JOB PROCEDURE FOR MATERIAL RECEIPT INSPECTION REPORT
                                    (PROCEDURE NO: 6724-700-50-MR-JP-001 )
    PROJECT                :     PROCUREMENT AND INSTALLATION OF ADDITIONAL BOIL OFF GAS (BOG) BOOSTER
                                 COMPRESSOR, RATNAGIRI
    CLIENT                 :     M/s RATNAGIRI GAS AND POWER PRIVATE LIMITED
    .                            (Promoters: M/S NTPC Limited & GAIL (INDIA) Limited)
    CONSULTANT             :     M/s ENGINEERS INDIA LIMITED
    CONTRACTOR         :         M/s SAVAIR ENERGY LIMITED 
                                                   LIMITED 
                               PREPARED BY        CHECKED BY          REVIEWED BY       APPROVED BY
        ORGANIZATION                 SEL                 SEL                 SEL              EIL
        SIGNATURE
        NAME                      Ganesh K.           Rakesh P.            Milind D.
        DATE
                                                                                                      Page 1 of  4 
 
    (PROCEDURE NUMBER : 6724-700-50-MR-JP-001
                        6724-700-50-MR-JP-001))
                        JOB PROCEDURE FOR MATERIAL RECEIPT INSPECTION REPORT
                                                  CONTENTS
        1.  PURPOSE
        2.  SCOPE
        3.  REFERENCE
        4.  PROCEDURE
        5.  INSPECTIONS & RECORDS
                                                                               Page 2 of  4 
 
                            JOB PROCEDURE FOR MATERIAL RECEIPT INSPECTION REPORT
    1.0    PURPOSE
           The purpose of this procedure is for keeping the records of incoming/ stacking and outgoing material and to
           ensure that proper record system is exercised at site.
    2.0    SCOPE
           The procedure covers supervision and method of record keeping for all incoming/ stacking and outgoing
           material
        
    3.0    R EFERENCE
             EFERENCE
            All related works will conform to
                                           to contract document
           •    Purchase order
           •    Quotation
           •    enquiries
    4.0    PROCEDURE
     A.    Incoming material
           •    Received material to checked as per invoice / PO and visual inspection also to be carried out
           •    Make the MIIR as per approved format
           •   Approved format to be filled with
                                            with Date , time, invoice number and material cond
                                                                                          condition
                                                                                              ition
           •    If any damage or short is found to be record and brought to the notice of respective vendor
           •    Prepare note for required insurance claimed, if any
           •    Make the entry pass / returnable pass of the material
           •    Report to be generated and copies to be mark to respective department
           •    Material entry to be record in respective record book
    B.     Stacking of material
                                                                                                                Page 3 of  4 
 
           •    Received material to be kept on individual place
           •    Material to be stored / stack on wooden sleeper/concrete sleeper such way, So that it can be issued /
                approach easily
           •    Material stack out side to be covered (Plastic, tarpaulin, GI sheets etc)
           •    Required color code to be put for identification
           •   Apply oil/grease for rust prevent
                                         prevent
           •    Pipes both end to be covered with caps so that end edge of the pipe to be protected
           •    Respective board to be displayed in from of stack material (like vendor name, JOB number, quantity,
                equipment number, PO invoice number etc)
    C.     ISSUE OF MATERIAL
           •    MIV / MRV to be raised by contractor / respective officer.
           •   Authorized signature to be obtained.
           •    Give MIV / MRV to store.
           •    Get material issued by store & lift the material from store with required trailer, truck etc.
           •    Make out gate pass from the store.
           •    Quantity to be noted in MIV / MRV with regards to any indented quantity / actual quantity done for records
                and payment.
    5.0 Inspection and Record : Material Receipt Inspection Report (
                                                            Report (6724-700-50-43-IR-001)
                                                                    6724-700-50-43-IR-001)
                                                                                                                Page 4 of  4 
 
