PLANNING SCHEDULE
PROJECT:MULTILEVEL CARPARKING AT CORPORATION OFFICE
   Task Name                                     Start         Finish       Duration
   SUMP TANK AT CORPORATION OFFICE                 28-Jan-20    25-Mar-20    57 day
 1 Footing Concrete 40 cum                         28-Jan-20    28-Jan-20     1 day
 2 Side wall (Shoe)                                29-Jan-20    29-Jan-20     1 day
 3 Side wall steel & Shuttering Lift I             1-Feb-20     8-Feb-20      8 day
 4 Side wall concrete Lift I                       9-Feb-20     9-Feb-20      1 day
 5 Side wall steel & Shuttering Lift II           10-Feb-20    15-Feb-20      6 day
 6 Side wall concrete Lift II                     16-Feb-20    16-Feb-20      1 day
 7 Cover slab                                     17-Feb-20    21-Feb-20      5 day
 8 Head room block work lift I                    22-Feb-20    26-Feb-20      5 day
 9 Sump tank plastering                           28-Feb-20     3-Mar-20      5 day
10 Side filling                                    4-Mar-20     4-Mar-20      1 day
11 Lintel Sunshade                                27-Feb-20    29-Feb-20      3 day
12 Remaining Blockwork                             1-Mar-20     3-Mar-20      3 day
13 Headroom Steel & shuttering                     4-Mar-20     8-Mar-20      5 day
14 Headroom slab concreting                        9-Mar-20     9-Mar-20      1 day
15 Headroom Plastering                            20-Mar-20    25-Mar-20      6 day
   OVER HEAD WATER TANK                            1-Feb-20     8-Mar-20     36 day
 1 Steel work                                      1-Feb-20     5-Feb-20      5 day
 2 Beam for tank                                   6-Feb-20     9-Feb-20      4 day
 3 Concrete                                       10-Feb-20    10-Feb-20      1 day
 4 Column                                         11-Feb-20    12-Feb-20      2 day
 5 Base slab                                      16-Feb-20    21-Feb-20      6 day
 6 wall                                           22-Feb-20    25-Feb-20      4 day
 7 Cover slab                                     26-Feb-20    28-Feb-20      3 day
 8 Plastering                                      4-Mar-20     8-Mar-20      5 day