Unit 1 Cement
Unit 1 Cement
1
CEMENT
A Cement is a binder, a substance that sets and hardeneds
independently, and can bind other materials together.
                                                            2
HISTORY OF CEMENT
                                                           3
                                                     cont.
• In India, Portland cement was first manufactured in 1904
  near Madras, by the south india industrial ltd. But this
  venture failed.
• Between 1912 and 1913, the indian cement co. ltd was
  established at porbander (gujrat) and by 1914 this
  company was able to deliver about 1000 tons of portland
  cement.
• German standard specification was drawn in 1877.
• British standard specification was drawn in 1904
• ASTM ( American standards for testing materials) in 1904
                                                         4
Manufacture of Portland cement
Raw Materials Required are
1. Calcareous Materials: Example Limestone or Chalk.
2. Argillaceous Material such as Shale or clay
General processes
• The process of manufacture of cement consists of grinding
  the raw materials, mixing them intimately in certain
  proportions depending upon their purity and composition and
  burning them in a kiln at a temperature of 1300 to 1500 oC, at
  this temperature, the material sinters and partially fuses to
  form nodular shaped clinker.
• The clinker is cooled and ground to fine powder with addition
  of about 3 to 5 % of gypsum. The product formed by using this
  procedure is Portland cement.
                                                               5
Main processes for manufacturing cement
Note:
Above process depends upon whether the mixing and
grinding of raw materials is done in dry or wet condition.
                                                             6
Flow Chart Wet Process
                         7
Wet Process
              8
9
Dry Process
              10
    Chemical composition for Portland cement
• The raw materials used for the manufacture of
  cement consist mainly of lime, silica, alumina and
  iron oxide.
• Chemical composition are
                                                       11
Bogue’s Compounds
• The oxides present in the raw materials when subjected to
  high clinkering temperature combine with each other to form
  complex compounds. The identification of the major
  compounds is largely based on R.H. Bogue’s work and hence it
  is called Bogue’s Compounds.
                                                            12
   Bogues equation
• The equations suggested by Bogue for calculating the
  percentages of major compounds are given below.
 C3S = 4.07 (CaO) – 7.60 (SiO2) – 6.72 (Al2O3) – 1.43(Fe2O3) –2.85 (SO3)
 C2S = 2.87 (SiO2) – 0.754(3CaO.SiO2)
 C3A = 2.65 (Al2O3) – 1.69 (Fe2O3)
 C4AF= 3.04 (Fe2O3)
                                                                     13
14
• Tricalcium silicate and dicalcium silicate are the most
  important compounds responsible for strength. Together
  they constitute 70 to 80 per cent of cement. The average
  C3S content in modern cement is about 45 per cent and
  that of C2S is about 25 per cent.
• The sum of the contents of C3A and C4AF has
  decreased slightly in modern cements.
• Cements with a high total alumina and high ferric
  oxide content is favourable to the production of high
  early strengths in cement.
• Excess of lime will cause unsoundness in cement.
• Increase in silica content will make cement difficult to
  fuse and form clinker.
                                                             15
Cement and hydration of Portland cement can be
schematically represented below
                                                 16
Hydration of Cement
• Anhydrous cement does not bind fine and coarse
  aggregate. It acquires adhesive property only when
  mixed with water.
• The chemical reactions that take place between cement
  and water is referred as hydration of cement.
• The hydration of cement can be visualised in two ways.
  The first is “through solution” mechanism. In this the
  cement compounds dissolve to produce a supersaturated
  solution from which different hydrated products get
  precipitated.
• The second possibility is that water attacks cement
  compounds in the solid state converting the compounds
  into hydrated products starting from the surface and
  proceeding to the interior of the compounds with time.
                                                       17
Heat of Hydration
 • The reaction of cement with water is exothermic. The
   reaction liberates a considerable quantity of heat. This
   liberation of heat is called heat of hydration.
 a) In the figure the peak ascending A
     refers to the heat evolved in
     due to the reaction of
     Aluminates and sulphates.
 b) Descending peak A represents
   This initial heat evolution
    ceases quickly when the
    solubility of aluminate is
    depressed by gypsum.
 c) The ascending peak B represents the heat evolved due to the
 accounting ettrigate (hexa calcium aluminate tri sulphate
 hydrate)-(cao)6 al2o3(so3)3.32H20 and also due to reaction C3S
                                                                  18
Heat of hydration can be predicted by following
                  H = aA + bB + cC + dD
Where H represents the heat of hydration in cal/g
• A, B, C, and D are the percentage contents
• of C3S, C2S, C3A and C4AF.
