PROJECT
BCA TOP CHECKLIST
AUTHORITIES ITEMS ACTION REMARKS
BCA 1. BCA BP obtained. QP(Archi)
- Minor deviation (not more than 20% deviation in non-
structural work) : Submit as Record Plan Approval
- Major deviation : Amendment Plan required
2. TOP Inspection Date application ( 2 weeks before) QP(Archi) Headroom,
3. Site Inspection – Compliance to Approved Documents QP(Archi) safety
barriers,
stairs. etc
* Safety Barrier submission to be done by PE/appointed PE by Builder & PE
Builder/Specialist. Copy of Annex A (List of safety barriers
installed on-site to be forwarded to QP(Archi)
* Engineered Façade (cladding, curtain wall. Screen/green wall) to Builder & PE
be submitted by QP-PE/Appointed PE. Copy of Annex A List of
Façade & submission nos. to be forwarded to QP (Archi)
QP(Archi) Builder to
4. Daylight Reflectance of material use <20%: QP(Archi) send a
declaration. supplier specs
QP (Archi)
5. Certificate of Supervision of Building Works
6. Builder’s Certificate of Completion of the Building Works Builder
7. ( BC-BC Cert)
8. Certificate of Supervision of Lightning Protection System,
Commissioning Test Report & As-built Plan
9. Certificate of Supervision of Air-conditioning/Mechanical
Ventilation System
10. Certificate of Supervision of Installation of Lift
HHS 1. Commissioning Approval
QP(Archi)
C&S Work 1. Certificate of Supervision of Structural Works (BEV-C1) PE
2. Certificates of supervision - Piling works (BEV-C2) PE
3. As-Built structural plans / calculations. (BEV-C3 PE
4. Annex A – list of safety barrier submission PE
LIFT 1. Cert. of Supervision of Lift Lift Specialist
2. Lift Lodgment by Lift Specialist upon obtaining ES number Lift Specialist
from QP(Archi). Required before lift commissioning
NEA / PUB
Minor Sewer 1. QP(Eng) to obtain clearance PE
(SEW) - C&S to arrange for inspection once sewer pipe is connected
and ready/before cover up
- Post CCTV to be submitted online by CCTV Contractors Builder
PUB 2. Sewerage Clearance for Compliance Certificate (CSC Cl) M&E
Sanitary (SAN) 3. As built Survey Plan Builder
Drainage 4. As built Plans Builder
5. QP to submit Drainage TOP QP (Archi)
6. Apply for PUB-TOP QP (Archi)
NEA 7. Stage 1 Submission (Plan Assessment) – provide location of QP(Archi)
Noise ACMV and ambient noise monitoring location. (CBPU takes AC Specialist
Assessment 4-8 weeks to reply) Builder
Report Stage 2 Submission (Reading Assessment) - submission of
noise measurement upon completion/installation of AC.
(CBPU takes 4-6 weeks to reply)
Environmental 7. Apply for NEA TOP with EH BP Clearance & Noise CL. QP(Archi)
Health
Pollution Control
(if applicable)
*** PUB and NEA are separate agencies already
LTA 1. Roads & Transport - BP Clearance/Lodgment PE
NPARKS BP Clearance – Internal (if applicable) QP (Archi)
BP Clearance – External PE
IDA 1. Cable Readiness Certificate Builder
(if applicable) Fibre Readiness Certificate
FSSD 1. Fire Safety Certificate QP (Archi)
(if applicable) - QP (Archi) to arrange RI Inspection
- when recommendation from RI received, QP to submit to FSSD
CSC CHECKLIST
LTA (Road & 1. Clearance required for External Work PE
Transport)
NPARKS 2. CSC External PE
3. CSC Internal (if applicable) QP (Archi)
PUB 4. Clearance required for External drain PE
5. Internal Drain QP(Archi)
NEA 6. EH BP QP(Archi)
FSSD 7. Fire Safety Certificate QP (Archi)