JOB SAFETY ANALYSIS
Project Name : Date :
Job Title : JSA No.
Prepared by : Revision : 00
S. WORK ACTIVITIES HAZARDS RISK CONTROL MEASURES Additional
No. Suggestion
if required
1 Manpower Lack of work knowledge, Personal Injury • Identify the hazards before starting the
mobilization into inexperience / no safety work.
work area. training • Only trained workers should be allowed
on site.
• Tool box talk & safe work procedure
should be explained to workers.
• Trained first aider should be available at
site.
• Work should be carried under continues
supervision.
• Proper PPE’s (Helmet, safety shoes,
reflective jackets, hand-gloves, to be
provided.
• Safety officer shall ensure only medically
fit and inducted workers shall be allowed
to work.
JOB SAFETY ANALYSIS
2 Material shifting Mis-handling, fall of Physical injury • Supervisor/engineer shall ensure the
/Handling by person on same level, Fall material shall be shifted safely on
manually/wheel of material while shifting wheel borrow.
barrow • Supervisor/engineer shall ensure
shifted materials are stacked properly
in a safe manner.
• Worker must be use nose mask and
safety glass safety hand gloves during
material shifting work.
3 Cleaning by tar Hand cut hazards and Physical injury • Supervisor/engineer shall ensure
brush and grinder electrical hazards. person using grinder must have
machine inspected and mandatory PPE’s. Shall
be use.
• Access and egress must be clear/free
from obstruction before start the work.
• Worker must be use nose mask and
safety glass safety hand gloves during
cleaning work.
4 Mixing of water Cut injury, person may Physical injury • Supervisor/engineer shall ensure
Fosroc X421IC fall while applying material damaged. person mixing of _______ and cement,
chemical, cement waterproofing chemical sand and water is using dust mask and
and sand and incorrectly, electrical Rubber/PVC hand gloves other than
applying. hazards, Inhalation and mandatory PPE’s.
Eye irrigate • Supervisor shall prepare standing
platform.
• Supervisor/engineer shall ensure
proper housekeeping before and after
completion of job on each day.
• Electrician shall be ensuring mixing
machine shall be inspected.
• Supervision shall be ensuring during
the applying of Fosroc X421IC chemical
JOB SAFETY ANALYSIS
person must have use safety Goggle and
nose mask.
• Supervisor and safety officer shall be
ensuring secondary contentment shall
be present during the mixing work.
•
JOB SAFETY ANALYSIS
5 In case of Confusion & fear will be Personal injury • Assembly points should be located at
emergency created in workers
site
• Emergency contact number shall be
displayed at site.
• Briefing shall be given at the time of
induction & at regular intervals.
• Emergency vehicle should be ready at
site.
• Trained first aider should be available
at site. ( Optional )
Sr. No Specific Recommended Safe Job Procedures Name of Responsible Designation Signature
Persons
1 Work Permit
2 Tool box talk for work
3 PPE’s Ensure and Area barricading
JOB SAFETY ANALYSIS
Prepared by Reviewed and approved by
Approved by
Prepared by Reviewed by Reviewed by
Roland Mago