67% found this document useful (6 votes)
2K views60 pages

Hazop Study

This document provides procedures and preparation for a Hazard and Operability (HAZOP) study for a gas cogeneration plant project. It outlines the scope, definitions, project reference documents, responsibilities, and process for the HAZOP study. The study will systematically identify potential hazards and operability problems in the plant design to improve safety and operability.

Uploaded by

Mohan Babu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
67% found this document useful (6 votes)
2K views60 pages

Hazop Study

This document provides procedures and preparation for a Hazard and Operability (HAZOP) study for a gas cogeneration plant project. It outlines the scope, definitions, project reference documents, responsibilities, and process for the HAZOP study. The study will systematically identify potential hazards and operability problems in the plant design to improve safety and operability.

Uploaded by

Mohan Babu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 60

 

 
PROCEDURE AND PREPARATION FOR HAZOP STUDY 
STUDY 

PT PUPUK INDONESIA ENERGI

GRESIK GAS COGENERATION PLANT PROJECT

CONTRACT NO : 010/SP/DIR/XI/2015

PROJECT CODE : P-6001


JOB NO : 781502

DOC NO : GGCP-00-P0-ES-010-PP
GGCP-00-P0-ES-010-PP

PURPOSE : ISSUED FOR APPROVAL


CONTRACTOR :

PT PP (Persero) Tbk – DIVISI EPC

CONSULTANT :

PT Rekayasa Engineering

REV.
DATE DESCRIPTION PREPARED CHECKED APPROVED
NO.

3 08/11/2016 Approval  
Issued for Approval  ANG SAW GWN/FIA FP

2 20/10/2016 Approval  
Issued for Approval  ANG SAW GWN/FIA FP

1 01/10/2016 Approval  
Issued for Approval  ANG SAW GWN/FIA FP

0 30/08/2016 Review  
Issued for Review  ANG SAW GWN/FIA FP
 

  JOB NO : 781502 

PROCEDURE AND
DOCUMENT NO : GGCP-00-P0-ES-010-PP 
PREPARATION FOR HAZOP
STUDY DATE : 08/11/2016 

REV : 3 

REVISION CONTROL SHEET

REV. NO. DATE DESCRIPTION

0 30/08/2016 Review  
Issued for Review

1 01/10/2016 Issued for Approval


Approval  

2 20/10/2016 Issued for Approval


Approval  

3 08/11/2016 Issued for Approval


Approval  

DISTRIBUTION ORDER

EXTERNAL ISSUE PT PP (Pers


(Persero
ero)) Tbk - INTERNAL ISSUE

PT PUPUK INDONESIA ENERGI PROJECT MANAGER CHIEF ADMINISTRATION

CHIEF SHE
TRACTEBEL / CONNUSA ENGINEERIN
ENGINEERING
G MANAGER

CONSTRUCTION MANAGER

PROCUREMENT
PROCUREMENT MANAGER

PROJECT CONTROL MANAGER

SHE MANAGER

QC MANAGER

CHIEF ENGINEERING

CHIEF PROJECT CONTROL

Page 2 of 15
15  
 

  JOB NO : 781502 

PROCEDURE AND
DOCUMENT NO : GGCP-00-P0-ES-010-PP 
PREPARATION FOR HAZOP
STUDY DATE : 08/11/2016 

REV : 3 

TABLE OF CONTENT

1.  INTRODUCTION .............


............................
.............................
...........................
..........................
...........................
.............................
.............................
...........................
..........................4 
.............
1.1.  Scop
Scope
e ...........................
........................................
...........................
............................
...........................
...........................
............................
..........................
......................................4 
..........................
1.2.  Defini
Definition
tion .............
...........................
...........................
...........................
...........................
...........................
...........................
...........................
........................
..................................4 
........................
1.3.  Project Reference Document ...........
......................
.......................
.......................
......................
......................
......................
......................
........................ ......... 4 
......................
1.4.  Abbreviations...........
......................
.....................
.....................
.....................
....................
.....................
......................
.....................
.....................
......................
......................... ..... 4 
...................
2.  FRAMEWORK OF HAZOP STUDY............
STUDY..........................
............................
...........................
...........................
............................
..........................................5 
............................
2.1.  Objec
Objectives
tives ............................
.........................................
...........................
...........................
...........................
............................
...........................
.......................
...............................5 
.....................
2.2.  Scope of Study ..................................................................................................................................... 5  
2.3.  Resou
Resources
rces .............
..........................
..........................
............................
............................
..........................
...........................
............................
.........................
................................6 
.....................
2.4.  Study Team .....................
.......... .......................
......................
.....................
......................
.....................
......................
.......................
.....................
.......................
........................ ...... 6 
.................
2.5.  Methodology ......................................................................................................................................... 8 
2.6.  Report Content ..................................................................................................................................... 9 

