EP Wells Operations Summary Report

This document summarizes drilling and completion operations for well LEKHWAIR-89 from August 1990 to April 1991. It details the drilling of the well to 897 meters using 17 1/2 inch and 12 1/4 inch drill bits, running and cementing 13 3/8 inch casing, installing blowout preventers, drilling ahead below the casing, getting stuck requiring fishing operations, and eventual completion of the well.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
151 views7 pages

EP Wells Operations Summary Report

This document summarizes drilling and completion operations for well LEKHWAIR-89 from August 1990 to April 1991. It details the drilling of the well to 897 meters using 17 1/2 inch and 12 1/4 inch drill bits, running and cementing 13 3/8 inch casing, installing blowout preventers, drilling ahead below the casing, getting stuck requiring fishing operations, and eventual completion of the well.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 7

PDO

EP Wells Operations Summary Report


Well: LEKHWAIR-89
Project: Lekhwair Site: LEKHWAIR-89 Rig Name No: Z Historical PDO Rig 5/
Event: Drilling +Completion Actual Start Date: 8/5/1990 End Date: 4/4/1991 Original Spud Date: 8/7/1990
Active Datum: TBF @105.80m (above Mean Sea Level) UWI (SAP PSN#): 410000002714
Date Time Hrs Phase Op WSOP Depth Description
Start-End Code (m)
8/5/1990 21:00 - 00:00 3.00 RM PMO -116.00 GENERAL RIGGING DOWN. PREPARING FOR LOWERING
MAST.

8/7/1990 00:00 - 06:00 6.00 RM NOA -116.00 CONT'D WAITING ON DAYLIGHT.


06:00 - 10:00 4.00 RM PMO -116.00 RAISED MAST @ 0615 hrs. TOP SECTION UP @ 0645 hrs.
GENERAL RIGGING UP. LEVELED MAST. INSTALLED CSG
STABBING BOARD.
10:00 - 10:30 0.50 PR PRE -116.00 M/U KELLY & P/T SURFACE LINES TO 11000 kPa. OK.
10:30 - 14:30 4.00 PR RUD -116.00 M/U TURBINE & DRILLED KELLYHOLE AND SINGLEHOLE.
INSTALLED SCABBARDS. L/D & SERVICED TURBINE.
BEARING PLAY 3 mm.
14:30 - 15:00 0.50 D17 DRT -116.00 M/U BHA # 1, 17 1/2" NEW BIT.
15:00 - 00:00 9.00 D17 DRR 1.00 SPUDDED LOCATION 74-31-48 AS L 89 @ 1500 hrs.
(ON 07.08.90). DRILLED TO 117 m. NO LOSSES.

8/8/1990 00:00 - 11:45 11.75 D17 DRR 234.00 CONT'D DRILLING AHEAD FROM 117 m. TO 350 m.
NO LOSSES.
11:45 - 12:00 0.25 D17 MNR 234.00 DAILY MAINTENANCE.
12:00 - 14:45 2.75 D17 DRR 300.00 DRILLED AHEAD FROM 350 m TO 416 m.
14:45 - 15:00 0.25 D17 NOA 300.00 H2s ALERT.
15:00 - 20:30 5.50 D17 DRR 382.00 CONT'D DRILLED AHEAD FROM 416 m TO 498 m.
20:30 - 20:45 0.25 D17 NOA 382.00 FLOW CHECK. NO LOSSES.
20:45 - 21:30 0.75 D17 PCD 382.00 CIRCULATED HOLE CLEAN. SPOTTED 10 m3 Hi-VISC
ON BOTTOM.
21:30 - 21:45 0.25 D17 DVM 382.00 DROP TOTCO. F/CHECK, STATIC.
21:45 - 00:00 2.25 D17 DRT 382.00 POOH TO 31 m MAX O/PULL 30000 daN. WIPED
TIGHT SPOTS.

