Prolongation Cost Revised

The document details expenses for a BPCL project from August 2019 to June 2020 totaling over ₹20 crores. It includes expenses for plant and machinery, staff salaries, transportation costs, rent, and overheads calculated using the Eichleay formula. Head office overheads for the extended project period until June 2020 are estimated at ₹86 lakhs.

Uploaded by

Svh Kamesh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
217 views2 pages

Prolongation Cost Revised

The document details expenses for a BPCL project from August 2019 to June 2020 totaling over ₹20 crores. It includes expenses for plant and machinery, staff salaries, transportation costs, rent, and overheads calculated using the Eichleay formula. Head office overheads for the extended project period until June 2020 are estimated at ₹86 lakhs.

Uploaded by

Svh Kamesh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Annexure-A

OJECT : BPCL Project

Total Expense
Sl. No. Description Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 during extended
stay (From Sep
2018 till June 2020 )

1 Plant & Machinery 136,978.00 1,289,502.28 608,472.72 271,718.48 111,749.75 186,840.00 854,897.00 320,701.54 - 751,500.00 223,000.00 4,755,360
2 Depreciation -
TOTAL T&P COST (A) : 608,472.72 271,718.48 111,749.75 186,840.00 854,897.00 320,701.54 - 751,500.00 223,000.00 4,755,360
1 Staff Salaries & Allowances 884,406.00 937,621.00 659,146.00 761,503.00 724,211.00 738,500.00 639,317.00 1,110,722.00 834,734.00 513,630.00 843,970.00 8,647,760
2 Business Development Expns, electricity & water 6,620.00 87,920.00 71,280.00 16,380.00 466,267.00 263,760.00 535,774.00 - - 5,000.00 3,030.00 1,456,031
3 Freight & Transportation 140,500.00 62,640.00 - 2,790.00 17,140.00 - 123,999.00 91,201.50 - 60,000.00 38,900.00 537,171
4 General Expenses(includes security expense) - - - - - - - - - - - -
5 Motor Vehicle Expenses (Petrol + Hire Charges) 107,881.00 107,069.00 109,327.75 115,893.50 113,666.00 107,661.00 109,665.00 117,544.00 - 269,990.00 159,000.00 1,317,697
6 Postage & Telephone Expenses - 580.00 - - 973.00 - - 85.00 - - - 1,638
7 Printing & Stationery - 28,105.00 - 2,050.00 6,000.00 - - 8,570.00 - - 4,260.00 48,985
8 Professional & Legal Expenses - - - 18,000.00 - - - - - - - 18,000
9 Rent ( Site Accomodation) 50,891.00 50,893.00 57,553.00 42,222.00 42,220.00 42,222.00 42,222.00 - - 63,333.00 21,111.00 412,667
10 Repair & Maintenance - 31,972.00 - 8,400.00 17,250.00 - - 2,764.00 - - 2,200.00 62,586
11 Travelling Expenses 16,076.72 6,023.74 1,000.00 28,672.00 36,479.00 16,417.00 - 19,241.50 - - 3,500.00 127,410
12 Miscellaneous - - - - - - - - - - - -
TOTAL SITE PROJECT MANAGEMENT (B) : 1,206,374.72 1,312,823.74 898,306.75 995,910.50 1,424,206.00 1,168,560.00 1,450,977.00 1,350,128.00 834,734.00 911,953.00 1,075,971.00 12,629,945
C. ADD-ONS -
1 Insurance - 121,001.04 - - 107,647.69 - - 109,566.00 - 49,161.00 26,815.00 414,191
2 Finance / Interest - 11,374.85 - - - - - - 27,986.00 76,433.00 1,931.00 117,725
3 Bank Guarantee Charges - 1,750.00 3,515.51 - 4,422.08 1,050.00 - 1,627.90 7,040.76 26,111.00 2,413.00 47,930
TOTAL ADD-ONS (C) : 3,515.51 - 112,069.77 1,050.00 - 111,193.90 35,026.76 151,705.00 31,159.00 579,846
Head Office Overheads Costs during Extended Period as per Eichleay Formula till June 2020
S.No. Description UOM Value (INR Lakhs)
1 Contractual Commencement Date Date 10-Aug-18
2 Original Completion Date Date 9-Aug-19
3 Original Days of Contract Performance (a1) Days 365

4 Calculation as on Date 30-Jun-20

5 Actual Period of Completion till June 2020 Days 690

5 Prolongation Period till June 2020 (a2) Days 325


Calculation of Project Allocable Overhead

1 Total Company Billings for Original Contract Period (b1) Rs. Lakhs 16,774

Total home office overhead incurred during Original


2 Contract Period (b2) (Considered Corporate overheads Rs. Lakhs 1,459
provided)
Total Contract Billing for the Actual Period till 30.06.2020
3 (b3) Rs. Lakhs 1,143

Contract Billings for the Original Contract Period (till Aug


4 2019 ) (b4) Rs. Lakhs 690

Contract Billings During Delay Period (Sep 2019 till june


5 2020) (b5) Rs. Lakhs 452
Project Allocable Overhead as on 30.06.2020 (PAO) =
(b2)/(b1+b5)*(b3) Rs. Lakhs 96.78
Daily Allocable Overhead (DAO) =(PAO)/(a1) Rs. Lakhs 0.27
Total Head Office Overhead for prolonged period till
30.06.2020= (DAO)*(a2) Rs. Lakhs 86