 APPENDIX I HAZOP Gui


Guidew
dewor or ds & Devi ati on s .............
.........................
......................
......................
.......................
......................
......................
.......................
............ 10 
 APPENDIX II HAZOP Wor kf
kflo
lo w ..............
........................
.....................
......................
......................
......................
......................
.....................
........................
......................... .... 12 
...............
 APPENDIX III HAZOP Wor ks heet For mat ............
......................
......................
.......................
......................
......................
......................
...................... ............. 13 
........................
 APPENDIX IV HAZOP Nod e Li st .....................
.......... ......................
......................
......................
......................
......................
......................
.....................
........................ ...... 14 
....................
 APPENDIX V P&IDs Mark
Mark-Up
-Up ......................
........... ......................
.....................
.....................
......................
.....................
.....................
......................
.....................
..................... .... 15 
...............

Page 3 of 15
15  
 

  JOB NO : 781502 

PROCEDURE AND
DOCUMENT NO : GGCP-00-P0-ES-010-PP 
PREPARATION FOR HAZOP
STUDY DATE : 08/11/2016 

REV : 3 

1. INTRODUCTION

1.1. Scope
This document stipulates the procedure of the Hazard & Operability (HAZOP) Study in terms of

objective, scope, resources requirements and methodology for the Gresik Gas Cogeneration Plant
(GGCP) Project.

1.2.. Definition
1.2
The following words shall have the meaning indicated when used herein:
Owner : PT. PUPUK INDONESIA ENERGI
Consultant PMC : TRACTEBEL ENGINEERING S.A.& PT. CONNUSA ENERGINDO
Contractor : PT. PP (Persero) Tbk – DIVISI EPC
Engineering Consultant : PT. REKAYASA ENGINEERING
Vendor/Subcontractor
Vendor/Subco ntractor : The party that manufactures or supplies equipment and services to
perform the duties specified by the Owner or Contractor

1.3.. Project Re
1.3 Reference
ference Document
   Basic Engineering Design Data, GGCP-00-P0-ES-001-PP 4.  
GGCP-00-P0-ES-001-PP Rev 4.

  Process Design Basis, GGCP-00-P0-ES-002


GGCP-00-P0-ES-002-PP
-PP Rev 4.4.  
  EPC Bid Document
Document Gresik Ga
Gas
s Co
Cogeneration
generation Plant (GGCP)
(GGCP) Pro
Project
ject A
Addendum
ddendum 1.
  EPC Bid Document
Document Gresik Ga
Gas
s Co
Cogeneration
generation Plant (GGCP)
(GGCP) Pro
Project
ject A
Addendum
ddendum 2.
  EPC Bid Document
Document Gresik Ga
Gas
s Co
Cogeneration
generation Plant (GGCP)
(GGCP) Pro
Project
ject A
Addendum
ddendum 3.
  IFB Document
Document for Engineering, Procurement, Construction and commcommissioning
issioning of Gresik Gas
Cogeneration Plant (GGCP) Project.
  Heat and
and M
Mass
ass Balance
Balance from Ma
Macchi,
cchi, GGCP
GGCP-03-P0-BE-001-PP
-03-P0-BE-001-PP Rev 1 (1168-C-021).

1.4.. Abbreviations
1.4
The following abbreviations are used within this document:
 API American Petroleum Institute
BFW Boiler Feed Water  
EPC Engineering, Procurement, and Construction
ESD Emergency Shutdown.
GGCP Gresik Gas Cogeneration Plant
GPSA Gas Processors Suppliers Association
HRSG Heat Recovery Steam Generator
HAZOP Hazard Operability
HVAC Heating, Ventilations & Air Conditioning.
HMB Heat & Mass Balance.
IFB Instruction for Bidder
LP Low Pressure
MP Medium Pressure
MCC Motor Control Centre.
PKG Petrokimia Gresik
PSD Plant Shut Down
SOP Standard Operating Procedure
UBB Utilitas Batu Bara
USD Unit Shut Down

Page 4 of 15
15  
 

  JOB NO : 781502 

PROCEDURE AND
DOCUMENT NO : GGCP-00-P0-ES-010-PP 
PREPARATION FOR HAZOP
STUDY DATE : 08/11/2016 

REV : 3 

2. FRAMEWORK OF HAZOP STUDY

2.1. Objectives

The purpose of the HAZOP Study / Assessment is as follows:


1. Identify all probable hazards, wh
which
ich are inherently exist in the p
process
rocess in terms of physical
physical / chemical
characteristics of material and operating condition and /or operability problems;
2. Judge whether a an
n identified hazard ne
needs
eds to be mitigated by:
by:
a. Engineering control (design modification), or by
b. Administrative control (operation / maintenance
maintenance procedure)
3. Identify hazards, for wh
which
ich future follow-up studies a
are
re required.