8/9/1990 00:00 - 02:45 2.75 D17 DRT 382.00 CONT'D POOH L/D STAB, 2 x 9 1/2 DCs, S/SUB &
BIT. RECOVERED TOTCO (1 DEGREE).
02:45 - 03:00 0.25 D17 NOA 382.00 HOUSEKEEPING ON RIGFLOOR.
03:00 - 03:30 0.50 D17 MNR 382.00 SLIPPED BLOCKLINE 8.4 m.
03:30 - 03:45 0.25 C17 NOA 382.00 HELD SAFETY TALK PRIOR RIH 13 3/8 CSG.
03:45 - 04:15 0.50 C17 RUD 382.00 R/U FOR 13 3/8 CSG.
04:15 - 08:30 4.25 C17 CLR 382.00 M/U 13 3/8" SHOETRACK, BACKERLOCKED. TESTED
FLOATS EQUIPS. OK. AND RIH 13 3/8" K55, BTC,
81.1 kg/m. TO RESISTANCE @ 455 m.
08:30 - 11:30 3.00 C17 CLR 382.00 W/DOWN FROM 455 m TO 497 m.
11:30 - 12:00 0.50 C17 PCD 382.00 CIRC. 120% CSG CONTENTS. NO LOSSES.
12:00 - 12:30 0.50 C17 CLC 382.00 R/U DOWELL CMT HEAD & CMT LINES.
12:30 - 12:45 0.25 C17 PRE 382.00 FLUSHED & P/TESTED CEMENT LINES TO 21000 kPa.OK.
12:45 - 13:30 0.75 C17 CLC 382.00 DOWELL PREFLUSHED 3m3, DROPPED BTM PLUG. INST.
TOP PLUG. CEMENTED 300 SKS POZMIX 16.1 kPa/m.
RELEASED TOP PLUG.
13:30 - 14:00 0.50 C17 PCD 382.00 PUMPED 1.5m3 AFTER FLUSH. DISPLACED PLUG AND
BUMPED SAME WITH RIG-PUMPS.

4/11/2011 12:18:42PM Report Version: 3.2.901 1


PDO

EP Wells Operations Summary Report


Well: LEKHWAIR-89
Project: Lekhwair Site: LEKHWAIR-89 Rig Name No: Z Historical PDO Rig 5/
Event: Drilling +Completion Actual Start Date: 8/5/1990 End Date: 4/4/1991 Original Spud Date: 8/7/1990
Active Datum: TBF @105.80m (above Mean Sea Level) UWI (SAP PSN#): 410000002714
Date Time Hrs Phase Op WSOP Depth Description
Start-End Code (m)
14:00 - 14:15 0.25 C17 PRE 382.00 P/TESTED CASING TO 12000 kPa. OK. CHECKED FOR
BACKFLOW. OK. CHECKED FOR LOSSES. OK.
ESTIMATED TOC = 295m.
16:00 - 17:15 1.25 C17 CLC 382.00 R/U & PERFORMED TOP-FILL WITH 50 SKS POSMIX.
CEMENT TO SURFACE.
17:15 - 18:15 1.00 C17 CLR 382.00 INSTALLED LANDING PLATES & CLAMP. HUNG-OFF CSG
WITH 30000 daN. BACKED-OFF & L/D LANDING JOINT.
18:15 - 00:00 5.75 C17 CLR 382.00 INSTALLED 13 3/8 CHH & SIDE OUTLETS.
N/U BOP's.

8/10/1990 00:00 - 03:00 3.00 C17 RUD 382.00 CONT'D N/U BOP's.
03:00 - 08:15 5.25 C17 BPT 382.00 FUNCTION TESTED KOOMEY UNIT & BOP. M/U 13.3/8
CTT. P/TEST S/O & HYDRIL 10500 kPa. M/U PTT
P/T BOP & RELATED EQUIPTS. TO 21000 kPa. OK.
08:15 - 10:15 2.00 C17 BPT 382.00 P/U KELLY. P/TEST SURFACE LINES, KK's AND
GRAY-VALVES TO 21000 kPa. OK.
10:15 - 13:15 3.00 D12 DRT 382.00 M/UP BHASSY NO.2 & RIH TO 471 m. TAGGED
TOC @ 471 m.
13:15 - 14:30 1.25 D12 DCM 382.00 DRILLED SHOETRACK AND POCKET. SHOE @ 496 m.
CLEANED AND WIPED SAME.
14:30 - 14:45 0.25 D12 NOA 382.00 FLOW-CHECK. STATIC.
14:45 - 23:45 9.00 D12 DRR 614.00 DRILLED AHEAD FROM 498 m TO 730 m.
LOSSES STARTED @ 580 m 2 m3/hr STATIC.
23:45 - 00:00 0.25 D12 MNR 614.00 DAILY MAINTENANCE.

