Constuction of 2 Storey Building in Islamabad                                                                                                 01-Sep-20 20:30
Activities Report
Activity ID         Activity Name                          Activity Status   Original Duration     Early Start   Early Finish   Longest Path
A1000               Start of Project                         Not Started            0d              28-Aug-20                       Yes
A1010               Contract Agreement                       Not Started            1d              28-Aug-20     29-Aug-20         Yes
A1020               Mobilization of temporary facilities     Not Started           14d              29-Aug-20     15-Sep-20         Yes
A1030               Initial Survey                           Not Started            1d              24-Sep-20     24-Sep-20         Yes
A1040               Site Clearance                           Not Started            5d              25-Sep-20     01-Oct-20         Yes
A1050               Final Survey                             Not Started            1d              01-Oct-20     02-Oct-20         Yes
A1060               Start of earthworks                      Not Started            0d              02-Oct-20                       Yes
A1070               Excavation layout                        Not Started            1d              02-Oct-20     03-Oct-20         Yes
A1080               Excavation of Foundation                 Not Started            3d              03-Oct-20     07-Oct-20         Yes
A1090               Termite Proofing                         Not Started            1d              07-Oct-20     08-Oct-20         Yes
A1100               Backfilling                              Not Started           10d              10-Dec-20     23-Dec-20         Yes
A1110               Finish of Earthwork                      Not Started            0d                            23-Dec-20         Yes
A1120               Start of Foundation                      Not Started            0d              08-Oct-20                       Yes
                    Structureworks
A1130               Layout of PCC                            Not Started            1d              08-Oct-20     09-Oct-20         Yes
A1140               PCC under footings                       Not Started            5d              09-Oct-20     15-Oct-20         Yes
A1150               Column Footings                          Not Started           20d              15-Oct-20     09-Nov-20         Yes
A1160               Wall Footings                            Not Started           15d              15-Oct-20     03-Nov-20         No
A1170               Columns upto plinth                      Not Started            5d              06-Nov-20     12-Nov-20         Yes
A1180               Plinth Beams                             Not Started           15d              12-Nov-20     01-Dec-20         Yes
A1190               External & Internal water proofing       Not Started            5d              01-Dec-20     07-Dec-20         Yes
A1200               Horizontal DPC                           Not Started            3d              07-Dec-20     10-Dec-20         Yes
A1210               Finish of foundation                     Not Started            0d                            10-Dec-20         Yes
                    structureworks
A1220               Walls                                    Not Started            5d              28-Aug-20     03-Sep-20         No
A1230               PCC Floor layout                         Not Started            5d              28-Aug-20     03-Sep-20         No
A1240               PCC Floor Pouring                        Not Started            5d              28-Aug-20     03-Sep-20         No
 © Oracle Corporation                                                                     Page 1 of 2
 Constuction of 2 Storey Building in Islamabad                                                                                       01-Sep-20 20:30
                                                        Activities Report
Activity ID         Activity Name                Activity Status   Original Duration     Early Start   Early Finish   Longest Path
A1250               Columns till first floor       Not Started            5d              28-Aug-20     03-Sep-20         No
A1260               Slab construction              Not Started            5d              28-Aug-20     03-Sep-20         No
Total                                                                    96d              28-Aug-20     23-Dec-20