Sample Question & Answer For WMS Assessment

The document provides sample questions and answers about key aspects of a Work Management System (WMS) framework. There are 25 multiple choice questions that address topics like the 5 standards of a WMS (PTW, JSA, EI, temporary defeat, SIMOPS), who owns the framework and issues permits, documentation retention duration, permit validity, the 8 steps of a WMS, types of JSAs and certificates, types of permits and how to determine them, differences between JSA levels, energy isolation types, temporary defeat definition and types, authorized signatories, permit extensions, and SIMOPS types.

Uploaded by

Hir
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
80% found this document useful (46 votes)
107K views4 pages

Sample Question & Answer For WMS Assessment

The document provides sample questions and answers about key aspects of a Work Management System (WMS) framework. There are 25 multiple choice questions that address topics like the 5 standards of a WMS (PTW, JSA, EI, temporary defeat, SIMOPS), who owns the framework and issues permits, documentation retention duration, permit validity, the 8 steps of a WMS, types of JSAs and certificates, types of permits and how to determine them, differences between JSA levels, energy isolation types, temporary defeat definition and types, authorized signatories, permit extensions, and SIMOPS types.

Uploaded by

Hir
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

Sample Question & Answer for WMS Assessment

1. What are the five standards of WMS system?

1. PTW (Permit to work)

2. JSA (Job safety analysis)

3. EI (Energy Isolation)

4. Temporary Defeat of HSECES

5. SIMOPS

2. Who is the custodian of WMS frame work? / Who is the owner of all PTW work
system?

Senior Vice President (SVP)

3. What is the duration of document retention as per WMS framework?

12 Months

4. What is the maximum validity of the permits?

7 consecutive calendar days

5. What are the 8 steps of WMS?

1. Work request and planning

2. Identify & approve controls

3. Worksite control implementation

4. Authorize work permit

5. Communicate controls & Commence work

6. Dynamic risk assessment

7. Work handover / Suspense / Extension

8. Permit closure / hand back

6. How many types of JSA and their validity?

1. JSA Level 1 (No validity, when work will finish apply new JSA Level 1)

2. JSA Level 2 (2 years validity)

3. FRA (1 year validity)


7. How many types of certificates?

1. Confined Space Entry (CSE)

2. Atmospheric Test record form

3. Vehicle and machinery entry

4. Diving

5. Excavation

6. Ionizing Radiation

7. Road closure

8. Easement

9. Energy Isolation

10. Temporary Defeat

8. How many types of permits and examples?

1. General work permit: example House keeping

2. Hot work permit: Grinding, cutting, welding

3. Critical work permit: Lifting, working over live lines

9. How to decide the type of permit and JSA required for the activity?

WCC (Work categorization chart)

10. What is difference between JSA Level 1 and Level 2?

JSA Level 1 – SHCF (Standard hazard control form)

JSA Level 2 – HMF (Hazard management form)

11. Who is deciding the requirement of FRA?

IWAP team

12. What are the cancelation rules of PTW?

• In certain circumstances or emergencies it may be appropriate to cancel the


permit
• A full re-assessment of work conducted in the affected area to ensure that
conditions have not altered
In all cases when a permit is cancelled, re-commencing the work activity shall
require a new permit with all the relevant approvals.

13. What are the validation rules of PTW?

Effective handover between incoming and outgoing personal and shift change

14. What are the suspension rules of PTW?

An emergency alarm,

Rescue resource no long available

Weather conditions

Shift ends and Time extension

15. Who are the authorized signatories for work management system?

1. Asset Approval Authority (AAA) --- (Shift Co coordinator)

2. Area Authority (AA) --- (Shift Controller)

3. Permit Issuer (PI) ---- (Operator)

4. Performing Authority (PA) --- (Contracting Engineer)

5. Job Performer (JP) --- (JP/Supervisor)

6. Permit Endorse (PE) ---- (AGP/ Project focal point)

16. Who will raise the permit?

Performing authority

17. How many hours permit can extend?

4 Hours

18. What is the required in job performing details?

Name, contact number, work area and work through number

19. How many types of Energy Isolation what are they?

Two types of energy isolation

1. Mechanical isolation
2. Electrical Isolation

20. What is the form required for electrical de isolation?

Sanction to test (STT) form

21. What is temporary defeat and example?


A work activity that requires the temporary bypassing of a safety system is taken
out of service. Ex: Block out, isolate, over ride, Disable a safety protection device.

22. How many types of temporary defeats and what are they?

Two types of temporary defeats

1. Process defeats
2. Maintains defeats

23. What is SIMOPS?

Simultaneous Operations (SIMOPS) are activities that take place at the same
time and meet the following conditions

Activities that are located in the same area; and activities that could affect the
safe performance of another activity.

24. What is the example of SIMOPS?

Breaking containment and hot work

25. How many types of SIMPOS and what are they?

Two types of SIMOPS

1. Routine SIMOPS
2. Non routine SIMOPS