8/11/1990 00:00 - 22:15 22.25 D12 DRR 781.00 CONT'D DRILLING AHEAD FROM 730m TO 897m.
LOSSES AT 870m:STATIC 10m3/hr.
22:15 - 23:15 1.00 D12 PCD 781.00 PRESSURE DROP OFF 4600Kpa AT 897m AND LOST 9 TONS
OFF STRING WEIGTH.CIRC HOLE CLEAN AND SPOT 5m3
VISC ABOVE TOP FISH.
23:15 - 00:00 0.75 D12 DRT 781.00 POOH

8/12/1990 00:00 - 02:00 2.00 D12 DRT 781.00 POOH.LEFT IN HOLE BIT-F/S-2xDC-STAB-3xDC.
LENGTH OF FISH 48.88m.
05:15 - 06:00 0.75 D12 SWF 781.00 LATCH ON FISH AND MAKE FISH FRE MAX O/P 25000dan
06:00 - 06:30 0.50 D12 PCD 781.00 CIRC HOLE CLEAN.
06:30 - 10:30 4.00 D12 DRT 781.00 POOH RELEASED O/S FROM FISH,L/D O/S DC AND BIT
VISUALLY INSPECTED ALL DC CONECTIONS FOR CRACKS.
10:30 - 15:00 4.50 D12 DRT 781.00 M/U BIT # 3 AND RIH TO 890m.
15:00 - 15:15 0.25 D12 PCD 781.00 W/D FROM 890m TO 897m AND CIRC FOR JUNK.
15:15 - 00:00 8.75 D12 DRR 996.00 DRILLED FROM 897m TO 1112m.
LOSSES: FROM 897m TO 1013m 25 TO 40m3/hr
: FROM 1013m TOTAL LOSSES.

8/13/1990 00:00 - 00:30 0.50 D12 DRR 1,000.00 DRILLED FROM 1112m TO 1116m
00:30 - 01:15 0.75 D12 PCD 1,000.00 PRESSUREDROP OF 4600kpa AT 1116m AND LOST 19000dan
STRING WEIGTH.CIRC HOLE CLEAN AND SPOT 5m3 VISC
ABOVE TOP FISH.
01:15 - 04:00 2.75 D12 DRT 1,000.00 POOH:LEFT IN HOLE BIT-JUNK BASKET-SHOCK EZE-2xDC-
STAB-9xDC:LENGTH OF FISH 109m.
04:00 - 06:45 2.75 D12 DRT 1,000.00 M/U 11 3/4" O/S WIDTH 8"BASKET GRAPPLE AND RIH TO
TOP OF FISH AT 1007m.

4/11/2011 12:18:42PM Report Version: 3.2.901 2


PDO

EP Wells Operations Summary Report


Well: LEKHWAIR-89
Project: Lekhwair Site: LEKHWAIR-89 Rig Name No: Z Historical PDO Rig 5/
Event: Drilling +Completion Actual Start Date: 8/5/1990 End Date: 4/4/1991 Original Spud Date: 8/7/1990
Active Datum: TBF @105.80m (above Mean Sea Level) UWI (SAP PSN#): 410000002714
Date Time Hrs Phase Op WSOP Depth Description
Start-End Code (m)
06:45 - 07:00 0.25 D12 SWF 1,000.00 LATCH ON FISH AND PULL FISH FREE MAX O/P 3000dan.
07:00 - 07:45 0.75 D12 PCD 1,000.00 CIRC HOLE CLEAN.F/C LOSSES STATIC 15m3/hr.
07:45 - 16:00 8.25 D12 DRT 1,000.00 POOH RELEASED O/S FROM FISH,L/D O/S AND DC.
UNPLUGGED DC,STAB,SHOCK EZE AND F/S.
VISUALLY INSPECTED DC CONNECTIONS FOR CRACKS.
16:00 - 20:30 4.50 D12 DRT 1,000.00 M/U BIT #4 & RIH TO 1110m.W/D FROM 1110m TO 1116m.
20:30 - 00:00 3.50 D12 DRR 1,036.00 DRILLED FROM 1116m TO 1152m.
DRILLING BREAK AT 1149m.
FROM 1116m TO 1152m TOTAL LOSSES.

