METHOD STATEMENT FOR
SUNKEN FILLING (AAC BROKEN
BLOCK & SCREED CONCRETE)
WORK
REV DATE DESCRIPTION PREPARED CHECKED APPROVED
BY BY BY
DEFINITION:
The method statement will describe the methodology of SUNKEN FILLING (AAC BROKEN
BLOCK & SCREED CONCRETE) work.
Metal works activity comprises of following steps
1. TOOLS AND ACCESSORIES
2. MATERIAL
3. METHODOLOGY
1. TOOLS AND MACHINERIES:
Masonry trowel
Aluminum straight edge
Spirit level
Line dori
Measurement box (1ft x 1ft x 1.25ft)
Level tube
Wheel barrow
Broom stick
Sponge
2. MATERIALS
OPC Cement
Sand
AAC Broken Block
20mm Aggregate
12mm Aggregate
3. METHODOLOGY:
1.AAC BROKEN BLOCK FILLING:
The surface to be water proofed should be prepare thoroughly by chipping all cement mortar
deposits / loose materials, dust etc. using a chisel, wire and coir brush & clean the area
thoroughly with water.
Open Slab area cracks if any visible to be clean and fill the joints with non- shrinkable grouting
material as per specified instruction at waterproofing manufacturer.
Mark the reference level at the sunken four corner area.
1
AAC Broken Blocks Filling Top Level Button Mark to be fixed at four corner area, slope level
also to be verify as per drawing specification.
Check the levels an thickness of the Sunken filling area.
Before starting the work to be get the clearance at client.
Broken AAC Block size to be followed 25mm to 50mm.
Mix proportion to be followed as sunken filling area 1:5:10 (one cement and five parts of M.sand
and Ten parts of AAC Broken Block) on Mixture machine or using Forma box for manual
mixing with MS sheet.
Moist the surfaces and cement slurry should be applied before sunken filling to reduce the water
loss due to absorption.
Top of the surface should be level by straight edges to control undulations.
Levelling top surface by tamping with wooden Rammer.
Brooming after drying of sunken AAC Broken Block Filling Area top surface.
2.SCREED CONCRETE:
Cleaning AAC Broken Block Filling top surface area thoroughly with water.
Screed top level button fixing at four corner area, slope level also to be verify as per drawing
specification.
Check the levels an thickness of the screed concrete.
Sequence of concreting has been planned and sufficient labour & Materials to be deployed.
Before starting the work to be get the clearance at client.
Moist the surfaces before concreting to Reduce the water loss due to absorption.
Mix proportion to be followed as sunken filling screed concrete area 1:2:4 (one cement and two
parts of M.sand and four parts of coarge aggregate) on Mixture machine or using Forma box for
manual mixing with MS sheet.
Levelling top surface by tamping with aluminum straight edge.
Brooming after drying of screed concrete top surface area.
Curing should be ensure 7days for OPC cement.