It should be underlined that the HAZOP study is not a design review therefore the team should be
reminded to avoid spending too much time for “Design Solutions”. The following items shall be subject
to the HAZOP study:
1. Process line
Major process lines and related utility lines contained in the subject P&IDs.
2. Chemicals
 All Hazardous material such as flammable,
flammable, explosive and toxic.
3. Equipment
 All process equipment identified on the subject
subject P&IDs.
4. Instrument Controls
 All basic process control system shall be considered for the effect during hazard identification. In
addition to this, main interlock system may be considered on the subjected P&IDs basis.
5. Operating Conditions

HAZOP study shall investigate the potential hazard and problem which are likely to occur during typical
normal operating conditions. Consideration should also be taken for start-up, normal shutdown and
emergency shutdown as a deviation from the reference (normal condition).
2.2.. Scope of Study
2.2

The scope of study covers all P&IDs latest achieved NO OBJECTION status revision that has been
developed by the Contractor as part of the Design Drawing. Those include all facilities in the Gresik
Gas Cogeneration Plant (GGCP) Project. System or unit are classified as in Table 3 below, shall be
subjected to the HAZOP Study.
3 Table 1. Process Units (Section)

No. Title / Sections

1 P&ID Gas Turbine Generator

2 P&ID Package Boiler

3 P&ID HRSG

4 P&ID Natural Gas Feed System

5 P&ID Waste Water Treatment System

6 P&ID Water Treatment System

7 P&ID Fire Water System

9 P&ID Compressed Air System

11 P&ID Cooling Water & Distribution System


Page 5 of 15
15  
 

  JOB NO : 781502 

PROCEDURE AND
DOCUMENT NO : GGCP-00-P0-ES-010-PP 
PREPARATION FOR HAZOP
STUDY DATE : 08/11/2016 

REV : 3 

No. Title / Sections

12 P&ID Plant Water Supply & Distribution System

13 P&ID Steam distribution system

In order to proceed with HAZOP work effectively, subjected units (sections) as listed in Table 3 above
will be divided into study NODEs. The study nodes defined mainly represent specific process lines,
equipment or units operated under same operating condition or specific process intentions.

Table 2. Node Identification 3

No. Titl e / Sectio ns NOD


NODE
E

1 P&ID Gas Turbine Generator 1, 2, 3, 4, 5, 6, 7

2 P&ID Package Boiler 8,9,10,11,12,13,14,15,16

3 P&ID HRSG 17,18,19,20,21,22,23,24

4 P&ID Natural Gas Feed System 25


5 P&ID Waste Water Treatment System 26

6 P&ID Water Treatment System 27

7 P&ID Fire Water System 30

9 P&ID Compressed Air System 33

11 P&ID Cooling Water & Distribution System 28

12 P&ID Plant Water Supply & Distribution System 29

13 P&ID Steam distribution system 31

 A set of P&IDs mark-up is provided in Appendix


Appendix V.
2.3. Resources

In addition to the P&ID’s, the following documents (preferred latest revision) may be referred in the
HAZOP Study:

1. Basic Engineering Design Data


2. Process Flow Diagrams (PFD)
3. Equipments Data Sheet
4. Piping Material Specification and Datasheets
5. Safety and Fire Fighting Philosophy Document
6. Instrument Data Sheets
7. Alignment Sheet Drawing

2.4. Stud y Team

2.4.1.
2.4.1. Study Te
Team
am Compo siti on
HAZOP Review shall be carried out by OWNER, PMC, CONTRACTOR and Subcontractor which
define as the following members;
1. HAZOP Chairma
Chairman n (Subcon
(Subcontractor)
tractor)
Page 6 of 15
15  
 