8/14/1990 00:00 - 01:00 1.00 D12 PCD 1,036.00 SWEEP 5m3 VISC ROUND AND SPOT 15m3 VISC ON BOTTEM.
01:00 - 01:15 0.25 D12 ELO LSS 1,036.00 DRILLED BIT SAMPLE.
01:15 - 02:30 1.25 D12 NOA 1,036.00 F/S WELL FLOWING,CLOSE BOP,pdp & pann 0,SQUEEZED
10m3 OF 13.3Kpa MUD,F/S TOTAL LOSSES,OPEN BOP,
FILL UP ANNULUS WITH WSW.
02:30 - 02:45 0.25 D12 DVM 1,036.00 DROP TOTCO.
02:45 - 04:45 2.00 D12 DRT 1,036.00 POOH AT 510m WELL FLOW AGAIN,CLOSE BOP.
pdp & pann 0Kpa.
04:45 - 05:15 0.50 D12 NOA 1,036.00 SQUEEZED 3m3 OF 13.3Kpa MUD,F/S TOTAL LOSSES.
FILL UP ANNULUS WITH WSW.
05:15 - 06:45 1.50 D12 DRT 1,036.00 CONT'D POOH TO 50m.WELL FLOW AGAIN,CLOSE BOP.
06:45 - 07:15 0.50 D12 NOA 1,036.00 SQUEEZED 3m3 OF 13.3Kpa MUD,F/S TOTAL LOSSES.
FILL UP ANNULUS WITH WSW.
07:15 - 08:15 1.00 D12 DRT 1,036.00 CONT'D POOH RETRIEVE TOTCO(miss fire),L/D STAB
AND BIT.
08:15 - 08:45 0.50 C12 RUD 1,036.00 CHANGE RAMS TO 9 5/8"
08:45 - 09:00 0.25 C12 BPT 1,036.00 P/T BONNETS TO 10500Kpa.
09:00 - 09:30 0.50 C12 RUD 1,036.00 R/U FOR RUNNING 9 5/8" CSG.WELL FLOW AGAIN
CLOSE BOP.
09:30 - 10:00 0.50 C12 NOA 1,036.00 SQUEEZED 5m3 13.3Kpa MUD.FC TOTAL LOSSES.
FILL UP ANNULUS WITH WSW.
10:00 - 17:30 7.50 C12 CLR 1,036.00 M/U & BACKERLOCK SHOE TRACK.TEST FLOAT EQUPMENT
RUN CSG TO 1150m.WASH DOWN LAST 10m.F/SHOE @ 1149m
F/COLLAR @ 1136m,BAFFLE PLATE @1124m,MSPC @ 882m
17:30 - 18:30 1.00 C12 PCD 1,036.00 CIRC 120% CSG CONTENTS.
18:30 - 19:15 0.75 C12 CLC 1,036.00 R/U CMT HEAD AND LINES.
19:15 - 19:30 0.25 C12 PRE 1,036.00 FLUSH LINES AND P/T TO 21000Kpa.
19:30 - 20:30 1.00 C12 CLC 1,036.00 DOWELL PUMP 3m3 PREFLUSH,MIX AND PUMP 878 sxs
POZMIX CMT 16.1Kpa/m.
20:30 - 21:00 0.50 C12 PCD 1,036.00 DROP SHUT OFF PLUG,DOWELL PUMP 1.5m3 AFTER FLUSH
DISPLACE CMT WITH RIG PUMPS UNTIL BUMP
21:00 - 21:15 0.25 C12 PRE 1,036.00 P/T CSG TO 17000Kpa.BLEED OFF NO BACKFLOW.
21:15 - 21:30 0.25 C12 CLC 1,036.00 DROP BOMB,INSTALL CLOSING PLUG,LEVEL ANNULUS:TOTAL
LOSSES.SET PACKER AND OPEN CIRC PORTS.AFTER SETING
PACKER LOSSES 15m/hr.
21:30 - 22:15 0.75 C12 PCD 1,036.00 CIRC ANNULUS CLEAN 4m3 CMT AT SURFACE.
22:15 - 22:45 0.50 C12 NOA 1,036.00 AFTER CIRC OUT CMT WELL FLOW AGAIN CLOSE BOP
SQUEEZED 4m3 OF 13.3Kpa MUD.F/C TOTAL LOSSES
22:45 - 00:00 1.25 C12 PCD 1,036.00 WAIT TILL SURFACE SAMPLES ARE HARD,MEANWHILE CIRC
TROUGH MSPC.