                                                          MATERIAL RECEIPT INSPECTION REPORT (MRIR)
        PROJECT : PROCUREMENT
                  PROCUREMENT AND INSTALLATION
                                  INSTALLATION OF ADDITIONAL
                                                  ADDITIONAL BOIL OFF GAS (BOG) BOOSTER COMPRESSOR , R
                                                                                                     RATNAGIRI
                                                                                                      ATNAGIRI
        CLIENT : M/s RGPPL, RATNAGIRI                                         FORMAT NO :SEL/QAD/
                                                                                        :SEL/QAD/001
                                                                                                  001       REV.NO. - 0
        PMC :M/s EIL                                                          REPORT NO :
        CHALLAN / INVOICE NO :                                                DATE :
                                                                           Heat No. / Lot
        Sr.No.    Material Description             Size         Qty                         Test Certificate No     Vendor / Make   Remark
                                                                           No./ ID No.
    REMARK : SEL/TPI Inspection Release Note No.
                                              SAVAIR ENERGY LIMITED                                                CLIENT/TPI
         NAME
          SIGN
          DATE
                                             JOB PROCEDURE FOR INTERNAL SITE AUDIT
                                                      (PROCEDURE NO: 6724-700-50-IA-JP-001 )
            PROJECT                      :      PROCUREMENT AND INSTALLATION OF ADDITIONAL BOIL OFF GAS (BOG) BOOSTER
                                                COMPRESSOR, RATNAGIRI
            CLIENT                       :       M/s RATNAGIRI GAS AND POWER PRIVATE LIMITED
    .                        (Promoters: M/S NTPC Limited & GAIL (INDIA) Limited)
    CONSULTANT         :     M/s ENGINEERS INDIA LIMITED
    CONTRACTOR         :     M/s SAVAIR ENERGY LIMITED
                           PREPARED BY        CHECKED BY          REVIEWED BY       APPROVED BY
        ORGANIZATION             SEL                 SEL                 SEL              EIL
        SIGNATURE
        NAME                  Ganesh K.           Rakesh P.            Milind D.
        DATE
                                                                                                  Page 1 of  4 
    (PROCEDURE NUMBER : 6724-700-50-IA-JP-001 )
                                 JOB PROCEDURE FOR INTERNAL SITE AUDIT
                                                   CONTENTS
        1.  PURPOSE
        2.  SCOPE
          3.  REFERENCE
          4.  PROCEDURE
          5.  INSPECTIONS & RECORDS
                                                                                   Page 2 of  4 
                                           JOB PROCEDURE FOR INTERNAL SITE AUDIT
    1.       Purpose:
             •       Complete the project within the time frame.
             •       Within the set quality norms.
             •       Without any unwanted incidents.
             •       Quality is maintained throughout the entire project
    2.       Scope:
          This procedure covers the system of Quality / Documentation systems at site & their effective application and
          follow ups.
    3.    Reference:
             All Approved job procedure.
          •
             Applicable standards.
          •
           
          •       Codes and Specification.
    4.    Purpose:
           
