Corporation Office Sump Tank

This document provides a planning schedule for two projects: a multilevel carparking at a corporation office and an overhead water tank. The carparking project involves 15 tasks from January 28th to March 25th including footing concrete, side walls, cover slabs, block work, sump tank plastering, and headroom plastering. The overhead water tank project involves 8 tasks from February 1st to March 8th including steel work, beams, concrete, columns, base slab, walls, cover slab, and plastering.

Uploaded by

ganeshkumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
97 views1 page

Corporation Office Sump Tank

This document provides a planning schedule for two projects: a multilevel carparking at a corporation office and an overhead water tank. The carparking project involves 15 tasks from January 28th to March 25th including footing concrete, side walls, cover slabs, block work, sump tank plastering, and headroom plastering. The overhead water tank project involves 8 tasks from February 1st to March 8th including steel work, beams, concrete, columns, base slab, walls, cover slab, and plastering.

Uploaded by

ganeshkumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

PLANNING SCHEDULE

PROJECT:MULTILEVEL CARPARKING AT CORPORATION OFFICE


Task Name Start Finish Duration
SUMP TANK AT CORPORATION OFFICE 28-Jan-20 25-Mar-20 57 day

1 Footing Concrete 40 cum 28-Jan-20 28-Jan-20 1 day


2 Side wall (Shoe) 29-Jan-20 29-Jan-20 1 day
3 Side wall steel & Shuttering Lift I 1-Feb-20 8-Feb-20 8 day
4 Side wall concrete Lift I 9-Feb-20 9-Feb-20 1 day

5 Side wall steel & Shuttering Lift II 10-Feb-20 15-Feb-20 6 day

6 Side wall concrete Lift II 16-Feb-20 16-Feb-20 1 day

7 Cover slab 17-Feb-20 21-Feb-20 5 day

8 Head room block work lift I 22-Feb-20 26-Feb-20 5 day

9 Sump tank plastering 28-Feb-20 3-Mar-20 5 day

10 Side filling 4-Mar-20 4-Mar-20 1 day

11 Lintel Sunshade 27-Feb-20 29-Feb-20 3 day


12 Remaining Blockwork 1-Mar-20 3-Mar-20 3 day
13 Headroom Steel & shuttering 4-Mar-20 8-Mar-20 5 day
14 Headroom slab concreting 9-Mar-20 9-Mar-20 1 day
15 Headroom Plastering 20-Mar-20 25-Mar-20 6 day
OVER HEAD WATER TANK 1-Feb-20 8-Mar-20 36 day

1 Steel work 1-Feb-20 5-Feb-20 5 day

2 Beam for tank 6-Feb-20 9-Feb-20 4 day

3 Concrete 10-Feb-20 10-Feb-20 1 day

4 Column 11-Feb-20 12-Feb-20 2 day

5 Base slab 16-Feb-20 21-Feb-20 6 day

6 wall 22-Feb-20 25-Feb-20 4 day

7 Cover slab 26-Feb-20 28-Feb-20 3 day


8 Plastering 4-Mar-20 8-Mar-20 5 day