  JOB NO : 781502 

PROCEDURE AND
DOCUMENT NO : GGCP-00-P0-ES-010-PP 
PREPARATION FOR HAZOP
STUDY DATE : 08/11/2016 

REV : 3 

2. HAZOP Secr
Secretary
etary (Subco
(Subcontractor)
ntractor)
3. Process Engineer (OWNER, PMC and CONTRACTOR)
4. Operating Represe
Representative
ntative (OWNER)
5. Other Discipline Engineer (OW
(OWNER,
NER, PMC and CONT
CONTRACTOR)
RACTOR)
6. OEM Engineers (GE, Macchi), whenever possible.
possible. 3
The core of the HAZOP Study team shall consist of a Chairman and Study Secretary. The process
engineers of CONTRACTOR project team and OEM Engineers (whenever possible) will attend the
Study Meeting and give explanation about process, instrumentation philosophy, operation and
maintenance for the facilities.

OWNER and PMC also will attend the HAZOP Meeting. CONTRACTOR will request the OWNER
and PMC should assign adequate personnel of engineers including OWNER’s operating personnel.

Other engineers, such as mechanical, electrical, instrument, piping, civil and HSE engineer of
CONTRACTOR team will attend as required (on call basis) by the
t he Chairman.

2.4.2.
2.4.2. Study Te
Team
am Responsi bilit ies
a) HAZOP Chairman
The following are principal responsibilities of the HAZOP Chairman throughout the HAZOP
Review:
1. Pre-HAZOP meeting w works:
orks:
-  Plan the key items of the HAZOP
3 -  Submit NODE identification for CONTRACTOR review and Approval prior to HAZOP study
commencement.
2. HAZOP Review mee meetings:
tings:
-  Lead the review meetings so as to identify exhaustively potential hazards and operational
concerns.
-  Settle discussion to a conclusion and ddefine
efine recommended HAZOP actions.
actions.
-  Control the progress of the HAZOP review meetings as sched
scheduled.
uled.
-  Be aware of the mental and p physical
hysical conditions of team membe
members
rs to maintain their interests
and energy levels, taking breaks appropriately.
-  Ensure the HAZOP Scribe to record the HAZOP findings and prepare the HAZOP action
sheets.

3. Post-HAZOP meeting works:


3 -  Review and approve HAZOP study rep
report
ort and submit to CONTRA
CONTRACTOR.
CTOR.
-  Receive and review any commen
comments
ts on HAZOP report and issue final report

b) HAZOP Secretary
HAZOP Secretary is the assistant of HAZOP Chairman and responsible for conducting
documentations as listed below under instruction of HAZOP Chairman:
1. Assist Chairman in preparing the discussion
discussion material
2. Record and filing all meeting resu
results
lts
3. Prepare minute ooff meeting and meeting report

c) Discipl ine Engineers, Ope


Operation
ration Representativ es and HS
HSE
E Representatives
Representatives
Discipline engineers including Project Engineers, Operation Representatives and HSE
Representative of OWNER, CONTRACTOR, PMC, and OEM Engineers (whenever possible)

are responsible
- Provide to conduct
technical info productive
information
rmation HAZOP review
and experiences meeting
for each through
discipline area the following roles:
areas.
s.

Page 7 of 15
15  
 

  JOB NO : 781502 

PROCEDURE AND
DOCUMENT NO : GGCP-00-P0-ES-010-PP 
PREPARATION FOR HAZOP
STUDY DATE : 08/11/2016 

REV : 3 

- Make every effort to identify, analyze and evaluate possib


possible
le hazard a
and
nd operational problems,
not as the designer of its discipline area but as a member of HAZOP team.

2.5. Methodology

2.5.1. Overview
HAZOP Study to be conducted primarily using the HAZOP deviation guideword technique. The
guidewords, in conjunction with the key process/ control parameters, prompt the HAZOP team to
brainstorm possible causes and potential consequences of deviation from design intention. For
example, the deviation “more pressure” would prompt the leader to ask the team “what could cause
more pressure in this section or line segment?” the ‘”possible cause” and potential consequences
scenarios are documented in the report worksheets. The “Existing system and procedure”
(safeguards) that reduce the risk associated with the specific cause/consequences
cause/consequences scenario are then
discussed and documented. For scenarios involving significant risk, “Recommendations” that the
team believes further reduce risk or improve the operability/controllability of the facility are also
documented.