4/11/2011 12:18:42PM Report Version: 3.2.901 3


PDO

EP Wells Operations Summary Report


Well: LEKHWAIR-89
Project: Lekhwair Site: LEKHWAIR-89 Rig Name No: Z Historical PDO Rig 5/
Event: Drilling +Completion Actual Start Date: 8/5/1990 End Date: 4/4/1991 Original Spud Date: 8/7/1990
Active Datum: TBF @105.80m (above Mean Sea Level) UWI (SAP PSN#): 410000002714
Date Time Hrs Phase Op WSOP Depth Description
Start-End Code (m)
8/15/1990 00:00 - 00:15 0.25 C12 CLC 1,036.00 DOWELL PUMP 3m3 PRE FLUSH,WELL FLOW AGAIN.
CLOSE BOP.
00:15 - 00:30 0.25 C12 NOA 1,036.00 SQUEEZED 3m3 OF 13.3Kpa MUD,F/S LOSSES 15m3/hr.
00:30 - 01:15 0.75 C12 CLC 1,036.00 DOWELL MIX & PUMP 1030sxs POZMIX CMT.DROP CLOSING
PLUG.
01:15 - 01:45 0.50 C12 PCD 1,036.00 DOWELL PUMP 1.5m3AFTER FLUSH,DISPLACE CMT UNTIL
BUMP,CLOSE MSPC.
01:45 - 02:00 0.25 C12 PRE 1,036.00 P/T CSG 17000Kpa,BLEED OFF NO BACKFLOW.
02:00 - 02:30 0.50 C12 CLR 1,036.00 DROP SLIP & SEAL ASSY,HUNG OFF CSG WITH 55000dan,
P/T SLIP & SEAL ASSY WITH 3500Kpa FROM ABOVE.
02:30 - 02:45 0.25 C12 CLC 1,036.00 R/D CMT HEAD AND LINES.
02:45 - 11:00 8.25 C12 CLR 1,036.00 N/D BOP's,CUT & DRESS CSG STUB(16cm).INSTALL THS
AND BOP's.C/O RAMS TO 4 1/2"-7"VAR.ENERGISED
P SEALS WITH 16 STICKS.
11:00 - 14:15 3.25 C12 BPT 1,036.00 P/T P-SEALS 9000Kpa,THS & S/O vlv's1 3500-17000Kpa
HYDRIL 3500-10500Kpa,PIPE/SHEAR RAMS,BPM,BOP-
OUTLETS,KILL & SHOKE LINE 3500-21000Kpa
14:15 - 14:30 0.25 C12 RUD 1,036.00 INSTALL WEARBUSHING.
14:30 - 16:15 1.75 D09 DRT 1,036.00 L/D 8 1/4" DC.
16:15 - 19:30 3.25 D09 DRT 1,036.00 M/U ASSY #5 (8 1/2 BIT) AND RIH TO MSPC @ 882m.
19:30 - 20:45 1.25 D09 DCM 1,036.00 DRILL MSPC.
20:45 - 21:00 0.25 D09 PRE 1,036.00 P/T MSPC TO 17000Kpa.
21:00 - 22:00 1.00 D09 DRT 1,036.00 RIH TO 1116m
22:00 - 22:30 0.50 D09 NOA 1,036.00 H2S DRILL.
22:30 - 00:00 1.50 D09 DCM 1,036.00 DRILL SHOE TRACK TO 1140m(baffle plate @ 1124m
F/C @ 1136m)

8/16/1990 00:00 - 00:45 0.75 D09 DCM 1,036.00 CONT'D DRILL SHOE TRACK (F/SHOE @1149m)MEANWHILE
CIRC TO 12.3Kpa MUD. CLEAN POCKET.
00:45 - 11:45 11.00 D09 DRR 1,109.00 DRILL FROM 1152m TO 1225m. O/P AT 1225m 40000dan.
11:45 - 12:45 1.00 D09 REM 1,109.00 MAKE STRING FREE. REAM 1203m-1225m.
12:45 - 21:15 8.50 D09 DRR 1,204.00 DRILL FROM 1225m TO 1320m.
21:15 - 22:00 0.75 D09 PCD 1,204.00 SWEEP HOLE WITH 5m3 VISC.
22:00 - 23:00 1.00 D09 CWT 1,204.00 CHECKTRIP TO 9 5/8"CSG SHOE.FROM 1281m T0 SHOE O/P
MAX 20000 dan.F/C IN SHOE:STATIC.
23:00 - 23:45 0.75 D09 PCD 1,204.00 CIRC HOLE CLEAN.
23:45 - 00:00 0.25 D09 DVM 1,204.00 DROP TOTCO AND DP DRIFT.FLOW CHECK:STATIC.

8/17/1990 00:00 - 04:15 4.25 D09 DRT 1,204.00 POOH FOR LOGGING L/D STAB AND RETRIEVE TOTCO
(incl 1.5 degree).
04:15 - 04:45 0.50 E09 ELO RUD 1,204.00 R/U FOR SCHLUMBERGER.
04:45 - 12:00 7.25 E09 ELO EME 1,204.00 RUN #1:PI/MSFL/SDT/GR(in:0515 out:0745 HUD:1320m)
RUN #2:LDT/CNT/PCD/GR(in:0815 out:1015 HUD:1320m)
RUN #3:SHDT(in:1030 out:1200 HUD:1320m).
12:00 - 12:30 0.50 E09 ELO RUD 1,204.00 R/D SCHLUMBERGER R/U SSL.
12:30 - 16:45 4.25 E09 ELO EME 1,204.00 RUN #4:VSP(in:1230 out:1645).
17:15 - 00:00 6.75 E09 ELO EME 1,204.00 RUN #5:RFT(in:1800).