• a, b, c and d are coefficients representing the
  contribution of 1 per cent of the corresponding
  compound to the heat of hydration.
                                                    19
20
                                                cont.
                                                    21
Calcium Silicate Hydrates:
• During the course of reaction of C3S and C2S with water,
  calcium silicate hydrate, abbreviated C-S-H and calcium
  hydroxide, Ca(OH)2 are formed.
• Calcium silicate hydrates are the most important products. It
  is the essence that determines the good properties of
  concrete.
• It makes up 50-60 per cent of the volume of solids in a
  completely hydrated cement paste.
                                                                  22
• C3S readily reacts with water and produces more heat of
  hydration. It is responsible for early strength of concrete.
• C2S hydrates rather slowly. It is responsible for the later
  strength of concrete. It produces less heat of hydration.
                                                        24
Calcium alumina Ferrite hydrate
                                                       25
26
Diagrammatic representation of hydration
process
 • T    and formation of cement gel
                                           27
                                                           cont.
• Fig. 1.8 (a) represents the state of cement particles immediately
  when dispersed in an aqueous solution.
• Fig. 1.8 (b) represents the formation of coating on cement grain
  by calcium silicate hydrates.
• Fig. 1.8 (c) represents formation of hydration product including
  calcium hydroxide and bridge the gap between cement grains,
  and paste stiffens into its final shape.
• Fig. 1.8 (d) represents final hydrated cement
                                                                  28
Structure of hydrated cement paste
The two phases in the concrete are
a) Paste phase
b) Aggregate phase
                                                               29
Paste phase
• Fresh cement paste is a plastic mass consisting of water and cement. With
  the lapse of time, say one hour, the hardening paste consists of hydrates
  of various compounds, unhydrated cement particles and water.
• With further lapse of time the quantity of unhydrated cement left in the
  paste decreases and the hydrates of the various compounds increase.
  Some of the mixing water is used up for chemical reaction, and some
  water occupies the gel-pores and the remaining water remains in the
  paste.
• After a sufficiently long time (say a month) the hydrated paste can be
  considered to be consisting of about 85 to 90% of hydrates of the various
  compounds and 10 to 15 per cent of unhydrated cement. The mixing
  water is partly used up in the chemical reactions. Part of it occupies the
  gel-pores and the remaining water unwanted for hydration or for filling in
  the gel-pores causes capillary cavities.
• These capillary cavities may have been fully filled with water or partly with
  water or may be fully empty depending upon the age and the ambient
  temperature and humidity conditions.
                                                                             30
31
Transition Zone
• Transition Zone a third phase apart from the paste phase and
  aggregate phase which represents the interfacial region
  between the particles of coarse aggregate and hardened
  cement paste.
• Transition zone is generally a plane of weakness and,
  therefore, has far greater influence on the mechanical
  behaviour of concrete.
• Although transition zone is composed of same bulk cement
  paste, the quality of paste in the transition zone is of poorer
  quality.
• Due to internal bleeding, water accumulate below elongated,
  flaky and large pieces of aggregates. This reduces the bond
  between paste and aggregate. Such a situation account for
  the lower strength of transition zone than bulk cement paste
  in concrete.
                                                                32
                                                        Cont.
• Due to drying shrinkage or temperature variation, the
  transition zone develops micro cracks even before a structures
  is loaded. When structure is loaded and at high stress levels,
  these micro cracks propagate and bigger cracks are formed
  resulting in failure of bond. Therefore, transition zone,
  generally the weakest link of the chain, is considered strength
  limiting phase in concrete.
                                                               33
Water Requirement for hydration
• C3S requires 24% of water by weight of cement and C2S
  requires 21%.
• On an average 23% of water by weight of cement is required
  for chemical reaction with Portland cement compounds. This
  23% of water chemically combines with cement and,
  therefore, it is called bound water.