2.5.2.. HAZOP Stud y Proced ur e


2.5.2

The guide word HAZOP method shall be applied for the review. The work flow of the review and the
list of applicable HAZOP guide word/process deviations are shown in Appendix I, respectively. The
specific steps of the HAZOP methodology used in this study are:
a) Choose study section or node
b) Apply a deviation (guideword+ parameter)
c) Brainstorm cause of deviation
d) Develop each ca cause
use to its global consequences
e) Identify existing safeguards
f) If warranted, ma make
ke recommenda
recommendation tion (s) to red
reduce
uce risk and / or improve the operability of the
facility

This process is repeated for each deviation and section/NODE until the entire process and control
system has been analyzed according to study flow diagram at Appendix II.
2.5.3. Assumption

Following
a. Singleassumptions
failure re sultsshould
results use,during
in hazard
hazard, conducting
as double the
jeopardy is HAZOP
believedstudy:
believed quite re
remote
mote case.
b. Equipment o orr machinery is designed, man manufactured
ufactured and properly inspected w with
ith no defect.
c. The facilities sha shallll be well maintained and operated in accordance with sound, internationa
internationally
lly
acceptable standards. This includes establishing and operating a high standard of housekeeping
throughout the site at all times. All loss prevention, safety and/or security equipment shall be
routinely tested/ recharged as recommended by the manufactures.
d. For duplicate trains /process unit, equipment or machinery is similar designed and
manufactured, therefore the study review shall be carried out only for one train. The study
review result, however, shall be applied for all the duplicated trains / process unit.
e. If all team membe
members rs agree, simplified h
hazardous
azardous review method such as “What IF” m method
ethod may
be used for utility system which is widely available in industrial applications. Team is requested
to discuss most effective hazardous review method for associated utility system prior to the
review
f. Operator are assumed to be competent and appropriately trained
g. Equipment/Instrumen
Equipment/Instrumentt are deemed suitable for design condition
h. Mechanical pro protection
tection devices (PV/PSV) are expe
expected
cted to function on demand

Page 8 of 15
15  
 

  JOB NO : 781502 

PROCEDURE AND
DOCUMENT NO : GGCP-00-P0-ES-010-PP 
PREPARATION FOR HAZOP
STUDY DATE : 08/11/2016 

REV : 3 

2.5.4.
2.5.4. Study Worksheets

Study worksheets were used during conducting HAZOP review shall consist of, but not limited to:
a) Node,

b) Design Condition/Parameter,
c) Deviation,
d) Cause,
e) Consequence,
f) Safeguard,
g) Recommendation,
h) Responsibility.

3 Team Member to evaluate effects/hazard caused by deviations, elaborate causes of deviations,


elaborate the evaluations of safeguards and criticality.

Review result shall be recorded by HAZOP secretary using spreadsheet 


spreadsheet  based HAZOP worksheet
displayed on projector screen to enable team members confirming and correcting recorded review.

The systematic approach of a HAZOP requires deviations (guide works+ parameters) be uniformly
applied to all sections under study. The work flow of HAZOP review in Appendix II shall be used for
each study section/node as much as applicable.
2.5.5. Recommendations

Team emphasized that some of existing safeguards were considered not sufficient; therefore team
could request additional safeguard or further study. HAZOP Secretary under direction of chairman
shall document the recommendation into HAZOP worksheets

Recommendations should be carefully


carefully worded to avoid ambiguity or or confusion. Particular effort
should be made to ensure recommendations are clear enough to be understood by project team
members who did not attend or may not have a clear recollection of the HAZOP workshop, or when
read out of context i.e. read separately to the hazard, initiating event, consequences and controls.

Finally, all recommendations should include a person or entity that will be responsible for
recommendation. 
implementing the recommendation. 

2.6. Report Content


The information gained from the HAZOP shall be translated into a report incorporating, but not limited
to:
  Executive Summary.
  Introduction, Purpose and Scope of Work.
  Brief description of the facilities.
  HAZOP Methodology in compliance with the procedure.
  Relevant input data including latest revision of d
drawings,
rawings, specification sheets, etc.
  Summary of recommendation result indicating actions register.
  HAZOP Worksheet.