          •       Complete the project within the time frame.
          •       Within the set quality norms.
          •       Without any unwanted incidents.
          •       Quality is maintained throughout the entire project
    5.    Procedure:
          •       Internal audit shall be conducted at an interval of three months
          •       Internal audit shall be conducted by a committee consisting of Audit Head and all
          •       members of the discipline, i.e. (Civil, Mechanical, Electrical, etc)
          •      Visiting site and verifying the record’s
                                                 record’s generated at site for Quali
                                                                                Quality
                                                                                     ty and other systems are as per
                                                                                                                 per procedure
                  or not for all related site activities or discipline.
                                                                                                                   Page 3 of  4 
          •       In case of any discrepancy proper corrective measures to be taken immediately.
          •       If anything found incorrect or beyond control then NCR (NON CONFIRMATION REPORT) to be raised.
          •      After completion of audit, all departments
                                                departments related audit reports shal
                                                                                  shalll be made & send to the respective
                  departments for the corrective action and information.
          •      All NCR raised in the internal audits shall be resolved
                                                                resolved and necessary documents / re
                                                                                                   reports
                                                                                                     ports generated which
                  is mandatory.
          •       Finally the internal reports copies to be send to respective department and EIL / OWNER for their review /
                  information.
    6.    Responsibilities and authorities:
              •     A audit plan and procedure to be prepared and
                                                              and submitted to owner / EIL for a
                                                                                               approval
                                                                                                pproval ,while preparing
                     audit plans we have to ensure that the frequency of audit does not exceed three months for a particular
                     facility.
              •      Functions and interrelations within the organization,
                                                             o rganization, including responsibilities,
                    Authorities are defined and communicated through
                                                             through the organization chart provided.
              •     All department heads should see and adhere to the
                                                                  the audit panel’s report to ensure
                                                                                              ensure that all major NCR are
                     closed.
        7.    Documentation
              Documentation:
              Internal Audit report Format.
                                                                                                                    Page 4 of  4 
                                     E.O.T. CRANE ERECTION PROCEDURE
                                         (PROCEDURE NO: 6724-700-50-45B-JP-001 )
        PROJECT                  :     PROCUREMENT AND INSTALLATION OF ADDITIONAL BOIL OFF GAS (BOG) BOOSTER
                                       COMPRESSOR, RATNAGIRI
        CLIENT                   :     M/s RATNAGIRI GAS AND POWER PRIVATE LIMITED
         .                                (Promoters: M/S NTPC Limited & GAIL (INDIA) Limited)
         CONSULTANT                :      M/s ENGINEERS INDIA LIMITED
        CONTRACTOR             :          M/s SAVAIR ENERGY LIMITED 
                                       PREPARED BY         CHECKED BY          REVIEWED BY       APPROVED BY
             ORGANIZATION                     SEL                 SEL                 SEL               EIL
             SIGNATURE
             NAME                          Ganesh K.           Rakesh P.            Milind D.
             DATE
                                                                                                              Page 1 of  3 
        (PROCEDURE NUMBER: 6724-700-50-45B-JP-001 )
                                                  E.O.T. CRANE ERECTION PROCEDURE
        1.     SCOPE
               This procedure covers the work method for EOT Crane erection and testing in idle and loaded condition.
        2.     METHODS
                 •      Pre erection activities
                 •      Lifting tackles
                 
                •     During erection
                 
                •     Post erection activities.
                 
                •     Inspection & test documentation.
        3.   ERECTION OF EOT CRANE:
                    PRE - ERECTION ACTIVITIES:
                 
                •     Collect the executive scheme of foundation plan from civil department.
                 
                •     Top level to be chipped / roughed & cleaned
                 
                •     Level plate fixing as per top of grouting
                   Availability of anchor bolt as per site
                •                                     site / spec / vendor
                   Availability of required capacity
                •                           capacity of crane.
                 
                •     Requirement of supporting crane.
                 
                •
                      Area of erection checked &. Visibility
                                                  Visibility of space established.
                   Availability of wooden sleepers for crane support
                •
                 
                •     Check tools & tackles of crane also verify the relevant TC to prove its Efficiency. (Lifting beams,
                      slings, d - shackles, wire rope, etc.)
                 
                •     Safety of erection area
                 
                •     Equipment, MTC, TC, inspected documents to be checked.
                                                                                                                    Page 2 of  3 
                 
                •     Equipments, machinery to check for free rotation of shafts.
                 
                •     Center line to be marked on foundation beds, with some reference points.
                    DURING INSPECTION:
                 
                •     Whether the crane has reached the demarcated area and the area has been barricaded.
                   After laying the rafts & positioning
                •                           positioning the crane visually to check for pr
                                                                                        proper
                                                                                          oper leveling of crane.
                 
                •     The foundation bed after laying the position of m/c, level to be checked by theodolite.
                 
                •     Proper packing & shims to be inserted to attain the proper level.
                 