• A certain quantity of water is imbibed within the gel-pores.
  This water is known as gel-water. It is estimated that about 15
  per cent by weight of cement is required to fill up the gel-
  pores.
• Therefore, a total 38 per cent of water by weight of cement is
  required for the complete chemical reactions and to occupy
  the space within gel-pores.
                                                                34
Physical Test on Cement
Physical test on Cement are as follows:
1. Fineness Test                                                               http://www.youtube.com/watch?v=44yrGm2fxfU
http://www.youtube.com/watch?v=44yrGm2fxfU
http://www.youtube.com/watch?v=MrwAjLwycN8
http://www.youtube.com/watch?v=6Hh8i0lpuCs &   http://www.youtube.com/watch?v=7ZvcKWUo1tg
http://www.youtube.com/watch?v=DWhHEh-27J4
http://www.youtube.com/watch?v=vqxAabDdmTE
                                                                                                                                 35
1. Fineness Test
http://www.youtube.com/watch?v=44yrGm2fxfU
                                                                 36
Sieve
        37
W
• C
      38
Standard Consistency Test
Apparatus and Material: vicat apparatus, Balance, vicat plunger,
Vicat mould, non porous dish, measuring jar and OPC
plunger
                                      Initial            Final
                                      Setting needle     Setting needle
40
                                                         cont.
Procedure:
• Take about 500 gms of cement and prepare a paste with a
  weighed quantity of water (say 24 per cent by weight of
  cement) for the first trial.
• The paste must be prepared in a standard manner and filled
  into the Vicat mould within 3-5 minutes. After completely
  filling the mould, shake the mould to expel air.
• A standard plunger, 10 mm diameter, 50 mm long is attached
  and brought down to touch the surface of the paste in the
  test block and quickly released allowing it to sink into the
  paste by its own weight.
• Take the reading by noting the depth of penetration of the
  plunger. Conduct a 2nd trial (say with 25 per cent of water)
  and find out the depth of penetration of plunger.
                                                                 41
                                                          cont.
                                                              42
Setting Time Test
Apparatus and Material: vicat apparatus, Balance, Initial setting ,
Vicat mould, non porous dish, measuring jar, stop watch and OPC
                                                                 43
Procedure for initial setting time
                                                                44
                                                           cont.
                                                                45
Procedure for final setting time
                                                                    46
Strength Test
                                                            47
Procedure.
• Cement mortar cube are prepared by mixing 1 part of cement
                         𝑃
  , 3 parts of sand and ( +3 ) % of water. Where P is % of water
                         4
  required for producing normal consistency paste of cement
  and 3 indicating 3 % of combine weight of cement and sand.
• The mould is filled with the mortar and vibrate using vibrating
  machine for 2 minutes.
• After 24 hours of casting, the block is removed from the
  mould and cured in water.
• The specimen is tested in compression after curing for 3 days
  and 7 days in a compression testing machine and 3 day
  compression value 16 Mpa and 7 days           22 Mpa.
• Compression strength is determined by dividing the load by
  area of the specimen which is 50 cm2.
                                                               48
Soundness Test
                                                             49
Procedure
• The mould is placed on a glass plate and filled with cement paste by
  mixing cement with 0.78 times Of P. where P is standard
  consistency value.
• The mould is covered with another piece of glass plate and a small
  weight is placed on it.
• The whole assembly is submerged immediately in water at a
  temperature of 27 to 32 oC and kept there for 24 hours.
• The mould is removed from water and the distance seperating the
  indicator points is measured.
• The mould is submerged again in water and the water is heated till
  it reaches the boiling point in 25 to 32 minutes.
• The mould is kept in boiling water for 3 hours. The mould is
  removed from water, allowing to cool and the distance between the
  indicator points is measured again.
• For a good cement the expansion should not exceed 10 mm. the
  change in distance is a measure of the unsoundness.
                                                                    50
 Types of Cement
a) Ordinary Portland Cement
(i ) Ordinary Portland Cement 33 Grade– IS 269: 1989
(ii ) Ordinary Portland Cement 43 Grade– IS 8112: 1989
(iii ) Ordinary Portland Cement 53 Grade– IS 12269: 1987
                                                           51
                                                             cont.