Page 9 of 15
15  
 

  JOB NO : 781502 

PROCEDURE AND
DOCUMENT NO : GGCP-00-P0-ES-010-PP 
PREPARATION FOR HAZOP
STUDY DATE : 08/11/2016 

REV : 3 

 APPENDIX I
HAZOP
HAZO P Guidewords & Deviation s
Table I.1 Deviations for HAZOP Study
3
No Description
1 More Flow
2 Less Flow
3 No Flow
4 Reverse Flow
5 Misdirected Flow

6 More pressure
7 Less pressure
8 Vacuum
9 More Temperature

10 Less Temperature
11 More Level
12 Less Level
13 Empty Level
14 Impurities
15 Composition
16 Erosion / Corrosion
17 Commissioning
18 Maintenance
19 Instrumentation/Control
20 Start-Up
21 Shutdown
22 Testing/Sampling
23 Miscellaneous

Page 10
10 of
 of 15
15  
 

  JOB NO : 781502 

PROCEDURE AND
DOCUMENT NO : GGCP-00-P0-ES-010-PP 
PREPARATION FOR HAZOP
STUDY DATE : 08/11/2016 

REV : 3 

The above list of GUIDE WORD is neither mandatory nor comprehensive. It should be treated as a
menu from which relevant words can be selected to from a deviation in conjunction with a Process
Parameter.

Table I.2 Examples of Deviations


3

No. Guidewords Process Parameter Deviations

1 More/ Less/No Flow More/Less/No/


/Reverse/Misdirected
Reverse/Misdirected Flow

2 More/Less/No Pressure More/Less/Vacuum Pressure

3 More/Less Temperature More/Less Temperature

4 More/Less/No Level More/Less/Empty Level

Page 11
11 of
 of 15
15  
 

  JOB NO : 781502 

PROCEDURE AND
DOCUMENT NO : GGCP-00-P0-ES-010-PP 
PREPARATION FOR HAZOP
STUDY DATE : 08/11/2016 

REV : 3 

3  APPENDIX II
HAZOP Workflow

Page 12
12 of
 of 15
15  
 

 APPENDIX III
HAZOP
HAZOP Works heet Format

 APPENDIX
 APPENDIX IV
3 HAZOP Node List
No d es Des c r i p t i o n / No d e L i s t No d es Des c r i p t i o n / No d e L i s t
1 Lube Oil System 18 Drain, Blowdown & CBD LP Steam System
2 Hydraulic Oil System 19 BFW System (HRSG)
3 Cooling Water System (GTG Side) 20 Chemical Dosing System
4 Fuel Gas System (GTG Side) 21 Lube Oil System (HRSG)
5 Cooling Air System 22 Fuel Gas System (HRSG Side)
6 Washing Water System 23 Instrument Air (HRSG Side) And Sealing Air System
7 Fire Fighting System 24 Cooling Water System (HRSG Side)
8 Steam/Water System 25 Fuel Gas System

9 Steam Drum System 26 Waste Water Treatment System

10 BFW System (Boiler) 27 Water Treatment System

11 Drain & Blowdown System 28 Cooling Water System

12 Fuel Gas System (Boiler Side) 29 Water Distribution System

13 Chemical Dosing System 30 Fire Water System


14 Instrument Air (Boiler Side) & Plant Air System 31 Steam Distribution System

15 Cooling Water System (Boiler System) 32 Steam Water Analysis System

16 Lube Oil System (Boiler) 33 Instrument Air System

17 Steam / Water System

 APPENDIX V
3
P&IDs Mark-Up

PIPING SYMBOLS
PI

GRESIK GAS COGENERATION PLANT PROJECT

CONSTRUCTION & INVESTMENT

INSTRUMENT SYMBOLS

PI
EQUIPMENT SYMBOLS

GRESIK GAS COGENERATION PLANT PROJECT

CONSTRUCTION & INVESTMENT

 
PI

GRESIK GAS COGENERATION PLANT PROJECT

CONSTRUCTION & INVESTMENT

NODE 25

PI

GRESIK GAS COGENERATION PLANT PROJECT

NODE 33
CONSTRUCTION & INVESTMENT

 
NODE 25

PI

GRESIK GAS COGENERATION PLANT PROJECT

CONSTRUCTION & INVESTMENT

NODE 33

NODE 26

PI

GRESIK GAS COGENERATION PLANT PROJECT

CONSTRUCTION & INVESTMENT


 

NODE 33

NODE 26

PI

GRESIK GAS COGENERATION PLANT PROJECT

CONSTRUCTION & INVESTMENT

NODE 26
 

NODE 27

NODE 28

PI

NODE 33 M

GRESIK GAS COGENERATION PLANT PROJECT

CONSTRUCTION & INVESTMENT

NODE 26
NODE 33

NODE 27

PI
GRESIK GAS COGENERATION PLANT PROJECT

CONSTRUCTION & INVESTMENT

NODE 27

PI

GRESIK GAS COGENERATION PLANT PROJECT

CONSTRUCTION & INVESTMENT

NODE 27
PI

GRESIK GAS COGENERATION PLANT PROJECT

CONSTRUCTION & INVESTMENT

NODE 27

PI

GRESIK GAS COGENERATION PLANT PROJECT

CONSTRUCTION & INVESTMENT

NODE 27
PI

GRESIK GAS COGENERATION PLANT PROJECT

CONSTRUCTION & INVESTMENT

NODE 27

PI

GRESIK GAS COGENERATION PLANT PROJECT

CONSTRUCTION & INVESTMENT


 