                •     Check proper alignment to be done after erection with its documentation
              •       Once the m /c, equipment is erected then locks nuts to be tightened &then the crane siling to be
                      loosened.
              •       Once the m /c, equipment is erected and the foundation bolt tightened, immediately the grouting has
                      to be done.
                  POST ERECTION ACTIVITIES:
              •       First of all to see that the grouting cement has cured properly,
              •      Auxiliary connection to be mounted on equipment / instruments,
                                                                       instruments, as per drawing
              •       Then final bolting & tightening is done, chemical cleaning is done for equipment & connected pipeline
                      is boxed up & tightened. Then all carried out for (motor, compressors, etc.) and the shaft freeness is
                      checked, just by rotating the shaft.
              •       Then alignment is subjected to check by EIL / GAIL, and inspection report is generated & preserved.
              •      All the aligned shaft & motors has to be in the same
                                                                     same plane & alignment.
                  INSPECTION & TEST DOCUMENTS:
              •       Periodical inspection shall be carried out and consultants to be consulted.
              •       Final alignment report to be prepared.
              •      All fit up; weld visual, erection, etc record
                                                            record to be submitted.
              •       Handing over report to be submitted.
                                                su bmitted. 
                                                                                                                 Page 3 of  3 
                              ROTARY EQUIPMENT ERECTION PROCEDURE
                                       (PROCEDURE NO: 6724-700-50-45A-JP-001 )
        PROJECT               :      PROCUREMENT AND INSTALLATION OF ADDITIONAL BOIL OFF GAS (BOG) BOOSTER
                                     COMPRESSOR, RATNAGIRI
        CLIENT                     :      M/s RATNAGIRI GAS AND POWER PRIVATE LIMITED
        .                                 (Promoters: M/S NTPC Limited & GAIL (INDIA) Limited)
        CONSULTANT                 :      M/s ENGINEERS INDIA LIMITED
    CONTRACTOR                 :          M/s SAVAIR ENERGY LIMITED 
                                                            LIMITED 
                                        PREPARED BY        CHECKED BY          REVIEWED BY       APPROVED BY
            ORGANIZATION                        SEL               SEL                 SEL              EIL
            SIGNATURE
            NAME                           Ganesh K.           Rakesh P.            Milind D.
            DATE
                                                                                                             Page 1 of  3 
    (PROCEDURE NUMBER : 6724-700-50-45A-JP-001  )
                                             ROTARY EQUIPMENT ERECTION PROCEDURE
    1.0       SCOPE :
              This procedure covers the work method for rotary equipments erection and testing in idle and loaded
              condition.
    3.0       METHODS :
              •      Pre erection activities.
              •      Lifting tackles.
              •    During erection.
              •    Post erection activities.
              •    Inspection & test documentation.
    4.0                                          EQUIPMENTS:  
              ERECTION OF ROTATING INSTRUMENTS / EQUIPMENTS: 
           (A) PRE – ERECTION ACTIVITIES :
              •    Collect the executive scheme of foundation
                                                   foun dation plan from civil department.
              •    Top level to be chipped / roughed & cleaned.
              •    Level plate fixing as per top of grouting.
              •     Availability of anchor bolt as per site / spec / vendor.
              •     Availability of required capacity of crane.
              •    Requirement of supporting crane.
              •     Area of erection checked & visibility of space established.
              •     Availability of wooden sleepers for crane
                                                        crane support.
              •    Check tools & tackles of crane also verify
                                                       verify the relevant TC to prove its efficiency.
                                                                                           efficiency. (Lifting    beams,
                   shillings, d – shackles, wire rope, etc.)
              •    Safety of erection area.
              •    Equipment, vessels, instruments, MTC, TC, inspected documents to be checked.
                                                                                                                    Page 2 of  3 
              •    Equipments, machinery to check for free rotation of shafts.
              •    Center line to be marked on foundation beds, with some reference points.
           (B) DURING INSPECTION :
              •    Whether the crane has reached the demarcated area and the area has been barricaded.
              •   After laying the rafts & positioning the crane visually to check for proper leveling of crane.
              •    The foundation bed after laying the frame, the position of m/c, instruments, vessels level to be checked
                   by theodolite.
              •    Proper packing & shims to be inserted to attain the proper level.
                •       Once the vessels, m /c, equipment is erected then locks nuts to be tightened & then the crane sling to
                        be loosened.