                                                                 52
(b) Rapid Hardening Cement – IS 8041: 1990
.
   • Also called as High early strength cement.
   • Rapid Hardening Cement develops the strength at the age of three
     days, the same strength as that is expected of OPC at seven days.
   • More fineness of grinding (specific surface area not less that 3250
     cm2 per gram) and Higher C3S and lower C2S content.
   • Should not be used in mass concrete construction.
                                                                           53
C. Extra Rapid Hardening Cement
• Extra rapid hardening cement is obtained by intergrinding calcium
  chloride with rapid hardening Portland cement.
• The normal addition of calcium chloride should not exceed 2 per
  cent by weight of the rapid hardening cement.
• It is necessary that the concrete made by using extra rapid
  hardening cement should be transported, placed and compacted
  and finished within about 20 minutes.
• It is also necessary that this cement should not be stored for more
  than a month.
• Extra rapid hardening cement accelerates the setting and hardening
  process.
• 25 % more strength than RHC at one or two days and 10-20 % more
  at 7 days and same as that of OPC at 90 days
• Specific surface area is 5000 to 6000 cm2 /gm
• Size of particles are generally less than 3 microns.
• Difficult to store as it is liable to air set.
• There is small amount of initial corrosion of reinforcement.
                                                                   54
D Sulphate resisting cement
                                                                      55
E Portland Slag cement
                                                                   56
f Quick Setting cement
                                                             57
h Low Heat Cement
• Low C3S and C3A contents and high C2S content.
• Slow rate of gain of strength but ultimate strength is same as
  that of OPC cement.
• 7 days- not more than 65 cal/gm.
   28 days- not more than 75 cal/gm
• Specific surface area is not less than 3200 cm2/gm.
                                                                   58
I Portland pozzolana Cement
• PPC is manufactured by the intergrinding of OPC clinker with 10
   to 25% of pozzolanic material.
              Ca(OH)2+pozzolana+waterC-S-H (gel)
• Less heat of Hydration and offers greater resistance to the
   attack of aggressive water than OPC.
• Useful in marine structures and hydraulic construction.
Advantage
a Economical b Improvement of permeability c low heat of
Hydration.
                                                              59
J Air Entraining Cement
• Air entraining agent+OPC clinker at the time ginder.
• These agents in powder or liquid forms are added to the the
   extent of 0.025-0.1% by weight of cement clinked.
• Air entraining cement will produce at time of mixing, tough,
   tiny, discrete non coalescing air bubbles in the body of concrete
   which will modify the properties of plastic concrete w.r.t
   workability, segregation and bleeding.
• It will modify the properties of hardened concrete w.r.t
   resistance to frost action.
                                                                 60
K Coloured cement ( White cement)
• Coloured cement consists of portland cement with 5-10 % of
   pigment.
• Cement and pigment are grinded together.
• The raw materials used are high purity limestone (96% caco3 and less
   than 0.07% iron oxide), China clay with iron content of about (0.72 to
   0.8%), silica sand, flour spar as flux and selenite as retarder.
L Hydrophobic cement
• Hydrophobic cement is obtained by grinding O.P.C clinker with water
   repellent film forming substance such as oleic and stearic acid.
• The water repellant film formed around each grain of cement,
   reduces the rate of deteriorationof the cement during long storage,
   transport, or under unfavourable condition.
• Cost slightly higher than OPC.
                                                                      61
M Masonry cement
• Masonry cement is made with a combination such material which
  when used for making mortar, incorporating all the good properties
  of lime mortar and discards all the not so ideal properties of cement
  mortar.
• Mostly used for masonry construction
• Contains certain amount of air entraining agent and mineral
  admixture to improve plasticity and water retentivity.
N Expensive cement
• ordinary Portland cement shrinks while setting due to loss of free
   water. This is known as drying shrinkage.
• a slight expansion with time will prove to be advantageous for
   grouting purpose.
• This type of cement which suffers no overall change in volume on
   drying is known as expansive cement.
• 8-20 parts of the sulphoaluminate clinker are mixed with 100 parts of
   the Portland cement and 15 parts of the stabilizer
                                                                     62
O Oil-Well Cement
• Cement slurry is used to seal off the annular space between
  steel casing and rock strata and also to seal off any other
  fissures or cavities in the sedimentary rock layer.