8/18/1990 00:00 - 01:00 1.00 E09 ELO EME 1,204.00 CONT'D RUN # 5
01:00 - 01:30 0.50 E09 ELO RUD 1,204.00 PREPARED CST TOOL.

4/11/2011 12:18:42PM Report Version: 3.2.901 4


PDO

EP Wells Operations Summary Report


Well: LEKHWAIR-89
Project: Lekhwair Site: LEKHWAIR-89 Rig Name No: Z Historical PDO Rig 5/
Event: Drilling +Completion Actual Start Date: 8/5/1990 End Date: 4/4/1991 Original Spud Date: 8/7/1990
Active Datum: TBF @105.80m (above Mean Sea Level) UWI (SAP PSN#): 410000002714
Date Time Hrs Phase Op WSOP Depth Description
Start-End Code (m)
01:30 - 04:00 2.50 E09 ELO EME 1,204.00 RUN #6:CST (IN @ 0130 hrs).
04:00 - 04:15 0.25 E09 ELO RUD 1,204.00 R/DOWN SCHLUMBERGER.
04:15 - 07:00 2.75 C09 CWT 1,204.00 M/U BHA # 6 & RIH TO SHOE.
07:00 - 08:30 1.50 C09 MNR 1,204.00 SLIPPED BLOCKLINE 8.4 m AND CUT 25.2 m.
ADJUSTED & TESTED C.O.M. OK.
08:30 - 09:00 0.50 C09 CWT 1,204.00 CONT'D RIH BHA TO 1307 m.
09:00 - 09:15 0.25 C09 PCD 1,204.00 P/U KELLY & W/DOWN TO 1320 m.
09:15 - 10:30 1.25 C09 PCD 1,204.00 CIRC AROUND 5 m3 Hi-VISC PILL ON BOTTOM.
10:30 - 10:45 0.25 C09 NOA 1,204.00 F/CHECK NO LOSSES.
10:45 - 13:45 3.00 C09 DRT 1,204.00 POOH FOR RUNNING 7" LINER.
13:45 - 14:15 0.50 C09 RUD 1,204.00 R/U TO RUN 7" LINER.
14:15 - 19:15 5.00 C09 CLR 1,204.00 M/U SHOETRACK. CHECK FLOAT EQUIPMENTS OK.
RUN 7" LINER. M/U BROWN LINER HANGER & RUNNING
TOOL. RIH 7" LINER ON 5" DP TO 1120 m.
19:15 - 19:45 0.50 C09 PCD 1,204.00 CIRCULATED 120% STRING CONTENT.
19:45 - 21:30 1.75 C09 CLR 1,204.00 CONT'D RIH 7" LINER ON 5" DP TO BOTTOM 1320 m.
21:30 - 21:45 0.25 C09 CLR 1,204.00 SPACE OUT. SET LINER 1 m OFF BOTTOM.
TOL @ 1100 m.
21:45 - 22:45 1.00 C09 PCD 1,204.00 CIRC HOLE CLEAN & COND. MUD. MEANWHILE DOWELL
MIXED SCAVENGER AND MAINSLURRY.
22:45 - 23:00 0.25 C09 CLC 1,204.00 FLUSHED CMT-LINES. P/T SAME TO 17000 kPa. OK.
23:00 - 23:45 0.75 C09 CLC 1,204.00 LOADED DP-WIPERPLUG. DS PUMPED 1m3 PREFLUSH
3m3 SCAV. SLURRY 9.9m3 CLASS-G MAINSLURRY. DROPPED
DP WIPERPLUG. PUMPED 1 m3 AFTERFLUSH & DISPL.PLUG.
23:45 - 00:00 0.25 C09 PCD 1,204.00 ATTEMPTED TO BUMPED PLUG. NO SUCESS.
CHECKED FOR BACKFLOW, OK.

