feeder

1.2 CT dimensioning for Metering: Applicable Core: 2

General Project Data:

Customer: PGCB
Project: DESIGN,SUPPLY,INSTALLATION,TESTING
AND COMMISSIONING OF 132/33KV
SUBSTATIONS ON TURNKEY BASIS
(PACKAGE-2.1)
Station: GHATAIL 132/33KV NEW AIS
SUBSTATION
Feeder: RPCL-1/2(LINE BAY-01)

General System and Substation Data:

Nominal Voltage: 132 kV

Nominal Frequency: 50 Hz

Power System Time Constant: 47.511 ms

Rated Short Circuit current of the station: 40 kA

Data of Line CT according to IEC Norm:

<For CT Ratio 2000/1A>

Accuracy Class: 0.2

Rated Burden: 15 VA

Rated Primary Current Ipn: 2000 A

Rated Secondary Current Isn: 1A

Internal Burden RCT at 75oC: 10 Ω

Instrument Security Factor FS: 5

<For CT Ratio 1000/1A>

Accuracy Class: 0.2

Rated Burden: 7.5 VA

Rated Primary Current Ipn: 1000 A


1 | Page
Rated Secondary Current Isn: 1A

Internal Burden RCT at 75oC: 5Ω

Instrument Security Factor FS: 5

DIGITAL METER IN BACKUP MIMIC DATA:

Manufacturer: ABB

Type: BCM 802

Rated relay current, Ir2 : 1A

Relay burden SR2 : 0.01VA

Permissive Overload for 1sec IPO : 50

ENERGY METER DATA:

Manufacturer: CEWE

Type: Prometer 100

Rated relay current, Ir3 : 1A

Relay burden SR3 (Per phase): 0.7mVA

Permissive Overload for 1sec IPO : 50

Calculation of Cable Burden:

Distance Iwire 170 m


Cable cross section αwire 4.0 mm2
Special resistivity(Cu) ρwire .02171 Ωmm2/m at 750C
Effective wire length kwire 1

𝐼𝑤𝑖𝑟𝑒 𝑥 𝜌𝑤𝑖𝑟𝑒 𝑥 𝑘𝑤𝑖𝑟𝑒


Rwire=
𝛼𝑤𝑖𝑟𝑒

Calculated Cable Burden Rwire 0.922675 Ω


With 20% margin RI 1.10721 Ω

2 | Page
CT requirements for metering:

Requirement 1:

The current transformer for metering must have an effective instrument security factor FS’ that is
smaller than the value of the equations below

(𝑅𝑐𝑡 + 𝑅𝑁 )
𝐹𝑆 ′ = 𝐹𝑆 × 𝑆 ≤ 𝐼𝑝𝑜 (Requirement 1)
𝑅𝑐𝑡 +𝑅𝑙 + 2𝑅
𝐼𝑟

Requirement 2:

The ratio of actual burden to rated burden should be the value of equations below:
𝑆
(𝑅𝑐𝑡 +𝑅𝑙 + 2𝑅 )
𝐼𝑟 )
25% ≤ (𝑅𝑐𝑡 + 𝑅𝑁 )
≤ 100% (Requirement 2)

Where,

FS: Instrument Security Factor

RCT: Internal CT burden at 75oC [Ω]


𝑉𝐴
RN: Rated CT burden ( 2 )[Ω]
𝐼𝑛

Rl: Secondary wire burden [Ω]

SR: Rated instrument Burden[VA]

Ir: Rated Secondary Current of Relay [A]

Ipo: Rated instrument minimum permissive overload

<For CT ratio 2000/1>

FS: Instrument Security Factor = 5

RCT: Internal CT burden at 75oC [Ω] = 10 Ω

RN: Rated CT burden = 15 Ω

RL: Secondary wire burden = 1.10721 Ω

SR: Rated instrument burden = 0.0121 Ω

Ir: Rated Secondary Current of Relay [A] = 1A

Ipo: Rated instrument minimum permissive overload = 50

3 | Page
Requirement 1:

10 + 15
𝐹𝑆 ′ = 5 ×
10 + 1.10721 + 0.0121

𝐹𝑆 ′ = 11.24 ≤ 50

Which fulfills requirement 1.

10+1.1072+0.0121
Requirement 2: Ratio =
10+15

= 44.48%

Therefore, Ratio=44.48% and fulfills requirement 2

<For CT ratio 1000/1>

FS: Instrument Security Factor = 5

RCT: Internal CT burden at 75oC [Ω] = 5 Ω

RN: Rated CT burden = 7.5 Ω

RL: Secondary wire burden = 1.10721 Ω

SR: Rated instrument burden = 0.0121 Ω

Ir: Rated Secondary Current of Relay [A] = 1A

Ipo: Rated instrument minimum permissive overload = 50

Requirement 1:

5 + 7.5
𝐹𝑆 ′ = 5 ×
5 + 1.10721 + 0.0121

𝐹𝑆 ′ = 10.2136 ≤ 50

Which fulfills requirement 1.

5+1.10721+0.0121
Requirement 2: Ratio =
5+7.5

= 48.95%

4 | Page
Therefore, Ratio=48.95 % and fulfills requirement 2

SO, CT IS CORRECTLY DIMENSIONED.

5 | Page

You might also like