• The cement slurry has to be pumped into position, at
  considerable depth where the prevailing temperature may be
  upto 175°C. The pressure required may go upto 1300 kg/cm2.
• It may also have to resist corrosive conditions from sulphur
  gases or waters containing dissolved salts. The type of cement
  suitable for the above conditions is known as Oil-well cement.
                                                               63
P Rediset Cement
• The cement allows a handling time of just about 8 to 10
   minutes.
• The strength pattern is similar to that of ordinary Portland
   cement mortar or concrete after one day or 3 days. What is
   achieved with “REDISET” in 3 to 6 hours can be achieved with
   normal concrete only after 7 days.
• More heat of hydration
• The rate of shrinkage is fast but the total shrinkage is similar to
   that of ordinary Portland cement concrete.
Application
(a ) very-high-early (3 to 4 hours) strength concrete and mortar,
(b) patch repairs and emergency repairs,
(c ) quick release of forms in the precast concrete products
industry,
                                                                    64
(q ) High Alumina Cement
• High alumina cement is obtained by fusing or sintering a
   mixture, in suitable proportions, of alumina and calcareous
   materials and grinding the resultant product to a fine powder.
• The raw materials used for the manufacture of high alumina
   cement are limestone and bauxite.
                                                                65
(r) Very high strength cement
(a) Macro-defect-free cements
• MDF refers to the absence of relatively large voids or defects
    which are usually present in conventional mixed cement pastes
    because of entrapped air and inadequate dispersion.
• In the MDF process 4-7% of one of several water-soluble
    polymers (such as hydroxypropylmethyle cellulose,
    polyacrylamide of hydrolysed polyvinylacetate) is added as
    rheological aid to permit cement to be mixed with very small
     amount of water.
• At final processing stage entrapped air is removed by applying
    a modest pressure of 5 MPa.
• With this process a strength of 300 MPa for calcium aluminate
    system and 150 MPa for Portland cement system can be
    achieved.
                                                               66
(b) Densely Packed System (DSP).
• Normal Portland cement and ultra-fine silica fume are mixed.
• The size of cement particles may very from 0.5 to 100μ and
   that of silica fume varies from 0.005 to 0.5μ.
• Silica fume is generally added from 5 to 25 %.
• A compressive strength of 270 MPa have been achieved with
   silica fume substituted paste.
                                                             67
(d) High Early Strength Cement.
• Lithium salts have been effectively used as accelerators in high
   alumina cement.
• Resulted in very high early strength in cement and a marginal
   reduction in later strength.
• Strength as high as 4 MPa has been obtained within 1 hour and
   27 MPa has been obtained within 3 hours time and 49 MPa in
   one day.
(e) Pyrament Cement
• In this cement no chlorides are added during the
   manufacturing process.
• Pyrament cement produces a high and very early strength of
   concrete and mortar which can be used for repair of Air Field
   Run-ways.
                                                                68
(f) Magnesium Phosphate Cement (MPC)
• Magnesium Phosphate Cement, an advanced cementing
    material, giving very high early strength mortar and concrete
    has been developed by Central Road Research Institute, New
    Delhi.
• MPC is a prepacked mixture of dead burn magnesite with fine
    aggregate mixed with phosphate. It sets rapidly and yields
    durable high strength cement mortar.
• This cement can be used for rapid repair of damaged concrete
    roads and airfield pavements.
                                                                69
                                                                Cont.
The following materials are used for making MPC:
• Magnesite (MgCO3) when calcined at or above 1500°C gives
  dead burnt magnesite (DBM). This material is ground to a
  fineness of 300-350 m2/kg (Blaines).
• This is mixed with commercially available crystalline Mono
  Ammonium Phosphate after grinding into fine powder passing
  600μ seive, and other ingredients like sodium tri-
  polyphosphate in the form of fine powder, di-sodium
  tetraborate (Borax), fine aggregate (crushed dolomite sand)
  and water.
• The DBM and sand mixture is added into cold phosphate and
  borax solution (12-15°C) and mixed for one minute. This mix is
  applied for the purpose of repair. It is air cured and is ready for
  opening traffic within 4-5 hours.
                                                                   70