8/19/1990 00:00 - 00:45 0.75 C09 CLR 1,204.00 PULLED CUPS OUT OF LINER, BALANCED OUT 1 m3
RETURNS. POOH TO 895 m.
00:45 - 01:00 0.25 C09 PCD 1,204.00 CIRCULATED STRING CLEAN.
01:00 - 03:00 2.00 C09 CLR 1,204.00 CONT'D POOH L/DOWN & SERVICED LINER SETTING
TOOL.
03:00 - 06:00 3.00 CU DRT 1,204.00 M/U BHA No.6 & RIH TO 889 m.
06:00 - 06:30 0.50 CU NOA 1,204.00 PERFORMED BOP DRILL + HELD SAFETY MEETING.
06:30 - 07:30 1.00 CU NOA 1,204.00 W.O.C.
07:30 - 07:45 0.25 CU DRT 1,204.00 CONT'D RIH TO RESISTANCE @ 958 m.
07:45 - 12:45 5.00 CU DCM 1,204.00 DRILLED HARD CMT FROM 958 m TO TOL @ 1100 m.
12:45 - 13:30 0.75 CU PCD 1,204.00 CIRC. HOLE CLEAN WITH 5 m3 Hi-VISC PILL.
13:30 - 13:45 0.25 CU NOA 1,204.00 F/CHECK STATIC.
13:45 - 17:15 3.50 CU DRT 1,204.00 POOH, L/D HWDP & 61/4" DCs, F/S & BIT.
17:15 - 23:00 5.75 CU DRT 1,204.00 M/U TANDEMSRAPER ASSY #7 & RIH TO RESISTANCE
@ 1258 m.
23:00 - 00:00 1.00 CU DCM 1,204.00 W/DOWN TO TOC @ 1260 m. DRILLED HARD CMT
FROM 1260 m TO 1275 m.

8/20/1990 02:15 - 03:30 1.25 CU PCD 1,204.00 DISPLACED HOLE TO UNFILTERED NACL BRINE OF
11.5 kPa/m. FLUSHED ALL SURFACE LINES.
03:30 - 04:00 0.50 CU PRE 1,204.00 P/TESTED LINER-LAP TO 10500 kPa. OK.
04:00 - 08:00 4.00 CU DRT 1,204.00 POOH & L/DOWN ALL TUBULARS.

4/11/2011 12:18:42PM Report Version: 3.2.901 5


PDO

EP Wells Operations Summary Report


Well: LEKHWAIR-89
Project: Lekhwair Site: LEKHWAIR-89 Rig Name No: Z Historical PDO Rig 5/
Event: Drilling +Completion Actual Start Date: 8/5/1990 End Date: 4/4/1991 Original Spud Date: 8/7/1990
Active Datum: TBF @105.80m (above Mean Sea Level) UWI (SAP PSN#): 410000002714
Date Time Hrs Phase Op WSOP Depth Description
Start-End Code (m)
08:00 - 11:00 3.00 CU ELO 1,204.00 R/U EASTMAN CHRISTENSEN & RUN GYRO SURVEY
TO HUD @ 1260 m.
11:00 - 11:15 0.25 CU RUD 1,204.00 R/U SCHLUMBERGER.
11:15 - 15:15 4.00 CU ELO EME 1,204.00 SCHLUMBERGER RUN #1 CBL/CET IN @ 1215 hrs.
OUT @ 1515 hrs.
15:15 - 15:30 0.25 CU RUD 1,204.00 R/D SCHLUMBERGER.
15:30 - 15:45 0.25 CU ELO RUD 1,204.00 RETRIEVED WEARBUSHING.
15:45 - 16:15 0.50 CU ELO RUD 1,204.00 M/U SHOOTING NIPPLE & SCHL. BOP.
16:15 - 16:30 0.25 CU PRE 1,204.00 P/TESTED SHOOTING NIPPLE TO 5000 kPa.
16:30 - 17:15 0.75 CU ELO RUD 1,204.00 SCHLUMBERGER PREPARED 4" PERFORATION GUNS.
17:15 - 23:15 6.00 CU ELO ELP 1,204.00 SCHLUMBERGER RUN #2 : PERF GUNS. PERFORATED
1271m - 1278m INTERVAL. RUN #3 : PERFORATED
1179m - 1191m. RUN #4 : A JUNK BASKET/GAUGE RING.
23:15 - 23:30 0.25 CU ELO RUD 1,204.00 NO LOSSES AFTER PERFORATION. R/D SCHLUMBERGER &
L/DOWN SHOOTING NIPPLE.
23:30 - 00:00 0.50 IC RUD 1,204.00 CHANGED RAMS TO 2 7/8" - 5" VARIABLE.