NODE 27

PI

GRESIK GAS COGENERATION PLANT PROJECT

CONSTRUCTION & INVESTMENT

NODE 27

PI

GRESIK GAS COGENERATION PLANT PROJECT

CONSTRUCTION & INVESTMENT


 

NODE 27

PI

GRESIK GAS COGENERATION PLANT PROJECT

CONSTRUCTION & INVESTMENT

NODE 27

PI

GRESIK GAS COGENERATION PLANT PROJECT


CONSTRUCTION & INVESTMENT

PI

GRESIK GAS COGENERATION PLANT PROJECT

NODE 27

CONSTRUCTION & INVESTMENT

NODE 27

PI
GRESIK GAS COGENERATION PLANT PROJECT

CONSTRUCTION & INVESTMENT

NODE 26

NODE 30

NODE 27
PI

GRESIK GAS COGENERATION PLANT PROJECT

CONSTRUCTION & INVESTMENT

NODE 26

ISO 30
PI

GRESIK GAS COGENERATION PLANT PROJECT

CONSTRUCTION & INVESTMENT

  

NODE 33

PI

GRESIK GAS COGENERATION PLANT PROJECT

ISO 28

CONSTRUCTION & INVESTMENT

  

 
NODE 33

PI

GRESIK GAS COGENERATION PLANT PROJECT

CONSTRUCTION & INVESTMENT

  

 

NODE 33

PI

GRESIK GAS COGENERATION PLANT PROJECT

CONSTRUCTION & INVESTMENT

NODE 26
 

NODE 28

PI

GRESIK GAS COGENERATION PLANT PROJECT

NODE 26

CONSTRUCTION & INVESTMENT

NODE 33

NODE 28
PI

GRESIK GAS COGENERATION PLANT PROJECT

CONSTRUCTION & INVESTMENT


 

NODE 27

NODE 29

PI

GRESIK GAS COGENERATION PLANT PROJECT

NODE 26
CONSTRUCTION & INVESTMENT

PI

GRESIK GAS COGENERATION PLANT PROJECT

NODE 31
CONSTRUCTION & INVESTMENT

NODE 27

NODE 32

PI
NODE 28

GRESIK GAS COGENERATION PLANT PROJECT

CONSTRUCTION & INVESTMENT

NODE 28
PI

GRESIK GAS COGENERATION PLANT PROJECT

NODE 32

CONSTRUCTION & INVESTMENT

PI

GRESIK GAS COGENERATION PLANT PROJECT

CONSTRUCTION & INVESTMENT

NODE 33

 
NODE 27

PI

GRESIK GAS COGENERATION PLANT PROJECT

CONSTRUCTION & INVESTMENT

PI

GRESIK GAS COGENERATION PLANT PROJECT

CONSTRUCTION & INVESTMENT

 
NODE 25 PI

GRESIK GAS COGENERATION PLANT PROJECT

CONSTRUCTION & INVESTMENT

NODE 27

PI

GRESIK GAS COGENERATION PLANT PROJECT

CONSTRUCTION & INVESTMENT


 

NODE 26

PI

GRESIK GAS COGENERATION PLANT PROJECT

CONSTRUCTION & INVESTMENT

ISO 9

PI

GRESIK GAS COGENERATION PLANT PROJECT

NODE 28

CONSTRUCTION & INVESTMENT


 

PI

NODE 31 PETROKIMIA
GRESIK

NODE 8

NODE 10

NODE 11

DETAIL "A"

DRAIN

MOV MOV MVR MVF MVL MVH


O C B B B B
MOV MOV MVR MVF MVL MVH
O C

MOV

MCC

 A1

841mmx594mm

DETAIL "B"

DRAIN

NODE 8

NODE 9

NODE 11

NODE 13

 A1
841mmx594mm

 
 A1
841 mm x 594 mm

DETAIL "B"