                •       Once the vessel, m /c, equipment is erected and the foundation bolt tightened, immediately the grouting
                        has to be done.
          (C)           POST ERECTION ACTIVITIES :
                •       First of all to see that the grouting cement has cured properly ,auxiliary connection to be mounted on
                        equipment / instruments ,as per drawing
                •       Then final bolting & tightening is done, chemical cleaning is done for equipment & connected pipeline is
                        boxed up & tightened .Then all carried out for (motor, compressors, etc.) and the shaft freeness is
                        checked, just by rotating the shaft.
                •       Then alignment is subjected to check by EIL / GAILL, and inspection report is generated & preserved.
                •      All the aligned shaft & motors has to be in the same plane
                                                                            plane & alignment.
          (F)           INSPECTION & TEST DOCUMENTS:
                •       Periodical inspection shall be carried out and consultants to be consulted.
                •       Final alignment report to be prepared.
                •       All fit up, weld
                                    weld visual, erection, etc record to be submitted.
                •       Handing over report to be submitted.
                                                                                                                      Page 3 of  3 
                                      STATIC EQUIPMENT ERECTION PROCEDURE
                                             (PROCEDURE NO: 6724-700-50-46-JP-001 )
        PROJECT                   :       PROCUREMENT AND INSTALLATION OF ADDITIONAL BOIL OFF GAS (BOG) BOOSTER
                                          COMPRESSOR, RATNAGIRI
        CLIENT                      :     M/s RATNAGIRI GAS AND POWER PRIVATE LIMITED
        .                                 (Promoters: M/S NTPC Limited & GAIL (INDIA) Limited)
        CONSULTANT                  :     M/s ENGINEERS INDIA LIMITED
    CONTRACTOR                  :         M/s SAVAIR ENERGY LIMITED 
                                                            LIMITED 
                                        PREPARED BY        CHECKED BY          REVIEWED BY           APPROVED BY
            ORGANIZATION                      SEL                 SEL                 SEL                    EIL
            SIGNATURE
            NAME                           Ganesh K.           Rakesh P.            Milind D.
            DATE
                                                                                                                   Page 1 of  3 
    (PROCEDURE NUMBER : 6724-700-50-46-JP-001  )
                                             STATIC EQUIPMENT ERECTION PROCEDURE
    1.  SCOPE:
            This procedure covers method for the erection Equipment like static equipment (Vessel, EOT) at RGPPL,
            Ratnagiri plant. 
                      plant. 
    2.  PURPOSE:
            The purpose of this job procedure is to provide guide lines and methodology to carry out erection of all the static
         equipments.  
         equipments.
    3.  REFERENCE:
         AFC / Equipments drg. / Foundation detail.
         EIL Spec:
             Spec:
    4.  METHOD:
         •    The foundation lay out shall be checked with respect to AFC drawings. Besides no. of pockets size, verticality
              of pockets, diameter and length of foundation bolts, positioning and placement of foundation bolts,
              correctness of center distance of foundation bolts and projection of foundation bolts shall be verified.
         •    Before erection the foundation bolt shall be prepared properly by roughening the foundation top and pocket
              intervals by chipping. Also the pockets shall be cleaned properly.
         •    Level plates to be fixed on foundation considering the depth of grouting & shall be fixed with cement
              mortar.
         •    Equipments shall be carefully erected on foundation with the help of suitable lifting equipments. Equipments
              shall be lifted by slings / ‘D’ shackles etc. only at lifting points of equipment provided for this purpose in the
              equipment.
         •   After alignment checking and acceptance of equipment
                                                        equipment alignment only, pocket grouting and ffinal
                                                                                                        inal grouting
              shall be done. Required curing for grouting shall be carried out.
         •   All equipments shall be grouted with approved
                                                  approved non shrink grouting material.
         •    The thickness of grout shall be as per AFC drawing or vendor specification or instructions.
                                                                                                                     Page 2 of  3 
         •   At the end of this grouting period anchor bolts to
                                                             to be tightened uniformly. Alignment of equipment shall be
              rechecked and if found correct, the voids left by the removal of plates (if removed) must be filled up with a
              similar mixture of grout. In case after checking, serious misalignment is indicated, the grout shall be
              removed completely and fresh grouting is done after making appropriate correction of alignment.
        5.0 DOCUMENTATION:
              Inspection reports.
              NOTE: - In case of any conflict between the requirement of this procedure & EIL specification the later shall
              govern.
Page 3 of  3