8/21/1990 00:00 - 01:00 1.00 IC BPT 1,204.00 P/TESTED BONNETS TO 10500 kPa.
01:00 - 01:45 0.75 IC TUR 1,204.00 M/U 2 3/8" COMPLETION TAIL & RIH TO 17 m.
01:45 - 02:00 0.25 IC RUD 1,204.00 R/U WIRE LINE.
02:00 - 02:15 0.25 IC SLO 1,204.00 W/LINE SET 2 3/8" XN PLUG @ XN NIPPLE.
02:15 - 02:45 0.50 IC PRE 1,204.00 P/TESTED COMPLETION TAIL TO 21000 kPa. OK.
02:45 - 03:00 0.25 IC SLO 1,204.00 W/LINE RETRIEVED XN PLUG.
03:00 - 03:15 0.25 IC RUD 1,204.00 R/DOWN W/LINE.
03:15 - 03:30 0.25 IC RUD 1,204.00 R/U SCHLUMBERGER.
03:30 - 04:45 1.25 IC SLO 1,204.00 SCHLUMBERGER RIH COMPLETION TAIL ON WIRELINE
AND SET MODEL 'D' PACKER @ 1193 m.
04:45 - 05:00 0.25 IC RUD 1,204.00 R/DOWN SCHLUMBERGER.
05:00 - 06:15 1.25 IC TUR 1,204.00 M/U 2 7/8" COMPLETION ASSY & RIH TO 71 m.
06:15 - 06:30 0.25 IC RUD 1,204.00 R/U WIRELINE LUBRICATOR & P/TESTED TO 21000 kPa.
06:30 - 07:00 0.50 IC SLO 1,204.00 W/LINE RIH & SET XN PLUG @ XN NIPPLE.
07:00 - 07:30 0.50 IC PRE 1,204.00 P/TESTED COMPLETION ASSY TO 21000 kPa.
07:30 - 07:45 0.25 IC SLO 1,204.00 W/LINE RETRIEVED XN PLUG.
07:45 - 08:00 0.25 IC RUD 1,204.00 R/DOWN W/LINE LUBRICATOR.
08:00 - 13:45 5.75 IC TUR 1,204.00 CONT'D RIH 2 7/8" COMPLETION TO 1210 m.
13:45 - 15:15 1.50 IC PCD 1,204.00 CIRCULATED CSG CONTENT ABOVE MODEL 'D' PACKER.
15:15 - 16:30 1.25 IC TUR 1,204.00 SPACED OUT. INSTALLED TBG HANGER AND
LANDED STRING WITH 14000 daN.(INJECTED 16 STICKS).
16:30 - 16:45 0.25 IC PRE 1,204.00 P/TESTED HANGER FROM ABOVE TO 3500 kPa. OK.
16:45 - 17:30 0.75 IC RUD 1,204.00 R/U W/LINE LUBRICATOR.
17:30 - 17:45 0.25 IC PRE 1,204.00 P/TESTED LUBRICATOR TO 21000 kPa.
17:45 - 19:00 1.25 IC SLO 1,204.00 W/L RIH & SET TEST TOOL IN 2 3/8" XN NIPPLE.
HUD @ 1209 m.
19:00 - 19:45 0.75 IC PRE 1,204.00 P/TESTED STRING AND G-22 SEALS TO 14000 kPa.
19:45 - 20:45 1.00 IC SLO 1,204.00 W/LINE RETRIEVED PRONG & PLUG.
20:45 - 21:45 1.00 IC SLO 1,204.00 W/LINE RIH 2 7/8" PXN PLUG & PRONG AND
SET IN 2 7/8" XN NIPPLE.
21:45 - 22:30 0.75 IC PRE 1,204.00 P/TESTED TUBING STRING TO 21000 kPa FOR
30 MINS. OK.

4/11/2011 12:18:42PM Report Version: 3.2.901 6


PDO

EP Wells Operations Summary Report


Well: LEKHWAIR-89
Project: Lekhwair Site: LEKHWAIR-89 Rig Name No: Z Historical PDO Rig 5/
Event: Drilling +Completion Actual Start Date: 8/5/1990 End Date: 4/4/1991 Original Spud Date: 8/7/1990
Active Datum: TBF @105.80m (above Mean Sea Level) UWI (SAP PSN#): 410000002714
Date Time Hrs Phase Op WSOP Depth Description
Start-End Code (m)
22:30 - 23:00 0.50 IC PRE 1,204.00 PERFORMED LEAK-OFF TEST, FORMATION TOOK
FLUID @ 4200 kPa.
23:00 - 23:45 0.75 IC SLO 1,204.00 W/LINE RIH AND SHIFTED SLEEVE RH-PACKER.
23:45 - 00:00 0.25 IC PCD 1,204.00 SET RH PACKER BY PRESSURING STRING IN 3500kPa
STAGES TO 21000 kPa.

8/22/1990 00:00 - 00:30 0.50 IC PRE 1,204.00 CONFIRMED PACKER SET BY PRESSURING ANNULUS
SLOWLY TO 6000 kPa.
01:00 - 05:30 4.50 IC TUR 1,204.00 INSTALLED BPV & N/DOWN BOP. INSTALLED
X-MAS TREE.
05:30 - 06:00 0.50 IC PRE 1,204.00 INSTALLED TWCV. P/T X-MAS TREE TO 21000 kPa.
INSTALLED BPV.

4/11/2011 12:18:42PM Report Version: 3.2.901 7