Project: Maruti Suzuki Hospital – Sitapur
PSP PROJECTS LTD.
METHOD STATEMENT
OF CHINA MOSAIC
Corporate Office:
PSP House,
Opp. Celesta Courtyard,
Opp. Lane of Vikramnagar Colony,
ISCON-Ambli Road,
Ahmedabad – 380058.
Tel Nos.: +91 -079 – 2693 6200, 2693 6300, 2693 6400
Fax Nos.: +91–079 – 2693 6500
E Mail: coordination@pspprojects.com
Web: www.pspprojects.com
1|Page
Project: Maruti Suzuki Hospital – Sitapur
PSP PROJECTS LTD.
Project Name:- Maruti Hospital, Sitapur
Client:- Maruti Suzuki Foundation
PMC:- JLL India Ltd.
CONTENTS
SR. NO. TITLE
1 Introduction
2 Scope of Work
3 References
4 Work Programme
5 Material
6 Methodology
7 HSE
PSP JLL MSIL
Sign
Name
Date
1. Introduction:
2|Page
Project: Maruti Suzuki Hospital – Sitapur
PSP PROJECTS LTD.
This method statement describing the outline procedure to be followed for china mosaic
to be executed at Maruti Hospital, Sitapur.
2. Scope of Work:
China mosaic work on terrace.
3. Reference and Standard:
This document should be read in conjunction with technical specification and approved
drawing for execution of work at site.
4. Work Programme:
The China mosaic work shall be carried out in accordance as per proposal.
5. Material
7. :
6.
1. cement
2. Sand
3. Water
4. Glazed tiles
6. Methodology:
The roughened top coat of brickbat coba is cleaned & washed properly.
Cement mortar made from the cement & fine sand in proportion of 1:4 is spread
uniformly on the surface with a thickness of 200mm to 25mm uniformly.
This bed is checked for levels & slopes.
Design pattern, if any, marked over this bed with use of cotton line string.
Cement –Water mixed slurry is spread on the work area. Pieces of china mosaic are
then pressed and fitted in position. The joints between these two pieces should be
3mm to 5mm.
After laying of the china mosaic pieces, they are hammered with wooden mallet to
achieve a uniform surface. The surface will be cured for three days.
White cement past will be applied in gap between to tiles.
7. Health and Safety:
1. All the workers shall wear proper personal protective equipment(PPE).
2. All the workers & staff personals shall be trained well in works to be executed
especially at height & precautionary & corrective measures to be taken for the
3|Page
Project: Maruti Suzuki Hospital – Sitapur
PSP PROJECTS LTD.
same.
3. All the workers shall be trained and safety induction shall be imparted to them
8. before the commencement of work at site.
9.
10. 4. Daily tool box talk shall be carried out for mutual understanding of work.
11. 5. A competent site supervisor shall be present at all times during work.
6. A first aid kit shall be provided in site office.
4|Page