CAESARS PALACE LUXURY VILLA FIT OUT
BLUEWATERS ISLAND
DUBAI, UNITED ARAB EMIRATES
SITE MANPOWER HISTOGRAM
FOR
MEP INSTALLATION
Name Position Date Signature
Prepared by Shinos M Bavu Project Manager 30/AUG/2022
Verified by Shanavas Operations Manager 30/AUG/2022
Main Contractor
Approval
Consultant’s
Approval
SITE MAN POWER HISTOGRAM
Month 1 Month 2 Month 3 Month 4 Month 5 Month 6
TECHNICIANS 6 10 16 16 2 5
HELPERS 3 5 8 8 2 3
TOTAL 9 15 24 24 4 8
24 24
16 16
15
10
9
8 8 8
6
5 5
4
3 3
2 2
MONTH 1 MONTH 2 MONTH 3 MONTH 4 MONTH 5 MONTH 6
TECHNICIANS HELPERS TOTAL
Includes subcontractors and suppliers for special systems (Fire, ELV,IT)