DRAIN

NODE 10

NODE 11

NODE 13

 A1
841mmx594mm

L L L L L L L L L

         L          L

         L

         L

         L

         L

         L
         L

         L

         L

         L

         L

         L

NODE 8          L

         L
NODE 10
         L

NODE 15
         L

         L

         L

         L

         L

         L

         L

         L

         L

         L

         L

 A1
841 mm x 594 mm

NODE 10

NODE 15

 A1
841mmx594mm

 
NODE 12

 A1
841mmx594mm

NODE 13
 A1
841mmx594mm

NODE 11

DETAIL "B"

DRAIN

MOV MOV MVR MVF MVL MVH


O C B B B B

MOV MOV MVR MVF MVL MVH


O C

MOV

MCC

 A1
841mmx594mm

NODE 15

NODE 16
 

NODE 15

 A1
841mmx594mm

NODE 12

NODE 14
 A1
841mmx594mm

NODE 12

NODE 14

 A1
841mmx594mm

 
NODE 14

NODE 15

 A1
841mmx594mm

   m
   m
  0
  5
  1
  =
  L

   m
   m
  0
  5
  1
  =
  L
   m
   m
  0
  5
  1
  =
  L

   m
   m
  0
  5
  1
  =
  L

  m
  m
   0
   0
   2
  =
   L

  m
  m
   4
   9
   1   5
   A  x 
  m
  m
   1
   4
   8

  r
   i
   A
  g
  n
   i
   l
  a    )
  e   e
   S    d
   i
   )
  e    d
  n
  a    S
   G
   d
   i    )    S
   S   e    R
   d
   i    H
   G    S    (
   S
   R    G   m
   H    S   e
   t
   (    R   s
   H   y
  m   m    (    S
  e   e
   t   r   r
   t   s    i   e
  s   y    A    t
  y    S    t   a
   S   s   n    W
   l
   i   e
  a   g
  m  m    i
   O    G   n
  e    l   u
  r   e    l
   t
   b   e    t   s   o
  u   u   s   y   o
   L    F   n   S    C
   I

   1    2    3    4


   2    2    2    2
   E    E    E    E
   D    D    D    D
   O
   N    O
   N    O
   N    O
   N

  m
  e
   t
  s
  y
   S
  m
  a
  e
   t
   S
   P
  m
  e    L
   D   m
   t    B   e
  s    t
  y    C   s
   S   y
   &    S
   R   n   g
   E   w   n
   i
   T   o   s
   A    d   m   o
   W   w   e
   t    D
   /   o
   l   s    l
   B   y   a
   M  ,    S   c
   i
   A   n     m
   E    i    W
   T   a
  r   e
   F    h
   S    D    B    C

   7    8    9    0


   1    1    1    2
   E    E    E    E
   D    D    D    D
   O    O    O    O
   N    N    N    N

  m
  m
   4
   9
   1   5
   A  x 
  m
  m
   1
   4
   8

 
   7    8    9    0
   1    1    1    2
   E    E    E    E
   D
   D
   O    D
   O    D
   O    O
   N    N    N    N

 
   9
   1
   E
   D
   O
   N

   0    7
   2    1    8
   E    1
   D    E    E
   O    D    D
   O    O
   N    N    N

   L
   A
   C
   I
   P
   Y
   T
 /        
 /        

 /        
 /        

 /        
 /        

 /        
 /        

//

   3
   2
   E
   D
   O
   N

  m
  m
   4
   9
   1   5
   A  x 
  m
  m
   1
   4
   8

 
   3
   2
   E
   D
   O
   N

  m
  m
   4
   9
   1   5
   A  x 
  m
  m
   1
   4
   8

 
   9
   1
   E
   D
   O
   N

  m
  m
   4
   9
   5
   1   x
   A  
  m
  m
   1
   4
   8

 
    L

   L

   L

   L

   L

   L

   L

   L

   L

   L
    L     L     L     L     L     L     L     L     L     L     L     L     L     L     L     L     L     L     L     L     L     L     L     L     L     L

   7    4    1


   1    2    2
   E    E    E
   D    D    D
   O    O    O
   N    N    N
  m
  m
   4
   9
   1   5
   A  x 
  m
  m
   1
   4
   8

   4
   2
   E
   D
   O
   N

  m
  m
   4
   9
   1   5
   A  x 
  m
  m
   1
   4
   8

 
   2
   2
   E
   D
   O
   N

 
   2    3
   2    2
   E    E
   D    D
   O    O
   N    N
 
   0
   2
   E
   D
   O
   N

  m
  m
   4
   9
   1   5
   A  x 
  m
  m
   1
   4
   8

 
   8
   1
   E
   D
   O
   N

   2
   3
   E
   D
   O
   N
   1
   2
   E
   D
   O
   N

You might also like